M/S Y.D Builders & Hotels Pvt Ltd vs Uoi & Anr
- Court
- Delhi High Court
$~3
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC011790402016
+ O.M.P. (COMM) 328/2016
M/S Y.D BUILDERS & HOTELS PVT LTD .....Petitioner
Through: Mr. Sanjeev Anmol, Sr. Advocate
with Mr. Bipin Kr. Prabhat, Mr.
Kislaya Prabhat, Mr. Ashok Verma
and Ms. Rinku Kumari, Advocates.
versus
UOI & ANR .....Respondents
Through: Mr. Ranjeev Khatana, SPC.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGEMENT (ORAL)
% 22.09.2026
1. The present petition has been filed by the Petitioner, M/s Y.D.
Builders & Hotels Pvt. Ltd., under Section 34 of the Arbitration and
1
Conciliation Act, 1996 , challenging the Arbitral Award dated
2
21.03.2014 passed by the learned Sole Arbitrator, Shri O.P. Bhatia, in
respect of disputes arising out of Contract Agreement No. 02/EE/CW-
122/PWD/2009-10.
2. In the present challenge to the impugned Award, the Petitioner
has confined its challenge to Claim No. 1, which relates to the
difference between the amount claimed in its final bill and the amount
actually paid, including the rates applied to quantities beyond the
deviated limit and extra items.
1
“the Act” hereinafter
2
“impugned Award” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 1 of 19
3. The relevant facts, to the extent necessary for deciding the
challenge now pressed, are set out below.
4. Under the Contract Agreement No. 02/EE/CW-122/PWD/2009-
3
10 , the Petitioner was entrusted with the work of developing the Park
and Ride Facilities for buses near Rajghat Power Plant and carrying
out other miscellaneous works connected with the Commonwealth
Games, 2010. The tendered amount was Rs.9,02,93,202/-.
5. The work commenced on 07.11.2009 and was stipulated to be
completed by 06.05.2010. The work was ultimately completed on
04.12.2010, and the extension of time was granted up to that date
without levy of compensation.
6. After completion of the work, the Petitioner submitted its final
bill for Rs.17,72,81,500/-. Against the said bill, the Respondent made
only payment of Rs.12,08,09,532/- as per the Petitioner. The balance
amount gave rise to disputes between the parties, which were not
merely as to the amount remaining unpaid, but also as to the rates at
which the quantities beyond the deviated limit and extra items
executed by the Petitioner were to be paid.
7. During execution of the work, the Executive Engineer, by letter
dated 25.06.2010, informed the Petitioner that the quantities of certain
agreement items were exceeding the permissible deviation limits and
called upon it to submit rates. The Petitioner, thereafter, submitted its
rate through various communications.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 2 of 19
8. In respect of the quantities beyond the deviated limit, after some
correspondences, the Petitioner by letters dated agreed to the rates
proposed by the Respondent for Items 62.62, 63.63 and 68.68 and to
the Agreement rates for the remaining deviated quantities. These
letters are of considerable importance, as the Petitioner subsequently
disputed the effect of these letters, whereas the Respondent relied
upon them as constituting an agreement between the parties.
9. In respect of the extra items, the Petitioner disputed the rates
applied by the Respondent and claimed payment in terms of market
rates. It also disputed the recovery of amounts earlier paid against
certain extra items in the final bill. When the disputes remained
unresolved despite the conciliation proceedings, the dispute were
ultimately referred to Arbitration.
10. By way of the impugned Award, the learned Arbitrator
adjudicated 12 claims raised by the Petitioner arising out of disputes
concerning, inter alia , payment for deviated and extra items,
escalation, delayed payments and interest.
11. For the purpose of the present petition, the relevant part of the
impugned Award is the adjudication of Claim No.1. The learned
Arbitrator divided that claim into (A) deviated items and (B) extra
items, and further considered the dispute relating to the extra items
under four separate heads.
3
“contract” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 3 of 19
12. Under Claim No.1, the learned Arbitrator finally awarded
Rs.11,13,256/- in respect of twelve extra items and Rs.25,73,190/-
towards amounts earlier paid for four extra items but subsequently
recovered in the final bill, making a total award of Rs.36,86,446/-
under Claim No.1.
13. At the outset, learned Senior Counsel for the Petitioner submits
that, in terms of Section 28(3) of the Act, the learned Arbitrator was
bound to give effect to the terms of the Contract, but failed to do so
while adjudicating Claim No.1.
14. It is submitted that the quantities beyond the permissible
deviation limits were admittedly executed and, in terms of Clauses
12.2 and 12.3 of the Contract, the Petitioner had submitted its rate for
such quantities. However, the Engineer-in-Charge failed to finalise the
rates within the stipulated period of one month. Therefore, it is
contended that such failure on the part of the Engineer-in-Charge
could not operate to the prejudice of the Petitioner, particularly when
the contractual procedure had been duly followed.
15. Learned Senior Counsel further submits that the letters dated
15.12.2011, on which reliance was placed by the learned Arbitrator,
were issued more than a year after completion of the work, when the
Petitioner’s dues were still outstanding. It is contended that the said
letters were issued under economic pressure to secure the release of
the withheld payments and, therefore, could not have been treated as a
voluntary settlement of the rates.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 4 of 19
16. Learned Senior Counsel also points out that the Respondent’s
own case in the Statement of Defence was that the rates had been
finalised by the Respondent and accepted by the Petitioner, and not
that they had been mutually negotiated. On that basis, the Petitioner
contends that the learned Arbitrator’s finding of a negotiated
settlement travels beyond the Respondent’s pleaded case.
17. Insofar as extra items are concerned, learned Senior Counsel for
the Petitioner submits that they were required to be paid at market
rates in terms of Clause 12.2, and that the Petitioner had accordingly
submitted its rate analysis, which were neither refuted by the
Respondent nor acted upon by the learned Tribunal. It is contended
that, in these circumstances, the learned Tribunal erred in adopting an
average enhancement of 38.90% for the twelve extra items. It is
further submitted that the additional quantities of Items 3/2 and 3/3
had been executed and recorded in the measurement books and that
the learned Tribunal, therefore, erred in denying payment for the
same.
18. Per contra , learned Counsel appearing for the Respondent
submits that the impugned award is well-reasoned and that none of the
objection discloses a ground for interference by this Court within the
limited scope of jurisdiction vested under Section 34 of the Act.
19. On the deviated items, learned Counsel submits that the learned
Arbitrator rightly relied upon the two letters dated 15.12.2011, which
expressly recorded the Petitioner’s unconditional acceptance of the
relevant rates. The plea of coercion, it is argued, was unsupported by
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 5 of 19
cogent material and would require this Court to re-appreciate a factual
issue already considered by the learned Arbitrator.
20. As regards the extra items, learned Counsel submits that the
Petitioner claimed rates which, for the twelve disputed items, were
154.45% above the DSR rates without sufficient material to
substantiate the same. The learned Arbitrator, therefore, adopted the
average enhancement of 38.90% already reflected in six other extra
items paid at market rates. As to the additional quantities of Extra
Items 3/2 and 3/3, the Respondent relies upon the absence of those
quantities from the R.A. bills. Hence, it is submitted that the
impugned Award does not warrant interference under Section 34 of
the Act.
21. I have heard the learned Counsel for both the parties and
perused the material on record.
22. At the outset, I find it relevant to note that the impugned arbitral
award was passed on 21.03.2014 and the present proceedings were
initiated prior to the coming into force of the Arbitration and
4
Conciliation (Amendment) Act, 2015 on 23.10.2015. The challenge
is, therefore, governed by Section 34 of the Act as it stood prior to the
2015 Amendment Act.
23. Keeping the aforesaid position in view, the scope of
intervention of this Court under the head of public policy has been the
subject matter of a catena of decisions. In ONGC v. Saw Pipes Ltd.,
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 6 of 19
(2003) 5 SCC 705 , the Supreme Court, while examining the scope of
public policy, also recognised patent illegality as a ground for
interference with an arbitral award in the following words:
“31. Therefore, in our view, the phrase “public
policy of India” used in Section 34 in context is
required to be given a wider meaning. It can be
stated that the concept of public policy connotes
some matter which concerns public good and the
public interest. What is for public good or in public
interest or what would be injurious or harmful to the
public good or public interest has varied from time
to time. However, the award which is, on the face of
it, patently in violation of statutory provisions
cannot be said to be in public interest. Such
award/judgment/decision is likely to adversely
affect the administration of justice. Hence, in our
view in addition to narrower meaning given to the
term “public policy” in Renusagar case [1994 Supp
(1) SCC 644] it is required to be held that the award
could be set aside if it is patently illegal. The result
would be — award could be set aside if it is
contrary to:
( a ) fundamental policy of Indian law; or
( b ) the interest of India; or
( c ) justice or morality, or
( d ) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the
illegality is of trivial nature it cannot be held that
award is against the public policy. Award could also
be set aside if it is so unfair and unreasonable that it
shocks the conscience of the court. Such award is
opposed to public policy and is required to be
adjudged void.”
24. There is no quarrel with the proposition that, under the pre-
amendment regime, an arbitral tribunal was required to decide in
accordance with the terms and conditions agreed between the parties
and that an award which disregards a binding contractual stipulation
may, in an appropriate case, be vulnerable under Section 34. At the
4
“2015 Amendment Act” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 7 of 19
same time, interpretation of the contract and appreciation of the
material bearing upon that interpretation lie primarily within the
domain of the learned Arbitrator. Interference is not warranted merely
because another view is possible, the view adopted must be shown to
be one that the contract cannot reasonably bear or the award must
otherwise disclose patent illegality going to the root of the matter.
25. The Hon’ble Supreme Court has also time and again cautioned
against interference with an arbitral award in a casual manner, as such
an approach would defeat the scheme of arbitration and the principle
of minimum judicial interference.
26. It is against this settled legal position that the challenge in the
present petition has to be examined by this Court.
27. The grievance in the present petition pertains to Claim No. 1,
which concerns the unpaid amount claimed in the final bill and, in
substance, raises two principal issues: (i) the rates payable for
quantities beyond the permissible deviation limits and (ii) the rates or
quantities payable in respect of extra items.
28. The case of the Petitioner is that despite having submitted its
rate analysis in terms of Clause 12, the Engineer-in-Charge failed to
determine the market rates within the stipulated period and, instead of
addressing this failure, the learned Tribunal rejected the claim on the
basis of the subsequent letters dated 15.12.2011, which, according to
the Petitioner, were issued under economic duress.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 8 of 19
29. In order to examine the aforesaid challenge against the
impugned Award, it would be apposite to first notice the relevant
findings returned by the learned Tribunal on the deviated items, which
read as follows:
“ Para 1.5 Award
(A) Deviation items (Amount claimed Rs 1,69,55,500/-)
As per clause 12.2 of the agreement, if quantities of the contract
items exceed the limits laid down in schedule F, the contractor may
within 15 days of receipt of order or occurrence of the excess,
claim revision of rates supported by proper analysis for the excess
quantities. The engineer-in-charge shall within one month of
receipt of the claim, after giving due consideration to the A/R
submitted by the contractor, determine the rates on the basis of the
market rates.
As explained under the foregoing para 1.2(b), the claimant
has claimed higher rates (i.e. more than agreement rates) even for
the quantities up to the deviation limit in respect of item numbers
1.1, 3.3, 4.4, and 62.62 which is not covered under any provisions
of the agreement. Under remarks column of the statement 'A'
submitted with Claimant's letter dtd 22.5.2013, it has been
explained that these rates have been claimed as per DSR-2007 +
1.85% enhancement. The Claimant entered into this agreement
with some specific rates for these items which are binding upon
both the parties and take precedence over another rates available
in the DSR. The Claimant cannot be paid more than agreement
rates for the quantities up to the deviation limits.
For the quantities beyond deviation limit, the EE had
written a letter no 572 dtd 25.6.2010 (Exh C8/6) to the claimant
informing him that quantities of certain items are exceeding the
deviation limits for which the claimant had not submitted the A/R
(for market rates). The claimant was asked to submit his rates for
these items. The claimant had submitted his rates through various
letters viz C8/1 dtd 15.6.2010, C8/2 dtd 30.11.2010, C8/3 dtd
24.6.2010 & C8/4 dtd 2.7.2010 etc. The Respondent in his letter no
698 dtd 11.11.2013 has stated that the
claimant had not submitted these rates within the specified time.
The EE vide his letter no 417 dtd 7.5.2010 &no 260 dtd 13.5.2010
had intimated the agency about the rates offered by the department
for few items and requested the agency to give their acceptance of
the rates. Subsequently, the rates were decided with mutual consent
of the claimant as evident from his letters at R9 (dtd 15.12.2011)
&R10 (dtd 15.12.2011). In Exh R9, the claimant had stated as
under:-
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 9 of 19
“we hereby agree unconditionally for the agreement rates offered
by us for all the quantities including the quantities beyond
permissible variation for all the agreement items except three items
(62.62, 63.63 &68.68) for which we have given a separate letter no
YDB/CW/Nil dtd 15-12-2011( which is available at Exh R10). The
Exh R10 states as under:-
We hereby unconditionally agree for the rate as mentioned below
for the following three items for the quantities deviated beyond
permissible variation:-
(i) 62:62 (P/L RCC 1:1:2 Rs 6000/- per cum
in all works upto plinth)
(ii) 63.63 (RCC in walls Rs 4758.98 per cum
1:1.5:3)
(iii) 68.68 (Reinf in RCC) Rs 63.70 per Kg.
(The agreement rates for these items are Rs 3801.04, Rs 4168.06,
and Rs 43.49 respectively). From the statement 'A' submitted by the
claimant with his letter dtd 22.5.2013, it is seen that there are six
items in total which have been deviated beyond deviation limit i.e.
item numbers 1(1), 3.3, 62.62, 63.63, 68.68 and 70.70. Rates for
the deviated quantities for all the six items have been paid by the
Respondent as per the claimant's letters as cited above i.e. Exh R9
& R10. Rates for item numbers 62.62, 63.63 &68.68 have been
paid as agreed upon by the claimant under R10 and for remaining
three items at agreement rates as per R9. The claimant has stated
that the Respondent has paid these items at his own rates, which is
not correct in view of the position explained above. It has further
been stated by the claimant that the Respondent forced the
claimant to accept these agreement and negotiated rates. This also
does not seem to be correct. If there was a coercion, how the
claimant could claim market rates for the three items (as listed
under R10) which are much higher than the agreement rates.
Evidently, rates for all these items were settled through
negotiations, and the same have already been accepted/agreed
th
upon by both the parties. Till the pre-final bill i.e. 13 RA bill paid
on 30.3.2011, the claimant had been paid agreement rates only for
all these deviated quantities. Settling of rates for the deviated
quantities through negotiations is quite a common and accepted
procedure also.
In view of the reasons explained above and with due
consideration to all facts of the case, and the submissions made, I
hereby give NIL award against this part of the claim.
30. A perusal of the aforesaid findings shows that the learned
Tribunal was conscious of the mechanism prescribed under the said
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 10 of 19
clause. It specifically noticed that, by letter dated 25.06.2010, the
Engineer-in-Charge had called upon the Petitioner to submit rate for
the quantities exceeding the permissible deviation limits and that the
Petitioner had thereafter submitted its rate through various letters.
Thus, this is not a case where the learned Tribunal ignored Clause
12.2 or proceeded on an interpretation which is not borne out by its
terms.
31. In the view of this Court, Clause 12.2 required the Engineer-in-
Charge, after considering the contractor’s analysis, to determine the
rate on the basis of market rates within the period prescribed. The
Respondent’s failure to complete that exercise within time is a
relevant circumstance. The clause, however, does not state that the
rate unilaterally submitted by the contractor becomes automatically
binding upon such failure, nor does it prohibit the parties from
subsequently settling the rates for the quantities actually executed.
32. The issue before the learned Arbitrator, therefore, was not
merely whether the rates were determined within the stipulated period,
but also what effect was to be given to the subsequent correspondence
between the parties and whether the same resulted in a mutual
agreement on the rates.
33. Admittedly, six items were found to have exceeded the
permissible deviation limits, namely Items 1(1), 3.3, 62.62, 63.63,
68.68 and 70.70. On the basis of the two letters dated 15.12.2011, the
learned Tribunal found that the Petitioner had accepted the Agreement
rates for Items 1(1), 3.3 and 70.70, and rates of Rs.6,000/-,
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 11 of 19
Rs.4,758.98/- and Rs.63.70/- for Items 62.62, 63.63 and 68.68,
respectively, as against the Agreement rates of Rs.3,801.04/-,
Rs.4,168.06/- and Rs.43.49/- for those three items. The letters, marked
R-9 and R-10, read as follows:
“R9
Sir,
We hereby agree unconditionally for the agreement rate
offered by us for all the quantities including deviated quantities
beyond permissible variation for all the agreement items except
three items (Item No. 62.62, 63.63 & 68.68) for which we have
given a separate letter No. YDB/CW/Nil dated 15-12-2011.
R10
Sir,
We hereby unconditionally agree for the rate as mentioned
for the following three items for the quantities deviating beyond
permissible variation:-
(i) 62.62 : P&L RCC in all work - Rs. 6000/- per cum
Upto plinth level
In 1:1:2
(ii) 63.63 : RCC in walls in 1:1.5:3 - Rs. 4758.98 per cum
(iii) 68.68 : Reinforcement in RCC - Rs. 63.70 per Kg”
work
34. The Petitioner does not dispute the authorship or contents of
these letters. Its case is that the words of unconditional acceptance do
not reflect free consent because the letters were furnished under
economic pressure while substantial payments remained outstanding
at the end of the Respondent.
35. However, this Court is unable to accept the aforesaid
submission, and the learned Tribunal had also rightly rejected the said
plea. The plea of coercion or economic duress is essentially a plea of
fact and cannot rest on a bald assertion without supporting material.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 12 of 19
5
Recently, in DDA v. Swastik , this Court emphasized that an
undertaking cannot be disregarded merely on a bare assertion of
financial pressure and that the circumstances said to vitiate consent
must have a proper factual foundation and be supported by identifiable
material. The relevant observations are as follows:
“On that basis, the undertaking was treated as
having no legal effect. It is true that the mere
existence of a no-claim certificate or undertaking is
not always conclusive and if it is established that
such a document was obtained by coercion, undue
influence or economic duress, the underlying
dispute may still survive.
At the same time, the document cannot be
discarded merely on a bare assertion of financial
pressure. In Union of India v. Master
Construction Co. (2011) 12 SCC 349, the Supreme
Court held that an allegation that a no- claim
document was obtained by coercion or duress must
have a credible factual foundation and cannot rest
on a bald ple
The fact that the agreement did not require such
an undertaking is undoubtedly relevant, but it does
not follow that an undertaking voluntarily given
would be without effect. Likewise, a later
withdrawal may have some evidentiary value, but it
does not by itself establish the circumstances in
which the earlier undertaking was executed. What
was required was a finding, based on identifiable
material, that DDA had made processing of the
extension or release of payment conditional upon
furnishing the undertaking, or had otherwise
exercised pressure of such a nature as to vitiate
consent.
The sequence of events relied upon by the
respondent could certainly raise a suspicion of
commercial pressure, particularly because the
undertaking preceded the final processing of the
extension of time case. The difficulty is that the
5
O.M.P. (COMM) 143/2016
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 13 of 19
award does not identify any demand, instruction,
correspondence or other material by which that
suspicion is converted into a finding of coercion.
The conclusion is drawn substantially from the
pendency of payments and the later withdrawal of
the undertaking. In my view, that reasoning is not
sufficient to deprive the undertaking of its legal
effect.”
36. On the present record, the plea of duress does not furnish a
ground for interference under Section 34. The letters are facially
unconditional. The Petitioner relies principally on the pendency of
substantial dues and the fact that the final bill payment followed the
letters, but no related communication has been identified in the
material considered by the learned arbitrator showing that the
Respondent expressly made release of payment conditional upon
execution of those letters or otherwise threatened non-payment unless
they were furnished.
37. There is a further circumstance which the learned Arbitrator
was entitled to consider and rightly relied upon. For three items, the
Petitioner accepted the Agreement rates, whereas for Items 62.62,
63.63 and 68.68, it secured rates materially higher than the Agreement
rates. On that material, the learned Arbitrator returned a finding that
the six rates had been settled through negotiations rather than simply
imposed by the Respondent. Whether that inference is the only
possible one is not the test, it is a plausible inference from the record.
38. The Petitioner’s explanation for issuing the letters may be
commercially understandable, but accepting it as establishing duress
would require this Court to re-appreciate the circumstances in which
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 14 of 19
the correspondence was issued and to substitute a different factual
inference for that drawn by the learned Tribunal. That exercise is
outside the permissible scope of Section 34 in the absence of
perversity or a finding unsupported by the record.
39. The finding also cannot be faulted merely because the
Respondent used the expression “accepted” instead of “negotiated” in
its Statement of Defence as the Respondent had relied upon the very
letters R-9 and R-10 as the basis for the rate paid. The learned
Tribunal was entitled to ascertain the legal effect of those letters and
to describe the process confirmed by them as a settlement through
negotiations.
40. Once the learned Tribunal returned a sustainable finding that
the parties had subsequently agreed upon the rates for the six deviated
items, the challenge found solely on the earlier non-determination of
rates under Clause 12.2 loses force. The clause prescribed the
mechanism for determination of rates, but did not prevent the parties
from subsequently agreeing upon the rates or reaching a later
consensual settlement. In these circumstances, the rejection of this part
(A) of Claim No.1 does not disclose any error or patent illegality
warranting interference under Section 34 of the Act.
41. As regards the challenge to the rates allowed for the extra items
component of Claim No.1, the learned Arbitrator considered the claim
under four heads: (B)(i) the claim for market rates for twelve extra
items; (B)(ii) the claim for four extra items for which amounts earlier
paid in R.A. bills were recovered in the final bill; (B)(iii) the claim
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 15 of 19
relating to payment of additional quantities claimed for Extra Items
3/2 and 3/3; and (B)(iv) the claim for extra items relating to brickwork
in the superstructure.
42. In respect of (B)(i), the impugned Award records that the
Respondent had determined and paid market rates for six extra items
but had paid only DSR-2007 rates plus the contractual enhancement of
1.85% for twelve other extra items. The learned Tribunal also
recorded that the Respondent had followed the mechanism under
Clause 12 in respect of six items, but not for the remaining twelve
items. However, at the same time, it noted that the Petitioner’s rates
claimed for the twelve extra items were “exorbitant” and higher than
the applicable rates. The learned Tribunal, therefore, did not find the
rates claimed by the Petitioner to be reliable.
43. The principal grievance of the Petitioner is that, once the
Respondent failed to determine the rates of the twelve extra items in
terms of Clause 12.2, the rates submitted by the Petitioner ought to
have been accepted or should have been paid on the market rate. This
submission, however, assumes that the Petitioner’s rate would become
binding merely because it was not rebutted by the Respondent. Clause
12.2 does not create such a default rule. It requires determination of
market rates having regard to the relevant cost material, it does not
convert an unaccepted contractor’s rate analysis into the contractual
rate merely by lapse of time.
44. The learned Tribunal was, therefore, justified in examining the
reliability of the rates put forward by the Petitioner. The finding that
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 16 of 19
those rates were excessive was based on the material on the record.
This Court finds no error in the approach adopted by the Tribunal, nor
can this Court re-appreciate the same material merely to arrive at a
different conclusion as it would amount to a review on merits which
Section 34 does not permit.
45. Having rejected both the Respondent’s DSR plus 1.85%
approach for the twelve items and the Petitioner’s claimed rates and in
absence of any market rate analysis by the Engineer-in-Charge for 12
extra items, the learned Tribunal used the six extra items already paid
at market rates under the same Contract as a benchmark. The average
enhancement over DSR for those six items was 38.90%, and applying
that enhancement yielded an additional amount of Rs.11,13,256/-. The
methodology is discernible from the impugned Award and is anchored
in the material on record. Whether some other method could have
been adopted is not a ground for setting aside the Award.
46. Head B(ii) was dealt with separately. The learned Arbitrator
found that amounts aggregating to Rs. 25,73,190/- had earlier been
paid against Extra Items 3/1, 2/1, 3/2 and 3/3 but were subsequently
recovered in the final bill. The impugned Award noted that their
execution was supported by the prior R.A. bills, rejected the absence
of departmental sanction as a sufficient reason to deny payment, and
restored the recovered amount. The claim for still higher rates was,
however, rejected for the same reason as under Head (B)(i), namely
that the Petitioner’s claimed rates were found to be excessive and
unrealistic. That distinction in the impugned Award is reasoned and
internally consistent.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 17 of 19
47. As regards B(iii), the Petitioner claimed an additional quantity
of 27,912.46 cubic metres for each of Extra Items 3/2 and 3/3, stating
that the work was executed between July and October 2010. The
learned Tribunal examined the R.A. Bills for that period and found
th th
that these quantities had not been claimed in the 7 to 12 R.A. bills,
th th
were not shown in the copies of the 12 and 13 R.A. bills relied upon
by the Petitioner, and were raised in the final bill only four days after
submission of the 13th R.A. Bill. The impugned Award also notices
th
that the 13 R.A. bill had been accepted without protest. On this
material, the learned Tribunal did not find sufficient basis to award
any amount under this head.
48. The Petitioner’s challenge to head (B)(iii) substantially invites
this Court to draw a different inference from the measurement books
and the sequence of billing. Those are matters of evidentiary
appreciation within the domain of the learned Tribunal. The reasons
given in the impugned Award are neither absurd nor irrational, and
therefore do not permit interference under Section 34.
49. For the reasons set out above, the findings of the learned
Tribunal on the deviated items and the extra item heads disclose a
reasoned assessment of the contractual provisions and the material
placed on record. No perversity, patent illegality, or disregard of a
binding contractual stipulation going to the root of Claim No.1 is
established. The challenge to Claim No.1 in entirety is, accordingly,
rejected.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:01.10.2026
20:36:27
O.M.P. (COMM) 328/2016 Page 18 of 19
50. For all the aforesaid reasons, the present petition is dismissed.
Pending application(s), if any, also stand disposed of.
OM PRAKASH SHUKLA, J
SEPTEMBER 22, 2026/pa