FRINDS ENGINEERING CO- OPERATIVE SOCIETY LTD. vs DIGHA SHANKARPUR DEVELOPMENT AUTHORITY

Court
Calcutta High Court

1

IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
COMMERCIAL APPELLATE DIVISION

Before:
The Hon’ble Justice Debangsu Basak
And
The Hon’ble Justice Aryak Dutt


AO-COM NO. 40 of 2026
Friends Engineering Co-operative Society Limited
Vs.
Digha Shankarpur Development Authority


For the Appellants : Mr. Debashis Kundu, Sr. Adv.
Mr. Indranil Nandi
Mr. D.P. Samanta
Mr. Sayak Konar

For the Respondents : Mr. Surojit Nath Mitra, Ld. A. G.
Mr. N.C. Bihani, Sr. Adv.
Mr. Soumya Mukherjee
Mr. Dibashis Basu, Ld. A.G.P.
Ms. Sneha Dutta
Mr. Purnendu Das

Hearing Concluded On : 23.09.2026
Judgment Delivered On : 06.10.2026



2


Aryak Dutt, J.:
1. This is an appeal under Section 37(1)(c) of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as
“the Act”) read with Section 13(1A) of the Commercial Courts Act,
2015 (hereinafter referred to as the “the Act of 2015”), directed
th
against the judgment and order dated 12 March, 2019, passed
by the learned District Judge, Purba Medinipur in J. Misc. Case
No. 23 of 2014. By that judgment, the learned District Judge
allowed the respondent's application under Section 34 of the Act
th
and set aside the award dated 14 February, 2014, made by the
learned Sole Arbitrator, the Hon'ble Justice Samaresh Banerjea
(Retd.).

2. The appellant, the claimant in the reference, seeks
restoration of the award. The respondent, Digha Shankarpur
Development Authority (hereinafter referred to as “DSDA”), on the
contrary supports the judgment.

3. The appeal was presented and registered in the Non-
Commercial Appellate Division. The disputes arise out of a
Memorandum of Understanding for construction work, entered

3

into pursuant to a tender process. The parties agreed before this
Court that the disputes between them fall within the meaning of
th
Section 2(1)(c)(vi) of the Act of 2015. By an order dated 13
August, 2026, in exercise of power under Section 15 of the Act of
2015, this Court directed the appeal to be transferred in the
Commercial Appellate Division. The appeal has accordingly been
transferred and numbered as AO-COM/40/2026 and has been
heard as a commercial appeal.

4. The appeal lies to this Division under Section 13(1A) of
the Act of 2015, the proviso to which preserves appeals against
orders specifically enumerated in Section 37 of the Act. An order
setting aside an Arbitral Award under Section 34 of the Act is one
such order. Registration of the appeal in the Commercial
Appellate Division does not enlarge or alter its scope. It remains
an appeal under Section 37(1)(c) of the Act and is to be decided
on the principles set out below.


5. DSDA is a statutory authority of the Government of
West Bengal. It proposed a two-storied market complex of about
690 stalls on some 7.50 acres of land at Sector B-7, New Digha
Township. The appellant, a co-operative society, submitted an

4

th
Expression of Interest on 24 September, 2004, which DSDA
th
accepted on 26 October, 2004.

6. A Memorandum of Understanding was executed on
th
25 November, 2004 (hereinafter referred to as “the MOU”).
Under it the appellant, as “Builder”, was to erect the complex “at
its own cost, expenses and charges” at an estimated cost of Rs.
5,26,90,708/-, within 24 months, under DSDA's technical
supervision. Clause 5 obliged the Builder to comply with the
building regulations of the concerned authorities and to
indemnify DSDA against breach of them. Clause 6 entitled the
Builder to levy the construction expenditure for each stall from
prospective lessees or buyers and the Builder will never claim the
construction cost for more than estimated cost. The per-stall
rates stipulated under Clause 6 were left blank. Clause 19
provided for an arbitration in the event of any dispute arising
between the parties.

th

7. A work order was issued on 29 November, 2004 and
possession of the site was made over. The appellant commenced
th
the foundation work on 12 January, 2005.

5

th
8. By a letter dated 24 March, 2005, DSDA directed
suspension of the work until further orders. It cited discrepancies
in the selection of the builder and the absence of permissions
from the Ministry of Environment, Government of India and the
st
West Bengal Pollution Control Board. By a letter dated 21 April,
th
2005, DSDA again directed the work to be stopped. On 20 April,
2005, DSDA resolved that MOUs with private contractors be
cancelled and construction be stopped “till fresh orders are
issued through completion of appropriate formalities and taking
nd
due care of CRZ norms”. By a letter dated 2 May, 2005, the
st
MOU was cancelled with effect from 21 April, 2005. By a Memo
th
dated 11 May, 2005, the work order was declared null and void.

th

9. On or about 26 May, 2005, DSDA published a fresh
notice inviting Expressions of Interest at the same site. That
notice was later withdrawn.

10. Joint measurements were taken in the presence of the
appellant's representative. The value of the unfinished work was
nd
assessed at Rs. 16,99,671/- on 22 August, 2006.

th
11. The appellant raised a formal claim on 9 April, 2008
th
and invoked arbitration on 28 April, 2008. On an application

6

th
under Section 11 of the Act, this Court by an order dated 5
February, 2010, appointed the Hon'ble Justice Samaresh
Banerjea (Retd.) as the Sole Arbitrator. The learned Arbitrator
th
entered upon reference on 11 March, 2010.

12. On the consent of the parties, and without prejudice to
the appellant's contentions, an interim award of Rs. 15,00,000/-
towards the cost of the unfinished construction was made. DSDA
had duly paid that sum.

13. On the joint prayer of the parties, the learned
Arbitrator appointed Sri Debal Roy, IFS, Member Secretary, West
Bengal State Coastal Zone Management Authority, as an expert.
The expert was to report whether the structure fell within the
prohibited zone under the CRZ Notification, 1991. The expert
th th
inspected the site on 4 and 5 September, 2010 using GPS
readings. He reported that the “disputed structure” lay outside
the 500-metre CRZ boundary. DSDA filed an objection to the
report through its Assistant Engineer, Sri Maicap, who was
examined and cross-examined.

th
14. By the award dated 14 February, 2014, the learned
Arbitrator held that the termination was illegal and arbitrary and

7

that DSDA was in breach. He reasoned that the letters of
suspension and cancellation gave vague reasons. DSDA produced
no resolution recording that the site fell within the CRZ
prohibited zone. DSDA itself invited fresh offers for the same site.
The expert's report placed the structure outside the 500-metre
line. He rejected the plea of supervening impossibility and held
that it was DSDA's duty to obtain the requisite clearances.

15. The award on the several claims is summarised below.
Claim Head Claimed (Rs.) Awarded (Rs.)
1 Value of work
32,50,000 15,00,000
executed
(interim) +
2,00,000 +
2,44,757
2 Establishment —
5,28,000 /
4,00,000 (on-site);
on-site / off-site
1,22,000
off-site of
1,00,000 held
payable in the
body but omitted
in the operative
part
3 Depreciation of
tools and plant
1,32,000 Nil
4
Loss of expected
74,16,000 51,85,243 in the
body; 51,08,000
profit on the
unexecuted
in the operative
portion
part
5 & 6 Mobilisation/mate
5,20,000/1,42,00
92,500
rials at site
0
7 Idle labour 1,43,500 1,43,500

8

8 Advances to
labour gangs
2,20,000 1,50,000
9
Advances to
16,50,000 10,00,000
suppliers
10
Interest on
blocked capital
4,06,000 Nil
11 Loss of goodwill 10,00,000 Nil
12 Interest 18% p.a. 10% p.a. from 9th
April, 2008 to the
award; 18% p.a. if
unpaid within 2
months
13 Costs As found due 2,00,000 + 10,000


16. The figure under Claim No. 4 was reached by taking
15% of the unexecuted value of the contract amounting to Rs.
74,16,000/- and deducting Rs. 22,30,757/-, being the aggregate
of the sums allowed under Claims 1, 2, 5, 7, 8 and 9.

17. DSDA challenged the award under Section 34 in J.
Misc. Case No. 23 of 2014. Among its grounds were that the
award conflicted with the public policy of India. The MOU was at
best a quasi-contract and the award ignored the evidence. The
grant of damages, costs and interest was bad and illegal.

18. By the impugned judgment, the learned District Judge
held that the expert's report bore no plot number, measurement,

9

photograph, high tide line or geo-referenced map and does not
reflect the actual state of affairs. He then relied on two memos of
th
the Urban Development Department dated 17 December, 2004
th
and 20 December, 2004, a letter of the Ministry of Environment
and Forests (No. J-17011/24/92-IA-II), and a CRZ map. He held
that the learned Arbitrator had failed to appreciate those
documents and that the award was “contrary to the law and
justice” and therefore is in conflict with the public policy of India,
and had set it aside.

19. Learned counsel appearing for the appellant
submitted that the court below acted as a Court of Appeal and
re-appreciated the expert's evidence. The expert was appointed at
DSDA's own suggestion. DSDA's objection was tested by the
examination of its witness. The findings that the report showed
no measurement or high tide line are contrary to the map
annexed to the report, which marks the CRZ boundary, the HTL,
the LTL and measurements sourced from Survey of India
toposheet No. 73 O/10.

20. It was urged that the two Urban Development
Department memos and the Ministry's letter were never placed

10

before the learned Arbitrator, were not pleaded in the Section 34
application, and were handed up as photocopies at the hearing.
The Court below could not set aside the award for failing to
appreciate documents that were never before the Tribunal.

21. It was contended that the impugned judgment gives no

reason as to why the award offends public policy. “Contrary to
law and justice” is not a ground under Section 34. The Court
below never addressed the core issues. The legality of the
termination and the several heads of claim.

22. On merits, it was argued that the burden of obtaining
permissions lay on DSDA as owner. A want of prior permission is
at most a curable irregularity. DSDA's fresh invitation for the
same site belied its plea of impossibility and that DSDA's new
case in its written notes before the Tribunal was rightly shut out.

23. On loss of profit, reliance was placed on the case of
A.T. Brij Paul Singh v. State of Gujarat , reported in (1984) 4
SCC 59 , and on the decision of a Co-ordinate Bench of this Court
in B.B.M. Enterprise v. State of West Bengal being FMA 1409
of 2022 with FMA 1419 of 2022 , for the proposition that 15%

11

of the value of the unexecuted work is a reasonable measure of
lost profit in a works contract.

24. Learned counsel appearing for DSDA submitted that
the Digha–Shankarpur belt is governed by the CRZ regime and
that no construction is permitted within 500 metres of the High
Tide Line. Sector B-7 was, by the Ministry's letter, incorporated
in the Coastal Zone Management Plan of West Bengal and
categorised as CRZ-II. The Urban Development Department had
directed DSDA to stop construction under MOUs at eight
locations including Sector B-7, and DSDA was bound to comply.

25. It was submitted that the MOU was not a complete
document, since the price of the stalls was never settled. It was
inoperative, or at best voidable and in the nature of a quasi-
contract. DSDA could therefore be liable at most for the value of
the work done, and not for loss of profit or other compensation.

26. It was contended that the appellant participated in the
joint measurement without protest and thereby accepted the
stoppage and the avoidance of the MOU.

12

27. It was argued that the award rested on an incomplete
inspection report and overlooked vital documents, including a
CRZ map that was on the arbitral record. Though re-appreciation
of evidence is not permitted under Section 34, an award that is
contrary to substantive law, unreasoned, or ignores vital material
is perverse and in conflict with public policy.

28. Reliance in this regard was placed on Associate
Builders v. Delhi Development Authority , reported in (2015) 3
SCC 49 ; Ssangyong Engineering & Construction Co. Ltd. v.
National Highways Authority of India , reported in (2019) 15
SCC 131 and Delhi Airport Metro Express (P) Ltd. v. Delhi
Metro Rail Corporation Ltd. , reported in (2022) 1 SCC 131 .

29. The application under Section 34 was filed in 2014,
rd
before 23 October, 2015. The challenge must therefore be tested
under Section 34 as it then stood, read with Oil and Natural
Gas Corporation Ltd. v. Saw Pipes Ltd., reported in (2003) 5
SCC 705 , Oil and Natural Gas Corporation Ltd. v. Western
Geco International Ltd. , reported in (2014) 9 SCC 263 and
Associate Builders v. Delhi Development Authority , reported
in (2015) 3 SCC 49 .

13


30. Under that regime, an award conflicts with the public
policy of India if it contravenes the fundamental policy of Indian
law, the interest of India, justice or morality, or if it is patently
illegal. Patent illegality includes contravention of the substantive
law of India, of the Act itself, and of Section 28(3), which then
required the tribunal to decide in accordance with the terms of
the contract. A finding based on no evidence, one that ignores
vital evidence, or one that takes irrelevant matter into account, is
perverse as held in the case of Associate Builders (supra) . An
award must also state reasons that are proper, intelligible and
adequate as held in the case of Dyna Technologies (P) Ltd. v.
Crompton Greaves Ltd., reported in (2019) 20 SCC 1 .

31. The Court under Section 34 does not sit in appeal. The
arbitrator is the master of the quantity and quality of evidence,
and a possible view on facts is not to be disturbed. The Appellate
Court under Section 37 is confined to the same grounds, reliance
in this regard is placed on MMTC Ltd. v. Vedanta Ltd., reported
in (2019) 4 SCC 163 .

32. The judgment rests on two findings. The expert's
report does not reflect the actual state of affairs. The learned

14

Arbitrator failed to appreciate the Urban Development
Department memos, the Ministry's letter and the CRZ map.

33. The weight to be attached to the expert's report was a
matter for the Tribunal. The expert was appointed under Section
26 of the Act, on the joint prayer of the parties and at DSDA's
suggestion. He inspected the site in the presence of both parties.
DSDA's objection was considered, and its only witness was
examined and cross-examined. The Tribunal found that the
witness had no expertise to dispute the method used, that he
raised no objection at the site, and that the map he relied on was
admittedly not prepared by the Geological Survey of India. That
was a possible view. The Court below substituted its own
assessment of the report. That is re-appreciation of evidence,
which Section 34 does not permit.

34. The Court below also faulted the Tribunal for not
appreciating documents that, on the appellant's unrebutted
submission, were never part of the arbitral record and were not
pleaded in the Section 34 application. DSDA's written notes
assert only that the CRZ map was produced before the Tribunal.

15

An application under Section 34 is ordinarily decided on the
record before the arbitrator.

35. Having so held, the Court below concluded that the
award was “contrary to the law and justice” and therefore is
opposed to public policy. The judgment does not identify which
head of public policy was offended, which provision of law was
contravened, or which term of the contract was disregarded.
“Contrary to law and justice” is not a ground under Section 34.
Nor did the Court below examine the grounds directed at the
grant of damages, interest and costs.

th
36. We therefore hold that the judgment dated 12 March,
2019 cannot be sustained.

37. The dispute dates from 2005, the award from 2014
and this appeal from 2019. The grounds under Section 34 are on
record. A respondent in appeal may support the result on a
ground urged below that the lower court did not decide. An
Appeal Court under Section 37 can therefore examine the
grounds on the arbitral record.

16

38. We do not disturb the Tribunal's finding of fact on
evidence being a plausible view. Our examination is confined to
grounds that go to the legal basis of liability and to the
quantification of the claims.

39. DSDA's case, taken in its defence was that the MOU
was incomplete and at best a quasi-contract. The MOU required
the Builder to build “at its own cost” and to recover its
expenditure from prospective lessees of stalls at rates specified in
Clause 6. Those rates were left blank.

40. The award does not examine this at all. It treats the
MOU throughout as a conventional works contract with a price of
Rs. 5,26,90,708/- payable by DSDA, and awards compensation
on that footing.

41. The award does not decide the dispute in accordance
with the terms of the contract. An award that is silent on such a
question is not reasoned within Dyna Technologies (supra),
and is patently illegal for disregarding of Section 28(3) as it then
stood.

17

42. The largest component of the award is Rs. 51,85,243/-
towards loss of expected profit. The Tribunal applied 15% of the
unexecuted value on the strength of A.T. Brij Paul Singh
(supra). It accepted the calculation because DSDA had not
challenged the arithmetic.

43. In the case of A.T. Brij Paul Singh (supra), it does
not lay down an inflexible rule that 15% of the unexecuted value
is payable whenever a works contract is terminated. What is
reasonable depends on the facts of each case, as that judgment
itself says. Damages under Section 73 of the Contract Act, 1872,
compensate loss that naturally arises from the breach and they
are not a penalty for it, reference is made through the case of
Kailash Nath Associates v. Delhi Development Authority,
reported in (2015) 4 SCC 136 . A claim for loss of profit must rest
on material showing that profit would in fact have been earned as
referred in the case of Unibros v. All India Radio , reported in
2023 SCC OnLine SC 1366 and Batliboi Environmental
Engineers Ltd. v. Hindustan Petroleum Corporation Ltd . ,
reported in (2024) 2 SCC 375 .

18

44. Here there was no such material. There was no
evidence of the rates, of demand for the stalls, or of the margin
the appellant would have earned. The Tribunal did not find that
the unexecuted work could lawfully have been carried out.
Expectation damages presuppose that performance would have
been completed. On this record, the award of loss of profit rests
on no evidence.

45. A.T. Brij Paul Singh (supra) and B.B.M. Enterprise
(supra) was concerned with works contracts in which the
employer paid the contract price. They do not assist the appellant
on an arrangement of this kind.

46. The quantification is also self-contradictory. The body
of the award arrives at Rs. 51,85,243/-; the operative part
awards a sum of Rs. 51,08,000/-. The figure was reached by
deducting from notional profit the sums awarded for the value of
work done, establishment expenses, mobilisation, idle labour and
advances. The deduction has no rational basis.

47. Under Claim No. 9, the appellant's witness admitted
that he could not show what quantity of materials was received
against the alleged advances. The Tribunal nonetheless

19

“reasonably presumed” that the unrealised advances were “not
less than Rs. 10 lacs” and awarded that sum. Under Claim No. 8,
no cash book was produced, and Rs. 1,50,000/- was again
allowed on presumption. It does not permit a Tribunal to
presume the existence of a loss for which there is no evidence.

48.
The Tribunal held that the appellant itself contributed
to the eight-month delay in dismantling its establishment, and
that DSDA's share was of 2 (two) months. It then awarded Rs.
4,00,000/- of the Rs. 5,28,000/- claimed, about three-quarters of
the claim, when 2 (two) months of 8 (eight) would yield Rs.
1,32,000/-. The body of the award also held Rs. 1,00,000/-
payable for off-site expenses, but the operative part omits it. An
award whose operative directions do not match its own findings
is not intelligible.

49. The awards of interest and costs are consequential on
the principal sums.

50. The award is patently illegal and perverse.

51. The award is not separable. Excising any of them
would require recomputing the others. A re-quantification of the

20

award on merits, by this Court cannot be undertaken. The award
must therefore be set aside in its entirety.

th
52. The judgment and order dated 12 March, 2019,
passed by the learned District Judge, Purba Medinipur in J.
th
Misc. Case No. 23 of 2014 is set aside. The award dated 14
February, 2014 made by the learned Sole Arbitrator is set aside.
The interim award for Rs. 15,00,000/-, made on consent of the
parties and since paid, was not the subject of the challenge
under Section 34 and is not affected by this judgment. The
appeal, AO-COM/40/2026 , is thus disposed of accordingly.

53. Connected applications, if any, stand disposed of.

54. There shall be no order as to costs.

(ARYAK DUTT, J.)
55. I Agree.

(DEBANGSU BASAK, J.)