Spvr Projects Private Ltd vs Energy Efficiency Services Limited (Eesl)

Court
Delhi High Court

$~25
* IN THE HIGH COURT OF DELHI AT NEW DELHI

% Date of Decision : 06.07.2026

+ W.P.(C) 8757/2026

SPVR PROJECTS PRIVATE LTD .....Petitioner
Through: Mr. Parag P. Tripathi and Mr. Ravi
Parkash, Sr. Advs. with Ms. Bani
Dikshit, Mr Uddhav Khanna, Mr
Dhruva Vig, Mr Raj Aryan Singh,
Ms. Astu Khandelwal and Mr.
Sarthak Segal, Advs.

versus

ENERGY EFFICIENCY SERVICES LIMITED (EESL)
.....Respondent
Through: Mr. Samdarshi Sanjay, Ms. Monika
Sharma and Mr. Ashish Kumar
Sharma, Advs.

CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA

MANMEET PRITAM SINGH ARORA, J. ( ORAL )

CM APPL. 41121-41122/2026 (Exemptions)
1. Exemptions are allowed, subject to all just exceptions.
2. The applications stand disposed of.
W.P.(C) 8757/2026 & CM APPL. 41120/2026
3. The present writ has been filed under Article 226 of the Constitution
of India with the following prayers:


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 1 of 10

“In the light of the aforesaid facts and circumstances, the Petitioner,
therefore, most respectfully prays that this Hon’ble Court may be
pleased to:
a. Issue an appropriate writ, order or direction in the nature of
certiorari or any other appropriate writ quashing and setting
aside the Notice Inviting Tender No. EESL/06/2026-
27/SL/AP ULBS-CDMA/OTE/262704001 dated 16.04.2026
issued by the Respondent, along with all amendments thereto,
being arbitrary, unreasonable, capricious and lacking
application of mind, and in contravention of the spirit of
Articles 14 and 19(1)(g) of the Constitution; and

b. Issue a writ, order or direction in the nature of a writ of
Mandamus or any other appropriate writ directing the
Respondent to undertake the procurement of the project (as
defined hereunder) through a fair, transparent and competitive
tender process in accordance with law.

c. Pass such other or further orders as this Hon’ble Court may
deem fit and proper in the circumstance of the case”
(Emphasis supplied)

4. The Petitioner, SPVR Projects Private Limited, is stated to be engaged
1
in the business of LED streetlighting infrastructure, smart lighting systems,
and operation and maintenance services.
5. The Respondent, Energy Efficiency Services Limited [‘EESL’], is
stated to be the tender-issuing authority which issued the NIT No.
EESL/06/2026-27/SL/AP ULBs-CDMA/OTE/262704001 [‘Impugned
Tender’] for replacement and Operation and Management of 7,41,366 street
lights , across the three [3] DISCOM-wise packages in the Urban Local
Bodies [‘ULBs’] namely Package-1 (APEPDCL), Package-2 (APSPDCL)
and Package-3 (APCPDCL), for a contract period of seven [7] years,

1
Light Emitting Diode


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 2 of 10

extendable by a period of two [2] years [‘Project’], fixing the base rate at Rs.
133 per LED light per month, exclusive of GST [‘approximately Rs.157
inclusive of GST’]. The bidders were permitted to quote only a downward
discount from the said base price of Rs. 133. It is stated that by Amendment
No. 4 dated 26.05.2026, Respondent clarified that bids above the base price
of Rs. 133 would be treated as non-responsive.

6. It is stated that the bid submission deadline for Package-3 has been
extended to 07.07.2026.
7. Mr. Tripathi, learned senior counsel for the Petitioner states that the
base rate of Rs. 133 is arbitrary and commercially unworkable as is evident
from the record of this tender.
7.1. In this regard, he submits that on 14.11.2025, the Government of
Andhra Pradesh and Respondent/EESL executed a Memorandum of
Understanding [‘Summit MoU’] at the CII Partnership Summit,
Visakhapatnam. The Summit MoU was only an expression of investment
intent and did not create procurement rights, contractual obligations, fixed
rates, or any procurement process.
7.2. He states that on 13.01.2026, Andhra Pradesh State Energy Efficiency
Development Corporation Limited [‘APSEEDCO’] issued a Notice inviting
Expression of Interest-bearing Bid No. APSEEDCO/AP Streetlights
Project/e-03/2025 [‘EOI’] for replacement as well as Operation and
Maintenance of around 10.20 lakh LED street lights, with ILMS-based
smart LED systems across Andhra Pradesh ULBs. The said EOI expressly
stated that it was non-binding, intended for market assessment and
benchmarking, and that the subsequent procurement was to proceed through
Open Competitive Bidding.


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 3 of 10

7.3. He states that significantly, the Respondent/EESL did not participate
in the EOI process.
7.4. He states that, however, in pursuance to the aforesaid EOI, it was
Respondent/EESL which conducted a vendor meeting on 26.02.2026 and
circulated budgetary enquiries to around 35 prospective bidders. Seven [7]
technically qualified agencies quoted indicative rates ranging from Rs. 184
to Rs. 610 per light per month. The seven [7] indicative rates disclosed by
EESL resulted in an average rate of Rs. 215.81 per light per month,
exclusive of GST.
7.5. He states that on 16.03.2026, the Government of Andhra Pradesh
passed a Memo approving entering into an MoU with Respondent/EESL for
ILMS-based enhanced energy-efficient LED street lighting at Rs. 175 per
light per month, inclusive of GST, across ULBs under the Commissioner &
Director, Municipal Administration, Andhra Pradesh [‘CDMA’].
7.6. He states that the Memo relied on the Summit MoU as justification
for bypassing competitive procurement for a public contract valued at
approximately Rs. 924 crores, and the competitive RFP contemplated under
the EOI was never issued.
7.7. He states that on 17.03.2026, Respondent/EESL wrote to CDMA
seeking reconsideration, stating that the price of Rs. 175 inclusive of GST
was not workable and requesting revision to Rs. 215 per light per month,
excluding GST. However, CDMA, without reconsidering the said request of
Respondent/EESL issued the Award Letter dated 02.04.2026, which was
accepted by the Respondent/EESL vide letter dated 06.04.2026. In its
acceptance letter Respondent/EESL conveyed its acceptance of the rate of
Rs. 175 per light per month inclusive of GST.


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 4 of 10

7.8. He states that Respondent/EESL thereafter issued the Impugned
Tender on 16.04.2026 wherein bidders were permitted to quote only a
downward discount from Rs. 133 per light per month exclusive of GST.
7.9. He states that the Petitioner challenges the said condition in the
Impugned Tender as arbitrary, unviable and anti-competitive because
Respondent/EESL itself found Rs. 175 inclusive of GST unworkable, yet
fixed an even lower downstream rate of Rs. 133 exclusive of GST, while
retaining a margin of approximately Rs. 95 crores for a limited facilitation
role.
8. Mr. Samdarshi Sanjay, learned counsel for the Respondent appears on
advance service and states that he has two preliminary objections with
respect to the maintainability of the present writ.
8.1. He states that the entire contract pertains to rendering of services in
the State of Andhra Pradesh and, therefore, no cause of action has arisen
within the jurisdiction of this Court.
8.2. He further states that Clause 5.1 of the General Conditions of Contract
[‘GCC’] referred to in the writ petition for invoking the jurisdiction of this
Court is inapplicable as the GCC will come into existence only after the
contract is awarded to the successful bidder. He states that, since in the facts
of the present case, the Petitioner is not a successful bidder, reliance placed
on the said clause is inadmissible.
8.3. He states that the Respondent’s corporate office is in Noida and the
bid was issued by the said office and not from the office at Delhi.
8.4. He states that, since in the facts of the present case, the Petitioner is
not a bidder, no writ petition can be maintainable at the instance of a party
which has not participated in the bidding process.


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 5 of 10

8.5. He submits that the contract for Package-1 and Package-2 of the
Impugned Bid has already been awarded to the successful bidder at Rs. 133
per light per month exclusive of GST. He states that there are several
bidders who are willing to submit bids at Rs. 133 per light per month
exclusive of GST, and therefore, the plea in the writ petition that the said
rate is not commercially workable is incorrect.

9. In response, learned senior counsel for the Petitioner states that since
the Respondent’s registered office is in Delhi, the writ can be maintained at
Delhi.
9.1. He also states that although the Petitioner has neither participated in
the pre-bid meeting nor submitted bids for Package-1 or Package-2, the
same does not disentitle/preclude the Petitioner from maintaining the present
petition, particularly since the last date for submission of bids for Package 3
is 07.07.2026.
10. This Court has heard the learned counsel for the parties and perused
the record.
11. The Impugned Tender invites bid for Package-1, Package-2 and
Package-3. Respondent has stated that Package-1 and Package-2 have
already been awarded to the successful bidder and it shows that the price of
Rs. 133 per light per unit is feasible. Bids for Package-3 are scheduled to be
submitted on 07.07.2026.
12. To a query from the Court, learned senior counsel for the Petitioner
submits that the Petitioner has not made any representation to the
Respondent with respect to the grounds now raised in this petition for
challenging the Impugned Tender. He also clarifies that the Petitioner did
not participate at the pre-bid meeting held on 23.04.2026. He also confirms


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 6 of 10

that Petitioner did not submit a bid for Package-1 and Package-2. He states
that the Petitioner, however, relies upon the queries raised by other intending
bidders at the said meeting questioning the commercial viability of the base
price of Rs. 133.
13. We note that the submission of the Respondent that the Petitioner has
not participated in the bidding process, till date, is admitted. The Impugned
Tender was published on 16.04.2026. The Petitioner neither participated in
the pre-bid meeting on 23.04.2026 or for bids of Package-1 and Package-2
under the Impugned Tender nor made any representation to the Respondent
with respect to the grounds of challenge now raised in the present petition
for interdicting the tender process. The filing of the present writ petition on
the eve of the bid closing for Package-3 raises question over the bonafide of
the Petitioner, which seeks to interdict the tender process for Package-3.
14. In response, learned senior counsel for the Petitioner states that the
Petitioner does not wish to interdict the tender process for Package-3,
however, it would be useful if the Respondent discloses to the Court its basis
for fixing the base price of Rs. 133 exclusive of GST, when the record [i.e.,
letter dated 17.03.2026] shows that the Respondent itself was of the opinion
that price of Rs. 175 inclusive of GST is unfeasible.
15. We are unable to accept the submission of the Petitioner. The present
writ petition cannot be converted into a roving enquiry at the behest of this
Petitioner to decide the reasonableness and feasibility of the base price of
Rs. 133. The subject matter of the writ petition is a challenge to the
Impugned Tender. We, however, of the considered opinion that the
Petitioner cannot maintain this petition, it has no locus, as it has not
participated in the bidding process and the filing of the present petition on


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 7 of 10

the eve of the bid submissions date of Package-3 does not appear to be bona
fide. A writ petition seeking to interdict the tender process cannot be
maintained at the behest of a non-bidder and in this regard, we rely upon the
2
judgment of this Bench in Gaurav Enterprises v. GTB Hospital & Anr.
wherein it has been held as under:
“ 11. The law is no longer res integra as regards the issue of locus in
the tender matters. It is only entities that have participated in the
bidding process who can lay a challenge to the tender. The petitioner,
before us, has failed to show any earnestness to participate in the tender
process. At this juncture, we find it apposite to refer to the dicta of the
Supreme Court in National Highways Authority of India v. Gwalior-
3
Jhansi Expressway Limited . The relevant part of the judgment reads
as follows: -

“20. While considering the relief claimed by the respondent
(claimant), the same should have been tested on the touchstone of
the principle governing the tender process, especially when the
validity of the tender document has not been put in issue or
challenged before any competent forum. Going by the terms and
conditions in the tender documents, as already alluded to in para
10 above, there is no tittle of doubt that the right of the claimant
(respondent) to match the bid of L-1 or to exercise ROFR would
come into play only if the respondent was to participate in the
tender process pursuant to the notice inviting tenders from the
interested parties. The objective of tender process is not only to
adhere to a transparent mechanism but to encourage competition
and give equal opportunity to all tenderers with the end result of
getting a fair offer or value for money. The plain wording of the
eligibility clause in the tender documents and the incidental
stipulations make it explicit that the respondent was required to
participate in the tender process by submitting its sealed bid
(technical and financial). The fact that a deeming clause has been
provided in the tender document that if the respondent was to
participate in the bidding process, it shall be deemed to fulfil all
the requirements of the tender Clauses 3 to 6 of RFP, being the
existing concessionaire of the project, does not exempt the
respondent from participating in the tender process; rather the

2
2026:DHC:1592-DB



Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 8 of 10

tenor of the terms of the documents made it obligatory for the
respondent to participate in the tender process to be considered as
a responsive bidder, along with others. Having failed to
participate in the tender process and, more so, despite the
express terms in the tender documents, validity whereof has
not been challenged, the respondent cannot be heard to
contend that it had acquired any right whatsoever. Only the
entities who participate in the tender process pursuant to a
tender notice can be allowed to make grievances about the
non-fulfilment or breach of any of the terms and conditions of
the tender documents concerned. The respondent who chose
to stay away from the tender process, cannot be heard to
whittle down, in any manner, the rights of the eligible bidders
who had participated in the tender process on the basis of the
written and express terms and conditions. At the culmination
of the tender process, if the respondent had not participated,
in law, the offer submitted by the eligible bidders is required
to be considered on the basis of the stated terms and
conditions.
Thus, if the claim of the respondent was to be strictly
adjudged on the basis of the terms and conditions specified in
the subject tender document, the respondent has no case
whatsoever .”
[emphasis supplied]
12. Furthermore, a Division Bench of this Court, while deciding on a
similar issue, has opined that a petitioner who failed to participate in the
tender due to a certain tender condition does not have any locus to
challenge the same at a belated stage [ Re: Brijesh Kumar v. Union of
India ].
Accordingly, in these facts and in view of the established law, this
Court finds that the objection raised by respondent no. 1 with respect to the
lack of locus standi of the petitioner to maintain this writ petition has
merit.”

[The bold and underline in the quote is as per the original text of the cited
judgement]

16. For the aforesaid reasons, we do not find any ground to entertain this
writ petition, which appears to be intended to interdict the tender process for
Package-3 and the same is dismissed for lack of locus standi.


Signature Not Verified
Signed By:MOHIT
Signing
Date:10.07.2026 17:31
W.P.(C) 8757/2026 Page 9 of 10

17. The issue of territorial jurisdiction is left open. We, also clarify that
we have not examined the merits of the challenge laid to the base price of
Rs. 133 per light per month in these proceedings.
18. With the aforesaid directions, the petition is dismissed. Pending
applications are disposed of.

MANMEET PRITAM SINGH ARORA, J



V. KAMESWAR RAO, J

JULY 6, 2026/ rhc/msh/AJ