Sri Debashish Das, vs The State of Tripura, represented by the Secretary-cum- Commissioner, Public Works Department
- Court
- Tripura High Court
- Case type
- Commercial Appeal
- Decided on
- 01-04-2026
<div> <i>Page </i> <b><i>1</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> <b>HIGH COURT OF TRIPURA </b><br /> <b>AGARTALA </b><br /> <b> </b><br /> <b> </b> <b> </b><br /> <b>Commercial Appeal No.03 of 2024 </b><br /> <b> </b><br /> <b> </b><br /> Sri Debashish Das, son of Lt. Nirmal Bikash Das, resident of village- <br /> Joynagar, Middle Road, P.O.-Agartala, P.S.-West Agartala, Sub-Division- <br /> Sadar, District-West Tripura, PIN-799002, Age-58 years. <br /> <i>………</i> Appellant(s). <i> </i><br /> V E R S U S <br /> 1. The State of Tripura, represented by the Secretary-cum-Commissioner, <br /> Public Works Department(R & B), New Secretariat Building, P.O.-Kunjaban, <br /> Agartala, West Tripura. <br /> <br /> 2. The State of Tripura, represented by the Executive Engineer, PWD(R & B), <br /> Kailashahar Division, Unokoti Tripura. <br /> <i>………</i> Respondent(s). <br /> <br /> <br /> For Appellant(s) : Mr. Somik Deb, Sr. Advocate, <br /> Mr. Haradhan Sarkar, Advocate, <br /> Mr. Jishan Samed, Advocate, <br /> Ms. Adwitiya Chakraborty, Advocate. <br /> <br /> <br /> <br /> <br /> For Respondent(s) : Mr. Kohinoor Narayan Bhattacharyya, G.A. <br /> <b> </b> <b> </b><br /> <b>HON’BLE THE CHIEF JUSTICE MR. M.S. RAMACHANDRA RAO </b><br /> <b>HON’BLE MR. JUSTICE BISWAJIT PALIT </b><br /> <b> </b><br /> <br /> Date of hearing : <b>26.02.2026</b> . <br /> <br /> Date of judgment : <b>01.04.2026.</b> <br /> <br /> Whether fit for reporting : <b>YES</b> . <br /> <br /> <br /> <b> </b><br /> <b>JUDGMENT & ORDER</b><br /> <b><i>(M.S. Ramachandra Rao, C.J.) </i></b><br /> <b> </b><br /> <b> </b><br /> <b> </b> <b> </b> Heard Mr. Somik Deb, learned Senior counsel assisted by Mr. <br /> Haradhan Sarkar, counsel for the appellant, and Sri Kohinoor N <br /> <br /> Bhattacharyya, Government Advocate for the respondent.<br /> 2. This appeal has been filed under Section 13(1A) of the <br /> Commercial Courts Act, 2015 read with Section 37(1)(c) of the Arbitration <br /> and Conciliation Act, 1996 ( for short ‘the Act’) challenging the judgment <br /><br /> <i>Page </i> <b><i>2</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> dt.31.08.2024 of the Commercial Court, Unakoti Judicial District, Kailashahar <br /> in case No.T.S.(ARB) 04 of 2020. <br /> <b>The Background facts: </b><br /> 3. A Notice Inviting Tender dt.27.12.2013 was issued by the Public <br /> Works Department of the Government of Tripura for executing the work of <br /> " <i>Construction of Kailashahar District Jail at Kailashahar, Unakoti District</i> ". <br /> 4. The appellant participated in the said tender and became the <br /> successful bidder, and in 2014, an agreement was executed between the <br /> appellant and the respondents for execution of the said works contract. <br /> 5. On 28.05.2019, disputes arose between the parties in connection <br /> with the said agreement. The appellant then made a request to respondents for <br /> appointment of an Arbitrator, and a Sole Arbitrator was appointed. <br /> 6. On 18.06.2019 the Sole Arbitrator entered into the reference, and <br /> registered it as ARB/SRB/2019(2). <br /> 7. The appellant then filed his claim statement and the respondents <br /> also filed their counter statement/written objection. <br /> 8. In 2019-2020, on various dates, proceedings took place before the <br /> Sole Arbitrator in connection with the above case. <br /> <b>The award of the arbitrator: </b><br /> 9. On 17.06.2020, by an elaborate Arbitral Award, the Arbitrator <br /> decided the dispute partly in favour of the appellant, i.e. claims under Head <br /> Nos.1, 5, 6, 6(a), partly under Head Nos.7 and 7(a), 8, partly under Head <br /> Nos.9, 11 and 12 were allowed in favour of the appellant, and claims under <br /> the other remaining Heads were held against the appellant. <br /> <br /> <br /><br /> <i>Page </i> <b><i>3</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> <b>The application under Section 34 of the Act by the respondents: </b><br /> 10. The respondents, on 24.09.2020, filed an application under <br /> Section 34 of the Arbitration and Conciliation Act, 1996 before the District <br /> Judge, Unakoti Judicial District, Kailashahar (for short ‘the Commercial <br /> Court’), which was numbered as Title Suit 04 (Arbitration) of 2020 <br /> challenging the Arbitral Award dt.17.06.2020. <br /> 11. The appellant on 11.11.2021 filed his objection thereto refuting <br /> the pleas advanced by the respondents. <br /> <b>The judgment dt.16.3.2022 of the Commercial Court in the Section 34 petition: </b><br /> 12. The Commercial Court on 16.03.2022 dismissed T.S. <br /> 04(Arbitration) of 2020 filed by the respondents. <br /> <b>Arbitration Appeal No.07 of 2022 filed by respondents in this Court: </b><br /> 13. Challenging the same, the respondents filed an appeal, being <br /> Arbitration Appeal No.07 of 2022 under Section 37(1)(c) of the Arbitration <br /> and Conciliation Act, 1996 before this Court. <br /> <b>The Judgment dt.31.1.2024 by this court in</b> <b>Arbitration Appeal No.07 of 2022</b> <b>and </b><br /> <b>remand of the matter back to the Commercial Court: </b><br /> <b> </b><br /> 14. On 31.01.2024, the said Arbitration Appeal No.07 of 2022 was <br /> allowed by the Division Bench of this Court and the matter was remitted to the <br /> Commercial Court with the observation that the Commercial Court had not <br /> made any reference to the grounds of challenge relating to price escalation and <br /> applicability of Clause 44 and 44.1 of the agreement; that the Commercial <br /> Court as well as the Sole Arbitrator had failed to consider whether the <br /> appellant herein was entitled to get payment relating to issue No.2 as the <br /> payment relating to issue No.2 has already been paid to him. It was further <br /> observed that there was complete non-consideration of several grounds urged <br /><br /> <i>Page </i> <b><i>4</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> by the respondents herein in the application under Section 34 filed by them in <br /> the Commercial Court. <br /> 15. The Division Bench also stated that the Commercial Court had <br /> failed to test the correctness of the award within the contours of the grounds <br /> available under Section 34(2) and 34(2-A) of the Act; and that it had without <br /> referring to the relevant Clauses of the agreement and without consideration of <br /> any of the grounds raised under Section 34 of the Act, passed judgment; and <br /> so it makes the judgment of the Commercial Court an unreasoned one and so <br /> unsustainable. <br /> 16. The Division Bench then stated as under: <br /> <i>"</i> <b><i>12.</i></b> <i> In view of the discussions made here-in-above, we </i><br /> <i>are of the view that the matter be remitted to the learned </i><br /> <i>District Court, Unakoti District to decide the grounds urged by </i><br /> <i>the appellant and also as to the applicability of Clause 44 of the </i><br /> <i>agreement and as regards to the expected loss of profit or </i><br /> <i>adjustment in accordance with law within a reasonable time </i><br /> <i>preferably 12(twelve) weeks from the date of receipt of the copy </i><br /> <i>of this order since the Arbitration proceeding was initiated way </i><br /> <i>back in the year 2019. Since the matter is remanded to the </i><br /> <i>learned Commercial Court only on the grounds that the </i><br /> <i>impugned Judgment shows complete non application of mind </i><br /> <i>and non consideration of the grounds urged in the Section 34 </i><br /> <i>application, we have consciously refrained from observing any </i><br /> <i>opinion on the grounds urged by the parties in the question of </i><br /> <i>sustainability of the Award rewarded by the Arbitrator at this </i><br /> <i>stage. </i><br /> <i> </i> <i>The appeal is disposed of in the manner and to the extent as </i><br /> <i>indicated above." </i><br /> <i> </i><br /> 17. Thus, the matter was remitted back to the Commercial Court for <br /> reconsideration as indicated above. <br /><br /> <i>Page </i> <b><i>5</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> <b>The judgment dt.31.8.2024 of the Commercial Court after remand by High Court: </b><br /> 18. Thereafter, the learned Commercial Court again heard the matter <br /> and by judgment dt.31.08.2024 set aside the Arbitral Award in its entirety. <br /> <b>The instant Arbitration Appeal: </b><br /> 19. Challenging the same, appellant has preferred the instant appeal. <b> </b><br /> <b>Scope of interference with an Arbitral award under Section 34 and by the Appellate </b><br /> <b>Court under Section 37 of the Act with a judgment under Section 34 of the Act: </b><br /> <br /> 20. Before we consider the Appeal, we shall briefly discuss the legal <br /> position regarding scope of interference by the Court (Commercial Court here) <br /> with an Arbitral award under Section 34 of the Act and by the Appellate Court <br /> under Section 37 of the Act while considering a judgment under Section 34 of <br /> the Act. <br /> 21. The legal position on this aspect has been discussed by the <br /> <b><i>1</i></b><br /> Supreme Court in <b><i>Somdatt Builders-NCC-NEC (JV) v. NHAI</i></b> <b><i>.</i></b> <br /> In that case, the Supreme Court relied on its previous judgments <br /> and emphasized that as far as Section 34 is concerned, the position is well <br /> settled that: <br /> (a) the Court does not sit in appeal over an arbitral award and <br /> may interfere on merits only on the limited ground provided under Section <br /> 34(2)(b)(ii) i.e. if the award is against the public policy of India. <br /> (b) Even then, the interference would not entail a review on <br /> the merits of the dispute but would be limited to situations where the findings <br /> of the arbitrator are arbitrary, capricious or perverse or when the conscience of <br /> the Court is shocked or when the illegality is not trivial but goes to the root of <br /> the matter. <br /> <br /> 1<br /> (2025) 6 SCC 757, at page 778 <b> </b> <br /><br /> <i>Page </i> <b><i>6</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> (c) An arbitral award may not be interfered with if the view <br /> taken by the arbitrator is a possible view based on facts. <br /> (d) As far as interference with an order made under Section 34 <br /> by the Court under Section 37 is concerned, it has been held that such <br /> interference under Section 37 cannot travel beyond the restrictions laid down <br /> under Section 34. In other words, the Court cannot undertake an independent <br /> assessment of the merits of the award and must only ascertain that the exercise <br /> of power by the Court under Section 34 has not exceeded the scope of the <br /> <b><i>2</i></b><br /> provision. ( <b><i>Reliance Infrastructure Ltd v. State of Goa</i></b> <b><i>)</i></b> <br /> (e) The scope of interference under Section 37 is all the more <br /> circumscribed keeping in view the limited scope of interference with an <br /> arbitral award under Section 34 of the 1996 Act. As it is, the jurisdiction <br /> conferred on courts under Section 34 of the 1996 Act is fairly narrow. <br /> Therefore, when it comes to scope of an appeal under Section 37 of the 1996 <br /> Act, jurisdiction of the appellate court in examining an order passed under <br /> Section 34, either setting aside or refusing to set aside an arbitral award, is all <br /> 3<br /> the more circumscribed. ( <b><i>UHL Power Co. Ltd v. State of HP</i></b> <b><i>)</i></b> <br /> 22. It also relied on its judgment in <b><i>Ssangyong Engg. & </i></b><br /> <b><i>4</i></b><br /> <b><i>Construction v. NHAI</i></b> <b><i> </i></b> to reiterate what public policy of India is and <br /> explained that it means the fundamental policy of Indian law. Violation of <br /> Indian statutes linked to public policy or public interest and disregarding <br /> orders of superior courts in India would be regarded as being contrary to the <br /> fundamental policy of Indian law. It would also mean that the arbitral award is <br /> against basic notions of justice or morality. An arbitral award can be set aside <br /> <br /> 2<br /> (2024) 1 SCC 479 <br /> 3<br /> (2022) 4 SCC 116 <br /> 4<br /> (2019) 15 SCC 131 <br /><br /> <i>Page </i> <b><i>7</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> on the ground of patent illegality i.e. where the illegality goes to the root of <br /> the matter but re-appreciation of evidence cannot be permitted under the <br /> ground of patent illegality. <br /> <b>Consideration by this Court: </b><br /> 23. We shall now discuss the correctness or otherwise of the <br /> judgment of the Commercial Court under Section 34 of the Act in the <br /> impugned judgment. <br /> 24. After extracting the pleadings, the written submissions and the <br /> judgments dealing with the scope of Section 34 of the Act, the Commercial <br /> Court, in the impugned judgment, considered the issues framed by the <br /> Arbitrator. <br /> <b>Re: Issue No.1:</b> <br /> 25. Issue No.(1) framed by the Arbitrator was <i>"Whether the claim </i><br /> <i>petition of the claimant contractor is maintainable?" </i><br /> This issue was held in favour of the appellant by the arbitrator <br /> and the Commercial Court . <br /> <b>Re: Issue No.2: </b><br /> 26. Then the Commercial Court considered issue No.(2) framed by <br /> the Arbitrator. <br /> The said Issue No.(2) was <i>"Whether the claimant is entitled to </i><br /> <i>balance outstanding payment against work executed up to 03.01.2017, but not </i><br /> <i>measured-Rs.50,00,000/-?"</i> <br /> 27. On this issue, the Arbitrator had not granted any relief to the <br /> appellant. <br /> 28. But the Commercial Court went into the said issue and found that <br /> on the face of the record, the award of the Arbitrator goes against the notions <br /><br /> <i>Page </i> <b><i>8</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> of justice and was in contravention with the fundamental policy of Indian law. <br /> It also stated that this matter is required to be dealt with and considered by the <br /> Arbitrator. <br /> 29. We cannot approve this view of the Commercial Court. When the <br /> Arbitrator had not granted any relief to the appellant on this issue, there was <br /> no necessity for the Commercial Court, while dealing with the application of <br /> the respondents under Section 34 of the Act, to take up this issue at all. <br /> 30. When the Arbitrator had not granted any relief to the appellant on <br /> this issue and the appellant had not challenged it by filing an application under <br /> Section 34 before the Commercial Court, and the respondents had succeeded <br /> before the Arbitrator on this ground, it is shocking that the Commercial Court <br /> went into this issue which was wholly unnecessary for it to go into, and held <br /> against the respondents. This is a clear error in its judgment and warrants <br /> interference with it. <br /> <b>Re: Issue Nos. 3 and 4: </b><br /> 31. Then the Commercial Court considered issue Nos.(3) and (4), <br /> which are as under: <br /> <i>"Issue Nos.3 and 4- Whether the claimant is entitled to get the </i><br /> <i>balance outstanding payment against the extra/deviated item for additional </i><br /> <i>lift, but not measured-Rs.1,31,44,169/-? and Whether the claimant is entitled </i><br /> <i>to get the balance outstanding payment against the work executed as extra </i><br /> <i>item for additional lead, but not measured-Rs.1,03,95,679/-?" </i><br /> 32. The Arbitrator had not granted any relief to the appellant on both <br /> these issues. <br /><br /> <i>Page </i> <b><i>9</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> 33. But the Commercial Court held that the Arbitrator's decision on <br /> these issues goes against the notions of justice and was in contravention with <br /> fundamental policy of Indian law. <br /> 34. We are of the view that in the application filed under Section 34 <br /> of the Act by the respondents, it was again wholly unnecessary for the <br /> Commercial Court to go into these issues and interfere with the Arbitrator's <br /> decision. <br /> 35. It was wholly unnecessary, in our opinion, for the Commercial <br /> Court to reverse the view of the Arbitrator, which was adverse to the appellant <br /> and which the appellant had not chosen to challenge by filing an application <br /> under Section 34 of the Act. Thus this is another clear error in his judgment <br /> warranting interference with it. <br /> <b>Re: Issue No.5: </b><br /> 36. Then the Commercial Court took up issue No.(5), which states as <br /> under: <br /> <i>"Issue No.5-Whether the claimant is entitled to get the balance </i><br /> <i>outstanding payment against the work executed and measured, but not paid </i><br /> <i>Rs.28,01,334/-?" </i><br /> 37. The Commercial Court stated as under: <br /> <i>"On the aforesaid fact, this court finds that while deciding </i><br /> <i>issue No.5 the Sole Arbitrator stated it is the claim against </i><br /> <i>execution of work which have been measured and entered in </i><br /> <i>st </i> <i>th</i><br /> <i>MB, according to which the 1</i> <i>R.A- 6</i> <i> R.A Bills have been </i><br /> <i>prepared and paid and 7th R.A and Final bill has been </i><br /> <i>prepared, but not paid. Hence, the question of entitlement of </i><br /> <i>payment remaining outstanding. The claim of the contractor in </i><br /> <i>this issue is Rs.28,01,334/- which has been recorded in the </i><br /> <i>claim statement but during hearing a written application has </i><br /><br /> <i>Page </i> <b><i>10</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> <i>been submitted by claimants lawyer claiming an amount of </i><br /> <i>Rs.39,66,805/- on the plea that the said outstanding amount has </i><br /> <i>been admitted as balance payment to be made to the claimant </i><br /> <i>(Respondent) (Annexure-2) and showed the same in Tabular </i><br /> <i>form along with interest to be paid by the Petitioner to the </i><br /> <i>Respondent. </i><br /> <i> </i> <i>This court finds that the Sole Arbitrator has mentioned that </i><br /> <i>the Petitioner has accepted an amount of Rs.39,66,805/- as </i><br /> <i>balanced outstanding payment and the said outstanding amount </i><br /> <i>being an admitted fact by the Petitioner, the Sole Arbitrator </i><br /> <i>allowed the claim of the Contractor-Respondent but whether </i><br /> <i>the payments claimed to be made by the petitioner to the </i><br /> <i>Respondent- Contractor in dispute Nos.2 and 3 has been </i><br /> <i>adjusted or not has not been discussed and decided as </i><br /> <i>Respondent is not entitled to such amount as opined by the </i><br /> <i>Arbitrator in Issue Nos.2, 3 and 4 but, in fact, paid by the </i><br /> <i>petitioner. Further, Annexure- R-2 as mentioned by the </i><br /> <i>Arbitrator in Issue No.5 has neither been submitted by the </i><br /> <i>Petitioner at present nor it is with the re-constructed record. </i><br /> <i>The said fact of the admission by the petitioner, thus, being </i><br /> <i>beyond record and the findings arrived by Sole Arbitrator, </i><br /> <i>appears to be, beyond record and in contravention with the </i><br /> <i>fundamental policy of Indian law." </i><br /> <i> </i><br /> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i><br /> 38. No doubt, the appellant had claimed under this issue only <br /> Rs.28,01,334/- in the claim statement, but during the hearing before the <br /> Arbitrator, he had filed a written application claiming Rs.39,66,805/- <br /> contending that this outstanding amount had been admitted as balance <br /> payment to be made to him as per Annexure-R/2, and he had showed the same <br /> to the Arbitrator in a tabular form along with interest to be paid by the <br /> respondents to the appellant. <br /><br /> <i>Page </i> <b><i>11</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> 39. The Commercial Court in its judgment states that this Annexure-<br /> R/2 [as mentioned by the Arbitrator in issue No.(5)] was not submitted by the <br /> respondents nor it was with reconstructed record. It therefore, states that the <br /> fact of admission by the respondents is beyond the record and so the findings <br /> on this issue by the Arbitrator were beyond the record and in contravention <br /> with the fundamental policy of Indian law. <br /> 40. From this statement in the judgment of the Commercial Court <br /> and also as per contentions of the parties, it is clear that the documents <br /> including Annexure-R/2, which had been filed before the Arbitrator by the <br /> respondents, had not come before the Commercial Court when the Section 34 <br /> application was before it. There was only a reconstructed record before the <br /> Commercial Court. <br /> 41. But admittedly Annexure-R/2 was available when the Arbitrator <br /> considered the matter and pronounced the award on 17.06.2020 and he had <br /> perused the said document, accepted the same, and granted relief to the <br /> appellant. <br /> 42. Merely because the respondents did not submit the said <br /> Annexure-R/2 before the Commercial Court or merely because it was not <br /> found in the reconstructed record, it is not permissible for the Commercial <br /> Court to interfere with the relief granted by the Arbitrator to the appellant. <br /> 43. As held by Justice A.P. Misra (as His Lordship then was) in <b><i>Ram </i></b><br /> <b><i>5</i></b><br /> <b><i>Khelwan v. Dy.Director of Consolidation, Allahabad</i></b> <b><i>, </i></b> the principle of <br /> reconstruction of document whether it is lost, burnt or misplaced not on <br /> account of fault of either parties is clearly covered under the Court’s inherent <br /> power under section 151 CPC. However, this power has to be exercised with <br /> <br /> 5<br /> 1988 All LJ 68 : 1987 (2) All WC 1255 <br /><br /> <i>Page </i> <b><i>12</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> great care and circumspection to see that in reconstruction of file, no party is <br /> getting favorable gains from the position what it was prior to the <br /> reconstruction. <br /> 44. So the loss of the Annexure R-2 filed before the Arbitrator by <br /> respondents either when it was in the custody of the Arbitrator, or after they <br /> had been submitted by the Arbitrator to the District Court, cannot be to the <br /> prejudice of the appellant, because neither party can be blamed for the loss of <br /> the said document. Its loss cannot put the respondents in a better position than <br /> they were in prior to the reconstruction of the record when its original was <br /> available before the Arbitrator. <br /> 45. In fact copy of the said Annexure R-2 was produced before us by <br /> counsel for the appellant and its contents were not disputed by counsel for the <br /> respondents. It supports the stand taken by the appellants that in the said <br /> document there was an admission of liability by respondents to the tune of <br /> Rs.39,66,805/-. So the arbitrator cannot be said to have committed any error <br /> which warranted interference by the Commercial Court under section 34 of <br /> the Act. <br /> 46. Secondly, the Commercial Court stated that payments claimed to <br /> be made by the respondents herein to the appellant in dispute Nos.2 and 3 had <br /> been adjusted or not, had not been discussed and decided by the Arbitrator. <br /> 47. When the appellant had been denied relief by the Arbitrator on <br /> issues (2), (3) and (4), it would be perverse for the Commercial Court to say <br /> that claims made under those issues should be verified as to their adjustment <br /> against the claim of the appellant referred to in issue No.(5). <br /> 48. Therefore, we find that the Commercial Court had erred in <br /> interfering with the award of the Arbitrator, which was based on evidence <br /><br /> <i>Page </i> <b><i>13</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> adduced before the Arbitrator and that the grounds of interference by it do not <br /> fall within Section 34 of the Act in any manner. There is also no contravention <br /> with any fundamental policy of Indian law as regards this particular finding of <br /> the Arbitrator is concerned. <br /> <b>Re: Issue No.8: </b><br /> 49. The Commercial Court then considered issue No.(8), which is as <br /> under: <br /> <i> </i> <i>"Issue No.8-Whether the rescission of contract by the respondent </i><br /> <i>is lawful or not?"</i> <br /> 50. Admittedly, the commencement of the original contract was <br /> 20.06.2014 and it fixed the date of completion of the work as 19.6.2016. There <br /> is also no dispute that its validity was extended by respondents up to <br /> 30.09.2018. It was rescinded on 31.1.2019 by respondents. <br /> 51. This issue is linked with the question as to who is responsible for <br /> delay in execution of the work order. <br /> 52. The stand of the respondents in their written objection filed <br /> before the arbitrator was as under: <br /> <i>"Para-1(9) </i><br /> <i>th</i><br /> <i> </i> <i>The reason of Hindrances up to 30</i> <i> April'2016 for a period </i><br /> <i>of 165 days has been considered by the Competent Authority </i><br /> <i>st</i><br /> <i>(The Superintending Engineer, 1</i> <i> Circle, Kumarghat) without </i><br /> <i>levy of compensation. </i><br /> <i> </i> <i>Para-1(10). </i><br /> <i> </i> <i>The payment for clearing of Jungles i/c uprooting of Sank </i><br /> <i>Vegetation, Brush Wood, Trees etc. has been measured and </i><br /> <i>paid as extra item for an area of 29,356.20 sqm. @Rs.2.70/sqm. </i><br /> <i>totaling a sum of Rs.79,262.00. </i><br /> <i> </i><br /><br /> <i>Page </i> <b><i>14</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> <i> </i> <i>Para-1(11) </i><br /> <i> </i> <i>The Claimant Contractor could visit the site-of-work before </i><br /> <i>submission of tender as provided vide clause of the Draft N.I.T. </i><br /> <i> </i> <i>Para-1(12). Payment for Earth work as Alleged have been </i><br /> <i>made in terms of item No.1 N and 2 and nothing extra is </i><br /> <i>entertainable. </i><br /> <i> </i> <i>Para-1(13) </i><br /> <i> </i> <i>The design and Drawing delivered to the Claimant </i><br /> <i>Contractor from time to time. Statement showing the details of </i><br /> <i>Design and Drawing handed over to the Claimant Contractor </i><br /> <i>showing the dates is appended for kind appraisal of the Ld. </i><br /> <i>Advocate. </i><br /> <i> </i> <i>Para-1(14) Reply submitted against para-1(13). </i><br /> <i> </i> <i>Para-1(15) There was some delay for a total period of 165 </i><br /> <i>days in finalization of working drawing and hindrance for 165 </i><br /> <i>days approved by the Competent Authority without levy of </i><br /> <i>compensation. </i><br /> <i> </i> <i>Para-1(17) Provision extension of time sanctioned up to 31-</i><br /> <i>01-2019 to keep the contract alive in accordance with the terms </i><br /> <i>of the Agreement. </i><br /> <i> </i> <i>Para-1(18) Provisional extension of time granted up to 31-</i><br /> <i>01-2019 for completion of work." </i><br /> <br /> 53. The arbitrator held in his Award, after appreciation of evidence <br /> on record, as under: <br /> (i) The Hindrance register filed by the parties shows that for <br /> period up to 30-4-2016, 165 days delay was attributable to the respondents; <br /> (ii) Correspondence between the parties further reveals that no <br /> clear site was available for executing the contracted work straightaway from <br /> beginning as per the work order and that the work started on 14.8.2014 instead <br /> of 20.6.2014. This delay of 54 days is also attributable to the respondents; <br /><br /> <i>Page </i> <b><i>15</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> (iii) changes in design and drawings by respondents on several <br /> occasions and non-supply of design and drawings in time also caused <br /> considerable delay in execution of work and that this was also not denied by <br /> the respondents; <br /> (iv) the contract was extended by the respondents <i>suo motu</i> up <br /> to 30.9.2018, but thereafter there was no extension of contract and that on <br /> 31.1.2019, the respondents all of a sudden decided to terminate a non-existent <br /> contract, without extending the validity of the contract upto the date of <br /> rescission; <br /> (v) that most of delays are attributable to the respondents <br /> (80%); and <br /> (vi) a non-existent contract cannot be terminated legally. <br /> 54. These findings are based on appreciation of record and cannot be <br /> termed as perverse or contrary to law. <br /> 55. If there was a valid extension of the contract only up to <br /> 30.09.2018 and there was no extension of the contract up to 31.01.2019, by <br /> efflux of time the contract stood rescinded on 30.09.2018 itself. This is also <br /> the view taken by the Commercial Court. To that extent it is correct. <br /> 56. However, the Commercial Court, in the impugned judgment, held <br /> that this opinion of the Arbitrator that respondents were responsible for delay <br /> in execution of the work, was beyond record and unjustified and goes against <br /> the notions of public policy and was in contravention with the fundamental <br /> policy of Indian law. <br /> 57. While giving these findings, again the Commercial Court says <br /> that : <br /><br /> <i>Page </i> <b><i>16</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> (i) copy of Hindrance Register, which was marked as an <br /> annexure before the Arbitrator, was not found with the reconstructed record; <br /> (ii) certain correspondence indicating that no clear site was <br /> available, was also not found with the record; and <br /> (iii) that certain documents marked before the Arbitrator as <br /> annexures showing that there were changes in design and drawing on several <br /> occasions and there was non-supply of design and drawing in time, were also <br /> not there in the reconstructed record etc. <br /> 58. But admittedly there is no dispute that the Arbitrator had seen <br /> these documents and had referred to them in his award. <br /> 59. As stated above, merely because they were not found in the <br /> reconstructed record, the award of the Arbitrator cannot be interfered with by <br /> the Commercial Court because such loss of original record cannot be put by <br /> the respondents as a point in their favour to doubt the Arbitrator's integrity and <br /> question the very existence of such material at all. Such material has to be <br /> believed to exist and also to have been considered by the Arbitrator, though it <br /> might have got lost subsequently. <br /> 60. So, the findings of the Arbitrator on issue No.(8) could not have <br /> been interfered by the Commercial Court as it had done and it erred in <br /> holding that respondents were not responsible for delay in execution of the <br /> work. <br /> <b>Re: Issue Nos.7 and 13: </b><br /> 61. Next the Commercial Court considered issue Nos.(7) and (13), <br /> which are as under: <br /> <i>th</i><br /> <i>"Issue No.7-Whether price escalation bill up to 6</i> <i> R.A. Bill?-</i><br /> <i>Rs.1,37,99,630/- and </i><br /><br /> <i>Page </i> <b><i>17</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> <i> Issue No.13-Whether any interference is called for, when the Ld. </i><br /> <i>Sole Arbitrator has considered the effect of Clause 44 of the Agreement?"</i> <br /> 62. The High Court in its judgment dt.31.01.2024 in Arbitration <br /> Appeal No.07 of 2022 filed by the respondents, while remitting the matter to <br /> the Commercial Court, had asked it to consider the effect of Clause 44 of the <br /> agreement. <br /> 63. This Clause dealt with price escalation and the Arbitrator had <br /> opined that the original contract period was for 24 months only, and the <br /> respondents were mostly responsible for delay of execution of work and so, <br /> the appellant was entitled to price escalation. <br /> 64. But since on issue No.(8), the Commercial Court had held against <br /> the appellant and held that respondents cannot be held liable for the delay in <br /> execution of work, the Commercial Court relied on it to set aside the <br /> Arbitrator's award in favor of the appellant on issue Nos.(7) and (13). <br /> 65. We have already held that the Commercial Court's decision on <br /> issue No.(8) is erroneous and that merely because the reconstructed record did <br /> not contain the documents which the Arbitrator had seen, the finding of the <br /> Arbitrator cannot be interfered with. <br /> 66. Also, when the respondents themselves have admitted in black <br /> and white in their very pleading before the arbitrator that there were <br /> hindrances because of which extensions had been granted to the appellant for <br /> execution of the work, and the Arbitrator had also relied on the documentary <br /> evidence produced before him to come to the same conclusion as indicated in <br /> his discussion on issue No.(8), the Commercial Court could not have <br /> interfered with finding of Arbitrator. <br /><br /> <i>Page </i> <b><i>18</i></b> <i> of </i> <b><i>18</i></b> <br /> <br /> 67. Since the Arbitrator's view cannot be said to be perverse or <br /> contrary to law on this aspect, we hold that the findings of the Commercial <br /> Court on issue Nos.(7) and (13) are also bad in law, and cannot be sustained. <br /> <b>Re: Issue No.9: </b><br /> 68. The Commercial Court then considered issue No.(9), which <br /> stated as under: <br /> <i>"Issue No.9-Whether the claimant is entitled to get loss of </i><br /> <i>expected profit @ 15% on the balance work remaining unexecuted?-</i><br /> <i>Rs.34,24,048/-" </i><br /> 69. While dealing with this issue, the Commercial Court again relied <br /> on its finding on issue No.(8), and based on that finding, interfered with the <br /> award of the Arbitrator, who had granted relief on this issue to the appellant. <br /> 70. Since we have held that the finding of the Commercial Court on <br /> issue No.(8) cannot be sustained, we hold that the Arbitrator did not err in <br /> granting relief to the appellant on this issue as well and the Commercial Court <br /> erred in interfering with it. <br /> <b>Conclusion: </b><br /> 71. For all the aforesaid reasons, the judgment dt.31.08.2024 of the <br /> Commercial Court, Unakoti District, Kailashahar is set aside, the award <br /> dt.17.6.2020 of the Arbitrator is upheld, and the Appeal is allowed with costs. <br /> Pending application(s), if any, also stands disposed of. <br /> <br /> <br /> <b>(BISWAJIT PALIT, J) </b> <b> </b> <b>(M.S. RAMACHANDRA RAO, CJ)</b> <br /> <i> </i><br /> <i> </i><br /> <i>Pulak</i> <b> </b> <br /> PULAK BANIK<br /> Digitally signed by PULAK BANIK <br /> Date: 2026.04.01 12:24:16 +05'30'</div>