M/S Daulat Ram Brake Mfg Co vs Northern Railways

Court
Delhi High Court

$~12
* IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
Date of Decision: 17.07.2026
ARB.P. 907/2026
M/S DAULAT RAM BRAKE MFG CO .....Petitioner
Through: Mr. Pranav Goswami, Advocate
(through VC)
versus

NORTHERN RAILWAYS .....Respondent
Through: Mr. Piyush Gupta, CGSC along with
Mr. Atishay Jain, Ms. Himanshi Soni
and Mr. Devansh Sewalia, Advocates.

CORAM:

HON'BLE MR. JUSTICE SACHIN DATTA

SACHIN DATTA, J ( Oral )

1. The present petition has been filed under Section 11 (6) of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as “ A&C
Act ”) seeking constitution of an independent Arbitral Tribunal comprising of
three arbitrators in terms of Clause 2900 of the Indian Railways Standard
General Conditions of Contract, 2018 (hereinafter referred to as " GCC "),
which forms part of the contract executed between the parties.
2. The petitioner is a proprietorship concern engaged in the business of
manufacturing brake blocks used in passenger coaches and has its registered
office at Mandideep, Bhopal, Madhya Pradesh. The respondent is
represented through the Deputy Chief Materials Manager, Northern
Railways, Baroda House, New Delhi.
3. It is submitted that the respondent floated a tender dated 16.08.2018
Signature Not Verified
ARB.P. 907/2026 Page 1 of 5

Digitally Signed
By:ABHISHEK THAKUR
Signing Date:22.07.2026
12:22:07

for the supply of “ non-asbestos based 'K' Type High Friction Composite
Brake Block for coaches with bogie mounted brake system as per RDSO’s
Drawing No. RDSO/SK-98066 alt (6), Specification No. C9809 (Rev.-4) with
amendment – 1 ”. The petitioner, in response thereto, submitted its bid,
which was duly accepted by the respondent and, pursuant thereto, the parties
entered into a contract governed by the Indian Railways Standard General
Conditions of Contract, 2018. The arbitration clause between the parties is
contained in Clause 2900 of the GCC, which reads as under:

Signature Not Verified
ARB.P. 907/2026 Page 2 of 5

Digitally Signed
By:ABHISHEK THAKUR
Signing Date:22.07.2026
12:22:07

4. It is the case of the petitioner that disputes subsequently arose
between the parties in relation to the quality of the material supplied by the
petitioner, wherein the respondent rejected the supplied goods. Aggrieved
thereby, the petitioner invoked arbitration by issuing a notice dated
26.03.2022 under section 21 of the A&C Act requesting the respondent to
nominate an independent arbitrator, while objecting to the appointment of
serving or retired Railway Officers as arbitrators in view of Section 12(5) of
the A&C Act.
5. It is submitted that, despite the aforesaid objection, the respondent
furnished a restricted panel comprising four retired Railway officers and
called upon the petitioner to suggest two names therefrom for appointment.
Thereafter, the respondent unilaterally constituted a three-member Arbitral
Signature Not Verified
ARB.P. 907/2026 Page 3 of 5

Digitally Signed
By:ABHISHEK THAKUR
Signing Date:22.07.2026
12:22:07

Tribunal consisting exclusively of retired Railway officers. The Tribunal
entered upon the reference and ultimately rendered the impugned Award
dated 16.11.2023 against the petitioner.
6. Aggrieved by the said Award, the petitioner preferred a petition under
Section 34 of the A&C Act being O.M.P. (COMM.) 151/2024 before this
Court. Vide judgment dated 31.07.2025, this Court set aside the Award on
the ground that the constitution of the Arbitral Tribunal was contrary to the
provisions of the A&C Act and the settled principles governing the
independence and impartiality of arbitrators. While doing so, liberty was
reserved in favour of the petitioner to seek constitution of a fresh Arbitral
Tribunal in accordance with law.
7. Pursuant to the aforesaid liberty, the petitioner issued a fresh notice

dated 15.09.2025 invoking arbitration under Section 21 of the A&C Act and
nominated its nominee arbitrator. The respondent was called upon to
nominate its arbitrator within thirty days.
8. It is submitted that despite service of the said notice and a reminder
dated 09.04.2026, the respondent neither nominated its arbitrator nor
responded to the petitioner's request for constitution of the Arbitral Tribunal,
thereby necessitating the filing of the present petition.
9. While the arbitration clause envisages constitution of a three-member
Arbitral Tribunal, learned counsel appearing for both parties fairly submit
that they have no objection to the disputes being referred to a Sole
Arbitrator.
10. In Gr Green Life Energy Pvt. Ltd. v. Leitwind Shriram
Manufacturing Pvt. Ltd. , 2021 SCC OnLine SC 133, the Supreme Court
has recognised that, where parties agree before the Court to have their
Signature Not Verified
ARB.P. 907/2026 Page 4 of 5

Digitally Signed
By:ABHISHEK THAKUR
Signing Date:22.07.2026
12:22:07

disputes adjudicated by a Sole Arbitrator, the contractual stipulation
providing for a three-member tribunal stands superseded to that extent.
11. Accordingly, at joint request, Mr. Upendra Malik (Retd. SDG,
CPWD) (Mob. No. + 91 9891318773) is appointed as the Sole Arbitrator to
adjudicate the disputes between the parties.
12. The learned Sole Arbitrator may proceed with the arbitration
proceedings subject to furnishing to the parties requisite disclosures as
required under Section 12 of the A&C Act.
13. The Arbitration shall take place under the aegis of, and as per the
rules of Delhi International Arbitration Centre (DIAC).
14. All rights and contentions of the parties in relation to the claims/
counter-claims are kept open, to be decided by the learned Arbitrator on
their merits, in accordance with law.
15. Needless to say, the learned Sole Arbitrator would consider the same
in accordance with law and take an appropriate decision.
16. The respondent shall be entitled to raise preliminary objections as
regards jurisdiction/ arbitrability, which shall be decided by the learned
arbitrator, in accordance with law.
17. Needless to say, nothing in this order shall be construed as an
expression of this Court on the merits of the case.
18. The petition stands disposed of in the above terms.

JULY 17, 2026/ ka SACHIN DATTA, J