TEJASCO TECHSOFT PVT LTD vs THE PRINCIPAL SECRETARY
- Court
- Karnataka High Court
- 1 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
®
HC-KAR
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
TH
DATED THIS THE 16 DAY OF JUNE, 2026
BEFORE
THE HON'BLE MR. JUSTICE SURAJ GOVINDARAJ
WRIT PETITION NO. 18183 OF 2024 (GM-RES)
BETWEEN:
TEJASCO TECHSOFT PVT LTD
REPRESENTED BY ITS DIRECTOR
MR N S PRASHANTH R/A NO 240,
ND ND
2 FLOOR, 32 CROSS,
TH
7 BLOCK, JAYANAGAR
BANGALORE - 560 082.
…PETITIONER
(BY SRI. SUNIL KUMAR H, ADVOCATE)
AND:
1. THE PRINCIPAL SECRETARY
DEPARTMENT OF HEALTH
AND FAMILY WELFARE
GOVERNMENT OF KARNATAKA
VIKASA SOUDHA
BENGALURU- 560 001.
2. THE COMMISSIONER
DEPARTMENT OF HEALTH
AND FAMILY WELFARE,
AROGYA SOUDHA,
MAGADI ROAD,
BENGALURU - 560 023.
…RESPONDENTS
(BY SRI. MOHAMMED JAFAR SHAH, ADVOCATE)
Digitally signed
by SHWETHA
RAGHAVENDRA
Location: HIGH
COURT OF
KARNATAKA
THIS W.P. IS FILED UNDER ARTICLES 26 AND 227 OF
THE CONSTITUTION OF INDIA PRAYING TO SET ASIDE THE
- 2 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
ORDER PASSED BY THE COURT OF LXXXVII ADDITIONAL CITY
CIVIL AND SESSIONS JUDGE COMMERCIAL COURT AT
BANGALORE (CCH-88) IN COM AP NO. 30/2023 DTD.
19.04.2024 IN PASSED IN IA NO. 2 OF 2023 VIDE ANNX-A.
THIS PETITION, COMING ON FOR PRELIMINARY HEARING
IN ‘B’ GROUP, THIS DAY, ORDER WAS MADE THEREIN AS
UNDER:
CORAM: HON'BLE MR. JUSTICE SURAJ GOVINDARAJ
ORAL ORDER
1. The petitioner is before this Court seeking following
reliefs:
a) Set aside the order passed by the Court of
LXXXVII Additional City Civil and Sessions
Judge Commercial Court at Bangalore (CCH-
88) in Com A.P.No.30/2023 dated
19/04/2024 in passed in I.A.No.2 of 2023
vide Annexure- A.
b) Pass such other orders or directions as this
Hon'ble Court deems fit in the facts and
circumstances of the case in the interest of
justice and equity.”
2. The petitioner had invoked the arbitral clause in the
agreement between the petitioner and the
respondent, which resulted in arbitral proceedings in
A.C.No.130/2022, where an award was passed on
26.08.2022 when the respondent was absent. The
minutes of the Arbitral Tribunal reads as under:
- 3 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
“Minutes of the Seventh Meeting dated
26.08.2022 at 12.30 p.m. at the Centre
Present:
1. Shri Sunil Kumar H and Shri Srikanth M,
learned Advocates for the Claimant.
2. None appears for the Respondents.
The Seventh Meeting of this Arbitration
is held physically, at the Arbitration & Conciliation
Centre, Race Course Road, Bengaluru.
1. The Award was made and signed at this
meeting.
2. A signed copy of the Award may be
furnished to the counsel for the Claimant by the
Centre, after completing its formalities.
3. Since none appears for the Respondents
the Centre is directed to furnish a copy of this
Minutes by email to the Respondents and its
counsel.”
3. Sri. Sunil Kumar H., learned counsel appearing for
the petitioner, would contend that
3.1. The Commercial Court committed a serious
error in condoning the delay and entertaining
the petition under Section 34 of the Arbitration
and Conciliation Act, 1996. According to him,
the arbitral award was admittedly pronounced
on 26.08.2022 and the parties were aware of
the pronouncement of the award on the said
- 4 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
date. Therefore, for the purpose of computing
limitation under Section 34(3) of the Act, the
date of the award, namely 26.08.2022, ought
to have been taken as the starting point.
3.2. He submits that Section 34(3) prescribes a
period of three months for filing an application
challenging an arbitral award and confers a
limited discretion upon the Court to condone a
further delay of thirty days, provided sufficient
cause is shown. The legislative intent
underlying the provision is to ensure finality of
arbitral awards and to prevent prolonged
uncertainty in arbitral proceedings. Once the
aggregate period of one hundred and twenty
days expires, the Court ceases to have
jurisdiction to entertain the challenge.
3.3. Learned counsel would further submit that the
expression "may not be made after three
months have elapsed from the date on which
the party making the application had received
the arbitral award" occurring in Section 34(3)
cannot be interpreted in a manner that defeats
the object of expeditious conclusion of arbitral
proceedings. According to him, where the
- 5 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
parties have participated in the arbitral
proceedings and are aware of the
pronouncement of the award, limitation cannot
be indefinitely postponed by relying upon the
date on which a physical copy of the award is
received.
3.4. It is his submission that even assuming the
respondent received a copy of the award on
03.11.2022, the fact remains that the award
had been pronounced on 26.08.2022 and the
respondent was aware of the same. Therefore,
the respondent was required to act with due
diligence and file the petition within the period
prescribed under Section 34(3) of the Act. The
challenge having been instituted beyond the
outer limit of one hundred and twenty days
reckoned from the date of the award, the
Commercial Court lacked jurisdiction to
condone the delay.
3.5. Learned counsel would therefore contend that
the limitation prescribed under Section 34(3) is
mandatory in nature and the proviso thereto
constitutes the maximum extent of discretion
available to the Court. Once the period of one
- 6 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
hundred and twenty days stands exhausted,
neither equitable considerations nor the general
provisions relating to condonation of delay can
be invoked to extend the period further. He
therefore submits that the Commercial Court
ought to have rejected the application seeking
condonation of delay and consequently
dismissed the petition under Section 34 of the
Act as being barred by limitation.
3.6. In this regard, he relies upon the decision of the
Hon’ble Apex Court in Bhimashankar
Sahakari Sakkare Karkhane Niyamita Vs.
Walchandnagar Industries Ltd. (WIL) -
(2023) 8 SCC 453, more particularly,
paragraph 51 thereof which is reproduced
hereunder for easy reference:
51. By holding so, this Court
considered the earlier decisions in the case of
Popular Construction Co. (Supra) and State of
Maharashtra vs. Hindustan Construction Co.
Ltd. reported in (2010) 4 SCC 518 and has
observed and held in paragraphs 6 to 9 as
under:
“6. Section 34(3) of the 1996 Act
provides that an application for setting
aside an award may be made within three
months of the receipt of the arbitral
- 7 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
award. The proviso that follows sub-
section (3) of Section 34 provides that on
sufficient cause being shown, the court
may entertain the application for setting
aside the award after the period of three
months and within a further period of 30
days but not thereafter.
7. In Popular Construction Co.1,
this Court has held that an application for
setting aside an award filed beyond the
period mentioned in Section 34(3) would
not be an application "in accordance with
subsection (3) as required under Section
34(1) of the 1996 Act" and Section 5 of
the 1963 Act has no application to such
application. In para 12 of the Report, it
was held in Popular Construction Co.1
thus: (SCC pp.47475)
"12. As far as the language of Section
34 of the 1996 Act is concerned, the crucial
words are "but not thereafter" used in the
proviso to subsection (3). In our opinion, this
phrase would amount to an express exclusion
within the meaning of Section 29(2) of the
Limitation Act, and would therefore bar the
application of Section 5 of that Act.
Parliament did not need to go further. To hold
that the court could entertain an application
to set aside the award beyond the extended
period under the proviso, would render the
phrase "but not thereafter" wholly otiose. No
principle of interpretation would justify such a
result".
8. Recently, in State of
Maharashtra v. Hindustan Construction
Company Limited2, a two Judge Bench of
this Court speaking through one of us
(R.M. Lodha, J.) emphasised the
mandatory nature of the limit to the
extension of the period provided in
proviso to Section 34(3) and held that an
application for setting aside arbitral award
under Section 34 of the 1996 Act has to
be made within the time prescribed under
sub section (3) of Section 34 i.e., within
- 8 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
three months and a further period of 30
days on sufficient cause being shown and
not thereafter.
9. Section 43(1) of the 1996 Act
provides that the 1963 Act shall apply to
arbitrations as it applies to proceedings in
court. The 1963 Act is thus applicable to
the matters of arbitration covered by the
1996 Act save and except to the extent
its applicability has been excluded by
virtue of the express provision contained
in Section 34(3) of the 1996 Act.”
3.7. By referring to Bhimashankar his submission
is that Hon’ble the Apex Court reiterated the
settled legal position regarding the limitation
prescribed under Section 34(3) of the
Arbitration and Conciliation Act, 1996. The
Supreme Court, after referring to its earlier
decisions in Union of India v. Popular
Construction Co. and State of Maharashtra
v. Hindustan Construction Co. Ltd.,
reaffirmed that an application seeking to set
aside an arbitral award is required to be filed
within a period of three months from the date
of receipt of the arbitral award and that the
Court is vested with a limited discretion to
condone delay for a further period of thirty days
upon sufficient cause being shown, but not
thereafter.
- 9 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
3.8. Learned counsel submits that the expression
"but not thereafter" occurring in the proviso to
Section 34(3) has repeatedly been interpreted
by the Hon’ble Supreme Court as an express
legislative bar on extension of limitation beyond
the aggregate period of one hundred and
twenty days. The said expression, according to
him, reflects the legislative intent of ensuring
finality and certainty in arbitral proceedings and
preventing arbitral awards from being subjected
to prolonged challenges. It is his submission
that once the prescribed period expires, the
Court becomes functus officio insofar as
extension of limitation is concerned and cannot
invoke either equitable considerations or the
provisions of the Limitation Act to enlarge the
period.
3.9. By placing reliance on Bhimashankar learned
counsel would contend that even within the
additional period of thirty days contemplated
under the proviso to Section 34(3), the
applicant is required to establish the existence
of "sufficient cause" for not having presented
the petition within the initial period of three
months. According to him, the power to
- 10 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
condone delay is not intended to be exercised
mechanically or as a matter of course merely
because the delay falls within the condonable
period. The applicant must disclose a bona fide
and satisfactory explanation demonstrating that
despite due diligence, the petition could not be
filed within the prescribed time.
3.10. Learned counsel submits that in the present
case no such sufficient cause has been made
out. The only explanation offered by the
respondent is that time was consumed in
obtaining approvals and permissions from the
concerned authorities before initiating
proceedings under Section 34 of the Act. Such
an explanation, according to him, does not
constitute sufficient cause in law.
Administrative procedures, movement of files,
internal correspondence and obtaining
departmental approvals are matters entirely
within the control of the respondent and cannot
furnish a valid justification for delay in invoking
a statutory remedy.
3.11. It is further submitted that if such explanations
are routinely accepted, the very object
- 11 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
underlying Section 34(3) would stand defeated.
Government departments and public sector
undertakings, by merely referring to internal
approvals and procedural formalities, would
effectively secure an extension of limitation
beyond what has been contemplated by
Parliament. This would be contrary to the
legislative policy of ensuring expeditious
resolution of disputes through arbitration.
3.12. Learned counsel therefore contends that the
Commercial Court failed to properly examine
whether the respondent had established
sufficient cause for condonation of delay.
According to him, the impugned order proceeds
on a liberal approach inconsistent with the strict
limitation regime prescribed under Section
34(3) of the Act. He therefore submits that the
order dated 19.04.2024 condoning the delay is
unsustainable in law and is liable to be set
aside.
3.13. He refers to the decision in the case of
Bharatiya Rashtriya Rajmarg Pradhikaran
Vs. Neeraj Sharma and Ors –
2024:AHC:94330 of the Hon'ble Allahabad
- 12 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
High Court in Appeal No.8/2020, more
particularly, paragraph Nos.10, 11, 12, 13 and
14 thereof which are reproduced hereunder for
easy reference:
10. The importance of Section 31(5) cannot
be overstated as it initiates several procedural
timelines. These include the periods within
which parties may seek to correct, interpret,
or request an additional award under Section
33 of the Arbitration Act, or challenge the
award under Section 34 of the Arbitration Act.
The delivery of the signed copy of the arbitral
award is not a mere formality; it is a
substantive requirement that marks the
conclusion of the arbitration proceedings and
the commencement of potential post-award
actions. In Union of India v. Tecco Trichy
(supra) , the Hon’ble Supreme Court
emphasized that the delivery of an arbitral
award is substantive, as it activates the
commencement of several critical timelines.
This stage marks the termination of the
arbitral proceedings and sets the clock ticking
for any remedial actions available under the
Arbitration Act.
- 13 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
11. However, interpreting Section 31(5) too
literally in all cases may lead to unjust
outcomes, undermining the fundamental
objectives of arbitration. The literal adherence
to this provision might be used strategically
by parties to delay the enforcement of the
award, thus defeating the principle of
expeditious dispute resolution that arbitration
seeks to promote.
12. In the instant case, the appellant has
assailed the order of the Learned District
Judge based on the assertion that they never
received a signed copy of the arbitral award.
However, as highlighted by the Learned
District Court, it is essential to consider
several critical facts. Relevant portions from
the impugned order dated November 16,
2019 passed by the Learned District Judge
Court under Section 34 of the Arbitration Act
are delineated below:
- 14 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
13. What emerges from the order of the
Learned District Judge is that the appellant
was fully aware of the contents of the arbitral
award dated July 28, 2016 and had acted on
it, thereby demonstrating a practical
acknowledgement of the arbitral award. In
view of the award dated July 28, 2016, the
Appellant through its letter dated May 22,
2017 asked the Special Land Acquisition
officer to calculate the compensation amount
and publish a supplementary award. In
compliance of the same, the Competent
- 15 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
Authority that is the Special Land Acquisition
Officer calculated the amount of compensation
to be paid and sent it to the Appellant on May
31, 2017. What is evident is that, the
Appellant, even despite the non-receipt of a
signed copy of the arbitral award dated July
28, 2016 accepted the same and acted upon
it. Therefore, the appellant cannot now evade
the consequences by exploiting a procedural
technicality regarding the non-receipt of a
signed copy. It is crucial to interpret Section
31(5) of the Arbitration Act in a matter that
aligns with the Arbitration Act’s overarching
goals of promoting fairness and expeditious
dispute resolution.
14. A literal interpretation, which ignores
the practical reality that the party was aware
of the arbitral award and acted upon it, would
be contrary to the spirit of the Arbitration Act.
This was aptly summarized by the Bombay
High Court in Akola Janta (supra) when it
remarked that a narrow view of Section 31(5)
of the Arbitration Act would defeat the
Arbitration Act’s purpose if it allowed a party
to delay proceedings unjustly by claiming
non-receipt of a signed copy despite having
knowledge of the award’s contents.
3.14. By relying on Neeraj Sharma his submission is
that while Section 31(5) of the Arbitration and
Conciliation Act, 1996 mandates delivery of a
signed copy of the arbitral award to the parties,
the requirement cannot be interpreted in a
manner that enables a party to indefinitely
- 16 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
postpone the commencement of limitation
despite having full knowledge of the award and
having acted upon it.
3.15. Learned counsel submits that the Hon’ble
Allahabad High Court, after considering the
decisions of the Hon'ble Supreme Court in
Union of India v. Tecco Trichy Engineers &
Contractors and other decisions on the
subject, observed that though delivery of a
signed copy of the award is an important
statutory requirement, a purely literal
interpretation of Section 31(5) may, in certain
situations, defeat the very object of arbitration
by permitting parties to delay enforcement of
awards on technical grounds. The Hon’ble
Allahabad High Court held that where a party is
fully aware of the contents of the award and
has acted upon it, such party cannot
subsequently seek to avoid the consequences
flowing from the award merely by contending
that a signed copy was not formally delivered.
3.16. Learned counsel submits that the Hon’ble
Allahabad High Court found that the appellant
therein had acted upon the arbitral award,
- 17 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
called upon the concerned authorities to
calculate compensation in terms thereof, and
had thereby unequivocally acknowledged the
award. In those circumstances, the Hon’ble
Allahabad High Court held that the appellant
could not rely upon the plea of non-receipt of a
signed copy of the award as a means to defeat
limitation and delay the arbitral process.
3.17. Placing reliance on Neeraj Sharma , learned
counsel submits that the governing principle
which emerges is that where a party has
acquired knowledge of the arbitral award and is
aware of its contents, limitation cannot be
indefinitely deferred by relying upon procedural
objections relating to formal receipt of the
signed copy of the award. According to him, the
purpose of Section 31(5) is to ensure
communication of the award to the parties and
not to create a mechanism by which a party,
despite having knowledge of the award, may
postpone commencement of limitation.
3.18. It is his submission that in the present case, an
email communication had been dispatched to
the respondent informing it that the arbitral
- 18 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
award had been passed. The respondent was
therefore aware of the passing of the award
and had knowledge of the same. Once such
knowledge was available, the respondent was
required to act diligently and take steps for
challenging the award, if so advised. The
respondent cannot, according to learned
counsel, contend that limitation would
commence only upon formal receipt of a signed
copy of the award when it was already aware
that the arbitral proceedings had culminated in
an award.
3.19. Learned counsel would further contend that
acceptance of the respondent's contention
would defeat the legislative objective
underlying Sections 31, 34 and 36 of the Act,
namely, expeditious finality of arbitral
proceedings. If parties who are aware of the
award are permitted to postpone limitation until
formal service of a signed copy, the certainty
and finality which arbitration seeks to achieve
would be seriously undermined.
3.20. He therefore submits that the Commercial Court
failed to properly appreciate the effect of the
- 19 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
respondent's knowledge of the award and
proceeded solely on the basis of the date on
which the respondent claims to have received a
signed copy thereof. According to him, the date
on which the respondent acquired knowledge of
the award ought to have been taken into
consideration while computing limitation under
Section 34(3) of the Act. Had the Commercial
Court done so, it would have come to the
conclusion that the petition under Section 34
was filed beyond the period prescribed under
law and was therefore liable to be rejected as
barred by limitation. The impugned order,
according to learned counsel, suffers from a
fundamental error in this regard and therefore
calls for interference by this Court.
3.21. He relies upon the decision of the Hon'ble
Chhattisgarh High Court in the case of Union
of India Vs. Bhola Prasad Agrawal and
Another – 2022 SCC OnLine Chh 1644 ,
more particularly, paragraph No.8 thereof,
which is reproduced hereunder for easy
reference:
“8. In order to ascertain the correctness at
the bar, it would be appropriate to notice
- 20 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
Section 34(3) of the Arbitration Act, which
runs thus:
"34. Application for setting aside arbitral
award.--(1) xxxx (3) An application for
setting aside may not be made after three
months have elapsed from the date on which
the party making that application had
received the arbitral award or, if a request
had been made under section 33, from the
date on which that request had been disposed
of by the arbitral tribunal:
Provided that if the Court is satisfied that the
applicant was prevented by sufficient cause
from making the application within the said
period of three months it may entertain the
application within a further period of thirty
days, but not thereafter."
3.22. Relying on Bhola Prasad Agrawal ,
particularly, he submits that the Hon’ble
Chhattisgarh High Court considered the
provisions of Section 34(3) of the Arbitration
and Conciliation Act, 1996. Learned counsel
submits that the statutory scheme governing
challenges to arbitral awards is clear and
unambiguous. Section 34(3) prescribes a period
of three months from the date on which the
party making the application has received the
arbitral award. The proviso confers a limited
discretion upon the Court to entertain the
application within a further period of thirty days
- 21 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
if sufficient cause is shown, but expressly
prohibits extension beyond the said period.
3.23. Learned counsel submits that the Hon’ble
Chhattisgarh High Court reiterated the settled
principle that the limitation prescribed under
Section 34(3) is a special limitation created by
the statute itself and that the Court's
jurisdiction to condone delay is confined strictly
to the parameters prescribed therein. According
to him, the legislative intent is to ensure finality
of arbitral awards and expeditious resolution of
disputes, which are the foundational objectives
underlying the Arbitration and Conciliation Act,
1996.
3.24. Placing reliance on Bhola Prasad Agrawal ,
learned counsel contends that while considering
an application for condonation of delay in
proceedings under Section 34, the Court cannot
adopt the liberal principles ordinarily applicable
under Section 5 of the Limitation Act. The
discretion available under the proviso to Section
34(3) is considerably narrower and is
circumscribed by the statutory mandate
contained in the expression "but not
- 22 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
thereafter". Therefore, unless the applicant
establishes sufficient cause for the delay and
demonstrates that the application has been
presented within the statutorily permissible
period, the Court lacks jurisdiction to entertain
the challenge.
3.25. It is his submission that the Commercial Court,
while allowing the application for condonation
of delay, failed to keep in view the strict
limitation regime governing arbitral proceedings
and proceeded as though a wider discretion was
available. Such an approach, according to
learned counsel, is contrary to the statutory
scheme as well as the consistent judicial
pronouncements interpreting Section 34(3) of
the Act.
3.26. Learned counsel therefore submits that the
impugned order deserves to be set aside on the
ground that the Commercial Court exercised
jurisdiction contrary to the limitations imposed
by Section 34(3) of the Act and thereby
defeated the legislative objective of ensuring
finality and certainty in arbitral adjudication.
- 23 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
3.27. He refers to the decision of the Hon'ble High
Court of Telangana in the case of Food
Corporation of India Vs. A.P. State
Warehousing Corporation - in
I.A.No.1/2022 and C.M.A.No.157/2022 ,
more particularly, paragraph No.8 thereof,
which is reproduced hereunder for easy
reference:
8. In Government of Maharashtra
(Water Resources Department) rep. by
Executive Engineer Vs Borse Brothers
Engineers & Contractors Private Limited
– (2021) 6 SCC 460 , the Hon'ble Supreme
Court held:
"32. Thus, from the scheme of the
Arbitration Act as well as the aforesaid
judgments, condonation of delay under
Section 5 of the Limitation Act has to be
seen in the context of the object of
speedy resolution of disputes.
58. Given the object sought to be
achieved under both the Arbitration Act
and the Commercial Courts Act, that is,
the speedy resolution of disputes, the
expression "sufficient cause" is not
elastic enough to cover long delays
beyond the period provided by the
appeal provision itself. Besides, the
expression "sufficient cause" is not itself
a loose panacea for the ill of pressing
negligent and stale claims. This Court,
in Basawaraj v. LAO [Basawaraj v. LAO,
- 24 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
(2013) 14 SCC 81] , has held : (SCC pp.
85-88, paras 9-15)
"9. Sufficient cause is the cause for
which the defendant could not be
blamed for his absence. The
meaning of the word "sufficient" is
"adequate" or "enough", inasmuch
as may be necessary to answer the
purpose intended. Therefore, the
word "sufficient" embraces no more
than that which provides a
platitude, which when the act done
suffices to accomplish the purpose
intended in the facts and
circumstances existing in a case,
duly examined from the viewpoint
of a reasonable standard of a
cautious man. In this context,
"sufficient cause" means that the
party should not have acted in a
negligent manner or there was a
want of bona fide on its part in
view of the facts and circumstances
of a case or it cannot be alleged
that the party has "not acted
diligently" or "remained inactive".
However, the facts and
circumstances of each case must
afford sufficient ground to enable
the court concerned to exercise
discretion for the reason that
whenever the court exercises
discretion, it has to be exercised
judiciously. The applicant must
satisfy the court that he was
prevented by any "sufficient cause"
from prosecuting his case, and
unless a satisfactory explanation is
furnished, the court should not
allow the application for
condonation of delay. The court has
to examine whether the mistake is
bona fide or was merely a device to
cover an ulterior purpose. (See
Manindra Land & Building Corpn. v.
Bhutnath Banerjee [Manindra Land
& Building Corpn. v. Bhutnath
Banerjee, AIR 1964 SC 1336] ,
- 25 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
Mata Din v. A. Narayanan [Mata
Din v. A. Narayanan, (1969) 2 SCC
770] , Parimal v. Veena [Parimal v.
Veena, (2011) 3 SCC 545 : (2011)
2 SCC (Civ) 1] and Maniben Devraj
Shah v. Municipal Corpn. of Brihan
Mumbai [Maniben Devraj Shah v.
Municipal Corpn. of Brihan Mumbai,
(2012) 5 SCC 157 : (2012) 3 SCC
(Civ) 24].)
10. In Arjun Singh v.
Mohindra Kumar [Arjun Singh v.
Mohindra Kumar, AIR 1964 SC
993] this Court explained the
difference between a "good cause"
and a "sufficient cause" and
observed that every "sufficient
cause" is a good cause and vice
versa. However, if any difference
exists it can only be that the
requirement of good cause is
complied with on a lesser degree of
proof than that of "sufficient
cause".
11. The expression "sufficient
cause" should be given a liberal
interpretation to ensure that
substantial justice is done, but only
[Ed. : The matter between two
asterisks has been emphasised in
original.] so long as negligence,
inaction or lack of bona fides
cannot be imputed to the party
concerned [Ed. : The matter
between two asterisks has been
emphasised in original.] , whether
or not sufficient cause has been
furnished, can be decided on the
facts of a particular case and no
straitjacket formula is possible.
(Vide Madanlal v. Shyamlal
[Madanlal v. Shyamlal, (2002) 1
SCC 535] and Ram Nath Sao v.
Gobardhan Sao [Ram Nath Sao v.
Gobardhan Sao, (2002) 3 SCC 195]
.)
- 26 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
12. It is a settled legal proposition
that law of limitation may harshly
affect a particular party but it has
to be applied with all its rigour
when the statute so prescribes. The
court has no power to extend the
period of limitation on equitable
grounds. 'A result flowing from a
statutory provision is never an evil.
A court has no power to ignore that
provision to relieve what it
considers a distress resulting from
its operation.' The statutory
provision may cause hardship or
inconvenience to a particular party
but the court has no choice but to
enforce it giving full effect to the
same. The legal maxim dura lex
sed lex which means "the law is
hard but it is the law", stands
attracted in such a situation. It has
consistently been held that,
"inconvenience is not" a decisive
factor to be considered while
interpreting a statute.
13. The statute of limitation is
founded on public policy, its aim
being to secure peace in the
community, to suppress fraud and
perjury, to quicken diligence and to
prevent oppression. It seeks to
bury all acts of the past which have
not been agitated unexplainably
and have from lapse of time
become stale. According to
Halsbury's Laws of England, Vol.
28, Para 605 p. 266:
'605. Policy of the Limitation Acts.--
The courts have expressed at least
three differing reasons supporting
the existence of statutes of
limitation, namely, (1) that long
dormant claims have more of
cruelty than justice in them, (2)
that a defendant might have lost
the evidence to disprove a stale
claim, and (3) that persons with
- 27 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
good causes of actions should
pursue them with reasonable
diligence.' An unlimited limitation
would lead to a sense of insecurity
and uncertainty, and therefore,
limitation prevents disturbance or
deprivation of what may have been
acquired in equity and justice by
long enjoyment or what may have
been lost by a party's own inaction,
negligence or laches. (See Popat &
Kotecha Property v. SBI Staff Assn.
[Popat & Kotecha Property v. SBI
Staff Assn., (2005) 7 SCC 510] ,
Rajender Singh v. Santa Singh
[Rajender Singh v. Santa Singh,
(1973) 2 SCC 705] and Pundlik
Jalam Patil v. Jalgaon Medium
Project [Pundlik Jalam Patil v.
Jalgaon Medium Project, (2008) 17
SCC 448 : (2009) 5 SCC (Civ)
907].) ...."
(emphasis supplied)
59. Likewise, merely because the
Government is involved, a different
yardstick for condonation of delay
cannot be laid down. This was
felicitously stated in Postmaster
General v. Living Media (India) Ltd.
[Postmaster General v. Living
Media (India) Ltd., (2012) 3 SCC
563 : (2012) 2 SCC (Civ) 327 :
(2012) 2 SCC (Cri) 580 : (2012) 1
SCC (L&S) 649] ["Postmaster
General"], as follows : (SCC pp.
573-74, paras 27-29).........."
......
63. Given the aforesaid and the
object of speedy disposal sought to
be achieved both under the
Arbitration Act and the Commercial
Courts Act, for appeals filed under
Section 37 of the Arbitration Act
that are governed by Articles 116
and 117 of the Limitation Act or
- 28 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
Section 13(1-A) of the Commercial
Courts Act, a delay beyond 90
days, 30 days or 60 days,
respectively, is to be condoned by
way of exception and not by way of
rule. In a fit case in which a party
has otherwise acted bona fide and
not in a negligent manner, a short
delay beyond such period can, in
the discretion of the court, be
condoned, always bearing in mind
that the other side of the picture is
that the opposite party may have
acquired both in equity and justice,
what may now be lost by the first
party's inaction, negligence or
laches.
.....
65. Apart from this, there is a long
delay of 131 days beyond the 60-
day period provided for filing an
appeal under Section 13(1-A) of
the Commercial Courts Act. There
is no explanation worth the name
contained in the condonation of
delay application, beyond the usual
file-pushing and administrative
exigency. This appeal is therefore
dismissed.
....
.....
67. That apart, on the facts of this
appeal, there is a long delay of 75
days beyond the period of 60 days
provided by the Commercial Courts
Act. Despite the fact that a certified
copy of the District Court's
judgment was obtained by the
respondent on 27-4-2019, the
appeal was filed only on 9-9-2019,
the explanation for delay being:
"2. That, the certified copy of
the order dated 1-4-2013 was
- 29 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
received by the appellant on
27-4-2019. Thereafter the
matter was placed before the
CGM purchase MPPKVVCL for
the compliance of the order.
The same was then sent to the
law officer, MPPKVVCL for
opinion.
3. That after taking opinion for
appeal, and approval of the
authorities concerned, the
officer-in-charge was appointed
vide order dated 23-7-2019.
4. That, thereafter due to bulky
records of the case and for
procurement of the necessary
documents some delay has
been caused however, the
appeal has been prepared and
filed pursuant to the same and
further delay.
5. That due to the aforesaid
procedural approval and since
the appellant is a public entity
formed under the Energy
Department of the State
Government, the delay caused
in filing the appeal is bona fide
and which deserve[s] to be
condoned."
......
69. In the civil appeal arising out of
SLP (C) Diary No. 18079 of 2020,
there is a huge delay of 227 days in
filing the appeal, and a 200-day
delay in refiling. The facts of this
case also show that there was no
sufficient cause whatsoever to
condone such a long delay. The
impugned judgment of the High
Court of Delhi dated 15-10-2019
[Union of India v. Associated
Construction Co., 2019 SCC OnLine
Del 10797] cannot be faulted on
this score and this appeal is
consequently dismissed.
- 30 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
(emphasis supplied) 8.1. In N.V.
International Vs State of Assam
and others5, the Hon'ble Supreme
Court held:
"4. We may only add that
what we have done in the
aforesaid judgment is to add
to the period of 90 days,
which is provided by statute
for filing of appeals under
Section 37 of the Arbitration
Act, a grace period of 30
days under Section 5 of the
Limitation Act by following
Lachmeshwar Prasad Shukul
[Lachmeshwar Prasad Shukul
v. Keshwar Lal Chaudhuri,
1940 SCC OnLine FC 10 :
AIR 1941 FC 5] , as also
having regard to the object
of speedy resolution of all
arbitral disputes which was
uppermost in the minds of
the framers of the 1996 Act,
and which has been
strengthened from time to
time by amendments made
thereto. The present delay
being beyond 120 days is not
liable, therefore, to be
condoned."
(emphasis supplied)
3.28. By relying on Food Corporation of India
Learned counsel submits that the Hon'ble High
Court of Telangana considered the principles
laid down by the Hon'ble Supreme Court in
Government of Maharashtra (Water
Resources Department) v. Borse Brothers
- 31 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
Engineers & Contractors Private Limited as
well as N.V. International v. State of
Assam . Learned counsel submits that the
aforesaid decisions unequivocally reiterate that
the law of limitation in matters arising under
the Arbitration and Conciliation Act, 1996 is
required to be applied with strictness, having
regard to the legislative objective of ensuring
expeditious resolution of disputes and finality of
arbitral awards.
3.29. Referring to the observations of the Hon'ble
Supreme Court in Borse Brothers , learned
counsel submits that the expression "sufficient
cause" occurring in limitation statutes cannot
be construed in an unrestricted or liberal
manner so as to condone negligence, inaction
or lack of bona fides. The Hon’ble Supreme
Court has repeatedly held that limitation
provisions are founded upon public policy and
are intended to secure certainty, finality and
diligence in legal proceedings. The Hon’ble
Supreme Court has also observed that a party
seeking condonation of delay must furnish a
satisfactory and bona fide explanation and that
mere administrative difficulties, movement of
- 32 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
files, procedural approvals or departmental
formalities cannot automatically constitute
sufficient cause.
3.30. Learned counsel further submits that the
Hon'ble Supreme Court in Borse Brothers has
specifically disapproved explanations founded
upon internal administrative procedures,
obtaining opinions from legal departments,
appointment of officers-in-charge, movement of
files between departments and similar
bureaucratic processes. The Hon’ble Supreme
Court has categorically held that such routine
explanations cannot justify condonation of
delay, particularly in arbitration matters where
expedition is the underlying legislative
objective.
3.31. Placing reliance on the observations extracted
in the aforesaid judgment, learned counsel
submits that the Hon’ble Supreme Court has
reaffirmed the well-established principle that
courts are not empowered to extend limitation
on equitable considerations. Merely because a
party may suffer hardship on account of expiry
of limitation, the statutory mandate cannot be
- 33 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
diluted. The maxim dura lex sed lex — "the law
is hard, but it is the law" — has been
specifically recognised and applied by the
Supreme Court while interpreting limitation
provisions.
3.32. Learned counsel further submits that the
Hon’ble Supreme Court has emphasised that
limitation statutes are founded on public policy,
intended to suppress stale claims, promote
diligence and ensure certainty in legal relations.
Therefore, once the legislature has prescribed a
specific period of limitation together with a
limited power of condonation, the Court is duty-
bound to give full effect to the statutory
scheme without being influenced by
considerations of sympathy or hardship.
3.33. By relying on the aforesaid decision, learned
counsel contends that the question of limitation
in the present matter has to be examined with
full rigour and in strict conformity with the
provisions of Section 34(3) of the Act.
According to him, even if the consequence of
applying the limitation provision strictly may
appear harsh in a given case, such hardship
- 34 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
cannot furnish a ground for extending the
period prescribed by Parliament.
3.34. It is his submission that the arbitral award in
the present case was pronounced on
26.08.2022. Therefore, even assuming that the
respondent was entitled to avail the entire
statutory period of three months together with
the additional grace period of thirty days
contemplated under the proviso to Section
34(3), the challenge to the award ought to
have been instituted within the outer limit
prescribed by law. Once the said period
expired, the Court ceased to possess
jurisdiction to entertain the challenge.
3.35. Learned counsel submits that the explanation
offered by the respondent, namely that time
was consumed in obtaining approvals from the
concerned authorities and in completing
internal administrative formalities, is precisely
the kind of explanation which has been
repeatedly rejected by the Hon'ble Supreme
Court. Such reasons, according to him, cannot
constitute "sufficient cause" within the meaning
of Section 34(3) of the Act.
- 35 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
3.36. He therefore contends that the Commercial
Court failed to appreciate the strict limitation
regime governing arbitral proceedings and
proceeded to condone the delay on
considerations which are legally impermissible.
The impugned order, according to learned
counsel, effectively defeats the legislative intent
underlying the Arbitration and Conciliation Act,
namely the speedy resolution of disputes and
finality of arbitral awards.
3.37. On these grounds, learned counsel submits that
the order dated 19.04.2024 passed by the
Commercial Court condoning the delay is
contrary to the settled principles governing
limitation under the Arbitration and Conciliation
Act and is therefore liable to be set aside.
4. Heard Sri.Sunil Kumar H., learned counsel for the
petitioner and learned AGA for the respondents and
perused the papers.
5. The short, but important, question that arises for
consideration is
“Whether the petition filed by the respondent
under Section 34 of the Arbitration and
Conciliation Act, 1996 ("the Act") was
- 36 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
presented within the period prescribed under
Section 34(3) of the Act and, if not, whether
the delay fell within the statutorily condonable
period and was supported by sufficient cause?
6. Sub-section (3) of Section 34 of the Arbitration and
Conciliation Act, 1996 is reproduced hereunder for
easy reference:
“34(3) An application for setting aside
may not be made after three months
have elapsed from the date on which
the party making that application had
received the arbitral award or, if a
request had been made under section
33, from the date on which that request
had been disposed of by the arbitral
tribunal:
Provided that if the Court is satisfied
that the applicant was prevented by
sufficient cause from making the
application within the said period of
three months it may entertain the
application within a further period of
thirty days, but not thereafter.”
7. The Arbitration and Conciliation Act, 1996 was
enacted with the avowed object of reducing judicial
intervention in arbitral proceedings and ensuring
speedy and final resolution of disputes. The limitation
prescribed under Section 34(3) is therefore not a
mere procedural requirement but is an integral part
- 37 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
of the legislative policy intended to confer finality
upon arbitral awards within a definite timeframe.
8. The provision strikes a careful balance between two
competing considerations. On the one hand, a party
aggrieved by an arbitral award must be afforded a
reasonable opportunity to challenge the same. On
the other hand, the successful party is entitled to
certainty and finality and ought not to be subjected
to indefinite uncertainty regarding enforcement of
the award. It is in furtherance of this balance that
Parliament has prescribed a limitation period of three
months coupled with a narrowly circumscribed grace
period of thirty days.
9. A plain reading of Section 34(3) makes it clear that
the starting point for computation of limitation is not
the date on which the award is pronounced, nor the
date on which the arbitral proceedings conclude, but
the date on which the party making the application
"had received the arbitral award". The legislature has
consciously employed the expression "received the
arbitral award" and not "became aware of the award"
or "the award was pronounced".
10. The significance of the expression "received the
arbitral award" has repeatedly been emphasised by
- 38 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
the Hon'ble Supreme Court. The reason is not
difficult to understand. A party can effectively
exercise its statutory right to challenge an award
only after obtaining access to the award and
understanding the findings, reasoning and operative
directions contained therein. Mere knowledge that an
award has been passed does not necessarily equip a
party to challenge the award. It is the receipt of the
award that enables a party to assess its rights,
obtain legal advice and determine whether a
challenge is required.
11. The second limb of Section 34(3), relating to disposal
of a request under Section 33 of the Act, is
admittedly not attracted in the present case.
Therefore, the controversy is confined to determining
the date on which the respondent received the
arbitral award and whether the petition was filed
within the period prescribed therefrom.
12. The proviso to Section 34(3) confers a limited
discretion upon the Court. The structure of the
provision itself indicates that the legislature has
treated the initial period of three months and the
additional period of thirty days differently.
- 39 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
13. The first period of three months is available as a
matter of right. The second period of thirty days is
not available automatically. It becomes available only
if the applicant demonstrates that sufficient cause
prevented filing within the original period of three
months. Thus, the proviso is not an extension of
limitation as a matter of course. It is a statutory
indulgence granted in deserving cases where the
Court is satisfied about the existence of sufficient
cause.
14. Three distinct principles emerge from a conjoint
reading of Section 34(3) and its proviso:
14.1. a petition under Section 34 must ordinarily be
filed within three months from the date of
receipt of the arbitral award;
14.2. a delay beyond the said period may be
condoned only if the petition is filed within the
further period of thirty days and sufficient
cause is established; and
14.3. upon expiry of the aggregate period
contemplated under the provision, the Court
becomes functus officio insofar as extension of
- 40 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
limitation is concerned and lacks jurisdiction to
entertain the challenge.
15. The first issue that therefore requires determination
is whether the respondent can be said to have
received the arbitral award on 26.08.2022 when the
award was pronounced, or on 01.09.2022 when the
email enclosing the minutes of the proceedings was
sent, or on 03.11.2022 when the signed copy of the
award was admittedly received.
16. The minutes of proceedings dated 26.08.2022 have
been extracted hereinabove. A perusal thereof
indicates that the award was pronounced on the said
date. However, it is equally evident that no
representative of the respondent was present when
the award came to be pronounced. The minutes
merely record the pronouncement of the award and
direct circulation of the proceedings.
17. The records do not disclose that a signed copy of the
award was delivered to the respondent on the said
date. Mere pronouncement of the award, in the
absence of the respondent and without delivery of
the award, cannot constitute receipt of the award
within the meaning of Section 34(3).
- 41 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
18. Reliance was sought to be placed on the email dated
01.09.2022. A careful examination of the said
communication indicates that what was transmitted
was only the minutes of the proceedings. The award
itself was not enclosed. The email therefore merely
informed the recipient that proceedings had been
conducted and the award had been pronounced. It
did not communicate the contents, reasoning,
findings or operative directions contained in the
award.
19. Knowledge that an award has been pronounced is
fundamentally different from receipt of the award
itself. A party cannot be expected to formulate
grounds under Section 34 merely because it is aware
that an award has been passed. What is relevant is
knowledge of the award itself and not merely
knowledge of its existence.
20. There is no material placed before this Court to
indicate that the respondent was furnished with the
award, made aware of its contents, acted upon its
directions or otherwise demonstrated knowledge of
the findings recorded therein prior to 03.11.2022.
21. The petitioner has not produced any
acknowledgment, communication or
- 42 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
contemporaneous material establishing that the
award had in fact been served upon the respondent
prior to the said date. In the absence of such
material, this Court cannot proceed on assumptions
or presumptions regarding receipt of the award.
22. Significantly, the receipt of the award by the
respondent on 03.11.2022 is not in dispute. Once
that factual position is accepted, the legal
consequence necessarily follows. The limitation
contemplated under Section 34(3) must commence
from 03.11.2022.
23. Any other interpretation would amount to rewriting
the statutory provision and substituting the
expression "receipt of the arbitral award" with
"knowledge of the award". Such an interpretation
would be contrary to the plain language employed by
Parliament.
24. Computing limitation from 03.11.2022, the initial
period of three months expired on 02.02.2023. Had
the respondent filed the petition on or before the said
date, no question of condonation would have arisen.
25. The petition admittedly came to be filed on
21.02.2023. Thus, while the petition was beyond the
- 43 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
original period of ninety days, it was filed within the
additional period of thirty days contemplated under
the proviso.
26. The next issue therefore is whether sufficient cause
has been established for the delay.
27. The expression "sufficient cause" is incapable of
precise definition and must necessarily be
determined on the facts of each case. While the
expression cannot be interpreted so liberally as to
render limitation meaningless, it also cannot be
construed in a manner that defeats substantial
justice where the party has acted bona fide and with
reasonable diligence.
28. The records produced by the respondent assume
significance in this regard. The documents disclose
that immediately upon receipt of the award on
03.11.2022, steps were initiated for examining the
feasibility of challenging the award. A Government
Advocate was appointed on 23.11.2022. Legal
opinion was obtained on 21.01.2023. Thereafter, the
matter was processed at various administrative
levels and approval to initiate proceedings was
accorded under Government Order dated
- 44 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
14.02.2023. The petition was thereafter filed on
21.02.2023.
29. The chronology does not indicate complete inaction
or negligence. On the contrary, it discloses
continuous movement of the matter through various
stages culminating in the filing of the petition.
30. It is no doubt true that administrative procedures
cannot invariably constitute sufficient cause. If
internal procedures are permitted to justify every
delay, the limitation prescribed under Section 34(3)
would become illusory. However, the facts of each
case must be independently assessed.
31. In the present case, the delay is not one extending
beyond the outer limit prescribed by the statute. Nor
is it a case where the respondent remained dormant
for months together and thereafter sought to revive
a stale claim. The challenge was instituted within the
statutorily condonable period. The material on record
demonstrates that steps were continuously being
taken for obtaining legal opinion and governmental
approval. The Commercial Court, upon appreciation
of these facts, has exercised its discretion in favour
of condonation.
- 45 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
32. The scope of interference with such exercise of
discretion is necessarily limited. Unless the discretion
is shown to be arbitrary, capricious, perverse or
contrary to settled principles of law, this Court would
be slow to substitute its own view merely because
another view is possible.
33. The decisions relied upon by the petitioner do not
advance his case. Bhimashankar reiterates the
strict limitation regime under Section 34(3), but
simultaneously recognises the statutory discretion
available within the additional period of thirty days.
Neeraj Sharma turned upon peculiar facts where
the party had acted upon the award despite alleging
non-receipt. No such circumstance exists in the
present case. Food Corporation of India reiterates
that limitation must be applied strictly. The said
principle is fully respected in the present matter
because the petition has not been entertained
beyond the period permitted by statute.
34. Thus, on a cumulative consideration of the statutory
scheme, the factual matrix and the documents
placed on record, I am of the considered view that
34.1. the respondent received the arbitral award on
03.11.2022;
- 46 -
NC: 2026:KHC:29276
WP No. 18183 of 2024
HC-KAR
34.2. limitation commenced from the said date;
34.3. the petition filed on 21.02.2023 was within the
additional thirty-day period contemplated under
the proviso to Section 34(3);
34.4. sufficient cause was established for the delay
beyond the initial period of three months; and
34.5. the Commercial Court was justified in exercising
its discretion to condone the delay.
35. The impugned order does not suffer from any
jurisdictional error, perversity or illegality warranting
interference by this Court in exercise of its
supervisory jurisdiction. The challenge therefore fails
and is liable to be rejected.
Accordingly, the petition stands dismissed.
Sd/-
(SURAJ GOVINDARAJ)
JUDGE
MDS
List No.: 1 Sl No.: 46