Bharat Sanchar Nigam Limited vs Royal India Technoprojects Limited
- Court
- Delhi High Court
$~40
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO (COMM) 134/2026, CM APPLs. 30636/2026,
30637/2026, 30638/2026, 30639/2026 & 30640/2026
BHARAT SANCHAR NIGAM LIMITED .....Appellant
Through: Mr. M.C. Kochhar and Ms.
Nikaasha Dogra, Advs.
versus
ROYAL INDIA TECHNOPROJECTS
LIMITED .....Respondent
Through:
CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT (ORAL)
% 07.05.2026
C. HARI SHANKAR, J.
1. This appeal assails orders dated 5 September 2023 and 27
November 2025, passed by the learned District Judge (Commercial
1
Courts-03) South West, Dwarka Courts, New Delhi .
2. An arbitral award, rendered in arbitral proceedings between the
appellant and the respondent, was challenged by the appellant under
2
Section 34 of the Arbitration and Conciliation Act, 1996 by way of
OMP (Comm) 35/2023 before the learned Commercial Court. On 5
September 2023, the said OMP was dismissed as withdrawn by
learned Counsel for the appellant. The order dated 5 September 2023
1
“learned Commercial Court”, hereinafter
2
“1996 Act”, hereinafter
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:11.05.2026
16:28:49
FAO (COMM) 134/2026 Page 1 of 5
read thus:
“Ld. Counsel for the petitioner has stated that he has been
authorized by the petitioner to state that the petitioner may be
allowed to withdraw the present petition with liberty to take
appropriate legal recourse. The present petition may, thus, be
dismissed as withdrawn, with the liberty as aforesaid.
Statement of Sh. Diptimaan Acharya, Ld. Counsel for the
petitioner, to the above effect, has been separately recorded.
Heard. In view of the aforsaid, the present petition is dismissed as
withdrawn, with liberty to the petitioner to take appropriate legal
recourse.”
3. 575 days after the aforesaid order was passed, the appellant
filed Misc DJ 246/2025 seeking restoration of the OMP.
4. In the first place, the said restoration application was not even
maintainable, as an order passed disposing of a petition under Section
34 of the 1996 Act is only appealable under Section 37 thereof.
5. Besides, the only explanation tendered for filing the restoration
application 575 days after the Section 34 petition had been disposed of
was that the Counsel for the appellant informed the appellant that he
was required to re-file the petition in some other forum. This
submission was apparently merely made for the sake of having the
restoration application entertained, as it is not even the appellant’s
case that, in terms of the purported advice given by its Counsel, the
appellant moved any other forum.
6. The learned Commercial Court, by order dated 27 November
2025, dismissed the restoration application, observing that the
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:11.05.2026
16:28:49
FAO (COMM) 134/2026 Page 2 of 5
appellant had miserably failed to assign any reason for delay in filing
the restoration application. Administrative lethargy and laxity in the
office of the appellant, it was noted, could not constitute a legitimate
basis to condone delay as inordinate as 575 days.
7. The appellant has now preferred the present appeal challenging
the orders dated 5 September 2023 and 27 November 2025 supra
passed by the learned Commercial Court.
8. The appeal is accompanied by CM Appl. 30639/2026, seeking
condonation of delay in filing the present appeal. The application,
which is all of five paragraphs, reads thus:
“1. That the accompanying appeal against the orders dated
05.09.2023 and ordersdated 27.11.2025 passed by the Ld. District
Judge in OMP (Comm) No. 35/2023 and in Misc DJ No. 246/2025
in OMP (Comm) No. 35/2023 in the case titled as "Bharat Sanchar
Nigam Limited vs Royal India Techno projects Ltd.". The contents
of the appeal may be read as a part and parcel of the present
application and are not repeated for the sake of brevity.
2. That the present appeal has been preferred by the Appellant
as the counsel for the Appellant without being authorized to
withdraw the appeal, made a statement on behalf of the Appellant
to withdraw the appeal and in fact withdrew the appeal without any
reason leaving appellant in a state which is causing irreparable loss
and injury.
3. That in fact on account of counsel conduct, the appellant
had to hire a new advocate and gave the brief after arranging
complete file who inturn prepared and filed this appeal. The filing
of appeal unfortunately has been delay by 809 days and there is
delay in filing the appeal of days.
4. That the present application is being made in the interest of
justice and is bonafide in nature.
5. That the appellant will suffer irreparable loss and injury if
the delay is not condoned by this Hon'ble Court.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:11.05.2026
16:28:49
FAO (COMM) 134/2026 Page 3 of 5
PRAYER
In the above stated facts and circumstances, it is therefore most
respectfully prayed that this Hon'ble Court may be pleased to:
a) Condone the delay of 809 days in filing the present
appeal on bealf of the Appellant,
b) Pass any other/further orders as this Hon'ble Court
may deem fit in the facts and circumstances of the
captioned proceedings.”
9. It is obvious that the appellant is least interested in prosecuting
these proceedings. Court after Court have been moved merely for the
sake of formality.
10. As there is no tenable explanation for the condonation of delay
of 575 days in filing the restoration application before the learned
Commercial Court which, even otherwise, was not maintainable in
law, we decline to entertain any challenge to the order dated 5
September 2023, 809 days after the order has been passed.
11. The only challenge which is within time, therefore, is to the
challenge to the order dated 27 November 2025, whereby the learned
Commercial Court dismissed the restoration application on delay.
12. No sustainable ground for entertaining such a challenge exists.
The application was itself not maintainable in the first instance.
Moreover, the learned Commercial Court has correctly observed that
there was no explanation worth the name for condonation of delay of
575 days.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:11.05.2026
16:28:49
FAO (COMM) 134/2026 Page 4 of 5
13. We may note that, in commercial matters, the Supreme Court
has held in Jharkhand Urja Utpadan Nigam Limited v. Bharat
3
Heavy Electricals Limited and Government of Maharashtra v.
4
Borse Brothers Engineers & Contractors Pvt Ltd , that delay has to
be viewed seriously and has to be completely explained with cogent
material on record. The latitude which a Court may otherwise display
while dealing with applications for condonation of delay in ordinary
suits or appeals cannot be exercised while dealing with the
commercial matters.
14. We, therefore, are of the view that no case is made out for
issuance of the notice in this appeal. The challenge to the order dated
5 September 2023 is hopelessly barred by time. The order dated 27
November 2025 is correct and does not call for any interference for us.
15. The appeal is accordingly dismissed in limine .
C. HARI SHANKAR, J.
OM PRAKASH SHUKLA, J.
MAY 7, 2026 /aky
3
2025 SCC OnLine SC 910
4
(2021) 6 SCC 460
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:11.05.2026
16:28:49
FAO (COMM) 134/2026 Page 5 of 5