SRI K C ANNEGOWDA vs THE STATE OF KARNATAKA
- Court
- Karnataka High Court
- 1 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
TH
DATED THIS THE 8 DAY OF OCTOBER, 2026
BEFORE
THE HON'BLE MR. JUSTICE R. NATARAJ
WRIT PETITION NO. 12472 OF 2026 (CS-RES)
C/W
WRIT PETITION NO. 2690 OF 2026 (CS-RES),
WRIT PETITION NO. 18567 OF 2026 (CS-RES)
IN WP No. 12472/2026
BETWEEN:
1. SRI K.C. ANNEGOWDA
AGED ABOUT 55 YEARS,
PRESIDENT,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ST TH
NO.11, 1 MAIN ROAD, 5 CROSS,
BEHIND VARUN MOTORS,
DEFENCE COLONY, BENGALURU-560073.
2. SRI. BHEEMA RAO V.
AGED ABOUT 66 YEARS,
VICE-PRESIDENT,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH
NO.10, GANGOTHRI, 7 F MAIN ROAD,
TH
19 A CROSS ROAD,
BEHIND MURALI TAKIES,
MUTHYALANAGARA, BENGALURU-560054.
3. SRI.SRINIVASA.N.
AGED ABOUT 62 YEARS,
DIRECTOR,
Digitally
signed by
HEMALATHA J
Location:
HIGH COURT
OF
KARNATAKA
- 2 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH ND
NO.69, 11 CROSS, 2 STAGE,
NGEF LAYOUT, NAGARABHAVI,
BANGALORE-560072.
4. SRI RAJU K G
AGED ABOUT 62 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH TH
NO.7, 5 CROSS, 4 B MAIN ROAD,
CHANDANA LAYOUT, SUNKADAKATTE,
BENGALURU-560091.
5. SRI. VENKATESH
AGED ABOUT 68 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ST
NO.272, NEW NO.562/3, 1 MAIN ROAD,
ST
1 CROSS, HIG COLONY,
ND
RMV 2 STAGE, DOLLARS COLONY,
BENGALURU-560094.
6.
SRI MANJUNATH K S,
AGED ABOUT 58 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ST RD
NO.16, 1 G H LAYOUT, 3 BLOCK,
JAYANAGARA, BENGALURU-560011.
7.
SRI SHASHIDHAR P G,
AGED ABOUT 46 YEARS,
- 3 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH TH
NO 1034, 14 CROSS, 9 MAIN,
JUDICIAL LAYOUT, GKVK POST,
BANGALORE-560065.
8.
SRI BALAKRISHNA KUMAR B
AGED ABOUT 52 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING CO-
OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ND TH
NO.54/7, 2 CROSS, 5 B MAIN ROAD,
NRI LAYOUT, RAMAMURTHYNAGARA,
BENGALURU-560016.
9. SRI. YATHEESH. R.
AGED ABOUT 58 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH ND
NO.288, 17 CROSS, 32 MAIN,
TH
6 STAGE, JP NAGAR,
BANGALORE-560078.
10. SRI. HANUMANTHAPPA H
AGED ABOUT 66 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
SHERISTADAR (RETD),
NO.540, NEAR BAIP OFFICE,
SHARADANAGARA, TIPTUR TOWN,
TUMKUR DISTRICT.
- 4 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
11. SMT. BHAGYA. T,
AGED ABOUT 52 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
NO.119/40, SRI LALITHA VAIBHAVA NILAYA,
SHIVU LAYOUT, BENGALURU UNIVERSITY ROAD,
MARIYAPPANA PALYA,
BENGALURU-560056.
…PETITIONERS
(BY SRI. ASHOK HARANAHALLI, SENIOR ADVOCATE FOR
SRI.MANJUNATHA REDDY N., ADVOCATE)
AND:
1. THE STATE OF KARNATAKA
DEPARTMENT OF CO-OPERATION
REPTED BY ITS PRINCIPAL SECRETARY
M.S.BUILDING, DR.B.R.AMBEDKAR VEEDHI,
BENGALURU-560 001.
2. THE REGISTRAR OF CO-OPERATIVE SOCIETIES
IN KARNATAKA, NO.1,
ALI ASKER ROAD,
BENGALURU-560052.
3.
THE ADDITIONAL REGISTRAR OF
CO-OP SOCIETIES (H AND M),
NO.1, OFFICE OF THE REGISTRAR OF
CO-OPERATIVE SOCIETIES IN KARNATAKA,
ALI-ASKAR ROAD,
BENGALURU-560 052.
4. THE KARNATAKA STATE JUDICIAL DEPARTMENT
EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
HAVING ITS REGISTERED OFFICE AT NO.178,
II FLOOR, CENTRAL
SQUARE PLAT FORM ROAD,
SHESHADRIPURAM,
- 5 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
BENGALURU-560020.
REPTED BY ITS SECRETARY.
5. SMT.PANKAJA.S,
W/O KRISHNA KUMAR.B.A,
ND
R/AT NO.30, 2 CROSS,
HARIKUMAR GARDEN, MANJUNATHANAGAR,
BAGALAGUNTE, BENGALURU-560073.
…RESPONDENTS
(BY SMT. POOJA M KOORSE, HCGP FOR R1 TO R3;
SRI. M.R.RAJAGOPAL, SENIOR COUNSEL FOR SRI.P.ANAND,
ADVOCATE FOR R4;
SRI. M.N.UMASHANKAR, ADVOCATE FOR C/R5)
THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF THE
CONSTITUTION OF INDIA PRAYING TO QUASH THE ORDER DATED
10.03.2026 PASSED IN PROCEEDINGS BEARING NO.HSG-
2/94/HHS/2025-26, NO.HSG-2/95/HHS/2025-26, NO.HSG-
2/98/HHS/2025-26, NO.HSG-2/99/HHS/2025-26, NO.HSG-
2/100/HHS/2025-26, NO.HSG-2/101/HHS/2025-26, NO.HSG-
2/102/HHS/2025-26, NO.HSG-2/103/HHS/2025-26, NO.HSG-
2/104/HHS/2025-26, NO.HSG-2/105/HHS/2025-26 AND NO.HSG-
2/106/HHS/2025-26 VIDE ANNEXURES-AJ, AJ1 TO AJ10 AND ETC.
IN WP NO. 2690/2026
BETWEEN:
THE KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO OPERATIVE SOCIETY LTD.,
HAVING ITS REGISTERED OFFICE AT
NO.178, II FLOOR,
CENTRAL SQUARE PLAT FORM ROAD,
SHESHADRIPURAM, BENGALURU-560020.
REPTED BY ITS SECRETARY
KARNATAKA CO-OPERATIVE SOCIETY
REGISTRATION ACT 1956
- 6 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
...PETITIONER
(BY SRI.M.R.RAJGOPAL, SENIOR COUNSEL FOR
SRI.ANAND P., ADVOCATE)
AND:
1. THE STATE OF KARNATAKA
DEPARTMENT OF CO-OPERATION
REPTED BY ITS PRINCIPAL SECRETARY
M.S.BUILDING, DR.B.R.AMBEDKAR VEEDHI,
BENGALURU-560 001.
2. THE REGISTRAR OF CO-OPERATIVE
SOCIETIES IN KARNATAKA,
NO.1, ALI ASKER ROAD, BENGALURU-560052.
3.
THE ADDITIONAL REGISTRAR OF CO-OP SOCIETIES
(H AND M), NO.1,
OFFICE OF THE REGISTRAR OF CO-OPERATIVE
SOCIETIES IN KARNATAKA,
ALI-ASKAR ROAD, BANGALORE-560 052.
4. SMT. PANKAJA S.
W/O KRISHNA KUMAR B.A.,
AGED ABOUT 46 YEARS,
WORKING AS ASSISTANT REGISTRAR(SS)
FF-59B, HIGH COURT OF KARNATAKA
BENGALURU - 560001
[AMENDED VIDE ORDER DATED 10.07.2026]
...RESPONDENTS
(BY SMT. POOJA M KOORSE, HCGP FOR R1 TO R3;
SRI. ABHINAV R. ADVOCATE FOR SRI. GURUPRASAD HEGDE,
ADVOCATE FOR R4)
THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF THE
CONSTITUTION OF INDIA PRAYING TO ISSUE A WRIT IN THE
NATURE OF PROHIBITION FOR BEARING THE RESPONDENT NO.3
FROM CONDUCTING THE PROCEEDINGS PENDING ON HIS FILE IN
- 7 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
SURCHARGE CASE NO. ANI(VA AND E)/D2/ADHIBHARA/07/2025-26
INITIATED SUO-MOTO UNDER SECTION 69 OF KCS ACT, 1959 VIDE
ANNEXURE-Z AND ETC.
IN WP NO. 18567/2026
BETWEEN:
1.
SRI K C ANNEGOWDA
AGED ABOUT 55 YEARS,
PRESIDENT, KARNATAKA STATE
JUDICIAL DEPARTMENT EMPLOYEES
HOUSE BUILDING CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH
NO. 11. 1 MAINROAD, 5 CROSS,
BEHIND VARUN MOTORS,
DEFENCE COLONY, BENGALURU-560073.
2.
SRI. BHEEMA RAO V.
AGED ABOUT 65 YEARS,
VICE-PRESIDENT,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH
NO. 10. GANGOTHRI, 7 F MAIN ROAD,
TH
19 A CROSS ROAD, BEHIND MURALI TAKIES,
MUTHYALANAGARA, BENGALURU-560054.
3. SRI. SRINIVASA.N.
AGED ABOUT 62 YEARS, DIRECTOR,
KARNATAKA STATE JUDICIAL DEPARTMENT
EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
TH ND
NO.69, 11 CROSS, 2 STAGE, NGEF LAYOUT,
NAGARABHAVI, BANGALORE-560072.
4. SRI. RAJU K G.
AGED ABOUT 62 YEARS,
DIRECTOR, KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD..
- 8 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
(NOW UNDER DISQUALIFICATION)
TH TH
NO.7. 5 CROSS, 4 B MAIN ROAD,
CHANDANALAYOUT, SUNKADAKATTE,
BENGALURU-560091.
5.
SRI. VENKATESH
AGED ABOUT 68 YEARS,
DIRECTOR, KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ST
NO.272. NEW NO.562/3, 1 MAIN ROAD,
ST ND
1 CROSS, HIG COLONY. RMV 2 STAGE.
DOLLARS COLONY. BENGALURU-560094,
6.
SRI. MANJUNATH K S.
AGED ABOUT 58 YEARS,
DIRECTOR, KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE BUILDING
CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ST
NO.16, 1 G H LAYOUT,
RD
3 BLOCK, JAYANAGARA,
BENGALURU-560011.
7. SRI. SHASHIDHAR P G.
AGED ABOUT 46 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD..
(NOW UNDER DISQUALIFICATION)
TH TH
NO.1034, 14 CROSS, 9 MAIN,
JUDICIAL LAYOUT, GKVK POST,
BANGALORE-560065.
8. SRI. BALAKRISHNA KUMAR B
AGED ABOUT YEARS,
DIRECTOR, KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
ND TH
NO.54/7, 2 CROSS, 5 B MAIN ROAD,
- 9 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
NRI LAYOUT, RAMAMURTHYNAGARA,
BENGALURU-560016.
9. SRI. YATHEESH. R.
AGED ABOUT 58 YEARS.
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD.
(NOW UNDER DISQUALIFICATION)
TH ND TH
NO.288, 17 CROSS, 32 MAIN, 6 STAGE,
JP NAGAR, BANGALORE-560078.
10.
SRI. HANUMANTHAPPA H
AGED ABOUT 66 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
SHERISTADAR (RETD), NO.540,
NEAR BAIP OFFICE, SHARADANAGARA,
TIPTUR TOWN, TUMKUR DISTRICT,
11. SMT BHAGYA. T.
AGED ABOUT 52 YEARS,
DIRECTOR,
KARNATAKA STATE JUDICIAL
DEPARTMENT EMPLOYEES HOUSE
BUILDING CO-OPERATIVE SOCIETY LTD.,
(NOW UNDER DISQUALIFICATION)
NO.119/40, SRI LALITHA VAIBHAVA NILAYA,
SHIVU LAYOUT, BENGALURU UNIVERSITY ROAD,
MARIYAPPANA PALYA,
BENGALURU-560056.
...PETITIONERS
(BY SRI. ASHOK HARANAHALLI, SENIOR ADVOCATE FOR
SRI. MANJUNATHA REDDY N., ADVOCATE)
AND:
- 10 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
1. THE STATE OF KARNATAKA
DEPARTMENT OF CO-OPERATION
REPTED BY ITS PRINCIPAL SECRETARY
M.S.BUILDING,
DR. B.R.AMBEDKAR VEEDHI,
BENGALURU-560 001
2.
THE REGISTRAR OF CO-OPERATIVE
SOCIETIES IN KARNATAKA,
NO. 1. ALI ASKER ROAD,
BENGALURU-560052.
3.
THE ADDITIONAL REGISTRAR
OF CO-OP SOCIETIES (H AND M),
NO.1, OFFICE OF THE REGISTRAR OF
CO-OPERATIVE SOCIETIES IN KARNATAKA.
ALI-ASKAR ROAD,
BENGALURU-560 052.
4. THE KARNATAKA STATE
JUDICIAL DEPARTMENT EMPLOYEES
HOUSE BUILDING CO-OPERATIVE SOCIETY LTD.,
HAVING ITS REGISTERED OFFICE AT NO.178
II FLOOR, CENTRAL SQUARE PLAT FORM ROAD
SHESHADRIPURAM, BENGALURU-560020
REPTED BY ITS SECRETARY
(REGISTERED UNDER KCS ACT, 1959).
5. SMT.PANKAJA.S.
WO KRISHNA KUMAR.B.A.
ND
R/AT NO.30. 2 CROSS,
HARIKUMAR GARDEN,
MANJUNATHANAGAR
BAGALAGUNTE,
BENGALURU-560073.
...RESPONDENTS
(BY SMT. POOJA M KOORSE, HCGP FOR R1 TO R3;
SRI. M.R.RAJAGOPAL, SENIOR COUNSEL FOR SRI. P. ANAND,
ADVOCATE FOR R4;
SRI. ABHINAV R., ADVOCATE FOR SRI. GURUPRASAD HEGDE,
ADVOCATE FOR C/R5)
- 11 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
THIS WP IS FILED UNDER ARTICLES 226 AND 227 OF THE
CONSTITUTION OF INDIA PRAYING TO ISSUE WRIT OF CERTIORARI
QUASHING THE ORDER BEARING NO.HSG-3/114/HHS/2024-25
DATED 01-12-2025 PASSED BY THE ADDITIONAL REGISTRAR OF
CO-OPERATIVE SOCIETIES (H AND M), BENGALURU I.E., THE
RESPONDENT NO.3 IN EXERCISE OF POWER CONFERRED UNDER
SECTION 68 OF KCS ACT, 1959, VIDE ANNEXURE-T AND ETC.
THESE PETITIONS, COMING ON FOR ORDERS, THIS DAY,
ORDER WAS MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE R. NATARAJ
ORAL ORDER
In W.P.No.12472/2026, the petitioners have sought for a
writ in the nature of certiorari to quash the order dated
10.04.2026 passed by the respondent No.3 in proceeding
bearing Nos.HSG-2:94:HHS:2025-26, HSG-2:95:HHS:2025-26,
HSG-2:98:HHS:2025-26, HSG-2:99:HHS:2025-26, HSG-
2:100:HHS:2025-26, HSG-2:101:HHS:2025-26, HSG-
2:102:HHS:2025-26, HSG-2:103:HHS:2025-26, HSG-
2:104:HHS:2025-26, HSG-2:105:HHS:2025-26 and HSG-
2:106:HHS:2025-26. The petitioners have also sought for a
writ in the nature of certiorari to quash the order bearing
No.HSG-2/03/HHS/2026-27 dated 10.04.2026 passed by the
- 12 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
respondent No.3 appointing a special officer to the respondent
No.4.
2. In W.P.No.2690/2026, the petitioner has sought for
a writ in the nature of prohibition to direct the respondent No.3
from conducting proceedings pending on his file in surcharge
case No.ANI(VA&E)/D2/ADHIBHARA/07/2025-26 initiated suo-
motu under Section 69 of the Karnataka Co-operative Societies
Act, 1959 (henceforth referred to as ‘the KCS Act’). The
petitioners have also sought for a writ in the nature of certiorari
quashing the notice bearing No. ANI(VA&E)/
D2/ADHIBHARA/07/2025-26 dated 16.01.2026 issued by the
respondent No.3.
3. In W.P.No.18567/2026, the petitioners have sought
for a writ in the nature of certiorari to quash the order bearing
No.HSG-3/114/HHS/2024-25 dated 01.12.2025 passed by the
respondent No.3 under Section 68 of the KCS Act. They have
also sought for an order to quash the order dated 30.05.2026
passed by the respondent No.2 in Appeal
No.RCS/DAP/D1/24/2025-26 under Section 106 of the KCS Act.
- 13 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
4. Since the facts in all these writ petitions are
common and interconnected, the same are captured below, so
as to avoid repetition.
5. (i) The Karnataka State Judicial Employees'
House Building Co-operative Society Limited., (henceforth
referred to as ‘Society’) is a Co-operative Society registered
under the provisions of the Karnataka Co-operative Societies
Act, 1959. The objective of the Society was to form residential
sites for allotment to its members. In order to achieve its
objectives, it proposed to form a layout of sites in different
survey numbers of Hejjala Village, Bidadi Hobli, Ramanagara
Taluk and District. It thus entered into an agreement dated
07.01.2005 with a developer, who was supposed to identify,
procure 100 acres of land for the formation of a layout, form
layout and deliver 2000 intermediate sites of various
dimensions on turnkey basis for allotment to the members of
the Society.
(ii) The Society had undertaken to pay a sum of
Rs.225/- per square feet of sital area to the Developer.
Accordingly, out of the funds of the Society, the Developer
- 14 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
procured 100 acres of land in Hejjala Village, Bidadi Hobli and
formed a residential layout in different survey numbers after
securing necessary orders of conversion, statutory clearances,
approvals, etc. It was agreed that the Developer shall convey
2000 intermediate sites to the members of the Society and he
was permitted to dispose of corner sites.
(iii) Amongst the intermediate sites formed was a site
bearing No.120 in Sy.Nos.91 and 92 of Hejjala Village, which
rd
was situate at 3 Block, measuring 20,789 square feet, which
was situate adjacent to a Park and Civic Amenity site (for short
‘CA site’). The petitioners who are the Directors of the Society
claimed that as the site was triangular in shape, the Developer
was not able to secure approval for formation of smaller
dimension sites. Therefore, he made a request in terms of his
representation dated 24.02.2023 to hand over site No.120 so
that he could convey it to the owners of Sy.No.92 where site
Nos.18, 19, 20, 22, 23, 24, 34, 35, 36, 39, 40, 41, 56, 57, 58,
61, 62 and 63 were formed, as the owners were disturbing the
purchasers of the aforesaid sites.
- 15 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
(iv) The petitioners claim that the Board of Management
convened a meeting on 11.03.2023, whereat it was resolved to
constitute a Sub-Committee under the chairmanship of
Sri.Bheem Rao, who was the Vice President of the Society. The
Committee was constituted with a specific mandate to examine
the viability of giving away site No.120 and to submit a report
to the Board. The Sub-committee invited the Developer for a
discussion and submitted an interim report dated 10.04.2023,
whereby the Developer had agreed to form six sites in site
No.120 and convey it to the members. The petitioners contend
that the mandate of the Sub-Committee stood terminated in
view of a resolution passed by the Board of Management of the
petitioners on 03.03.2024.
(v) The petitioners claim that the developer, without
bringing to the notice of the Society, sold and conveyed site
No.120 in favour of Sri.C.S.Ramesh Babu, in terms of a sale
deed dated 25.08.2023. The petitioners claim that the
Developer had done so behind their back and the respondent
No.5 herein and Sri.M.L.Prasad Rao, Directors of the Society,
informed the same to the Society in terms of their
- 16 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
communication dated 12.03.2024. This communication was
placed before the meeting of the Board on 28.04.2024.
However, the meeting was deferred due to the death of one of
the founding Directors of the Society. Thereafter, the subject
was placed before the meeting of the Board of Directors on
01.05.2024. At the said meeting, at the request of the
respondent No.5 and Sri.M.L.Prasad Rao, in terms of a letter
dated 23.04.2024, the meeting was deferred to 07.07.2024. On
07.07.2024, after holding a detailed discussion, it was resolved
to call for an explanation from the Developer regarding the sale
of site No.120 without the permission of the Society.
(vi) The petitioners claim that the Society addressed a
communication dated 15.07.2024 to the Developer, calling
upon him for an explanation regarding the sale of site No.120
without its permission. This was followed by another
communication dated 22.01.2025, in response to which, the
Developer replied on 15.03.2025 that six sites measuring 30X
50 feet are formed in site No.120 and that he is ready and
willing to register six sites in favour of the members identified
by the Society. On receipt of the aforesaid reply, when the
- 17 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
petitioners were contemplating to allot and register the
aforesaid six sites in favour of its members based on seniority,
the respondent No.3 directed a comprehensive statutory
enquiry under Section 64 of the KCS Act regarding the illegal
sale of site No.120 and other charges and appointed the
Deputy Registrar of Co-operative Societies (henceforth referred
to as ‘DRCS’) Zone-III, Bengaluru Urban District, as an Enquiry
Officer. By a communication dated 10.01.2025, the respondent
No.3 restrained the Society from allotting and registering the
sites till the respondent No.3 secured a report under Section 64
of the KCS Act.
(vii) Pursuant to the aforesaid order, the Enquiry Officer
sought for an explanation from the petitioners and the
Developer and submitted a report dated 04.10.2025 to the
respondent No.3, holding that the charges against the
petitioners and the Developer were proved. On 01.12.2025, the
respondent No.3 passed an order in exercise of power
conferred under Section 68 of the KCS Act and directed the
Society to rectify the defects pointed out in the enquiry report
and to submit a compliance report within a period of 45 days
- 18 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
from the date of receipt of the order. The respondent No.3 also
directed the Society to raise a dispute against the Developer,
purchasers and also file an interim application under Section
103 of the KCS Act for an order of attachment before judgment
in respect of the property in question.
(viii) The petitioners claim that pursuant to the order
passed by the respondent No.3, the Society raised a dispute
against the Developer and purchasers of site No.120 before the
respondent No.3 and sought a direction to the Developer to
hand over the property bearing site No.120 in order to enable
the Society to allot and register the same in favour of its
eligible members. The petitioners claim that they filed an
interim application under Section 103 of the KCS Act for
conditional attachment before judgment of the property in
question pending disposal of the dispute under Section 70 of
the KCS Act.
(ix) The petitioners claim that the President, Vice
President and other Directors of the Society had filed an appeal
under Section 106 of the KCS Act, challenging the correctness
of the order dated 01.12.2025 passed by the respondent No.3
- 19 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
in exercise of the power conferred under Section 68 of the KCS
Act before the respondent No.2. The petitioners contend that
notice of this appeal is issued to the respondents in the appeal.
6. The petitioners contend that the respondent No.3,
despite the compliance of the directions issued under Section
68 of the KCS Act and during pendency of the appeal before the
respondent No.2 against the order passed under Section 68 of
the KCS Act, initiated surcharge proceedings under Section 69
of the KCS Act to restore a sum of Rs.2,61,62,000/-, which was
the value of the site bearing No.120. Being aggrieved by the
said surcharge proceedings, the Society has filed
W.P.No.2690/2026. During the pendency of the appeal under
Section 106 of the KCS Act, the respondent No.3 initiated
proceedings under Section 29-C(8)(b)(c) and (d) of the KCS
Act, to disqualify the petitioners for a period of 5 years.
Thereafter, respondent No.3 passed an order disqualifying the
petitioners. Being aggrieved by the said order, the petitioners
have filed W.P.No.12472/2026.
7. During the pendency of W.P.No.12472/2026, the
appeal filed by the petitioners against the order passed under
- 20 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Section 68 of the KCS Act was dismissed by the respondent
No.2 on 30.05.2026. The Directors of the Society have filed
W.P.No.18567/2026 challenging the order passed under
Section 68 of the KCS Act and under Section 106 of the KCS
Act.
8. The W.P.No.12472/2026 and W.P.No.18567/2026
are opposed by the respondent No.5 who has filed a detailed
statement of objections, wherein she admitted that the Society
entered into an agreement with the Developer on 07.01.2005
in terms of which the Developer agreed to procure land out of
the funds of the Society, form a full-fledged layout as per the
specifications contained in the agreement dated 07.01.2005.
She contends that as per the agreement, a full-fledged layout
rd
known as Judicial Layout, 3 Phase, Hejjala was formed. As per
the terms and conditions of the agreement, the Developer and
the Society had agreed to reserve all the intermediate sites of
various dimensions for the benefit of the members of the
Society and all corner sites for the benefit of the Developer.
She contends that an intermediate site bearing No.120
measuring 20,789 sq. ft was surrendered to the Society for
- 21 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
allotment to its members. Thus, she contends that the
Developer had handed over site No.120 to the Society and
hence, it was the Society which was the owner of the site.
9. (i) She contends that the In-charge Secretary of
the Society did not record the resolutions of the Board meeting
periodically. She along with another director repeatedly raised
the issue of non-recording of the resolutions in the book till
03.03.2024 to which he replied that the President of the
Society had instructed him not to write the resolutions in the
book. She contends that in the Board meeting held on
03.03.2024 when the very same question was posed to the In-
charge Secretary and the President, the In-charge Secretary
furnished the draft resolutions of the Board meeting dated
21.04.2023, 28.05.2023, 30.07.2023, 03.09.2023, 16.10.2023,
05.11.2023, 06.12.2023 in loose sheets.
(ii) The respondent No.5 after perusing the draft
resolutions felt that resolutions were falsely recorded in respect
of subjects that were not discussed. As regards the resolution
of the board at the meeting held on 28.05.2023 with regard to
subject No.2, she contends that it was falsely recorded that the
- 22 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
board had unanimously resolved to hand over site No.120 to
the Developer and that the In-charge Secretary and the
President were authorized by the Board to take further action.
She submits that no such subject with regard to handing over
of site No.120 was discussed either in the meeting held on
28.05.2023 or in any other meeting of the Board.
(iii) She contends that the fact of sale of site No.120
came to her knowledge only on 03.03.2024 through the draft
resolutions. She has placed on record a copy of the draft
resolution dated 28.05.2023. She further contends that she and
another Director submitted their objections on 12.03.2024 to
the President and In-charge Secretary regarding the
irregularities in recording the minutes of the meeting in the
resolution book and also highlighted the conspiracy of the
President of the Developer in sale of site No.120 and called
upon them to desist from recording any resolution regarding
site No.120 which was never discussed either by the Sub-
Committee or by the Board of the Society.
(iv) She submits that even after receiving the letter
dated 12.03.2024, the In-charge Secretary failed to record the
- 23 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
resolutions in the book. Therefore, the respondent No.5 was
constrained to address a communication dated 15.05.2024 to
the In-charge Secretary to record the resolutions of the
meeting from 21.04.2023. This letter was neither replied nor
denied by the In-charge Secretary. She contends that the letter
dated 12.03.2024 was thereafter placed before the Board at its
meeting held on 07.07.2024. In the said meeting, the earlier
resolutions which are recorded in the resolution book were
placed for signature of the members of the Board. The
respondent No.5 and another Director signed all the resolutions
except the resolution dated 11.03.2023 and affixed their
signature as on 07.07.2024, as the resolutions were placed on
the said day. The respondent No.5 contends that in respect of
the resolution of the meeting dated 28.05.2023 no resolution
was recorded regarding site No.120 as mentioned in the draft
resolution placed on 03.03.2024. Therefore, she and another
Director signed the resolution dated 28.05.2023 on
07.07.2024. She and another Director refused to affix their
signatures to the resolution of the meeting dated 11.03.2023
on 07.07.2024 since the minutes of the meeting were not truly
- 24 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
and accurately recorded and whatever that was recorded was
contrary to the actual deliberations that took place in the
meeting. She contends that she and another Director submitted
their dissent to the resolution of the meeting dated 11.03.2023
on 06.08.2024. She contends that the report of the Sub-
Committee dated 10.04.2023 established that there was no
letter of the developer that was discussed in the meeting held
on 11.03.2023.
(v) She contends that the resolution of the meeting
held on 07.07.2024 was placed for approval in the Board
meeting held on 26.08.2024 and to her shock and surprise, it
was recorded in the said meeting that the sale of site No.120
was brought to the notice of the Board, which in fact was false,
as on the said day respondent No.5 and another director
expressed their dissent to the resolution dated 07.07.2024.
Accordingly, respondent No.5 and another Director submitted
the dissent to the resolution dated 07.07.2024 on 27.08.2024.
However, she claims that the conspiracy of the President with
the Developer as mentioned in her letter dated 12.03.2024 was
not denied in the resolution dated 07.07.2024.
- 25 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
(vi) She contends that she and another Director, apart
from raising objection against the sale of site No.120 by the
Developer, they also submitted a letter to the Auditor bringing
to his notice the illegal sale of site No.120 thereby causing loss
to the Society. The Auditor of the Society prepared a report
which was placed before the Annual General Body Meeting
(henceforth referred to as ‘AGM’) of the Society that was
convened on 15.09.2024. In the AGM, the President and other
Directors assured the members that suitable action would be
taken in the next Board meeting. However, no action was
taken. She contends that she submitted complaints to the
respondent No.3, who is the concerned Registrar of the Society.
(vii) Upon receipt of the complaints, the respondent
No.3 sought for an explanation from the President and In-
charge Secretary. However, no plausible explanation was
offered by them, which compelled the respondent No.3 to
initiate suo motu enquiry under Section 64 of the KCS Act and
appointed the DRCS Zone-III as the Enquiry Officer. He was
directed to probe into the irregularities and submit a report.
The Enquiry Officer on 09.04.2025 issued notice to the
- 26 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Directors including the respondent No.5 and after considering
the objections filed, submitted a report on 04.10.2025, holding
that all the allegations against the Directors of the Society were
proved and also held that a Memorandum of Understanding
(henceforth referred to as ‘MOU’) furnished by the directors
was suspicious.
10. (i) She contends that on 02.07.2025 she
obtained the certified copy of the written statement submitted
by the petitioners before the Enquiry Officer and found that the
petitioners had enclosed a Memorandum of Understanding
dated 05.04.2023 entered into between the developer and the
purchasers. The petitioners had placed this document in
support of their claim that site No.120 was encroached by third
party strangers and that the Society faced the threat of losing
the site. Therefore, the Society proposed to form six sites in
site No.120 and subject to that, it had entered into an MOU
with the Developer. The respondent No.5 contends that she
doubted the genuineness of this MOU and on verification, she
found that the stamp paper for the MOU was purchased on
11.04.2025, but the document was drawn on 05.04.2023. She
- 27 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
therefore brought this fact to the notice of the Enquiry Officer
vide her letter dated 05.07.2025 and also to the respondent
No.3 vide her letter dated 14.07.2025. She contends that since
the respondent No.3 failed to take any action on the letter
dated 14.07.2025, she lodged a complaint before the
Karnataka Lokayuktha on 25.11.2025 against the respondent
No.3.
(ii) In the meanwhile, the respondent No.3 had
addressed a letter dated 24.11.2025 to the Inspector General
of Registration Stamps for verification whether the MOU was
genuine or not and to submit a report. The respondent No.5
submits that after the report was submitted by the Enquiry
Officer in terms of Section 64 of the KCS Act, the respondent
No.3 passed an order under Section 68 of the KCS Act on
01.12.2025 directing the petitioners and two other Directors to
comply the directions contained therein within 45 days. She
contends that a notice was issued by the Karnataka Lokayuktha
to the respondent No.3 on 04.12.2025. However, before that,
the respondent No.3 had already passed an order under
Section 68 of the KCS Act.
- 28 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
11. She contends that the Inspector General of
Registration Stamps verified the genuineness of the e-stamp
paper which was used for drawing up the MOU and submitted a
report that the e-stamp on which the MOU was drawn was
forged/fake. Later, the respondent No.3 addressed a letter
dated 24.12.2025 to the petitioner No.1 and In-charge
Secretary bringing to their notice that the e-stamp on which
MOU was executed was fake and forged and directed to take
action against the concerned. However, neither the petitioner
No.1 nor the In-charge Secretary placed the said letter before
the Board to take action against the Developer. She contends
that the Enquiry Officer before whom the fake MOU was
furnished, based on the authorization issued by the respondent
No.3, lodged a complaint before the jurisdictional police against
the signatories of the said MOU and the police registered Crime
No.1/2026, which was challenged in Crl.P.No.1208/2026 and
W.P.No.2718/2026. The said petitions were dismissed in terms
of the order dated 09.04.2026.
12. The respondent No.5 contends that the petitioners
have no grievance against the order dated 01.12.2025 passed
- 29 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
by the respondent No.3 yet have preferred an appeal before
the respondent No.2 on 13.01.2026 and also sought for stay of
the order dated 01.12.2025. The respondent No.5 contends
that the petitioners and other two Directors did not comply with
the directions under Section 68 of the KCS Act within 45 days
which expired on 15.01.2026. On 16.01.2026, the petitioners
without complying with the directions in the guise of filing a
compliance report made allegations against the respondent
No.5 and her husband and another director stating that it is
they who had conspired with the developer in the illegal sale of
site No.120. As such on 16.01.2026, the respondent No.3
having found that the petitioners and two others have incurred
disqualification to be members of the Board of the respondent
No.4, as they violated the mandatory provisions of the KCS Act
and they failed to comply with the orders passed under Section
68 of the KCS Act and they having acted fraudulently, initiated
suo motu proceedings in terms of Section 29-C (8)(b)(c) and
(d) of the KCS Act, 1959.
13. In view of the direction contained in the order
passed by the respondent No.3 under Section 68 of the KCS
- 30 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Act, the respondent No.3 also initiated surcharge proceedings
under Section 69 of the KCS Act against the petitioners and the
In-charge Secretary. The respondent No.5 contends that the
order passed under Section 69 of the KCS Act was in the best
interests of the Society. Nonetheless, the In-charge Secretary
of the Society filed W.P.No.2690/2026 without being authorized
by the Board of Directors to do so. She contends that the
petitioners, who had challenged the order passed under Section
68 of the KCS Act before the respondent No.2, did not attend to
the office objections but rushed to this Court in
W.P.No.2917/2026 contending that the respondent No.2 did
not consider their application for stay.
14. In the meanwhile, the developer addressed a letter
dated 02.02.2026 to the respondent No.3 and requested to
drop the action against him as per the order dated 01.12.2025
and stated that he had executed a sale deed dated 25.08.2023
at the instance of the petitioner No.1 because he was told that
site No.120 was not allotted to the members of the Society and
therefore, he was asked to sell the same to third parties with
an assurance that necessary permission/No Objection
- 31 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Certificate (henceforth referred to as ‘NOC’) from the Society
would be issued.
15. She contends that the respondent No.5 on coming
to know of the filing of W.P.No.2917/2026 filed an application
for impleadment. This Court in terms of an order dated
10.02.2026, disposed of the writ petition directing the
respondent No.2 to dispose of the interlocutory application for
stay within 15 days from the date of receipt of a copy of this
order. Liberty was also reserved to the petitioners to file their
reply to the show-cause notice under Section 29-C of the KCS
Act. The respondent No.5 contends that the respondent No.2 in
compliance with the direction issued by this Court after
providing sufficient opportunity, rejected the application for
stay of the order dated 01.12.2025.
16. The petitioners again approached this Court in
W.P.No.8291/2026 challenging the order refusing to grant an
interim stay of proceedings under Section 69 of the KCS Act.
During the pendency of W.P.No.8291/2026, the proceedings
under Section 29-C of the KCS Act had proceeded and the case
was listed for pronouncement of orders. On 12.03.2026, the
- 32 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
petitioners made a submission in W.P.No.8291/2026 that
pursuant to the order dated 01.12.2025 under Section 68 of
the KCS Act, surcharge proceedings were initiated and
therefore, sought for interim stay of the order dated
01.12.2025. The respondent No.5 claims that the petitioners
were aware of the stage of the proceedings under Section 29-C
of the KCS Act. However, they did not make any grievance
before this Court to stay the proceedings under Section 29-C of
the KCS Act. On the other hand, their grievance was to stay the
proceedings under Section 69 of the KCS Act. The respondent
No.5 appeared and on hearing the petitioners and the
respondent No.5, this Court directed the respondent No.2 to
dispose of the appeal itself on merits within two months and
directed the respondent No.3 not to take any precipitative
action against the petitioners pursuant to the order dated
01.12.2025. The respondent No.5 therefore contends that this
Court stayed the respondent No.3 from taking any action under
Section 69 of the KCS Act but did not intend to interfere with
the proceedings under Section 29-C of the KCS Act.
- 33 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
17. The respondent No.5 claims that a memo was filed
by the petitioners before the respondent No.3 requesting the
respondent No.3 to stop the proceedings under Section 29-C of
the KCS Act. The respondent No.5 also filed a memo to comply
with the order passed by this Court in W.P.No.2917/2026, as
there was no indication that proceedings under Section 29-C of
the KCS Act has to be stayed. The respondent No.3 therefore
sought opinion from the office of the Advocate General, who in
terms of a communication dated 09.04.2026 informed the
respondent No.3 to comply with the order dated 10.02.2026
passed in W.P.No.2917/2026. The respondent No.3 thereafter
proceeded to pass an order under Section 29-C of the KCS Act
and disqualified the petitioners and two others under Section
29-C (8)(b)(c) and (d) of the KCS Act, which is challenged in
this writ petition.
18. The respondent No.5 contends that the petitioners
having failed to comply with the directions issued by the
respondent No.3 under Section 68 of the KCS Act, are liable to
be disqualified. She also contends that the petitioners having
joined hands with the Developer in compromising the interest
- 34 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
of the Society and acting fraudulently in allowing the Developer
to convey the sites to third party purchasers, have incurred
disqualification and therefore, no reliefs can be granted to the
petitioners in this writ petition. She also contends that the
petitioners have an effective alternative remedy under Section
106 (1)(d-2) of the KCS Act and therefore, a writ petition under
Article 226 of the Constitution of India is not maintainable. She
has generally denied the assertions made in the contentions
urged in the writ petition.
19. An additional statement of objections is filed by her
wherein, she has contended that the letter dated 02.02.2026
addressed by the developer indicates the conspiracy between
the developer and the petitioners and also that the petitioners
and the developer have brought about antedated letters. She
also contends that the conduct of the petitioners, in failing to
initiate criminal action against the developer, the petitioners
and the Secretary and to raise a dispute under Section 103 of
the KCS Act to send a proposal under Section 29-C of the KCS
Act for disqualification of the petitioners and to initiate
- 35 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
disciplinary proceedings against the Secretary, shows that the
petitioners are all complicit in hushing up the fraudulent act.
20. She also contends that even after an enquiry was
initiated, the irregularities of the Secretary and the petitioners
continue. She contends that the resolution dated 06.08.2025
passed by the petitioners clearly establish the same. She
contends that in respect of the subject No.2 in the resolution
dated 06.08.2025, it was recorded that except Smt.Pankaja,
the other Directors i.e. the petitioners resolved to allot/register
six sites as mentioned in the letter of the developer dated
15.03.2025 and the Secretary was accordingly instructed to
take necessary action. However, the actual deliberation at the
meeting held on 06.08.2025 was to obtain clarification from the
Department. Since the Secretary was in the habit of recording
false resolutions and the petitioners were in the habit of signing
the said false resolutions, left with no other option, in order to
prove the irregularities and illegalities of the petitioners and the
Secretary, the respondent No.5 audio recorded the
deliberations of the meeting. Thereafter, the respondent No.5
had submitted her objection in that regard to the Secretary on
- 36 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
20.08.2025. She contends that apart from her, another
Director named Prasad Rao also submitted his dissent to the
resolution dated 06.08.2025. She contends that thereafter
respondent No.3 addressed a letter dated 31.12.2025 to the
President to take disciplinary action against the Secretary and
to discharge the Secretary from his post. The said letter was
placed before the Board meeting held on 03.01.2026. However,
on the same day, instead of taking action against the Secretary
for his continuous dereliction of duty, the petitioners resolved
to revise the pay of the Secretary, though that was not the
resolution. Therefore, respondent No.5 submitted her dissent to
the resolution dated 03.01.2026, immediately after the meeting
i.e. on 05.01.2026 and after receipt of the copy of the
resolution, on 12.01.2026. She contends that another Director,
Sri.Prasad Rao, also submitted dissent to the resolution dated
03.01.2026.
21. She contends that after the receipt of the order
dated 01.12.2025 passed under Section 68 of the KCS Act, the
petitioners casually and leisurely called a meeting on
28.12.2025 vide their meeting notice dated 19.12.2025. The
- 37 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
respondent No.5 addressed a letter dated 20.12.2025 to the
Secretary to fix the Board meeting to discuss with regard to
compliance of Section 68 of the KCS Act order and requested
not to conduct the meeting between 26.12.2025 and
30.12.2025 because of her pre-occupation. Despite her
request, the Secretary informed the respondent No.5 that as all
other Directors were available, the President/petitioner No.1
has instructed him to go ahead with the meeting. She claims
that she informed the Secretary that she cancelled her pre-
occupation and would attend the meeting on 28.12.2025.
Accordingly, she attended the meeting, but the meeting was
postponed as there was no quorum for the meeting. She
contends that the meeting was postponed to 03.01.2026. She
therefore contends that the conduct of the petitioners clearly
depicts that they were least bothered to comply the order
passed under Section 68 of the KCS Act and the same is clear
from the letter of the developer dated 02.02.2026.
22. She contends that at the meeting held on
03.01.2026, although respondent No.5 and Sri.Prasad Rao
expressed their dissent and insisted that the order under
- 38 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Section 68 of the KCS Act should be complied, the petitioners
decided to file a compliance report. Accordingly, they filed a
compliance report but did not comply the directions but
complained that the respondent No.5, her husband and
Sri.Prasad Rao had conspired with the developer in respect of
the illegal sale of site No.120. She therefore contends that her
husband is unnecessarily roped into the case and hence, her
husband filed a private complaint against the developer.
23. She contends that thereafter a meeting was
scheduled on 29.03.2026, as per the meeting notice dated
18.03.2026. However, the said notice was not served to her
and Sri.Prasad Rao. After coming to know of the same, a letter
was addressed to the Secretary and also to the respondent
No.3 on 26.03.2026. The respondent No.3 therefore
consequently addressed a letter dated 26.03.2026 to the
petitioners and the secretary indicating the dereliction of duty
on the part of the Secretary and failure of the petitioners to
supervise the conduct of the Secretary and further directed to
conduct the meeting strictly in accordance with the KCS Act
and Rules. She contends that on 07.04.2026, she scrolled the
- 39 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
messages on her WhatsApp and came to know that the meeting
was scheduled on 08.04.2026 and again the Secretary had
failed to notify her. She then sent a reply to the Secretary on
WhatsApp on 07.04.2026. The Secretary thereafter sent a
meeting notice on 07.04.2026. The respondent No.5 thereafter
addressed a letter dated 08.04.2026 to the Secretary regarding
the non-receipt of the notice as per the Rules. She therefore
contends that the petitioners and the Secretary intentionally
wanted to avoid the respondent No.5 from attending the
meeting so that they can approve the draft agreements with
rd th
the developer regarding the 3 phase and 4 phase and the
account statement of December, 2025, January and February,
2026.
24. She contends that after raising a dispute under
Section 103 of the KCS Act, the Secretary moved an application
for attachment of the property stating that the respondents
therein were about to dispose of the property. Although the
Secretary and the petitioners did not take any action against
the developer and the purchasers, they filed a dispute for
recovery of the property till which time the property was not at
- 40 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
all disposed of due to the present litigation. However, all of a
sudden, the Secretary moved an application on 29.01.2026
stating that purchasers were about to dispose of the property
and hence, an order of attachment was passed.
25. She contends that the order was passed on
29.01.2026 but was dispatched on 06.02.2026. However, the
developer submitted his letter along with the undertaking of the
purchasers on 02.02.2026 to the respondent No.3 in
compliance of the order under Section 68 of the KCS Act, even
before receipt of the said notice of attachment of property,
which makes it clear that the developer and purchasers were
ready to hand over the property even before initiation of the
dispute. She therefore contends that no interference is
warranted with the order of disqualification of the petitioners.
26. During pendency of the writ petitions, a sale deed
dated 07.07.2026 is executed by the purchasers of site No.120
in favour of the Society to which the developer is a consenting
party. It appears that the consideration for the sale deed is
paid by the developer. An affidavit dated 06.08.2026 is filed by
- 41 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
the In-charge Secretary of the Society in W.P.No.2690/2026
which inter alia reads as follows:
"7. I submit that, the aforesaid execution of sale
deed in respect of site bearing No.120 was not within the
knowledge of the Petitioner, however the said act was
later brought to the knowledge of the Petitioner based on
the complaint made in that regard. The issue was
discussed in detail in the meeting of the Board of
Management of the Petitioner which was held on 07-07-
2024 and after the deliberations it was resolved to issue
notice to the Developer and thereby calling for
explanation of the Developer and accordingly a notice
dated 15-07-2024 was sent to the Developer which was
followed another notice dated 22-01-2025 issued by the
Petitioner. Copy of the aforesaid notices are produced
herewith and marked as Annexure-II & III.
8. I submit that, after issuance of aforesaid notices
the Developer was initiated the attempts to restore back
the property in question back to domain of the Petitioner
society and has made an advance payment of sum of
Rs.50,00,000/- (Rupees Fifty Lakhs only) under RTGS to
the Purchasers of the property and then sale deed dated
25-08-2023.
9. I submit that, when the attempts were made to
restore the property to the Petitioner, a comprehensive
statutory enquiry under section 64 of the Act, 1959, was
initiated in pursuance of the order dated 19-02-2025
- 42 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
passed by the Respondent No.3 herein. The Inquiry
Officer after holding an Inquiry has submitted his findings
in the form of report dated 04-10-2025 to the Respondent
No.3 Authority.
10. I submit that, in pursuance of the report of Inquiry,
the Respondent No.3 has passed an order dated 01-12-
2025 under section 68 of the Act 1959 and thereby
directed the Petitioner to submit compliance report within
a period of 45 days from the date of receipt of the said
order. Copy of the said order dated 01-12-2025 is
produced herewith as Annexure-IV
11. I submit that, from the perusal of aforesaid order
dated 01-12-2025 it is crystal clear that the Respondent
No.3 Authority has directed the Petitioner society to
initiate the proceedings under section 70 of Act of 1959
and also to move an application seeking attachment
before judgment of the property in question under section
103 of Act of 1959. In compliance of the aforesaid order
dated 01-12-2025, the Petitioner has filed dispute petition
in No.ANI(H & M)/D2/NMD/34/2025-26 under section 70
of Act of 1959 and also moved an application seeking for
attachment before judgment in respect of property
bearing No.120. The Respondent No.3 Authority upon
considering the said application filed by the Petitioner had
issued a notice of dispute to Respondent in the dispute
and also order of conditional attachment in respect of
property in question. It is relevant mention here that the
dispute was filed on 12-01-2026 before Respondent No.3.
Copy of the memorandum of dispute petition and notice of
- 43 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
conditional attachment issued by the Respondent No.3 are
produced herewith as Annexure-V and VI
12. I submit that, as stated above, the Petitioner
society has duly complied with the order dated 01-12-
2025 and also submitted compliance report on 16-01-
2026 to the Respondent No.3. Notwithstanding such
compliance is made, the Respondent No.3 authority has
initiated suo-motto proceedings in surcharge case
No.ANI(VA&E)/D2/ADHIBHARA/07/2025-26 under section
69 of the Act for recovery of sum of Rs.2,61,62,000/-
from the Respondents therein. Copy of the compliance
report and surcharge petition are produced herewith as
Annexure-VII
13. I submit that, as the Respondent No.3 authority
initiated the proceedings for surcharge even after filing
the dispute on the very same cause of action feeling
aggrieved by the aforesaid action of Respondent No.3, the
Petitioner has filed the above writ petition thereby seeking
writ of prohibition and other consequential relief/s.
14. I further submit that, in response to the notice, the
Developer and other contesting Respondents in the
dispute have appeared on their appearance the
Respondent No.2 to 5 have filed an application under
Order XII Rule 6 R/w Section 151 of CPC and thereby by
conceding to the prayer sought for by the Petitioner have
prayed the authority to allow the dispute petition and
grant the relief as sought for by the Petitioner. Copy of
- 44 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
the said application is produced herewith as Annexure-
VIII
15. I submit that, as the Developer arrayed as
Respondent No. 1 in the dispute petition he has also
submitted a letter in the form of request addressed to the
Respondent No.3 and wherein has stated that he is ready
to bear a stamp duty and registration charges applicable
to the execution sale deed by prospective buyers in favour
of Petitioner society. Copy of the said undertaking is
produced herewith as Annexure-IX
16. I submit that, the above matter had come up
before this Hon'ble Court on 02-07-2026 and on the said
day this Hon'ble Court by considering the submission
made by the Petitioner, has permitted the Petitioner to
secure the sale deed in respect of site bearing No. 120 in
its favour and produce the deed of conveyance on the
next date of hearing.
17. I submit that, in pursuance to the aforesaid order
of the Hon'ble Court, the Developer as confirming party as
Sri Ramesh Babu.C.S, Smt. Kavitha.S, Sri. Hariprasad &
Smt. Deepa H Prasad as Vendors have executed absolute
sale deed dated 07-07-2026 in respect of the property in
question in favour of the Petitioner society. The said
absolute sale deed is registered as document No.RMN-1-
04734/2026-27. Copy of the document is produced is
herewith Annexure- X
18. I submit that, from the perusal of aforementioned
sale deed it is crystal clear that the conveyance of
- 45 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
property No.120 made in favour of the Petitioner society
and the sale consideration of Rs.3,10,00,000/- was paid
by the confirming party ie., Developer who received the
sale consideration from Sri Hariprasad and others under
sale deed dated 25-08-2023. The details of payment of
sale consideration is shown in page No.5 & 6 of sale deed
dated 07-07-2026. The aforesaid schedule of payment of
sale consideration of sum of 50 Lakhs was shown to be
paid by way of RTGS on 07-10-2024 in favour of Sri.
Hariprasad and similarly Ramesh Babu.C.S, & Kavitha S.
(a, i, j & k) was made as:
i) Rs.50,00,000/- (Rupees Fifty Lakhs only) by way of
RGTS through the KSC Apex Bank Ltd., dated 07-10-
2024 in favour of Sri. Hariprasad.
ii) Rs.5,00,000/- (Rupees Five Lakhs only) by way of
RTGS through The KSC Apex Bank Ltd., dated 29-01-
2025 in favour of Ramesh Babu.C.S.
iii) Rs.5,00,000/-(Rupees Five Lakhs only) by way of
RTGS, through the KSC Apex Bank Ltd., dated 29-01-
2025 in favour of Smt.Kavitha. S,
iv) Rs. 10,00,000/- (Rupees Ten Lakhs only) by way of
RTGS through HDFC Bank Ltd., dated 11-12-2025 in
favour of Sri. Ramesh Babu.C.S
19. It is relevant to mention here that the aforesaid
payments were made by the Developer in favour of Sri.
Hariprasad and others pursuant to the issuance of notice
by the Petitioner society asking him to restore the
- 46 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
property back to the Petitioner society. All rest of the
payments were made after filing of the dispute by the
Petitioner before the Respondent No.3. That apart the
Developer and Sri Hariprasad and others have submitted
sworn affidavits and thereby reiterating conveyance of
property bearing No. 120 in favour of Petitioner society.
In the affidavit submitted by the Developer and Sri
Hariprasad and others they have categorically mentioned
about the execution of sale deed in respect of property
No.120 and also duly acknowledged the receipt of
payment of sale consideration by the confirming
party/developer. They have further stated in the affidavit
that they have absolutely no claim, right, interest and
possession over the property in question and as they have
relinquished the same in favour of Petitioner under
absolute sale deed dated 07-07-2026. Copy of the sworn
affidavits submitted by Sri.Lakshman, Sri Hariprasad and
others to the Petitioner society are produced herewith as
Annexure - XI & XII."
27. This affidavit is opposed by the respondent No.4 in
W.P.No.2690/2026 primarily contending that the sale deed
must have been executed in the favour of the developer and
thereafter, the Developer had to convey the same to the
members identified/suggested by the Society. She contends the
execution of the sale deed in favour of the Society will give rise
to further complications in as much as the Society will have to
- 47 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
explain as to how it came in possession of such a huge sum of
money to pay to the purchasers and this might result in income
tax issues. It is also contended that the sale deed itself is very
doubtful in as much as the consideration paid by the Developer
to the purchasers is not at the time of execution of the sale
deed but it is much prior namely on 07.10.2024, 16.02.2026,
17.02.2026, 24.02.2026, 13.04.2026, 04.07.2026, 29.01.2025
etc. It is contended that this does not seem to be a true
transaction as the consideration ought to have been
contemporaneous with the execution of the sale deed dated
07.07.2026. She contends that if there is any challenge to the
sale deed there could be legal complications not only to the
society but also to the members who will be allotted sites in
site No.120. She therefore prays that the sale deed executed
on 07.07.2026 be rejected.
28. The learned Senior Counsel for the petitioners in
W.P.Nos.18567/2026 and 12472/2026 contended that the
petitioners have complied the order passed under Section 68 of
the KCS Act, by initiating proceedings against the Developer as
well as the purchasers. They have also sought for an order of
- 48 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
attachment of the site bearing No.120. He therefore contends
that the petitioners have complied with the order dated
01.12.2025 and therefore, the respondent No.3 could not have
initiated proceedings against the petitioners under Section 69
of the KCS Act and under Section 29-C of the KCS Act. He also
contends that since the purchasers have already conveyed the
property to the Society, the continuation of the proceedings
against the petitioners under Section 69-C of the KCS Act, is
unwarranted and the order of disqualification of the petitioners
is being harsh, is liable to be set at nought and the position of
the petitioners as the Directors of the Society should be
restored.
29. The learned Senior Counsel for the petitioners in
W.P.No.2690/2026 virtually reiterated the submissions made as
above and contended that since the sale deed is already
executed in favour of the Society, the proceedings under
Section 69 of the KCS Act, be set at nought.
30. Per contra, the learned counsel for the respondent
No.5 submitted that at no point of time there was any
discussion regarding authorizing the Developer to encumber
- 49 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
site No.120. He contends that the petitioners had sought to
justify their conduct by placing on record an MOU dated
05.04.2023 to contend that the Society assessed the risk of
losing site No.120 which was encroached by strangers and
therefore authorized the Developer to encumber the sites. He
contends that this document was apparently fake in as much as
the stamp paper on which the document was drawn up was
purchased on 11.04.2025 and therefore, the MOU could not
have been drawn on 05.04.2023. He contends that the
Developer had submitted a letter dated 02.02.2026 before the
respondent No.3 stating that he was ready to re-convey the
site No.120 to the Society and he also affirmed that the
Directors of the Society who had informed him that the site is
not allotted to anyone and that the same could be disposed of
and that consent/NOC would be obtained from the Society.
Therefore, he contends that it is the Directors of the Society,
who had conspired with the Developer in bringing about a sale
deed in respect of site No.120 and therefore, the Directors of
the Society have compromised the interest of the Society and
- 50 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
hence, proceedings under Section 29-C of the KCS Act were
justified.
31. He also contends that the Directors of the petitioner
have not challenged the report under Section 64 of the KCS Act
and therefore, the proceedings under Section 68 of the KCS Act
was invariable and the petitioners were bound to comply with
the deficiencies pointed out in the order passed under Section
68 of the KCS Act. He contends that the order under Section 69
of the KCS Act, is a follow-up action pursuant to the order
dated 01.12.2025 passed under Section 68 of the KCS Act and
it is in the best interests of the Society. However, he contends
that the Society has filed W.P.No.2690/2026, which is
represented by the In-charge Secretary though he had no
authority to represent the Society and there was no resolution
passed in that regard. He therefore contends that the
proceedings initiated against the Directors of the petitioner
under Section 29-C of the KCS Act, is thoroughly justified and
does not warrant any interference.
32. As regards the sale deed now executed in favour of
the Society, he contends that the sale deed is a recipe for
- 51 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
litigation as the consideration is not contemporaneous with the
date of the sale deed and hence, it is not free from doubt and
can be litigated before the Courts. He therefore contends that
the sale deed executed in favour of the Society be rejected and
a direction be issued to the Developer to obtain back a sale
deed from the purchasers at his cost and thereafter, transfer
the sites formed in site No.120 to the eligible members of the
Society.
33. The learned Additional Government Advocate also
supported the contentions of the learned counsel for the
respondent No.5.
34. I have considered the submissions of the learned
counsel for the petitioners as well as the learned counsel for
the contesting respondent.
35. The issue is though simple but is blown out of
proportions by both the parties by filing unending pleadings and
referring to unwanted proceedings. The fact that site No.120
formed in the layout by the Developer is an intermediate site,
which is released by the Bangalore Metropolitan Region
- 52 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Development Authority (for short, ‘BMRDA’) is not in dispute. It
is also not in dispute that by virtue of the agreement dated
07.01.2005 between the Society and the developer, this site
No.120 had to be conveyed to the members of the Society. It is
also not in dispute that the Developer had conveyed this site to
the purchasers on 28.05.2023. The question therefore is
whether this was done in collusion with the Directors of the
Society or was it a unilateral act on the part of the Developer.
An enquiry was initiated into the affairs of the Society under
Section 64 of KCS Act to report the following:
"«ZÁgÀuÉUÉ M¼À¥Àr¸À¨ÉÃPÁzÀ CA±ÀUÀ¼ÀÄ :-
1. ¸ÀAWÀzÀ ºÉeÁÓ® §qÁªÀuÉAiÀÄ 3£Éà ¨ÁèPï£À ¤ªÉñÀ£À ¸ÀASÉå 120 £ÀÄß ¸ÀAWÀzÀ
C©üªÀÈ¢ÞzÁgÀjUÉ AiÀiÁªÀÅzÉà DPÉëÃ¥ÀuÉ E®èzÉà ©lÄÖPÉÆlÄÖ ¸ÀAWÀzÀ D¹ÛAiÀÄ£ÀÄß
¸ÀAgÀQë¸ÀzÉà ¸ÀAWÀPÉÌ £ÀµÀÖ GAlÄ ªÀiÁrgÀĪÀ §UÉÎ «ZÁgÀuÉ £Àqɹ dªÁ¨ÁÝj
¤UÀ¢¥Àr¸ÀĪÀÅzÀÄ.
2. DqÀ½vÀ ªÀÄAqÀ°AiÀÄ ªÀiÁ¹PÀ ¸À¨sÉAiÀÄ £ÀqÀªÀ½UÀ¼À£ÀÄß PÀ£ÁðlPÀ ¸ÀºÀPÁgÀ
¸ÀAWÀUÀ¼À PÁAiÉÄÝ 1959 gÀ PÀ®A 14(J)(PÉ)(9) jÃvÁå ¸ÀAWÀzÀ ªÀÄÄRå
PÁAiÀÄð¤ªÀðºÀuÁ¢üPÁjAiÀÄÄ ¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ° ¤zÉÃð±ÀPÀgÀÄUÀ½UÉ
¤AiÀĪÀiÁ£ÀĸÁgÀ gÀªÁ¤¸ÀzÉà PÀvÀðªÀå¯ÉÆÃ¥À J¸ÀVgÀĪÀÅzÁV DgÉÆÃ¦¹zÀÄÝ, F
§UÉÎ «ZÁgÀuÉ £Àqɹ dªÁ¨ÁÝj ¤UÀ¢¥Àr¸ÀĪÀÅzÀÄ.
3. ¸ÀAWÀzÀ ¤zÉÃð±ÀPÀgÁzÀ ²æÃªÀÄw J¸ï.¥ÀAPÀd EªÀgÀÄ ¢£ÁAPÀ 11-03-2023
ªÀÄvÀÄÛ 07-07-2024 gÀ DqÀ½vÀ ªÀÄAqÀ° ¸À¨sÉAiÀÄ°è ¸À°è¹zÀ ©ü£Àß
C©ü¥ÁæAiÀĪÀ£ÀÄß £ÀªÀÄÆ¢¸ÀzÉà PÀvÀðªÀå¯ÉÆÃ¥ÀªÉ¸ÀVgÀĪÀÅzÁV DgÉÆÃ¦¹zÀÄÝ, F
§UÉÎ «ZÁgÀuÉ £Àqɹ dªÁ¨ÁÝj ¤UÀ¢¥Àr¸ÀĪÀÅzÀÄ."
- 53 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
36. The enquiry officer appointed by respondent No.3
conducted an enquiry and gave his findings which are as below:
"«ZÁgÀuÁ¢üPÁjAiÀÄ C©ü¥ÁæAiÀÄ :
¨sÀÆ C©üªÀÈ¢ÞzÁgÀgÀÄ ¸ÀAWÀPÉÌ 2011-12 gÀ CªÀ¢üAiÀİèAiÉÄà ¸ÀAWÀPÉÌ
¤ªÉñÀ£À ¸ÀASÉå -120 £ÀÄß ªÀUÁð¬Ä¹zÀÝgÀÆ ¸ÀzÀj ¤ªÉñÀ£ÀªÀ£ÀÄß ¸ÀAWÀzÀ
¸ÀzÀ¸ÀåjUÉ £ÉÆÃAzÁ¬Ä¸À®Ä ¸ÀAWÀzÀ ªÀw¬ÄAzÀ AiÀiÁªÀÅzÉà PÀæªÀĪÀ»¹gÀĪÀÅzÀÄ
PÀAqÀÄ §A¢gÀĪÀÅ¢®è.
¨sÀÆ C©üªÀÈ¢ÞzÁgÀgÀÄ ¸ÀAWÀzÀ UÀªÀÄ£ÀPÉÌ vÁgÀzÉAiÉÄà ªÀÄvÉÆÛ§â
C©üªÀÈ¢ÞzÁgÀgÉÆA¢UÉ C£À¢üPÀÈvÀ JA.M.AiÀÄÄ ªÀiÁrPÉÆAqÀÄzÀ®èzÉà ¸ÀAWÀ¢AzÀ
AiÀiÁªÀÅzÉà ¤gÁ¥ÉÃPÀëuÁ ¥ÀvÀæ ¥ÀqÉAiÀÄzÉà ¢:25-08-2023 gÀAzÀÄ ¸ÀzÀj
¤ªÉñÀ£ÀªÀ£ÀÄß ¥ÀgÀ¨sÁgÉ ªÀiÁrgÀĪÀÅzÀÄ ªÀÄvÀÄÛ ¸ÀzÀj ¥ÀgÀ¨sÁgÉ PÀÄjvÀAvÉ ¸ÀAWÀPÉÌ
AiÀiÁªÀÅzÉà ¥ÀǪÀð ªÀiÁ»w ªÀÄvÀÄÛ WÀl£ÉÆÃvÀÛgÀ ªÀiÁ»wAiÀÄ£ÀÄß ¸Àé-
¥ÉæÃgÀuɬÄAzÀ ¸ÀAWÀPÉÌ ¤ÃqÀzÉ EgÀĪÀÅzÀÄ PÁ£ÀÆ£ÀĨÁ»gÀªÁVgÀÄvÀÛzÉ. C®èzÉÃ
¤ªÉñÀ£À ¸ÀASÉå 120 ¸ÀĪÀiÁgÀÄ 20,789 ZÀzÀgÀ CrUÀ¼À¶ÖzÀÄÝ, PÉêÀ® 9000
CrUÀ¼À£ÀÄß «¹ÛÃtðzÀ ¤ªÉñÀ£ÀUÀ¼À£ÀÄß ªÀiÁvÀæ ¸ÀAWÀPÉÌ ¤ÃqÀ®Ä C©üªÀÈ¢ÞzÁgÀgÀÄ
w½¹gÀĪÀÅzÀÄ ¸ÀAWÀPÉÌ ¸ÀĪÀiÁgÀÄ 11,789 ZÀzÀgÀ CrUÀ¼À£ÀÄß «¹ÛÃtðzÀ
¤ªÉñÀ£ÀUÀ¼ÀÄ £ÀµÀÖªÀÅAmÁUÀ®Ä PÁgÀtªÁVgÀÄvÀÛzÉ.
¤ªÉñÀ£À ¸ÀA-120 ªÀiÁgÁlªÁzÀ PÀÄjvÀÄ zÀÆgÀÄzÁgÀgÀ
¤zÉÃð±ÀPÀgÀÄUÀ¼ÁzÀ ²æÃªÀÄw J¸ï. ¥ÀAPÀd ªÀÄvÀÄÛ ²æÃ JA.J¯ï. ¥Àæ¸ÁzïgÁªï
gÀªÀgÀÄ ¥ÀvÀæ ªÀÄÄSÉãÀ ¯ÉPÀÌ ¥Àj±ÉÆÃzsÀPÀgÀ UÀªÀÄ£ÀPÉÌ vÀA¢zÀÝgÀÆ C©üªÀÈ¢ÝzÁgÀgÀ
«gÀÄzÀÞ AiÀiÁªÀÅzÉà PÁ£ÀÆ£ÀÄ PÀæªÀÄ«qÀzÉà C©üªÀÈ¢ÞzÁgÀgÀUÉ ¸Àà¶ÖÃPÀgÀt PÉÆÃj
¥ÀvÀæ ¤ÃrgÀĪÀÅzÀÄ ¸ÀªÀÄAd¸À PÀæªÀĪÁVgÀĪÀÅ¢®è.
C®èzÉà ¨sÀÆ C©üªÀÈ¢ÞzÁgÀgÀÄ ¤ªÉñÀ£ÀªÀ£ÀÄß ªÀiÁgÁl ªÀiÁrgÀĪÀ §UÉÎ
DqÀ½vÀ ªÀÄAqÀ° ¸À¨sÉUÀ¼À°è ZÀZÉðUÀ¼ÁV CjªÁzÀ £ÀAvÀgÀªÀÇ ªÀÄvÀÄÛ ¯ÉPÀÌ
¥Àj±ÉÆÃzsÀPÀgÀ ªÀgÀ¢UÀ¼À°è G¯ÉèÃRªÁzÀ £ÀAvÀgÀªÀÇ C©üªÀÈ¢ÞzÁgÀgÀ «gÀÄzÀÞ
AiÀiÁªÀÅzÉà PÁ£ÀÄ£ÀÄ PÀæªÀÄ PÉÊUÉÆ¼ÀîzÉà EgÀĪÀÅzÀÄ ¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ½
¤zÉÃð±ÀPÀgÀÄ ¸ÀAWÀPÉÌ DyðPÀ £ÀµÀÖ GAmÁUÀ®Ä PÁgÀt PÀvÀðgÁVgÀÄvÁÛgÉ. F
DgÉÆÃ¥ÀPÉÌ ¸ÀA§A¢ü¹zÀAvÉ DqÀ½vÀ ªÀÄAqÀ½ ¸ÀzÀ¸ÀågÀÄ (²æÃªÀÄw ¥ÀAPÀd J¸ï.
ªÀÄvÀÄÛ JA. J¯ï. ¥Àæ¸ÁzïgÁªï gÀªÀgÀ£ÀÄß ºÉÆgÀvÀÄ¥Àr¹), ¥Àæ¨sÁgÀ PÁAiÀÄðzÀ²ð
ªÀÄvÀÄÛ ¨sÀÆ C©üªÀÈ¢ÞzÁgÀgÀÄ £ÉÃgÀ dªÁ¨ÁÝgÀgÁVgÀÄvÁÛgÉ.
- 54 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
«ZÁgÀuÁ¢üPÁjUÀ¼À C©ü¥ÁæAiÀÄ:
zÀÆgÀÄzÁgÀgÁzÀ ²æÃªÀÄw J¸ï. ¥ÀAPÀd gÀªÀgÀÄ DgÉÆÃ¦¹gÀĪÀAvÉ
¸ÀAWÀzÀ ¥Àæ¨sÁgÀ PÁAiÀÄðzÀ²ðAiÀĪÀgÀÄ PÀ£ÁðlPÀ ¸ÀºÀPÁgÀ ¸ÀAWÀUÀ¼À PÁAiÉÄÝ
1959 gÀ PÀ®A 14(J)(PÉ)(9) gÀ CA±ÀUÀ¼À jÃvÁå DqÀ½vÀ ªÀÄAqÀ½ ¸À¨sÉ dgÀÄVzÀ
07 ¢ªÀ¸ÀUÀ¼ÉƼÀUÁV J¯Áè ¤zÉÃð±ÀPÀgÀÄUÀ½UÉ PÀ¼ÀÄ»¸À®Ä «¥sÀ®gÁVgÀĪÀÅzÀÄ
¸Á©üÃvÁVgÀÄvÀÛzÉ. F DgÉÆÃ¥ÀPÉÌ PÀÄjvÀAvÉ ¸ÀAWÀzÀ ¥Àæ¨sÁgÀ PÁAiÀÄðzÀ²ðAiÀĪÀgÀÄ
£ÉÃgÀ dªÁ¨ÁÝgÀgÁVgÀÄvÁÛgÉ.
«ZÁgÀuÁ¢üPÁjUÀ¼À C©ü¥ÁæAiÀÄ :
¸ÀºÀPÁgÀ ¸ÀAWÀUÀ¼À PÁAiÉÄÝ 1959, ¤AiÀĪÀÄUÀ¼ÀÄ 1960 gÀ C£ÀĸÁgÀ
¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ° ¸À¨sÉUÀ¼À°è ZÀaðvÀªÁUÀĪÀ «µÀAiÀÄUÀ¼ÀÄ ªÀÄvÀÄÛ D
«µÀAiÀÄUÀ¼À ªÉÄð£À wêÀiÁð£ÀUÀ¼ÀÄ, AiÀiÁªÀÅzÉà ¤zÉÃð±ÀPÀgÀÄ MAzÀÄ ªÉüÉ
AiÀiÁªÀÅzÉà «µÀAiÀÄzÀ PÀÄjvÀAvÉ ©ü£Áß©ü¥ÁæAiÀÄ ªÀåPÀÛ¥Àr¹zÀ°è, CAvÀºÀ
©ü£Áß©ü¥ÁæAiÀÄUÀ¼À£ÀÄß ¤zÉÃð±ÀPÀgÀ ºÉ¸Àj£À ¸À»vÀ ¸À¨sÁ £ÀqÀªÀ½ ¥ÀŸÀÛPÀzÀ°è
£ÀªÀÄÆ¢¸ÀĪÀÅzÀÄ ¸ÀAWÀzÀ PÁAiÀÄðzÀ²ðAiÀÄ ¥ÀæªÀÄÄR dªÁ¨ÁÝjAiÀiÁVgÀÄvÀÛzÉ.
zÁR¯ÁwUÀ¼À ¥Àj²Ã®£É¬ÄAzÀ ¸ÀAWÀzÀ §ºÀ¼ÀµÀÄÖ ¸À¨sÁ £ÀqÀªÀ½UÀ¼À°è
wêÀiÁð¤¹vÀÄ / C£ÀÄªÉÆÃ¢¹vÀÄ JAzÀÄ £ÀªÀÄÆ¢¸À¯ÁVzÉAiÉÄà ºÉÆgÀvÀÄ
¸ÀªÁð£ÀĪÀÄvÀ¢AzÀ wêÀiÁð¤¸À¯Á¬ÄvÀÄ / C£ÀÄªÉÆÃ¢¸À¯Á¬ÄvÀÄ JAzÀÄ
£ÀªÀÄÆzÁVgÀĪÀÅ¢®è. ¸ÀAWÀzÀ ¤zÉÃð±ÀPÀgÁzÀ ²æÃªÀÄw J¸ï. ¥ÀAPÀd ªÀÄvÀÄÛ ²æÃ
JA.J¯ï. ¥Àæ¸ÁzïgÁªï gÀªÀgÀÄ ¸ÀºÀPÁgÀ ¸ÀAWÀUÀ¼À C¥ÀgÀ ¤§AzsÀPÀjUÉ
©ü£Áß©ü¥ÁæAiÀÄ £ÀªÀÄÆ¢¸ÀĪÀ PÀÄjvÀÄ £ÀqɹgÀĪÀ ¥ÀvÀæ ªÀåªÀºÁgÀªÀ£ÀÄß
UÀªÀĤ¸À¯ÁV, ©ü£Áß©ü¥ÁæAiÀÄUÀ¼À £ÀªÀÄÆzÀÄ PÀÄjvÀAvÉ ¸ÀAWÀzÀ ¥Àæ¨sÁgÀ
PÁAiÀÄðzÀ²ð AiÀĪÀgÀÄ PÀvÀðªÀå¯ÉÆÃ¥À J¸ÀVgÀĪÀÅzÀÄ ¸Á©üvÁVgÀÄvÀÛzÉ."
37. Following this, the respondent No.3 passed an order
under Section 68 of KCS Act to ensure compliance of the below
mentioned acts within 45 days:
"«ZÁgÀuÁA±À-1
xxxxx
«ZÁgÀuÁ¢üPÁjUÀ¼À C©ü¥ÁæAiÀÄ :
- 55 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
xxxxx
«ZÁgÀuÁ ªÀgÀ¢AiÀÄ CA±ÀUÀ½UÉ ¸ÀA§A¢ü¹zÀAvÉ PÀ®A 68gÀ ¤zÉÃð±À£À:-
xxxxx
ªÉÄîÌAqÀ PÀÈvÀåPÉÌ ¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ½AiÀĪÀgÀÄ, ªÀÄÄRå
PÁAiÀÄð¤ªÁðºÀPÀgÀÄ, C©üªÀÈ¢ÞzÁgÀgÀÄ £ÉÃgÀªÁV ºÉÆuÉUÁgÀgÁVgÀÄvÁÛgÉ. ¸ÀAWÀzÀ
¸ÀzÀ¸ÀågÀ »vÀ PÁ¥ÁqÀĪÀ°è «¥sÀ®gÁV EAvÀºÀ ¤AiÀĪÀĨÁ»gÀ PÀÈvÀåzÀ°è
¨sÁVAiÀiÁVgÀĪÀ ªÀÄvÀÄÛ ¸ÀAWÀPÉÌ £ÀµÀÖªÀÅAlÄ ªÀiÁrgÀĪÀ PÁgÀtPÁÌV ªÉÄîÌAqÀ
¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ½ ¸ÀzÀ¸ÀågÀÄ, ªÀÄÄRå PÁAiÀÄð¤ªÁðºÀPÀgÀÄ ºÁUÀÆ
C©üªÀÈ¢ÞzÁgÀgÀ «gÀÄzÀÞ Qæ«Ä£À¯ï ªÉÆPÀÌzÀݪÉÄ zÁR°¸À®Ä ¤zÉÃð²¹zÉ.
ªÀÄÄAzÀĪÀgÉzÀÄ, ¸ÀzÀj ¤ªÉñÀ£À ¸ÀASÉå 120 PÉÌ ¸ÀA§A¢ü¹zÀAvÉ ¸ÀAWÀzÀ ¸ÀzÀ¸ÀågÀ
»vÀzÀȶÖAiÀÄ£ÀÄß PÁ¥ÁqÀĪÀ ¤nÖ£À°è PÀ£ÁðlPÀ ¸ÀºÀPÁgÀ ¸ÀAWÀUÀ¼À PÁAiÉÄÝ 1959
gÀ PÀ®A 103 gÀr ¸ÀzÀj D¹ÛAiÀÄ£ÀÄß DzÉñÀ ¥ÀǪÀð d¦ÛUÉ M¼À¥Àr¸À®Ä ¸ÀPÀëªÀÄ
¥Áæ¢üPÁgÀzÀ ªÀÄÄAzÉ zÁªÁ zÁR°¸À®Ä ¤zÉÃð²¹zÉ. ¸ÀzÀj D¹ÛAiÀÄ£ÀÄß ¸ÀAWÀPÉÌ
ªÀÄgÀ½ ¥ÀqÉAiÀÄ®Ä «¥sÀ®ªÁzÀ°è ¥ÀgÀ¨sÁgÉ ªÀiÁrgÀĪÀ 11789 ZÀzÀgÀ Cr
«¹ÛÃtðzÀ eÁUÀzÀ EA¢£À ªÀiÁgÀÄPÀmÉÖ ªÀiË®åªÀ£ÀÄß ¯ÉPÀÌ ªÀiÁr ªÉÄîÌAqÀ
¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ½AiÀĪÀgÀÄ, ªÀÄÄRå PÁAiÀÄð¤ªÁðºÀPÀgÀÄ,
C©üªÀÈ¢ÞzÁgÀgÀ£ÀÄß ºÉÆuÉUÁgÀgÀ£ÁßV¹ ¸ÀzÀjAiÀĪÀjAzÀ ¤AiÀĪÀiÁ£ÀĸÁgÀ
¥ÀgÀ¨sÁgÉ ªÀiÁrzÀ ¢£ÁAPÀ¢AzÀ §rØAiÉÆA¢UÉ ªÀ¸ÀƯÁw ªÀiÁqÀ®Ä
¤zÉÃð²¹zÉ. ªÀÄÄAzÀĪÀgÉzÀÄ, DqÀ½vÀ ªÀÄAqÀ½AiÀÄ F PÀÈvÀåPÁÌV PÀ£ÁðlPÀ
¸ÀºÀPÁgÀ ¸ÀAWÀUÀ¼À PÁAiÉÄÝ 1959 gÀ PÀ®A 29-¹ gÀr DqÀ½vÀ ªÀÄAqÀ½
¸ÀzÀ¸ÀåvÀé¢AzÀ C£ÀºÀðvÉUÉÆ½¸À®Ä ¥Àæ¸ÁÛªÀ£É ¸À°è¸À®Ä ¸ÀAWÀzÀ ªÀÄÄRå
PÁAiÀÄð¤ªÁðºÀPÀjUÉ ¤zÉÃð²¸À¯ÁVzÉ.
«ZÁgÀuÁA±À-2
xxxxx
«ZÁgÀuÁ¢üPÁjUÀ¼À C©ü¥ÁæAiÀÄ :
xxxxx
- 56 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
«ZÁgÀuÁ ªÀgÀ¢AiÀÄ CA±ÀUÀ½UÉ ¸ÀA§A¢ü¹zÀAvÉ PÀ®A 68gÀ ¤zÉÃð±À£À:-
xxxxx
PÀ®A 64 gÀ «ZÁgÀuÁ ªÀgÀ¢AiÀÄ CA±ÀUÀ¼ÀÄ, ¸À°è¹gÀĪÀ zÁR¯ÁwUÀ¼ÀÄ
ªÀÄvÀÄÛ «ZÁgÀuÁ¢üPÁjUÀ¼À C©ü¥ÁæAiÀĪÀ£ÀÄß CªÀ¯ÉÆÃQ¸À¯ÁV ¸ÀAWÀzÀ ¥Àæ¨sÁgÀ
PÁAiÀÄðzÀ²ðAiÀĪÀgÀÄ DqÀ½vÀ ªÀÄAqÀ½ ¸À¨sÉ dgÀÄVzÀ 07 ¢ªÀ¸ÀzÉÆ¼ÀUÁV J¯Áè
¤zÉÃð±ÀPÀgÀÄUÀ½UÉ DqÀ½vÀ ªÀÄAqÀ½ ¸À¨sÉAiÀÄ £ÀqÀªÀ½UÀ¼À£ÀÄß PÀ£ÁðlPÀ ¸ÀºÀPÁgÀ
¸ÀAWÀUÀ¼À PÁAiÉÄÝ 1959 gÀ PÀ®A 14(J)(PÉ)(9) gÀ CªÀPÁ±ÀUÀ¼À jÃvÁå PÀ¼ÀÄ»¸ÀzÉÃ
EgÀĪÀÅzÀÄ «ZÁgÀuÁ¢üPÁjUÀ¼À ªÀgÀ¢AiÀÄ CA±ÀUÀ½AzÀ zÀÈqsÀ¥ÀnÖgÀÄvÀÛzÉ. F
»£É߯ÉAiÀÄ°è ¸ÀAWÀzÀ ¥Àæ¨sÁgÀ PÁAiÀÄðzÀ²ðAiÀĪÀgÀ PÀvÀðªÀå ¯ÉÆÃ¥À ºÁUÀÆ
¤®ðPÀëvÀ£ÀzÀ PÀÈvÀåPÁÌV ¸ÀzÀjAiÀĪÀgÀ «gÀÄzÀÞ ¤AiÀĪÀiÁ£ÀĸÁgÀ ²¸ÀÄÛ PÀæªÀÄ dgÀÄV¹
CUÀvÀå PÁ£ÀÆ£ÀÄ PÀæªÀÄ PÉÊUÉÆ¼Àî®Ä DqÀ½vÀ ªÀÄAqÀ½UÉ ¤zÉÃð²¹zÀ.
«ZÁgÀuÁA±À-3
xxxxx
«ZÁgÀuÁ¢üPÁjUÀ¼À C©ü¥ÁæAiÀÄ :
xxxxx
«ZÁgÀuÁ ªÀgÀ¢AiÀÄ CA±ÀUÀ½UÉ ¸ÀA§A¢ü¹zÀAvÉ PÀ®A 68gÀ ¤zÉÃð±À£À:-
xxxxx
F DgÉÆÃ¥ÀPÉÌ PÀÄjvÀAvÉ ¸ÀAWÀzÀ ¥Àæ¨sÁgÀ PÁAiÀÄðzÀ²ðAiÀĪÀgÀÄ £ÉÃgÀ
dªÁ¨ÁÝjAiÀiÁVzÀÄÝ, ¸ÀzÀjAiÀĪÀgÀ PÁAiÀÄðPÀëªÀÄvÉAiÀÄ£ÀÄß ªÉÄîĸÀÄÛªÁj ªÀiÁqÀ®Ä
«¥sÀ®gÁzÀ ¸ÀAWÀzÀ DqÀ½vÀ ªÀÄAqÀ° ¸ÀzÀ¸ÀågÀÄ ªÀÄvÀÄÛ ¥ÀzÁ¢üPÁjUÀ¼ÀÄ
¥ÀgÉÆÃPÀëªÁV (¸ÀAWÀzÀ ¤zÉÃð±ÀPÀgÁzÀ ²æÃªÀÄw J¸ï ¥ÀAPÀd ªÀÄvÀÄÛ ²æÃ
JA.J¯ï ¥Àæ¸ÁzïgÁªï gÀªÀgÀ£ÀÄß ºÉÆgÀvÀÄ¥Àr¹) dªÁ¨ÁÝgÀgÁVgÀÄvÁÛgÉ."
38. The Society purportedly in compliance of the above
raised a dispute under Section 70 of KCS Act against the
- 57 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
developer and the purchasers of plot No.120. It submitted a
letter dated 16.01.2026 reporting the compliance of directions
under Section 68 of the KCS Act. However, a perusal of this
letter shows that the Society was trying to justify its action in
allowing the developer to alienate site No.120. As regards the
second direction issued by respondent No.3, the Society
claimed that there was no need to take any disciplinary action
against the Chief Executive Officer. As regards the third
direction, the Society again justified its stand for not taking
action against the In-charge Secretary. The explanation offered
by the Society in respect of unauthorized sale of site No.120 is
simply unacceptable as the Society itself was unaware of the
sale of site No.120 till a subcommittee was constituted.
However, it has now claimed that respondent No.5 i.e. the
other director were privy to all decisions.
39. The Directors of the Society while participating in
proceedings under Section 64 of the KCS Act, filed their
statement before the Enquiry Officer and enclosed therewith a
copy of the MOU entered into between the Developer as well as
the purchasers. It was stated in the objections that site No.120
- 58 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
was being encroached by the owners of various survey
numbers and adjoining owners and therefore, to protect the
site No.120, the Society chose to form six sites of 30x50 feet
and consequently, entered into a MOU. This MOU was though
dated 05.04.2023, but the report of the Inspector General of
Registration Stamps would show that the stamp paper for this
document was issued on 11.04.2025. It is therefore clear that
MOU itself was fraudulent, as the stamp paper issued in the
favour of the Chief Commissioner of Bruhat Bengaluru
Mahanagara Palike is sought to be misused. The Directors of
the Society have not placed on record any authenticated
resolution in terms of which, they had authorized the Developer
to convey the site bearing No.120 to third parties. The only
perceivable document is a draft resolution dated 28.05.2023,
where it is mentioned that the Board had unanimously resolved
to hand over site No.120 to the Developer and that the In-
charge Secretary and the President of the Society were
authorized by the Board to take further action. This draft
resolution was objected by the respondent No.5 and another
Director who also opposed the same being recorded in the
- 59 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
minutes book as the subject was not discussed. It appears that
the draft resolution dated 28.05.2023 was not recorded in the
minutes book as depicted in the draft resolution placed on
03.03.2024. Therefore, it goes without saying that there was
no resolution by the Board of the Society to authorize the
developer to convey site No.120.
40. On the other hand, the letter dated 02.02.2026
addressed by the Developer to the respondent No.3
categorically indicates that he sold site No.120 on the
instructions of the Directors of the Society and that the
Directors assured that they would obtain the NOC from the
Society. The In-charge Secretary of the Society against whom
the respondent No.3 passed an order under Section 68 of the
KCS Act, has not challenged the order. Therefore, it can safely
be held that all is not well with the Society and the Directors of
the Society have conducted the affairs of the Society in a
manner opposed to the interests of the Society and its
members.
41. The Directors of the Society having participated in
the proceedings of an enquiry under Section 64 of the KCS Act,
- 60 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
cannot assail the proceedings under Section 68 of the KCS Act
and also certainly cannot assail the action under Section 69 of
the KCS Act. Surprisingly, it is not the directors of the Society,
who have challenged the action under Section 69 of the KCS
Act, but it is the Society itself which has challenged it,
unmindful of the fact that an order under Section 68 of the KCS
Act is taken to protect the interests of the Society. It also
appears that W.P.No.2690/2026 is filed without the proper
authorization by the Board of Directors by the Incharge
Secretary against whom proceedings are pending.
42. As regards the proceedings initiated against the
Directors of the Society under Section 29-C of KCS Act, the
Directors have acted in a way prejudicial to the interests of the
Society and have also failed to initiate steps to recover back the
site No.120. The proceedings initiated by the Directors of the
Society under Section 70 of the KCS Act against the Developer
and the purchasers is prima facie not maintainable under
Section 70 of the KCS Act. The appropriate remedy for the
Directors of the Society was to invoke the arbitration clause in
the agreement dated 07.01.2005 against the Developer under
- 61 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
the provisions of the Arbitration and Conciliation Act, 1996 or
file a civil suit against the purchasers for recovery of
possession. The Society failed to initiate criminal and civil
proceedings against the Developer and the Chief Executive
Officer and members of the Managing Committee. Likewise, the
Society failed to take action against the Chief Executive Officer
for not conducting and recording the proceedings of the
meeting and to take departmental action against the In-charge
Secretary. These are not in dispute and therefore, the Directors
of the petitioner had not complied with the order under Section
68 of the KCS Act, in full but had made a vain attempt to
comply one of the directions namely to initiate proceedings
against the Developer and the purchasers.
43. This Court is therefore of the opinion that the order
passed under Section 68 of the KCS Act and the consequent
order passed by the respondent No.2, in an appeal under
Section 106 of the KCS Act are perfectly justified and do not
call for any interference. Furthermore, the Directors of the
petitioners have not taken any steps to explain to the Registrar,
the defects or the irregularities pointed out in the inspection
- 62 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
under Section 64 of the KCS Act. Therefore, the petitioners
being the Directors of the Society cannot in any manner assail
the order passed under Section 68 of the KCS Act. Once the
Directors of the Society have indulged in acts which is
prejudicial to the interests of the Society, they are not entitled
to continue as the Directors and it is not the case of the
Directors of the Society that they were not provided with an
opportunity in proceedings under Section 29-C of the KCS Act
and therefore, this Court does not see any exception to the
order passed under Section 29-C of the KCS Act.
44. As regards the challenge to proceedings under
Section 69 of the KCS Act, the writ petition is not maintainable
as it is filed by the Society itself and not the Directors. The
Society does not have any locus standi to challenge the
surcharge proceedings initiated against the Directors of the
Society. Furthermore, the Secretary of the Society has filed this
writ petition without there being proper authorization.
Therefore, W.P.No.2690/2026 does not merit consideration.
45. As regards the sale deed executed by the
purchasers in favour of the Society, which is confirmed by the
- 63 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
Developer, as rightly contended by the learned counsel for the
respondent No.5, there are certain defects which are
irreconcilable. When the sale deed dated 07.07.2026 is
executed, the consideration must have been either
contemporaneous or immediately prior. However, the payments
are made much prior to the execution of the sale deed itself.
There are no reasons mentioned to how and why the payment
was made prior to the execution of the sale deed. Ideally, the
sale deed dated 25.08.2023 executed by the developer in
favour of the purchasers must have been cancelled and
thereafter, the developer could have conveyed the sites that
may be formed in site No.120 to the members of the Society.
46. In that view of the matter, the apprehension
expressed by the respondent No.5 that this sale deed is
susceptible to be challenged before the Courts cannot be ruled
out. However, having regard to the fact that site No.120 has
come back into the coffers of Society by virtue of the sale deed
dated 07.07.2026, it is appropriate that the reliefs in the writ
petition is suitably moulded so that the interests of the
members of the Society is fully protected.
- 64 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
47. In view of the above, the following order is passed:
ORDER
i. W.P.No.12472/2026 is dismissed ;
ii. The order of disqualification of the petitioners of
the Society is upheld. Consequently, the order
appointing a Special Officer to conduct elections to
the Society is also upheld;
iii. W.P.No.18567/2026 is allowed in part ;
iv. The order bearing No. HSG-3/114/HHS/2024-25
dated 01.12.2025 passed by the respondent No.3
under Section 68 of the Karnataka Co-operative
Societies Act, 1959 and the order dated
30.05.2026 passed in appeal filed in case No.
RCS/DAP/D1/24/2025-26 under Section 106 of
the Karnataka Co-operative Societies Act, 1959
are confirmed;
v. However, the direction by respondent No.3 to the
Society under Section 68 of the Karnataka Co-
operative Societies Act, 1959, to initiate criminal
- 65 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
prosecution against the Developer and the
purchasers of site No.120 is kept on hold for a
period of six months from the date of receipt of a
copy of this order, to enable the developer to
cancel the sale deed dated 25.08.2023 in favour
of the purchasers so that the title of the developer
to site No.120 is restored and the Developer shall
thereafter submit a modified plan to the
concerned Planning Authority to form 16 sites in
site No.120 and thereafter, convey the sites to the
members of the Society. After such conveyance,
the sale deed dated 07.07.2026 executed by the
purchasers in favour of the Society and registered
at the office of the Sub-Registrar, Ramanagara, as
document No.RMN-1-04734-2026-2027 shall
stand cancelled;
vi. It is declared that neither the developer nor the
purchasers shall have any right, title or interest in
respect of site No.120 formed in Sy.Nos.91 and 92
of Hejjala Village and they shall not raise any
- 66 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
dispute before the Civil Court or any other judicial
or quasi-judicial forum challenging the
correctness/ validity/genuineness of the sale deed
dated 07.07.2026 executed by them in favour of
the Society in respect of site No.120 at the layout
formed by the Developer at Hejjala Village in
Sy.Nos.91 and 92;
vii. W.P.No.2690/2026 is also disposed of , upholding
the action taken by the respondent No.2 under
Section 69 the Karnataka Co-operative Societies
Act, 1959. However, further action shall be kept
on hold for a period of six months from the date
of receipt of a certified copy of this order to
enable the Developer to convey the sites formed
in site No.120 as stated while disposing of
W.P.No.18567/2026;
viii. The Special Officer appointed shall initiate
appropriate disciplinary action against the In-
charge Secretary and the Chief Executive Officer
as per the order dated 01.12.2025 passed by
- 67 -
HC-KAR
NC: 2026:KHC:59247
WP No. 12472 of 2026
C/W WP No. 2690 of 2026
WP No. 18567 of 2026
CNR: KAHC010286012026
respondent No.3 under Section 68 of the
Karnataka Co-operative Societies Act, 1959;
ix. List for compliance of (viii) above and to monitor
steps taken to implement (v) above on
08.01.2027 ;
x. It is made clear that the expenses incurred or
registering the sale deed dated 07.07.2026 by the
purchasers to the Society and the stamp duty
shall be borne entirely by the Developer and shall
not be charged to the account of the Society.
Sd/-
(R. NATARAJ)
JUDGE