Sadguru Engineers And Allied Services Pvt Ltd vs National Highways Infrastructure Development Corporation Ltd Represented By Its Managing Director & Ors.
- Court
- Delhi High Court
- Case type
- Original Misc Petition Interlocutory Commercial
- Decided on
- 24-02-2026
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 20.01.2026
Judgment pronounced on:24.02.2026
+ O.M.P.(I) (COMM.) 18/2026 & I.A. 1378/2026 (Ex.)
SADGURU ENGINEERS AND ALLIED SERVICES PVT
LTD .....Petitioner
Through: Mr. Ashkrit Tiwari, Ms. Aditi
Shrivastava, Mr. Kartik
Pendharkar, Ms. Kanika Arora,
Mr. Aman Kumar and Mr.
Abhinav Akash, Advocates.
versus
NATIONAL HIGHWAYS INFRASTRUCTURE
DEVELOPMENT CORPORATION LTD REPRESENTED BY
ITS MANAGING DIRECTOR & ORS. .....Respondents
Through: Mr. Gopal Singh, Mr. Shivam
Singh and Mr. Shubham
Janghu, Advocates for
Respondent No. 1.
Mr. Santosh Kumar Rout,
Standing Counsel for
Respondent No. 2.
Ms. Devna Soni, Mr.
Shivashish Dwivedi and Ms.
Varsha Jain, Advocates for
Respondent No. 4.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
J U D G M E N T
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition has been filed under Section 9 of the
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 1 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
1
Arbitration and Conciliation Act, 1996 , seeking the following
reliefs:
“ a. Pass an ex-parte ad-interim order, thereby restraining the
Respondents from invoking/ encashing the bank guarantees issued
by the State Bank of India i.e., herein Respondent No.2; namely: -
i. Performance Bank Guarantee No. 0151824BG0000014 for
Rs.3,24,00,324/- dated 20.01.2024;
ii. Mobilization Bank Guarantee No. 0151824BG0000057 for
Rs.3,50,46,351/- dated 04.03.2024; and
iii. Performance Bank Guarantee No. 0151824BG0000016 for
INR. 1,89,00,019/- dated 20.01.2024
b. Pass an order restraining Respondent No.1, its servants,
employees and agents from terminating the contracts for Pkg-I and
Pkg-IV, in as much as the EPC Contract is also “the subject matter
of the arbitration agreement”;
c. Confirm the orders passed in terms of aforesaid Prayers „a‟ and
„b‟ after notice to the Respondents;
d. Award costs of the present proceedings in favour of the
Petitioner and against the Respondents;
e. Pass such other order or further orders as this Hon‟ble Court may
deem fit and proper in the facts and circumstances of the present
case.”
BRIEF FACTS:
2
2. M/s Sadguru Engineers and Allied Services Pvt. Ltd. , the
3
Engineering, Procurement and Construction Contractor herein, is
a construction company incorporated under the Companies Act, 1956,
having its registered office at 406, 4th Floor, Hanuman Tower,
Athgaon, Guwahati, Assam-781001.
3. National Highways & Infrastructure Development
4
Corporation Ltd is a Central Public Sector Undertaking under the
Ministry of Road Transport and Highways, Government of India,
which, on 25.09.2023, issued certain tenders for execution of balance
1
A&C Act
2
Petitioner
3
EPC
4
NHIDCL/Respondent No.1
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 2 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
5
works of four-laning of National Highway No.37 (Old) , Jorhat-
Jhanji stretch, under the EPC mode for Package-I (consisting the
6
Road Works) and Package-IV (consisting the Structures & Toll
7
Plaza) .
4. The Petitioner emerged as the lowest bidder for the said tenders
and was issued Letters of Acceptance dated 15.01.2024 for both
8
packages. Pursuant thereto, Contract Agreements dated 07.02.2024
in respect of both said packages came to be executed with NHIDCL.
5. In compliance with the contractual stipulations, the Petitioner
furnished two Performance Bank Guarantees and a Mobilisation
9 10
Bank Guarantee , issued by State Bank of India (through the
Branch Manager), SME AT Road Branch, Guwahati-794106,
aggregating to INR 8,63,46,694/-.
6. It is stated that the appointed date for commencement of works
for both packages was fixed as 14.02.2024, and in the course of
execution thereafter, the Petitioner achieved substantial progress,
namely approximately 97% physical progress and 93.18% financial
progress in Pkg-I, and 94.73% physical progress and 92.35% financial
progress in Pkg-IV, as reflected in the Stage Payment Statements.
7. It is further stated that in pursuance thereof, certain applications
11
seeking Extension of Time , including formal applications, were
submitted by the Petitioner for completion of the balance of works.
The Petitioner, however, asserted that delays in said completion of the
5
NH-37
6
Pkg-I
7
Pkg-IV
8
Agreements
9
BGs
10
Respondent No.2
11
EOT
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 3 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
project occurred due to Authority Defaults and Force Majeure events,
including non-availability of encumbrance-free right of way, flooding
and unseasonal rainfall, obstruction by utility lines, delays by other
contractors, and execution of additional works beyond the original
scope. It is further the Petitioner‟s case that such extensions as sought
by the Petitioner were either withheld by Respondent No.1 or made
conditional upon execution of no-claim undertakings.
8. It is the Petitioner‟s case that the entire mobilisation advance
stood fully recovered along with interest, yet the Mobilisation Bank
12
Guarantee was not released and was instead required to be extended
without any contractual basis.
9. Notwithstanding the Petitioner‟s letter dated 05.01.2026,
reiterating its readiness to complete the balance works by 28.02.2026,
13
Mr. Devendra Kumar , General Manager (Projects), NHIDCL
Project Monitoring Unit, Jorhat, Assam-785006, on 14.01.2026,
14
issued a Letter presaging invocation of the bank guarantees and
demanding additional performance security, followed by issuance of
15
the Termination Notice dated 15.01.2026 alleging contractor
default.
10. It is the Petitioner‟s case that Respondent No.3 is hand in glove
with one Mr. Shiva Harlalka, Proprietor of Kiraats Construction
16
Pvt. Ltd. (formerly, Shiva Harlalka Pvt. Ltd.), having its registered
st
office at Parmeshwari Building, 1 Floor, Chatribari Road, Guwahati-
781001, who is a private contractor earlier engaged by Respondent
12
MBG
13
Respondent No.3
14
Impugned Letter
15
Termination Notice
16
Respondent No.4
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 4 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
No.1. The Petitioner alleges that Respondent Nos. 3 and 4 have acted
in concert with a common intention to misappropriate government-
sanctioned funds allotted to the Petitioner for their personal gains.
11. Aggrieved by the said issuance of Termination Notice by
Respondent No.3, the present Petition came to be filed seeking, inter
alia , directions of this Court to the Respondents restraining them from
encashing the BGs as well as terminating the Contract.
SUBMISSIONS OF THE PETITIONER:
12. Learned counsel for the Petitioner would state that he has been
constrained to approach this Court due to the issuance of the
Impugned Letter by which Respondent No.1 has sought to encash the
BGs.
13. Learned counsel for the Petitioner would further submit that the
invocation of the BGs is illegal, inasmuch as the Respondent No.1
seeks to encash them in respect of two separate aspects. It would be
submitted that one of these aspects pertains to the alleged disputed and
undisputed amounts claimed to be payable to various vendors.
14. In pursuance of said aspect, the learned counsel for the
Petitioner would further submit that, in respect of one of the vendors,
17
namely M/s AB Industries , there is no dispute regarding the
existence of an undisputed outstanding amount of ₹81 lakhs.
However, he would seriously dispute the alleged outstanding amounts,
both disputed and undisputed, claimed in respect of M/s Lummar
18
Enterprise , as mentioned in the Impugned Letter at Para 5 (v). He
would premise his objection to the inclusion of the said amounts on
17
Vendor No.1
18
Vendor No.2
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 5 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
two grounds, the first being the Petitioner’s Letter dated
19
07.07.2025 , whereby the alleged amounts claimed to be payable to
Vendor No.2 were disputed by him. He would state that in view of the
same, the tabulation of dues as per the Impugned Letter is clearly
ambiguous. Secondly, learned counsel for the Petitioner would further
contend that, in any event, Vendor No.2 has initiated proceedings
20
before the learned National Company Law Tribunal in respect of
the total amount alleged to be outstanding. In view thereof, it would
be submitted that no occasion arises for Respondent No.1 to invoke
the BGs, as any dues, if at all payable by the Petitioner to Vendor
No.2, are now subject to adjudication in the proceedings pending
before the learned NCLT. Consequently, the Impugned Letter is stated
to be wholly unsustainable.
15. As respects the second aspect, the learned counsel for the
Petitioner would submit that the calculation, as set out in Para 7 of the
Impugned Letter, cannot form the subject matter for the purpose of
invocation of the BGs, since the sum of Rs. 6.216 Crores as indicated
in Para 7 of the said communication pertains to the alleged recovery of
the funds released on assurances that were not honoured. Para 7 is
reproduced for ready reference herein under:
“ 7. Accordingly, the total amount presently claimed as payable by
the EPCC to NHIDCL stands at Rs. 8.496 Crore (Rs. 2.28 Crore
towards undisputed vendor dues, as set out above, and Rs. 6.216
Crore towards recovery of funds released on assurances which
have not been honoured). The EPCC is hereby directed to forthwith
remit the entire amount of Rs. 8,496 Crore to NHIDCL by
17.01.2026, without any demur or adjustment. Further, the EPCC
shall furnish in favour of NHIDCL an unconditional and
irrevocable BG of Rs. 2.50 Crore securing any potential exposure
of NHIDCL arising out of the comfort letters, which amount is
19
Petitioner‟s Letter
20
NCLT
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 6 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
disputed by the EPCC and may, subject to the outcome of the
ongoing litigation between the EPCC and the concerned vendor, be
determined as payable by the EPCC. The BG, so submitted, shall
be encashed only after a valid demand is raised against NHIDCL
by the vendor; until such time, the BG is to be always kept
renewed and valid by the EPCC at all times. The Account details
for depositing the above-mentioned amounts are as follows:
Bank Name: Canara Bank
Branch: Specialised Govt Business Branch, Guwahati
A/c Name: RO NHIDCL PROJECTS
A/c No. : 73653210000013
IFSC: CNRB0007374”
16. The Petitioner would further submit that, as per the
Agreements, as between the parties, the invocation of the BGs could
only be in terms of the clauses as set out therein, particularly Para 7.3,
which is extracted herein under: -
“ 7.3 Appropriation of Performance Security
(i) Upon occurrence of a Contractor‟s Default, the Authority shall,
without prejudice to its other rights and remedies hereunder or in
law, be entitled to encash and appropriate the relevant amounts
from the Performance Security as Damages for such Contractor‟s
Default.
(ii) Upon such encashment and appropriation from the
Performance Security, the Contractor shall, within 30 (thirty) days
thereof, replenish, in case of partial appropriation, to its original
level the Performance Security, and in case of appropriation of the
entire Performance Security provide a fresh Performance Security,
as the case may be, and the Contractor shall, within the time so
granted, replenish or furnish fresh Performance Security as
aforesaid failing which the Authority shall be entitled to terminate
the Agreement in accordance with Article 23. Upon replenishment
or furnishing of a fresh Performance Security, as the case may be,
as aforesaid, the Contractor shall be entitled to an additional Cure
Period of 30 (thirty) days for remedying the Contractor‟s Default,
and in the event of the Contractor not curing its default within such
Cure Period, the Authority shall be entitled to encash and
appropriate such Performance Security as Damages, and to
terminate this Agreement in accordance with Article 23. ”
17. He would further submit that the Contractor‟s default as
mentioned in aforesaid Clause 7.3, is defined in Clause 1.1 read with
Clause 23.1, while Clause 1.1 defines “ Contractor Default to have the
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 7 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
same meaning as set out in Clause 23.1 ”. The said Clause 23.1 reads
as follows:
“ 23.1 Termination for Contractor Default
(i) Save as otherwise provided in this Agreement, in the event that
any of the defaults specified below shall have occurred, and the
Contractor fails to cure the default within the Cure Period set forth
below, or where no Cure Period is specified, then within a Cure
Period of 60 (sixty) days, the Contractor shall be deemed to be in
default of this Agreement (the “ Contractor Default ”), unless the
default has occurred solely as a result of any breach of this
Agreement by the Authority or due to Force Majeure. The defaults
referred to herein shall include:
(a) the Contractor fails to provide, extend or replenish, as the case
may be, the Performance Security in accordance with this
Agreement;
(b) after the replenishment or furnishing of fresh Performance
Security in accordance with Clause 7.3, the Contractor fails to
cure, within a Cure Period of 30 (thirty) days, the Contractor
Default for which the whole or part of the Performance
Security was appropriated;
(c) the Contractor does not achieve the latest outstanding Project
Milestone due in accordance with the provisions of Schedule-],
subject to any Time Extension, and continues to be in default
for 45 (forty-five) days;
(d) the Contractor abandons or manifests intention to abandon the
construction or Maintenance of the Project Highway without
the prior written consent of the Authority;
(e) the Contractor fails to proceed with the Works in accordance
with the provisions of Clause 10.1 or stops Works and/or the
Maintenance for 30 (thirty) days without reflecting the same in
the current programme and such stoppage has not been
authorised by the Authority‟s Engineer;
(f) the Project Completion Date does not occur within the period
specified in Schedule-] for the Scheduled Completion Date, or
any extension thereof;
(g) the Contractor fails to rectify any Defect, the non-rectification
of which shall have a Material Adverse Effect on the Project,
within the time specified in this Agreement or as directed by
the Authority‟s Engineer;
(h) the Contractor subcontracts the Works or any part thereof in
violation of this Agreement or assigns any part of the Works or
the Maintenance without the prior approval of the Authority;
(i) the Contractor creates any Encumbrance in breach of this
Agreement;
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 8 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
(j) an execution levied on any of the assets of the Contractor has
caused a Material Adverse Effect;
(k) the Contractor is adjudged bankrupt or insolvent, or if a trustee
or receiver is appointed for the Contractor or for the whole or
material part of its assets that has a material bearing on the
Project;
(l) the Contractor has been, or is in the process of being
liquidated, dissolved, wound-up, amalgamated or reconstituted
in a manner that would cause, in the reasonable opinion of the
Authority, a Material Adverse Effect;
(m) A resolution for winding up or insolvency of the Contractor is
passed, or any petition for winding up or insolvency of the
Contractor is admitted by a court of competent jurisdiction and
a provisional liquidator or receiver or interim resolution
professional, as the case may be, is appointed and such order
has not been set aside within 90 (ninety) days of the date
thereof or the Contractor is ordered to be wound up by court
except for the purpose of amalgamation or reconstruction;
provided that, as part of such amalgamation or reconstruction,
the entire property, assets and undertaking of the Contractor
are transferred to the amalgamated or reconstructed entity and
that the amalgamated or reconstructed entity has
unconditionally assumed the obligations of the Contractor
under this Agreement; and provided that:
i. the amalgamated or reconstructed entity has the
capability and experience necessary for the performance
of its obligations under this Agreement; and
ii. the amalgamated or reconstructed entity has the
financial standing to perform its obligations under this
Agreement and has a credit worthiness atleast as good as
that of the Contractor as at the Appointed Date;
(n) any representation or warranty of the Contractor herein
contained which is, as of the date hereof, found to be false or
the Contractor is at any time hereafter found to be in breach or
non-compliance thereof;
(o) the Contractor submits to the Authority any statement, notice
or other document, in written or electronic form, which has a
material effect on the Authority‟s rights, obligations or
interests and which is false in material particulars;
(p) the Contractor has failed to fulfil any obligation, for which
failure Termination has been specified in this Agreement; or
(q) the Contractor commits a default in complying with any other
provision of this Agreement if such a default causes a Material
Adverse Effect on the Project or on the Authority.
(r) gives or offers to give (directly or indirectly) to any person any
bribe, gift, gratuity, commission or other thing of value, as an
inducement or reward:
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 9 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
iii. for doing or forbearing to do any action in relation to the
Contract, or
iv. for showing or forbearing to show favour or disfavour to
any person in relation to the Contract,
or if any of the Contractor‟s personnel, agents or
subcontractors gives or offers to give (directly or indirectly) to
any person any such inducement or reward as is described in
this sub-paragraph (s). However, lawful inducements and
rewards to Contractor's Personnel shall not entitle termination.
(ii) Without prejudice to any other rights or remedies which the
Authority may have under this Agreement, upon occurrence of a
Contractor Default, the Authority shall be entitled to terminate this
Agreement by issuing a Termination Notice to the Contractor;
provided that before issuing the Termination Notice, the Authority
shall by a notice inform the Contractor of its intention to issue such
Termination Notice and grant 15 (fifteen) days to the Contractor to
make a representation, and may after the expiry of such 15 (fifteen)
days, whether or not it is in receipt of such representation, issue the
Termination Notice.
(iii) The following shall apply in respect of cure of any of the
defaults and/ or breaches of the Agreement:
(a) The Cure Period shall commence from the date of the notice by
the Authority to the Contractor asking the latter to cure the
breach or default specified in such notice;
(b) The Cure Period provided in the Agreement shall not relieve
the Contractor from liability for Damages caused by its breach
or default;
(c) The Cure Period shall not in any way be extended by any period
of suspension under the Agreement;
(d) If the cure of any breach by the Contractor requires any
reasonable action by the Contractor that must be approved by
the Authority hereunder the applicable Cure Period (and any
liability of the Contractor for damages incurred) shall be
extended by the period taken by the Authority to accord its
required approval.
(iv) After termination of this Agreement for Contractor Default, the
Authority may complete the Works and/or arrange for any other
entities to do so. The Authority and these entities may then use any
Materials, Plant and equipment, Contractor‟s documents and other
design documents made by or on behalf of the Contractor. ”
18. Learned counsel for the Petitioner would further submit that the
recovery of the said amount of Rs.6.216 Crores is not traceable in any
of the conditions as set out in Clause 23.1 and resultantly, there arises
no occasion for the Respondents to predicate the invocation of the
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 10 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
BGs on the alleged recovery of funds which were released on the
alleged assurances that have allegedly not been honoured.
19. Learned counsel for the Petitioner would submit that the
invocation of the BGs is patently illegal, inasmuch as even if only the
terms of the BGs are taken into consideration for examining the
legality of the invocation, the same clearly stipulate that invocation
can be made only in the event of non-performance of obligations
under the Contract and not on the basis of any alleged extra-
contractual obligation between the parties.
20. The learned counsel for the Petitioner would further contend
that the invocation of the BGs towards the alleged recovery of funds
which were released on assurances but not honoured is not a
contractual condition and in view of the same, the attempt on the part
of the Respondent to invoke and encash said BGs is clearly
unsustainable.
SUBMISSION OF THE RESPONDENTS:
21. Per Contra, learned counsel for the Respondents would submit
that the interdiction of the encashment of the BGs has to be purely on
the basis of the clauses as contained in said BGs themselves which
forms a separate Agreement and the grounds under which such an
invocation can be interdicted is if there is egregious fraud or a case of
irretrievable injustice is made out and also if there are special equities
in favour of the Petitioner.
22. The Respondents would further submit that in the present case,
even a cursory reading of the various grounds relating to egregious
fraud that have been taken would make it evident that there is, in fact,
no ground made out in this respect. He would further submit that on
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 11 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
this ground, the invocation of the BGs cannot be interdicted.
23. With respect to the aspect as to whether there arose any special
equities, the learned counsel for the Respondents would contend that
no such special equities are also evident from the pleadings as well as
the various arguments that have been canvassed by the learned
counsel for the Petitioner.
24. Learned counsel for the Respondents would further submit that
the invocation of the BGs for the purpose of recovery of funds is
predicated on the alleged breach of Clause 23.1(i)(n) and the same is
extracted herein under:
“ 23.1 Termination for Contractor Default
(i) Save as otherwise provided in this Agreement, in the event that
any of the defaults specified below shall have occurred, and the
Contractor fails to cure the default within the Cure Period set forth
below, or where no Cure Period is specified, then within a Cure
Period of 60 (sixty) days, the Contractor shall be deemed to be in
default of this Agreement (the “ Contractor Default ”), unless the
default has occurred solely as a result of any breach of this
Agreement by the Authority or due to Force Majeure. The defaults
referred to herein shall include:
*
(n) any representation or warranty of the Contractor herein
contained which is, as of the date hereof, found to be false
or the Contractor is at any time hereafter found to be in
breach or non-compliance thereof;
…..”
25. Learned counsel for the Respondents would further contend that
the present Contracts are of a sensitive nature, inasmuch as they
pertain to the construction of border roads, which are regarded as vital
infrastructure and have also been a subject of deliberation in the
Parliament of India.
26. Learned counsel for the Respondents would also contend that
the Petitioner has miserably failed in performing his part of the
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 12 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
Contract and even as of this date, no work for advancing the project is
being carried out at the site by the Petitioner.
27. Learned counsel for the Respondent would further submit that
the main Promoter of the Petitioner-Company, i.e., Mr. Mukesh Jalan,
is currently incarcerated and undergoing criminal investigation for
various counts of fraud allegedly committed by him.
28. Learned counsel for the Respondent would also submit that by
way of the Letter dated 07.06.2024, damages to the tune of 0.05% per
day were imposed on the Petitioner and it is the non-payment of this
amount which also led to the invocation of the BGs for the purpose of
recovery of the said damages.
ANALYSIS:
29. Heard the learned counsel for the parties and, with their able
assistance, perused the record and the various documents that have
been filed and handed over to this Court across the bar.
30. It is apposite to emphasise that this Court remains acutely
conscious of the fact that the present Petition has been filed under
Section 9 of the A&C Act, and therefore, at this stage, the remit of this
Court is confined to ensuring preservation of the subject matter of the
dispute till such time as the same is adjudicated by the appropriate
forum, i.e., the learned Arbitral Tribunal.
31. Additionally, in the considered view of this Court, having
regard to the limited and protective nature of the jurisdiction exercised
under Section 9 of the A&C Act, it is neither necessary nor
appropriate to delve into a detailed examination of the factual matrix
or to undertake an exhaustive examination of the various contractual
clauses and documents relied upon by the parties, all of which are
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 13 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
matters to be considered by the learned Arbitral Tribunal.
32. The raison d’être of Section 9 of the A&C Act is to preserve
and protect the subject matter of the dispute in the interregnum, so
that the arbitral proceedings, when commenced, are not rendered
nugatory. The power vested with the Courts under Section 9 is thus
essentially protective and facilitative in character, intended to
safeguard and secure the efficacy of the arbitral process and not to
supplant it.
33. The Hon‟ble Supreme Court, in a gamut of judgments, inter
21
alia , in Sundaram Finance Ltd. v. NEPC India Ltd. , Arcelor Mittal
22
Nippon Steel India Ltd. v. Essar Bulk Terminal Ltd. and Adhunik
23
Steels Ltd. v. Orissa Manganese and Minerals (P) Ltd , has
authoritatively held that the jurisdiction of the Courts under Section 9
of the A&C Act can be exercised even prior to the constitution of the
Arbitral Tribunal, with a view of safeguarding and preserving the
subject-matter of the dispute till such time as the Arbitral Tribunal
undertakes adjudication.
34. Further, a Division Bench of this Court, in M/s GTL
24
Infrastructure Ltd. v. S.C. Wadhwa and Sons (HUF) , has held that
the powers of the Court under Section 9 of the A&C Act are of wide
amplitude and are not circumscribed by the contours of interim reliefs
contemplated under Order XXXIX of the Civil Procedure Code,
25
1908 . The Court observed that Section 9 vests broad discretion to
grant such interim measures of protection as may be just and
21
(1999) 2 SCC 479
22
(2022) 1 SCC 712
23
(2007) 7 SCC 125
24
2025:DHC:1475-DB
25
CPC
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 14 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
convenient, including mandatory injunctions, where the circumstances
so warrant. It was further emphasised that such powers are to be
exercised to preserve the subject matter of arbitration and to ensure
that the arbitral proceedings are not rendered futile or inefficacious.
The relevant Para of M/s GTL Infrastructure Ltd. (supra) is
reproduced herein under:
“ 14. In the given facts, the contention that an order under Section 9
of the A&C Act could not be passed directing the appellant to
remove the tower is unpersuasive. It is settled law that powers of a
court under Section 9 of the A&C Act are wide and encompass
such orders as are necessary to protect and preserve the subject
matter of the arbitration, including issuing mandatory injunctions.
The court must adopt a course, which is least likely to result
injustice if the same is finally found to be wrong…..”
35. In view of the foregoing discussion, this Court is of the
considered opinion that no relief can be granted insofar as the stay of
the effect and operation of the Termination Notice is concerned. It is a
well-settled position of law that a Contract which is, by its very
nature, determinable does not admit of an order of interdiction or stay
restraining its termination. Any such restraint would, in effect, amount
to enforcing the continuance of a contractual relationship which the
law itself recognises as terminable, and is therefore impermissible.
36. The Hon‟ble Supreme Court in Indian Oil Corporation vs.
26
Amritsar Gas Service & Ors. has categorically held that granting a
stay against termination of such a Contract, i.e., a Contract that is by
its very nature determinable, would amount to enforcing a contractual
relationship which the law expressly recognises as terminable, and is
therefore impermissible. The relevant paragraph of the said decision is
reproduced herein under for ready reference:
26
(1991) 1 SCC 533
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 15 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
“12. The arbitrator recorded finding on Issue No. 1 that termination
of distributorship by the appellant-Corporation was not validly
made under clause 27. Thereafter, he proceeded to record the
finding on Issue No. 2 relating to grant of relief and held that the
plaintiff-respondent 1 was entitled to compensation flowing from
the breach of contract till the breach was remedied by restoration of
distributorship. Restoration of distributorship was granted in view
of the peculiar facts of the case on the basis of which it was treated
to be an exceptional case for the reasons given. The reasons given
state that the Distributorship Agreement was for an indefinite
period till terminated in accordance with the terms of the
agreement and, therefore, the plaintiff-respondent 1 was entitled to
continuance of the distributorship till it was terminated in
accordance with the agreed terms. The award further says as under:
“This award will, however, not fetter the right of the
defendant Corporation to terminate the distributorship of
the plaintiff in accordance with the terms of the agreement
dated April 1, 1976, if and when an occasion arises.”
This finding read along with the reasons given in the award clearly
accepts that the distributorship could be terminated in accordance
with the terms of the agreement dated April 1, 1976, which
contains the aforesaid clauses 27 and 28. Having said so in the
award itself, it is obvious that the arbitrator held the distributorship
to be revokable in accordance with clauses 27 and 28 of the
agreement. It is in this sense that the award describes the
Distributorship Agreement as one for an indefinite period, that is,
till terminated in accordance with clauses 27 and 28. The finding in
the award being that the Distributorship Agreement was revokable
and the same being admittedly for rendering personal service, the
relevant provisions of the Specific Relief Act were automatically
attracted. Sub-section (1) of Section 14 of the Specific Relief Act
specifies the contracts which cannot be specifically enforced, one
of which is „a contract which is in its nature determinable‟. In the
present case, it is not necessary to refer to the other clauses of sub-
section (1) of Section 14, which also may be attracted in the
present case since clause (c) clearly applies on the finding read
with reasons given in the award itself that the contract by its nature
is determinable. This being so granting the relief of restoration of
the distributorship even on the finding that the breach was
committed by the appellant-Corporation is contrary to the mandate
in Section 14(1) of the Specific Relief Act and there is an error of
law apparent on the face of the award which is stated to be made
according to „the law governing such cases‟. The grant of this relief
in the award cannot, therefore, be sustained.”
(emphasis supplied)
37. Hence, in respect of Prayer Clause „b‟, since the same pertains
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 16 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
to passing a direction restraining Respondent No.1 from terminating
the Contracts, and in view of the foregoing discussion, this Court is of
the considered view that no stay or injunction can be granted against
the Termination Notice.
38. However, having due regard to the settled position of law as
enunciated in M/s GTL Infrastructure Ltd. ( supra ), wherein it has
been crystallised that, depending upon the facts and circumstances of a
given case, Section 9 of the A&C Act, vests the Court with powers of
granting interim reliefs broader than those contemplated under Order
XXXIX of the CPC, the underlying rationale being the preservation of
the subject matter of arbitration so as to ensure that the arbitral
proceedings do not become futile. In furtherance thereof, and having
regard to the facts and circumstances of the present case, this Court is
of the considered view that the Petitioner has been able to establish a
strong prima facie case warranting the grant of a limited interim
protection.
39. In the aforesaid backdrop, this Court now turns to Prayer Clause
„a‟, which pertains to the restraint sought against the Respondents
from invoking and encashing the BGs referred to therein.
40. At the outset, learned counsel for the Petitioner would submit
that the ground of egregious fraud is not being pressed. The analysis,
therefore, is limited to the question as to whether there are any special
equities or irretrievable injustice or under the expressed terms of the
BGs, there arises any occasion for the Respondents to invoke the
same.
41. This Court considers it unnecessary to examine whether the
facts disclose the existence of any special equities or whether the
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 17 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
present case is one of irretrievable injustice, as upon a conjoint
reading of the clauses of the BGs and the relevant contractual
provisions which govern the circumstances in which invocation may
be made, it becomes apparent that the conditions precedent for such
invocation have not arisen. The analysis, therefore, is confined to the
terms of the BGs themselves and the question as to whether, in terms
thereof, said invocation is at all permissible.
42. This Court would caveat the analysis with the statement that
while adjudicating the present Petition, it is only expressing its prima
facie opinion and the same will not be treated as a final adjudication
on any of the issues or factual matrix of the present matter.
43. The relevant clauses of the BGs read as follows:
“WHEREAS M/s Sadguru Engineers & Allied Services Private
Limited [name and address of Contractor] (hereafter called the
"Contractor") has undertaken, in pursuance of Letter of Acceptance
(LOA) No. NHIDCL/ Assam/J-J/Pkg-1/232667/2955 Date
15.01.202 4 for construction of "Construction of Balance Work of
the 4-laning of the Section from Jorhat to Jhanji of NH-37 (Old):
Pkg-I: Road Works from Km 453+000 to Km 463+000(10.000
Km), under SARDP-NE, under EPC Mode" [name of the Project]
(hereinafter called the "Contract")
AND WHEREAS the Contract requires the Contractor to furnish
an {Performance Security/ Additional Performance Security} for
due and faithful performance of its obligations, under and in
accordance with the Contract, during the {Construction Period/
Defects Liability Period and Maintenance Period} in a sum of Rs
3,24,00,324.00 (Rupees Three Crore Twenty-Four Lakhs Three
Hundred and Twenty-Four Rupees only) (the "Guarantee
Amount"').
AND WHEREAS we, State Bank of India through our branch at
SME. AT.Road, Guwahati (the "Bank") have agreed to furnish
this Bank Guarantee (hereinafter called the "Guarantee") by way
of Performance Security.
NOW, THEREFORE, the Bank hereby, unconditionally and
irrevocably, guarantees and affirms as follows:
1. The Bank hereby unconditionally and irrevocably guarantees the
due and faithful performance of the Contractor's obligations during
the {Construction Period/ Defects Liability Period and
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 18 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
Maintenance Period} under and in accordance with the Contract,
and agrees and undertakes to pay to the Authority, upon its mere
first written demand, and without any demur, reservation, recourse,
contest or protest, and without any reference to the Contractor,
such sum or sums up to an aggregate sum of the Guarantee
Amount as the Authority shall claim, without the Authority being
required to prove or to show grounds or reasons for its demand
and/or for the sum specified therein.
A letter from the Authority, under the hand of an officer not below
the rank of [General Manager of National Highways &
Infrastructure Development Corporation Limited], that the
Contractor has committed default in the due and faithful
performance of all or any of its obligations under and in
accordance with the Contract shall be conclusive, final and binding
on the Bank. The Bank further agrees that the Authority shall be
the sole judge as to whether the Contractor is in default in due and
faithful performance of its obligations during and under the
Contract and its decision that the Contractor is in default shall be
final and binding on the Bank, notwithstanding any differences
between the Authority and the Contractor, or any dispute between
them pending before any court, tribunal, arbitrators or any other
authority or body, or by the discharge of the Contractor for any
reason whatsoever.
….”
(emphasis supplied)
44. As is manifest, the terms of the BGs are explicit and the
invocation of the BGs can only be predicated on a breach of the terms
of the Contract itself. The attempt of the Respondents to encash the
BGs for the alleged recovery of funds, which were released on
assurances that were not honoured, is therefore clearly unsustainable
since these assurances were not assurances that were contractually set
out. These assurances were extra contractual and, acting on which, the
Respondent No.1 apparently has returned certain amounts that had
been originally imposed as liquidated damages. A reading of Clause
23.1(i)(n) ( which is reproduced in the preceding paragraph ) clearly
nuances that any representation or warranty, which may be found to
be false or the Contract were to be found in breach or non-compliance
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 19 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
thereof, is to be such as is found in the Contract itself.
45. Learned counsel for the Respondents was unable to point out
any such representation or warranty made by the Petitioner which is
expressly stated in the Agreement itself and of which the Petitioner is
stated to be in breach or non-compliance thereof. In view of the same,
this Court is of the prima facie view that the alleged invocation of the
BGs towards recovery of funds released on the basis of the assurances,
clearly relates to the assurances which were not enshrined in the
Agreement itself but were extra contractual and on the basis of which
certain amounts came to be released.
46. This Court now turns toward the encashment of the BGs,
allegedly on the grounds of certain outstanding undisputed as well as
disputed dues by the Petitioner. Keeping in mind the fact that, except
for the undisputed outstanding amount of ₹81 lakhs with respect to
Vendor No.1, there is no other amount that can be termed as
undisputed. Furthermore, since the concerned Vendor No.2 has
already sought independent reliefs as against the Petitioner before the
learned NCLT, this Court does not find it apposite to permit the
Respondents to encash bank guarantees towards satisfaction of dues as
against Vendor No.2.
47. The learned counsel for the Respondents would also contend
that the amounts as sought to be encashed by way of BGs relate to the
imposition of liquidated damages, which is provided for in Clause
10.3(iii) of the Agreements as between the parties, which is
reproduced herein under:
“ 10.3 Construction of the Project Highway
*
(iii) The Authority shall notify the Contractor of its decision to
impose Damages in pursuance with the provisions of this Clause
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 20 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
10.3. Provided that no deduction on account of Damages shall be
effected by the Authority without notifying the Contractor of its
decision to impose the Damages, and taking into consideration the
representation, if any, made by the Contractor within 20 (twenty)
days of such notice. The Parties expressly agree that the total
amount of Damages under Clause 10.3 (ii) shall not exceed 10%
(ten percent) of the Contract Price. If the damages exceed 10% (ten
percent) of the Contract Price, the Contractor shall be deemed to be
in default of this agreement having no cure and the Authority shall
be entitled to terminate this Agreement by issuing a Termination
Notice in accordance with the provisions of Clause 23.1 (ii). ”
48. However, a perusal of the said Clause would make it obvious
that any such damages that were to be recovered would be by way of
deduction from the payments that were to be made to the Petitioner.
The Respondents‟ contention that invocation by operation of Clause
10.3 permits the recovery of the amounts thereof by way of invocation
of the BGs, in view of this Court, is clearly unsustainable. As is
manifest from a reading of Clause 23.1 and which is admittedly the
only clause that, if contravened, would be relatable to the occasioning
of invocation or the encashment of the BGs and since the recovery of
damages is not specified therein, invocation of the BGs for the said
purpose is clearly unsustainable.
49. The contention that MBG cannot be invoked since Clause 7.3
only enumerates the Performance Bank Guarantees and not the MBG,
in the opinion of this Court, may not be entirely correct. The
Petitioner, by its Letter dated 29.04.2025, had expressly agreed to the
invocation of the MBG only in the event of its inability to clear the
outstanding dues of the vendors. Whether such outstanding dues, in
fact, subsist remains ambiguous and constitutes a matter requiring
adjudication.
50. The net result of the above discussion is that there is only an
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 21 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
amount of ₹81 lakhs which is in fact admitted to be outstanding by the
Petitioner to Vendor No.2, which is payable as per the terms and
conditions of the Agreements and the various comfort letters that had
been issued by NHIDCL/Respondent No. 1. There is no serious
dispute to this factual aspect by the parties in the present matter.
51. It is further pertinent to note here that the present case pertains
27
to Conditional Bank Guarantees insofar as the BGs herein are to
operate only upon the fulfilment of predefined contingencies, linked to
contractor performance or contractual compliance, and are invocable
only upon failure to satisfy such stipulated conditions, thereby serving
as a protective safeguard for the project owner against possible
contractual breach.
52. It is a well settled position of law that CBG do not warrant the
application of a stringent or severe standard while considering the
grant of stay against their invocation, particularly where such
guarantees form part of the subject matter and their invocation, prior
to adjudication, would render the ensuing arbitral proceedings
infructuous and occasion irreparable injustice to the party against
whom such guarantees are sought to be invoked.
53. The Hon‟ble Supreme Court in M/S Jindal Steel & Power Ltd
28
vs M/S Bansal Infra Projects Pvt. Ltd upheld the grant of stay on
invocation of guarantees by the Odisha High Court, holding in clear
terms that where refusal of injunction would result in the subject
matter before the arbitral tribunal itself becoming infructuous, judicial
intervention becomes imperative to preserve the same for effective
27
CBG
28
2025 INSC 640
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 22 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
adjudication. The relevant Paras of M/S Jindal Steel & Power Ltd
( supra )are extracted herein under:
“ 11. We are aware of the established legal principle that the Courts
should refrain from interfering with the invocation of a bank
guarantee except in cases of fraud of an egregious nature or in
cases where allowing encashment would result in irretrievable
injustice. This Court in Hindustan Construction Co. Ltd v. State of
Bihar and others5, emphasized that bank guarantees serve as the
backbone of (1999) 8 SCC 436 commercial transactions and must
be honoured in accordance with their terms. The following
paragraphs are pertinent in this regard:
“ 8. Now, a bank guarantee is the common mode of
securing payment of money in commercial dealings as the
beneficiary, under the guarantee, is entitled to realise the
whole of the amount under that guarantee in terms thereof
irrespective of any pending dispute between the person on
whose behalf the guarantee was given and the beneficiary.
In contracts awarded to private individuals by the
Government, which involve huge expenditure, as, for
example, construction contracts, bank guarantees are
usually required to be furnished in favour of the
Government to secure payments made to the contractor as
"advance" from time to time during the course of the
contract as also to secure performance of the work
entrusted under the contract. Such guarantees are
encashable in terms thereof on the lapse of the contractor
either in the performance of the work or in paying back to
the Government “advance", the guarantee is invoked and
the amount is recovered from the bank. It is for this reason
that the courts are reluctant in granting an injunction
against the invocation of bank guarantee, except in the
case of fraud, which should be an established fraud, or
where irretrievable injury was likely to be caused to the
guarantor. This was the principle laid down by this Court
in various decisions. In U.P. Coop. Federation Ltd v.
Singh Consultants & Engineers (P) Ltd.6, the law laid
down in Bolivinter Oil SA v. Chase Manhattan Bank 7 was
approved and it was held that an unconditional bank
guarantee could be invoked in terms thereof by the person
in whose favour the bank guarantee was given and the
courts would not grant any injunction restraining the
invocation except in the case of fraud or irretrievable
injury. In Svenska Handelsbanken v. Indian Charge
Chrome8, Larsen & Toubro Ltd v. Maharashtra
SEB9, Hindustan Steel Works Construction Ltd v. G.S.
Atwal & Co. (Engineers) (P) Ltd 10, National Thermal
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 23 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
Power Corporation Ltd v. Flowmore (P) Ltd11, State of
Maharashtra v. National Construction Co.12, Hindustan
Steel Works Construction Ltd v. Tarapore & Co.13 as also
in U.P. State Sugar Corporation v. Sumac International
Ltd 14, the same principle has been laid down and
reiterated.
9. What is important, therefore, is that the bank guarantee
should be in unequivocal terms, unconditional and recite
that the amount would be paid without demur or objection
and irrespective of any dispute that might have cropped up
or might have been pending between the beneficiary under
the bank guarantee or the person on whose behalf the
guarantee was furnished. The terms of the bank guarantee
are, therefore, extremely material. Since the bank
guarantee represents an independent contract between the
bank and the beneficiary, both the parties would be bound
by the terms thereof. The invocation, therefore, will have
to be in accordance with the terms of the bank guarantee;
or else, the invocation itself would be bad.”
12. However, it cannot be disputed that after hearing both sides and
with the consent of the parties, the High Court disposed of the writ
petition by the order impugned herein, inter alia stating that if the
appellants were permitted to invoke the bank guarantee, the prayer
made in the Section 9 arbitration petition would likely become
infructuous. Furthermore, the High Court clearly observed that the
Commercial Court shall proceed in accordance with law and
adjudicate upon the prayers made in the arbitration petition on its
own merits, considering the pleadings and documents placed on
record, without being influenced by any of the observations made
therein. Ultimately, it was directed that the interim order
restraining the appellants from encashing the bank guarantee shall
remain in force until the disposal of the arbitration petition pending
before the Commercial Court, subject to Respondent No. 1
extending the validity of the bank guarantee. Thus, we are of the
view that the order passed by the High Court is merely an interim
measure intended to protect the interests of both parties.
13. Admittedly, Respondent No. 1 initiated arbitration proceedings
to resolve the disputes with the appellants. In the Section 9
arbitration petition filed by them, the arguments on behalf of
Respondent No. 1 and Respondent No. 2 have already been
concluded, and the matter stands partly heard, pending further
arguments on behalf of the appellants. Furthermore, pursuant to the
order dated 06.11.2024 passed by the High Court, an Arbitral
Tribunal was constituted to adjudicate the disputes between the
parties and a hearing was held on 03.01.2025, during which, the
parties involved herein appeared and the Arbitral Tribunal directed
them to file statement of claim, statement of defence and counter
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 24 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
claim, if any, and reply to the same. Thus, in view of the ongoing
arbitration proceedings concerning the bank guarantee, it is
imperative to maintain the existing position regarding the bank
guarantee until the final outcome of the Section 9 arbitration
petition.
15. Since the Section 9 arbitration petition is now ripe for
arguments before the Commercial Court on behalf of the
appellants, the parties are directed to advance all their contentions
along with necessary documents, and the Commercial Court shall
pass appropriate orders within a period of eight weeks thereafter.
Until such time, the bank guarantee shall be kept alive and shall be
subject to the outcome of the Section 9 arbitration petition.”
(emphasis supplied)
54. In view of the foregoing analysis, and having regard to the facts
and circumstances accruing in the present case, this Court is of the
considered opinion that the balance of convenience tilts in favour of
the Petitioner. The encashment of the said BGs at this stage would
result in serious and irreparable prejudice to the Petitioner, which
cannot be adequately compensated in monetary terms at a later stage,
particularly if the Petitioner ultimately succeeds in the arbitral
proceedings.
55. The issue pertaining to the legality and validity of the
invocation of the BGs is inextricably intertwined with the underlying
contractual disputes and the specific factual matrix of the case. Such
questions necessarily require a detailed examination of the terms of
the Contract, the circumstances leading to the invocation, and the
conduct of the parties, an exercise that squarely falls within the
domain of the learned Arbitral Tribunal.
56. Accordingly, this Court is of the view that the matter warrants
adjudication by the appropriate forum, namely, the learned Arbitral
Tribunal, and ought not to be conclusively determined at this
interlocutory stage.
Signature Not Verified
O.M.P.(I) (COMM.) 18/2026 Page 25 of 26
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:27.02.2026
13:58:07
CONCLUSION:
57. Accordingly, having heard the parties at length with respect to
Prayer Clause „a‟ which is in respect of restraining the Respondents
from the encashment of the BGs namely , Bank Guarantee No.
0151824BG0000014 for ₹3,24,00,324/- dated 20.01.2024,
Mobilization Bank Guarantee No. 0151824BG0000057 for
₹3,50,46,351/- dated 04.03.2024 and Performance Bank Guarantee
No. 0151824BG0000016 for ₹1,89,00,019/- dated 20.01.2024, the
encashment thereof is stayed.
58. Further, in view of the foregoing discussion, Prayer Clause „b‟
pertaining to the interdiction of the Termination Notice cannot be
granted, the Contract being determinable in nature.
59. Needless to state, nothing contained in this Judgement shall be
construed as an expression of opinion by this Court on the merits of
the controversy as between the parties. The observations made herein
are confined solely to the determination of the present Petition and
shall not prejudice the rights of either party in the arbitral proceedings
or any other appropriate forum. All rights and contentions of the
parties are expressly kept open and reserved.
60. At this stage, the Registry is directed to take on record and
incorporate into the case file all the documents handed over by the
parties during the course of the hearing.
61. Accordingly, the present Petition, along with pending
application(s), is disposed of in the aforesaid terms.
62. No Order as to costs.
HARISH VAIDYANATHAN SHANKAR, J.