Transtonnelstroy Afcons Jv Chennai Metro Limited vs Oriental Insurance Company Limited
- Court
- Delhi High Court
$~2
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC010153932022
+ O.M.P. (COMM) 193/2022
TRANSTONNELSTROY AFCONS JV CHENNAI METRO
LIMITED .....Petitioner
Through: Mr. Anil K., Sr. Advocate with
Mr. Deepesh, Mr. Himanshu
Gulliya, Mr. Vishal Tyagi, Mr.
Harsh Gautam and Ms. Bindiya
Logawney, Advocates.
versus
ORIENTAL INSURANCE COMPANY LIMITED
.....Respondent
Through: Mr. Amandeep Singh and Mr.
Pradeep Desodya, Advocates.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGEMENT (ORAL)
% 12.08.2026
1. Learned Counsel for the Respondent has waived his right to file
reply.
2. With the consent of the parties this Court is finally hearing the
matter.
3. The present petition is being preferred under Section 34 of the
1
Arbitration and Conciliation Act, 1996 filed by the Petitioner assailing
2
Majority Arbitral Award dated 13.01.2022 passed by the Arbitral
1
“Act” hereinafter
2
“Majority Award” hereinafter
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 1 of 8
Tribunal comprising three Arbitrators. The Petitioner assails the
Majority Award to the limited extent of the findings recorded under
issue no. C by which the Petitioner’s claim for Rs.1 crore, interest and
cost, was rejected. The issue No. C which forms the subject
consideration in this matter is as follows:
"Whether the Respondent has correctly applied the excess clause
i.e., "tunnel risk/collapse (AOG/normal) is 5% of claim amount
subject to a minimum of Rs. 1 ,00,00,000/- while settling each of the
claim no. 112500/44/2016/0000032 under policy bearing no.
112200/44/2011/153 and in Claim no. 112500/44/2011/154/
(OPR)."
4. Briefly stating, the factual matrix of the present petition are that
in January, 2011, Chennai Metro Rail Corporation Limited awarded the
Petitioner a contract for “Design and Construction of Underground
Stations and Associated Panels” in Chennai “package UAA-01” for
approximately Rs.2597 crores.
5. In order to protect himself from the potential damages, the
Petitioner purchased Contractor All Risk Insurance Policy bearing
No.112200/44/2011/154 (Policy No.154) from the
Respondent/Company on 04.02.2011/25.02.2011 after payment of a
premium of Rs.7.8 crores.
6. The tenure of the said policy was 5 years and 6 months. As far as
policy deductible terms are concerned under Schedule ENDT-36 of
Policy No.154, the same are as follows:
(i) Normal claims – 5% of claim subject to a minimum of
Rs.20,00,000/-.
(ii) AOG/Major Perils/Maintenance – 5% of claim subject to a
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 2 of 8
minimum of Rs.50,00,000/-.
(iii) Tunnel Collapse (AOG and Normal)/Design Defect – 5% of claim
subject to a minimum of Rs.100,00,000/-.
7. Abruptly, in December, 2015, the severe flooding/heavy rainfall
in Chennai caused damage to the project sites of the Petitioner.
Consequently, concerned insurance surveyors were appointed by the
Respondent and an interim survey was issued by the surveyor by report
on 15.06.2016 recommending an interim ad hoc payment of Rs.3 crore,
which was released by the Respondent on 23.08.2016.
8. On 29.07.2016, upon payment of an additional premium of
Rs.4.58 crores by the Petitioner, Policy No.154 was extended by the
Respondent from 01.08.2016 to 30.04.2018 with identical deductible
terms as endorsement No.36.
9. The concerned surveyors submitted its final survey report on
31.05.2018 assessing the gross liability payable at Rs.7,38,19,499/- (net
Rs.4,38,19,499/- after deducting the interim Rs.3 crores). The surveyor
applied the Act of God Peril excess clause i.e. 5% of the claim amount
subject to a minimum of Rs.50,00,000/-.
10. On 30.01.2019, the Respondent sent a discharge voucher offering
only Rs.2,29,64,223/-. The Respondent made two unilateral deductions
of Rs.1 crore each applying an excess clause of “tunnel risk/collapse”
(minimum Rs.1 crore) instead of AOG perils
(minimum Rs.50,00,000/-) and adjusting Rs.1 crore towards alleged
excess payment made under a separate CAR Policy No.153 (UAA-05).
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 3 of 8
11. Rs.2,29,64,223/- was accepted by the Petitioner under protest and
invoked arbitration on 18.04.2019.
12. Before the Arbitral Tribunal the pleadings led to the framing of
the following issues:
(i) Issue A – entitlement of claim of Rs.2 crores
(ii) Issue B – correctness of Respondent adjusting Rs.1 crore from
Policy No.153 into Policy No.154
(iii) Issue C – whether Respondent correctly applied the excess clause
“tunnel risk/collapse (AOG/normal)” 5% subject to minimum of Rs.1
crore under Policy No.154”.
13. The Arbitral Tribunal concluded the proceedings and delivered
the award on 13.01.2022 and rendered anonymous findings on Issue B.
14. The Tribunal held that the Respondent could not adjust Rs.1
crore from Policy No.153 against Policy No.154, holding the two
contracts to be distinct.
15. As far as Issue C is concerned, by 2:1 majority, the Tribunal held
in favour of the Respondent, holding that the tunnel risk was omitted
due to a typographical error in Policy No.154. The majority relied upon
pre-contract cover note/discussions to interpret the deductible schedule
and upheld the application of Rs.1 crore, tunnel risk/collapse peril.
16. The Minority Arbitrator disagreed with the other arbitrators and
held that the insurer was wrong to apply the “Tunnel Risk/Collapse”
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 4 of 8
deductible to this claim. The minority view was that the Respondent
should not have deducted the ₹1 crore minimum amount under the
tunnel/risk clause while settling the claim under Policy No. 154.
17. Learned Senior Counsel for the Petitioner assails the majority
award under Section 34 of the Act on the ground that the majority
Tribunal committed a fundamental jurisdictional error by looking into
pre-contract negotiations/held cover notes to alter the plain text of
Policy No.154.
18. He asserts that once a formal insurance policy is issued, pre-
contract cover notice cease to operate and the terms and conditions
given in policy governs.
19. He has further submitted that the majority award completely
ignored pre-extension letter dated 29.07.2016 which reaffirmed the
schedule of deductible without reverse tunnel risk even after 5 years.
20. Learned Counsel for the Petitioner further contends that under
Section 26 of the Specific Relief Act, 1963, the rectification of
instrument cannot be granted unless it is specifically claimed by
pleadings/counter-claims. It is submitted that Respondent has not filed
any counter-claim nor issued any rectification endorsement.
21. It is further submitted that the majority Tribunal presumed the
decision of the respondent’s head office without any internal file or
competent authority being produced on record.
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 5 of 8
22. Learned Senior counsel further submits that the majority award
in paragraph 78, has expressly declined to adjudicate whether loss
occurred in the station or tunnel area despite the Respondent’s own
witness (RW-3/server) admitting in cross-examination that loss
occurred in the tunnel area.
23. Per contra , learned Counsel for the Respondent supports the
majority award by submitting that the Arbitral Tribunals are the
ultimate master of evidence on contract interpretation and mere error of
law does not warrant interference under Section 34 of the Act.
24. He also submits that the a plausible view given by the Arbitral
Tribunal within the limited scope of Section 34, and therefore no
interference is warranted.
25. Having considered the rival submissions and arbitral record, this
Court finds that the majority award suffers from patent illegality and
jurisdictional error rendering the majority award unsustainable under
Section 34(2)(a) and 34(2)(b) of the Act for the following reasons:
(i) It is a fundamental principal of insurance jurisprudence that upon
issuance of a formal insurance policy, all prior noting, discussions,
cover notes and pre-contract negotiations merge into the final contract.
The Hon’ble Supreme Court in K. Nagendra v. New India Insurance
3
Co. Ltd. & Ors. held that once the insurance policy is issued, the rights
and obligations inter se between the insurer and the insured are
governed by the terms and conditions of the policy, which delineate the
3
2025 INSC 1270
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 6 of 8
four corners within which the insurance contract operates.
(ii) In the present case, Policy No.154 contained the deductible clause
“tunnel/collapse (AOG and normal)/design defect”. It is categorically
admitted by the Respondent in a statement of defence which was filed
after 8 years, that omission of “tunnel risk” was a typographical error.
The majority members of the Tribunal acceded their jurisdiction by
travelling beyond the executed policy to insert words based on a pre-
contract cover notes. An Arbitral Tribunal is a creature of the contract
and cannot rewrite explicit contractual provisions.
(iii) The record demonstrate that after 5 years and 6 months, the
Respondent extended Policy No.154 vide extension letter dated
29.07.2016 upon receiving an additional premium of Rs.4.85 crores.
The extension schedule specifically reiterated the deductibles without
reverse tunnel risk. The majority award completely overlooked this
critical document constituting a fatal perversity and failure to consider
vital evidence.
(iv) Under clause 26 of the Specific Relief Act, 1963, a Court or
Tribunal cannot grant the relief of instrument rectification unless a party
specifically prays or claims it. The Respondent never filed a counter-
claim for rectification nor issued a mandatory policy endorsement
during the entire 8 year tenure of the policy. The majority Tribunal
unilateral correction of the policy terms is legally unsupportable.
(v) The majority Tribunal failed to adjudicate genesis of the dispute to
apply a tunnel specific deductible clause, as it was imperative to
Signature Not Verified
Signed By:PRAGYA
ARORA
Signing Date:18.08.2026
20:34:04
O.M.P. (COMM) 193/2022 Page 7 of 8
determine whether damage occurred in the station area or the tunnel
area. In this regard, Para 78 of the majority award of the Tribunal is
stated below:
“We feel that unnecessary controversy is raised on behalf of both
parties in the arguments regarding meaning of tunnel and
contradiction in the reports of Select Surveyor and Plea of defence
in Statement of Defence. . . still we do not want to go into this
controversy raised from both sides for two very strong reasons ...”.
(vi) Refusing to decide the fundamental issue and going to the root of
the dispute constitute a failure of the adjudicatory process. Moreover, it
is an admitted fact by witness produced by Respondent (RW-
3/surveyor) who confirmed during cross-examination that zero-loss
occurred in the tunnel area. Furthermore, it was presumed by majority
Tribunal that a final decision of the Respondent’s head office without
any documentary evidence on record misinterpreting.
26. Thus, in light of the above findings, in the majority award dated
13.01.2022 in respect of Issue C are perverse patent illegal and opposed
to the fundamental policy of the Indian law.
27. Accordingly, the present petition is allowed. The majority award
to the extent of the findings of issue C is set aside.
OM PRAKASH SHUKLA, J
AUGUST 12, 2026 / pa