National Highways Authority Of India vs Patel Knr Heavy Infrastructure Pvt Ltd
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 24.03.2026
Judgment pronounced on: 21.04.2026
+ O.M.P. (COMM) 195/2023, I.A. 10225/2023 (Stay) & I.A.
10226/2023
NATIONAL HIGHWAYS AUTHORITY OF INDIA
.....Petitioner
Through: Mr. Rajkumar Dubey, Ms.
Bhavana Bhardwaj and Mr.
Arpit Singhal, Advocates
versus
PATEL KNR HEAVY INFRASTRUCTURE PVT LTD
.....Respondent
Through: Mr. George Thomas, Dr.
Swaroop George, Mr.
Abhinandan Jain, Mr. Sunny
Thomas, Mr. Abhigyan
Dwivedi, Mr. Shivam Prajapati
and Mr. Kartikey, Advocates
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
J U D G M E N T
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition under Section 34 of the Arbitration and
1
Conciliation Act, 1996 , has been preferred assailing the Arbitral
2
Award dated 16.01.2023 , rendered by the majority of the members
1
A&C Act
2
Impugned Award
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 1 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
of the learned Arbitral Tribunal, as well as the dissenting Award
3
dated 23.01.2023 passed by the learned third Arbitrator.
2. By way of the Impugned Award, the learned Arbitral Tribunal
has, in sum and substance, allowed the claim of the Respondent
towards the cost incurred on account of the additional thickness of 10
4
mm Bituminous Concrete applied as a renewal coat on the Project
Highway, which constitutes the core subject matter of the present
challenge.
3. Further, the limited challenge raised herein to the dissenting
Award pertains to the rejection of the Counter-Claim preferred by the
Petitioner and, to that extent, is in consonance with and supportive of
the Majority Award.
BRIEF FACTS:
4. The facts germane to the institution of the present Petition are
as follows:
a. The Petitioner herein invited proposals for Design,
Construction, Development, Finance, Operation and
Maintenance of “ 2 lane portion from Km 230/000 to Km
5
278/000, covering 53.017 kilometres” NH-7 on a Build-
Operate-Transfer Annuity basis vide notice dated 07.07.2006,
subject to the terms and conditions contained in the tender
.
notice
3
Dissenting Award
4
BC
5
Project Highway
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 2 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
b. The Respondent emerged as the successful bidder. Consequent
thereof, a letter of acceptance was issued by the Petitioner to the
Respondent dated 30.03.2007 and thereafter, the parties entered
6
into a Concession Agreement dated 05.09.2007 .
c. The work scope, as laid down in the Agreement, was as
follows:
i. To develop, design, engineer, finance, construct, operate
and maintain the project highway during the concession
period.
ii. Upon completion of the Project highways and during the
operations period, to manage, operate and maintain the
project highway and regulate the use thereof by third
parties,
iii. to allow NHAI to levy, demand, collect and appropriate
the fees from vehicles and persons liable to payment of
fees for using the project Highways or any part thereof as
per Article VII,
iv. perform and fulfil all of the Concessionaire's obligations
under this agreement,
v. bear and pay all expenses, cost and charges incurred in the
fulfilment of all the Concessionaire's obligations under this
Agreement, and
vi. not assign or create any lien or encumbrance on the
concession hereby granted on the whole or any part of the
Project Highways, nor transfer, lease, or part possession
6
Agreement
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 3 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
therewith, save and except as expressly permitted by the
agreement or the substitution Agreement.
d. The date for commencement of the Project was 02.03.2008 with
a total concession period of 20 years, which included a
construction period of 2 years and Operation and Management
of 18 years.
e. For the sake of clarity, the timeline and milestones that were
decided as per the Agreement are tabulated herein below:
| PARTICULARS | DATE/PERIOD |
|---|---|
| Date of signing the Concession Agreement | 05.09.2007 |
| Period of Concession Agreement | 20 years |
| Construction Period | 24 months |
| Development period | 05.09.2007 - 02.03.2008<br>(180 days) |
| Scheduled Project Completion Date | 01.03.2010 |
| Independent Consultant appointed | 02.11.2007 |
| Provisional Commercial Operation Date<br>certificate issued | 11.06.2010 |
| Commercial Operation Date certificate<br>issued | 27.12.2016 |
| First renewal coat completed on | 28.02.2017 |
| Second renewal coat completed on | 04.05.2021 |
Operations Date was issued on 11.06.2010.
g. In terms of the Agreement, the Respondent was required to
maintain the Project Highway at all times in conformity with
the Agreement and as per its standards laid down in the
schedules thereof and the good engineering practice.
h. The Agreement also provides for a renewal coat after every five
years, irrespective of the condition of the Highway. This
particular requirement forms the genesis of the present dispute.
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 4 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
i. It is the case of the Petitioner that the Team Leader has issued a
letter dated 26.02.2019, since the Respondent was supposed to
undertake and complete the second periodic maintenance by
10.06.2020, considering the first period maintenance was
completed on 10.06.2015.
j. At the time of the second renewal coat, the Respondent
proposed laying a 30mm thick layer of BC as per the
specification of the Ministry of Road Transport and
7
Highways , which requires only a thin layer of BC for a smooth
riding surface when no strengthening measures are warranted.
However, the said proposal was not agreed upon by the
Petitioner, and the thickness of BC was insisted on to be 40
mm.
k. The Respondent, after various correspondences, vide its letter
dated 14.04.2020, informed the Petitioner that, as per the
confirmation given by the Petitioner, they shall proceed with
laying the 40 mm thick layer of the BC.
l. However, the Respondent further stated in the said letter that
they shall be lodging a claim for the extra 10mm layer that they
have been constrained to lay. They further stated that since the
confirmation regarding the second renewal coat has only been
received during the nationwide lockdown, if any penalty is
levied due to delay in works, the same shall also be resolved by
way of dispute resolution as stipulated in the Agreement.
7
MoRTH
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 5 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
m. Thereafter, the Respondent vide its letter dated 27.05.2020
sought to invoke mediation to resolve the said disputes.
n. Various correspondences were exchanged between the
Respondent and Petitioner and an extension of time was sought
by the Respondent. The second periodic maintenance process
was completed on 04.05.2021.
o. The Petitioner, vide letter dated 19.02.2022, submitted its claim
for final damages on account of delay in the second periodic
overlay, calculated as per the terms of Articles 18.12 and 18.13
of the Agreement, which came up to an amount of Rs.
1,92,58,192/-, payable by the Respondent for the said delay.
p. Thereafter, arbitration proceedings were initiated at the instance
of the Respondent and the learned Arbitral Tribunal was
constituted.
q. The learned Arbitral Tribunal, upon completion of pleadings,
framed the following issues for consideration:
“…..
i. Whether the thickness of Bituminous Concrete liable to
be laid by the Claimant as the second renewal coat was
to be 40mm BC? OPCR
ii. Whether the Claimant is entitled for an amount of Rs.
13,44,09772/- towards cost of extra thickness of 10mm
BC laid as renewal coat in project highway? OPC
iii. Whether the Claimant is entitled for a declaratory award
that it had completed renewal coat within the eligible
time and that the Claimant is not liable to pay any
damages to the respondent under Clause 18.12 or under
18.13 of the Concession Agreement? OPC
iv. Whether there was any delay on the part of the Claimant
in the completion of the second periodic maintenance as
alleged by the Respondent/Counter Claimant? OPR
v. Whether the Claimant is entitled to interest and
arbitration cost? OPC
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 6 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
vi. Whether the Respondent/Respondents entitled to any
final damages for an amount of Rs. 1,92,58,192/- from
the Claimant? OPR
vii. Whether the Respondent/Respondents entitled to any
interest and cost? OPR”
r. The learned Arbitral Tribunal, consisting of the majority of its
members, rendered the Impugned Award on 16.01.2023,
whereas the dissenting Award was passed by the learned third
Arbitrator on 23.01.2023.
s. Brevitatis causa, the claims awarded by the learned Arbitral
Tribunal are summarised and tabulated below:
| Sr.<br>no. | Claims and Counterclaims | Award | Awarded<br>Amount |
|---|---|---|---|
| Claims preferred by the Respondent (claimant therein) | |||
| 1. | Claim A - Claim for extra<br>thickness of 10 mm BC laid as<br>renewal coat in the Project<br>Highway | Partly<br>allowed | Rs.<br>12,35,18,570/- |
| 2. | Claim B - Declaratory award by<br>the Hon‟ble Arbitral Tribunal<br>that the Claimant has completed<br>renewal coat within the eligible<br>time and that the Claimant is not<br>liable to pay any damages to the<br>Respondent under clause 18.12.<br>and 18.12 or any other<br>conditions of the Concession<br>Agreement | Allowed | Nil |
| 3. | Claim C - Claim for Past,<br>Pendente lite and future interest | Allowed | |
| 4. | Claim D - Claim for Arbitration<br>Cost | Partly<br>Allowed | Rs.<br>40,00,000/- |
| Counter-Claims preferred by the Petitioner (Respondent therein) | |||
| 5. | Counter Claim A - Claim for<br>final damages towards delay in<br>completion of second periodical | Partly<br>Allowed | Rs.<br>25,30,000/- |
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 7 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
| maintenance | |||
|---|---|---|---|
| 6. | Counter Claim B - Claim for<br>Past, Pendente lite and future<br>interest | Allowed | |
| 7. | Counter Claim C - Claim for<br>Arbitration Cost | Rejected | NIL |
5. Aggrieved by the Impugned Award and the dissenting Award
insofar as it affirms the findings of the Majority Award pertaining to
the partial rejection of the counterclaims of the Petitioner, the
Petitioner has preferred the present Petition before this Court.
SUBMISSIONS ON BEHALF OF THE PARTIES:
6. Learned counsel for the Petitioner has assailed the Impugned
Award, stating it to be vitiated by patent illegality.
7. He would rely upon Clause 1 of Schedule L of the Agreement
to state that the said clause provides that the Project Highway shall be
constructed, operated, and maintained during the concession period in
accordance with the Scope defined in Schedules-B&C, and therefore,
any maintenance activity had to be carried out by Respondent in
consonance and in conformity with the standards provided in
Schedules-B & C.
8. He would further rely on Clause 7.3 of Schedule B of the
Agreement to buttress his argument that the same provides a 40 mm
BC overlay for strengthening of the existing pavement.
9. Learned counsel for the Petitioner would also seek to rely upon
Clause 1.6 of Schedule D to submit that the Project Highway was
required to conform with the guidelines of the MoRTH and IRC
Standard and Code, as a reading of Para 81 of IRC would make it
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 8 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
clear that the same provides that from structural considerations, the
recommended minimum bituminous overlay thickness is 50 mm
bituminous macadam with an additional surfacing course of 50 mm
DBM or 40 mm BC.
10. He would submit that the learned Arbitral Tribunal has
erroneously granted the claim in favour of the Respondent and has
done selective reading and interpretation while arriving at the
impugned finding that only Schedule-L will be applicable insofar as
the Operation and Management period is concerned and that the same
has been arrived at by doing an isolated and selective reading of
Schedule L. Therefore, he would submit that the Majority Award is
perverse and illegal and contrary to the terms of the Agreement and
liable to be set aside.
11. To further buttress his argument, learned counsel for the
Petitioner would rely upon the selective reasoning given by the
learned Arbitrator in the dissenting Award.
12. Learned counsel would submit that the learned Arbitrator in his
dissenting opinion has rightly held that the argument advanced by the
Respondent before the learned Arbitral Tribunal proceeded on an
erroneous premise and was vitiated by a fundamental misconception
inasmuch as it equated the concept of a “Renewal Coat”, undertaken
once every five years, with routine or periodic maintenance activities.
Such an interpretation disregards both the rationale and the intended
purpose underlying the provision for a Renewal Coat. The Renewal
Coat is not a mere maintenance exercise; rather, it is a specialized
intervention aimed at restoring the pavement, as far as practicable, to
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 9 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
its original condition. It serves to remedy the cumulative wear and tear
sustained over a five-year period, preserve the essential structural and
functional characteristics of the pavement, and prepare it to withstand
the operational demands of the ensuing cycle. Accordingly, any
attempt to conflate it with ordinary maintenance is misconceived and
deserves outright rejection.
13. The second grievance that the learned counsel for the Petitioner
has raised is with respect to the partial rejection of the counterclaim of
the Petitioner pertaining to the delay in execution of the renewal coat.
14. He would submit that the learned Arbitral Tribunal has erred in
rendering this finding, as in terms of the Contractual time schedule,
the second periodic maintenance ought to have been completed by the
Respondent by 21.01.2021, which was instead completed only on
27.01.2022, i.e., after a delay of 341 days.
15. He would submit that the learned Arbitral Tribunal has wrongly
calculated that the Respondent completed the BC overlay on
04.05.2021, i.e., 14 days behind schedule, but within the 30-day cure
period. He would submit that the alleged finding is factually incorrect,
as the cure period had ended on 20.02.2021 and the BC overlay was
completed on 04.05.2021, which is an admitted position. Hence, there
was a delay of 73 days in the BC overlay by the Respondent.
Therefore, he would submit that the impugned finding in the Award
that the Respondent is not liable to pay damages to the Petitioner
towards delay in completion of laying of BC coat is factually wrong,
incorrect and not sustainable.
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 10 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
16. He would further submit that the finding wherein the learned
Arbitral Tribunal has altered the calculation and quantum of damages
that were originally claimed by the Petitioner is beyond the
contractual provision and is therefore liable to be set aside.
17. It would be submitted by learned counsel for the Petitioner that
the impugned finding in the Award, whereby, while referring to
Clause 18.13 of the Agreement, it is held that damages at the rate of
0.1% of the estimated cost of repair per day of delay constitute a
penalty and are thus unenforceable, whereas damages of Rs. 10,000/-
per day are treated as liquidated damages being a genuine pre-estimate
of loss, is legally untenable and stands vitiated by patent illegality on
the face of the Award.
18. It would also be submitted that Clause 18.13 of the Agreement
provides that the amount of damages shall be calculated for each day
of default at the higher of the following, namely , (a) Rs. 10,000/- and
(b) 0.1% of the cost of such repair as estimated by the Independent
Consultant. Hence, the mandate of Clause 18.13 of the Agreement is
clear, i.e., the Respondent shall be liable to pay to the Petitioner the
higher of the two above-referred amounts. Accordingly, the findings
in the Impugned Award, being contrary to the aforesaid provisions,
are ex facie beyond the terms of the Agreement and are, therefore,
liable to be set aside in toto .
19. Per Contra, learned counsel for the Respondent would, at the
very outset, draw the attention of this Court to a judgment of the co-
ordinate Bench of this Court in NHAI vs. Patel KNR Infrastructure
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 11 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
8
Ltd. and would submit that the present dispute stands squarely
covered by the said judgement.
20. He would further submit that the learned Arbitral Tribunal has
rightly rendered the finding that the only applicable schedule during
the Operation & Maintenance period (period in which renewal coat
was laid), as provided in the Contract Agreement, is Schedule- L.
21. He would submit that the reliance of the learned counsel for the
Petitioner on Clause 7.3 of Schedule B is misplaced, as the same is to
be considered when a structural deficiency is found.
22. Further, he would submit that the learned Arbitral Tribunal has
not erred in interpreting the terms of the Agreement, as a perusal of
Clauses 2.6 and 4.3 and of the Schedule L would make it clear that the
strengthening course is required only when certain technical
parameters call for the strengthening and structural deficiencies are
found. The learned Tribunal, upon an appreciation of the
contemporaneous road test results, has returned a finding of fact that
the prescribed parameters were not satisfied, and consequently, no
requirement for strengthening arose, particularly in view of the
relevant Clauses.
23. Learned counsel for the Respondent would also support the
finding of the learned Arbitral Tribunal by stating that the Agreement
does not specify the thickness of the renewal coat and MoRTH
specifications also provide for 30mm thickness being a sufficient layer
when applying a renewal coat.
8
OMP (COMM) 554/2020
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 12 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
24. He would submit that the learned Arbitral Tribunal has rightly
held that a penalty cannot be levied in terms of the law, and only a
genuine pre-estimate of the damages caused can be recovered as
liquidated damages. Further, the learned Tribunal rightly held that
when the agreement mentions two amounts and saddles the party in
breach with a liability to pay the higher of the two amounts and that
higher amount has no reference to the actual loss/damage, it cannot be
said to be a genuine pre-estimate of the loss/damage that may be
suffered in the future. If the pre-estimate is to be genuine, there can
only be one sum stipulated as payable. Thereby, the learned Arbitral
Tribunal has awarded damages on the basis of Rs. 10,000 per day.
25. It would be further argued by the learned counsel for the
Respondent that for 0.1% of the cost to be applicable, there would
need to be repair work. No repair work is involved in the renewal of
the wearing course of road/pavement once every 5 years, as stipulated
in clause 2.6.1(i) and 4.3.1 (ii) of Schedule L of the Agreement. This
is for the simple reason that the renewal of the wearing surface is not
“repairs” stipulated in Article 18.13(b) of the Concession Agreement.
The words „maintain‟ and „repair‟ have different meanings, and the
same is revealed from the wording in Article 18.12. The word
„maintenance‟ is intentionally removed from 18.13(b). Therefore,
Article 18.13 damages are confined to Rs 10,000/- per day in the
subject case, as there was no repair involved in doing the renewal
coat.
26. In view thereof, the learned counsel for the Respondent would
urge that the Impugned Award does not merit any interference and if
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 13 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
the finding of the learned Arbitral Tribunal is one of two possible
views, then this Court shall only intervene when the view taken is
perversely and patently illegal, which is not the case in the present
dispute.
ANALYSIS:
27. This Court has carefully considered the submissions advanced
on behalf of both sides and, with their able assistance, has perused the
Impugned Award as well as the dissenting Award and other materials
placed before this Court.
28. At the outset, it is apposite to note that this Court remains
conscious of the limited scope of its jurisdiction while examining an
objection petition under Section 34 of the A&C Act. There is a
consistent and evolving line of precedents whereby the Hon‟ble
Supreme Court has authoritatively delineated and settled the contours
of judicial intervention in such proceedings.
29. In this regard, a three-Judge Bench of the Hon‟ble Supreme
Court, after an exhaustive consideration of a catena of earlier
judgments, in OPG Power Generation (P) Ltd. v. Enexio Power
9
Cooling Solutions (India) (P) Ltd. , while dealing with the grounds of
conflict with the public policy of India and patent illegality, grounds
which have also been urged in the present case, made certain pertinent
observations, which are reproduced hereunder:
“Relevant legal principles governing a challenge to an arbitral
award
30. Before we delve into the issue/sub-issues culled out above, it
would be useful to have a look at the relevant legal principles
9
(2025) 2 SCC 417
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 14 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
| governing a challenge to an arbitral award. Recourse to a court | |
|---|---|
| against an arbitral award may be made through an application for | |
| setting aside such award in accordance with sub-sections (2), (2-A) | |
| and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section | |
| 34 has two clauses, (a) and (b). Clause (a) has five sub-clauses | |
| which are not relevant to the issues raised before us. Insofar as | |
| clause (b) is concerned, it has two sub-clauses, namely, (i) and (ii). | |
| Sub-clause (i) of clause (b) is not relevant to the controversy in | |
| hand. Sub-clause (ii) of clause (b) provides that if the Court finds | |
| that the arbitral award is in conflict with the public policy of India, | |
| it may set aside the award. | |
| Public policy | |
| 31. “Public policy” is a concept not statutorily defined, though it | |
| has been used in statutes, rules, notification, etc. since long, and is | |
| also a part of common law. Section 23 of the Contract Act, 1872 | |
| uses the expression by stating that the consideration or object of an | |
| agreement is lawful, unless, inter alia, opposed to public policy. | |
| That is, a contract which is opposed to public policy is void. | |
| ***** | |
| 37. What is clear from above is that for an award to be against | |
| public policy of India a mere infraction of the municipal laws of | |
| India is not enough. There must be, inter alia, infraction of | |
| fundamental policy of Indian law including a law meant to serve | |
| public interest or public good. | |
| ***** | |
| The 2015 Amendment in Sections 34 and 48 | |
| 42. The aforementioned judicial pronouncements were all prior to | |
| the 2015 Amendment. Notably, prior to the 2015 Amendment the | |
| expression “in contravention with the fundamental policy of Indian | |
| law” was not used by the legislature in either Section 34(2)(b)(ii) | |
| or Section 48(2)(b). The pre-amended Section 34(2)(b)(ii) and its | |
| Explanation read: | |
| ***** | |
| 44. By the 2015 Amendment, in place of the old Explanation to | |
| Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove | |
| any doubt as to when an arbitral award is in conflict with the public | |
| policy of India. | |
| 45. At this stage, it would be pertinent to note that we are dealing | |
| with a case where the application under Section 34 of the 1996 Act | |
| was filed after the 2015 Amendment, therefore the newly | |
| substituted/added Explanations would apply [Ssangyong Engg. & | |
| Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131]. | |
| 46. The 2015 Amendment adds two Explanations to each of the | |
| two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b), in | |
| place of the earlier Explanation. The significance of the newly | |
| inserted Explanation 1 in both the sections is two-fold. First, it |
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 15 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
does away with the use of words : ( a ) “ without prejudice to the
generality of sub-clause (ii) ” in the opening part of the pre-
amended Explanation to Section 34(2)(b)(ii); and (b) “ without
prejudice to the generality of clause (b) of this section ” in the
opening part of the pre-amended Explanation to Section 48(2)( b );
secondly, it limits the expanse of public policy of India to the three
specified categories by using the words “ only if ”.
Whereas, Explanation 2 lays down the standard for adjudging
whether there is a contravention with the fundamental policy of
Indian law by providing that a review on merits of the dispute shall
not be done. This limits the scope of the enquiry on an application
under either Section 34(2)( b )( ii ) or Section 48(2)( b ) of the 1996
Act.
47. The 2015 Amendment by inserting sub-section (2-A) in Section
34, carves out an additional ground for annulment of an arbitral
award arising out of arbitrations other than international
commercial arbitrations. Sub-section (2-A) provides that the Court
may also set aside an award if that is vitiated by patent illegality
appearing on the face of the award. This power of the Court is,
however, circumscribed by the proviso, which states that an award
shall not be set aside merely on the ground of an erroneous
application of the law or by reappreciation of evidence.
48. Explanation 1 to Section 34(2)( b )( ii ), specifies that an arbitral
award is in conflict with the public policy of India, only if :
( i ) the making of the award was induced or affected by fraud or
corruption or was in violation of Section 75 or Section 81; or
( ii ) it is in contravention with the fundamental policy of Indian law;
or
( iii ) it is in conflict with the most basic notions of morality or
justice.
49. In the instant case, there is no allegation that the making of the
award was induced or affected by fraud or corruption, or was in
violation of Section 75 or Section 81. Therefore, we shall confine
our exercise in assessing as to whether the arbitral award is in
contravention with the fundamental policy of Indian law, and/or
whether it conflicts with the most basic notions of morality or
justice. Additionally, in the light of the provisions of sub-section
(2-A) of Section 34, we shall examine whether there is any patent
illegality on the face of the award.
50. Before undertaking the aforesaid exercise, it would be apposite
to consider as to how the expressions:
( a ) “in contravention with the fundamental policy of Indian law”;
( b ) “in conflict with the most basic notions of morality or justice”;
and
( c ) “patent illegality” have been construed.
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 16 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
| In contravention with the fundamental policy of Indian law | |
|---|---|
| 51. As discussed above, till the 2015 Amendment the expression | |
| “in contravention with the fundamental policy of Indian law” was | |
| not found in the 1996 Act. Yet, in Renusagar Power Co. | |
| Ltd. v. General Electric Co., 1994 Supp (1) SCC 644, in the | |
| context of enforcement of a foreign award, while construing the | |
| phrase “contrary to the public policy”, this Court held that for a | |
| foreign award to be contrary to public policy mere contravention of | |
| law would not be enough rather it should be contrary to: | |
| (a) the fundamental policy of Indian law; and/or | |
| (b) the interest of India; and/or | |
| (c) justice or morality. | |
| ***** | |
| 55. The legal position which emerges from the aforesaid discussion | |
| is that after “the 2015 Amendments” in Section 34(2)(b)(ii) and | |
| Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the | |
| public policy of India” must be accorded a restricted meaning in | |
| terms of Explanation 1. The expression “in contravention with the | |
| fundamental policy of Indian law” by use of the word | |
| “fundamental” before the phrase “policy of Indian law” makes the | |
| expression narrower in its application than the phrase “in | |
| contravention with the policy of Indian law”, which means mere | |
| contravention of law is not enough to make an award vulnerable. | |
| To bring the contravention within the fold of fundamental policy of | |
| Indian law, the award must contravene all or any of such | |
| fundamental principles that provide a basis for administration of | |
| justice and enforcement of law in this country. | |
| 56. Without intending to exhaustively enumerate instances of such | |
| contravention, by way of illustration, it could be said that: | |
| (a) violation of the principles of natural justice; | |
| (b) disregarding orders of superior courts in India or the binding | |
| effect of the judgment of a superior court; and | |
| (c) violating law of India linked to public good or public interest, | |
| are considered contravention of the fundamental policy of Indian | |
| law. | |
| However, while assessing whether there has been a contravention | |
| of the fundamental policy of Indian law, the extent of judicial | |
| scrutiny must not exceed the limit as set out in Explanation 2 to | |
| Section 34(2)(b)(ii). | |
| ***** | |
| Patent illegality | |
| 65. Sub-section (2-A) of Section 34 of the 1996 Act, which was | |
| inserted by the 2015 Amendment, provides that an arbitral award | |
| not arising out of international commercial arbitrations, may also | |
| be set aside by the Court, if the Court finds that the award is visited | |
| by patent illegality appearing on the face of the award. The proviso |
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 17 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
to sub-section (2-A) states that an award shall not be set aside
merely on the ground of an erroneous application of the law or by
reappreciation of evidence.
66. In ONGC Ltd. v. Saw Pipes Ltd. , (2003) 5 SCC 705 , while
dealing with the phrase “public policy of India” as used in Section
34, this Court took the view that the concept of public policy
connotes some matter which concerns public good and public
interest. If the award, on the face of it, patently violates statutory
provisions, it cannot be said to be in public interest. Thus, an award
could also be set aside if it is patently illegal. It was, however,
clarified that illegality must go to the root of the matter and if the
illegality is of trivial nature, it cannot be held that award is against
public policy.
67. In Associate Builders v. DDA , (2015) 3 SCC 49 , this Court
held that an award would be patently illegal, if it is contrary to:
( a ) substantive provisions of law of India;
( b ) provisions of the 1996 Act; and
( c ) terms of the contract [See also three-Judge Bench decision of
this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd. , (2022)
2 SCC 275 ].
The Court clarified that if an award is contrary to the substantive
provisions of law of India, in effect, it is in contravention of
Section 28(1)( a ) of the 1996 Act. Similarly, violating terms of the
contract, in effect, is in contravention of Section 28(3) of the 1996
Act.
68. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 this Court specifically dealt with the 2015
Amendment which inserted sub-section (2-A) in Section 34 of the
1996 Act. It was held that “patent illegality appearing on the face
of the award” refers to such illegality as goes to the root of matter,
but which does not amount to mere erroneous application of law. It
was also clarified that what is not subsumed within “the
fundamental policy of Indian law”, namely, the contravention of a
statute not linked to “public policy” or “public interest”, cannot be
brought in by the backdoor when it comes to setting aside an award
on the ground of patent illegality [ See Ssangyong Engg. &
Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ]. Further, it
was observed, reappreciation of evidence is not permissible under
this category of challenge to an arbitral award [See Ssangyong
Engg. & Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ].
Perversity as a ground of challenge
69. Perversity as a ground for setting aside an arbitral award was
recognised in ONGC Ltd. v. Western Geco International Ltd. ,
(2014) 9 SCC 263 . Therein it was observed that an arbitral
decision must not be perverse or so irrational that no reasonable
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 18 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
| person would have arrived at the same. It was observed that if an | |
|---|---|
| award is perverse, it would be against the public policy of India. | |
| 70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests | |
| were laid down to determine whether a decision of an Arbitral | |
| Tribunal could be considered perverse. In this context, it was | |
| observed that where: | |
| (i) a finding is based on no evidence; or | |
| (ii) an Arbitral Tribunal takes into account something irrelevant to | |
| the decision which it arrives at; or | |
| (iii) ignores vital evidence in arriving at its decision, such decision | |
| would necessarily be perverse. | |
| However, by way of a note of caution, it was observed that when a | |
| court applies these tests it does not act as a court of appeal and, | |
| consequently, errors of fact cannot be corrected. Though, a possible | |
| view by the arbitrator on facts has necessarily to pass muster as the | |
| arbitrator is the ultimate master of the quantity and quality of | |
| evidence to be relied upon. It was also observed that an award | |
| based on little evidence or on evidence which does not measure up | |
| in quality to a trained legal mind would not be held to be invalid on | |
| that score. | |
| 71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019) | |
| 15 SCC 131, which dealt with the legal position post the 2015 | |
| Amendment in Section 34 of the 1996 Act, it was observed that a | |
| decision which is perverse, while no longer being a ground for | |
| challenge under “public policy of India”, would certainly amount | |
| to a patent illegality appearing on the face of the award. It was | |
| pointed out that an award based on no evidence, or which ignores | |
| vital evidence, would be perverse and thus patently illegal. It was | |
| also observed that a finding based on documents taken behind the | |
| back of the parties by the arbitrator would also qualify as a decision | |
| based on no evidence inasmuch as such decision is not based on | |
| evidence led by the parties, and therefore, would also have to be | |
| characterised as perverse [ See Ssangyong Engg. & Construction | |
| Co. Ltd. v. NHAI, (2019) 15 SCC 131]. | |
| 72. The tests laid down in Associate Builders v. DDA, (2015) 3 | |
| SCC 49 to determine perversity were followed in Ssangyong | |
| Engg. & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131 and | |
| later approved by a three-Judge Bench of this Court in Patel Engg. | |
| Ltd. v. North Eastern Electric Power Corpn. Ltd., (2020) 7 SCC | |
| 167. | |
| 73. In a recent three-Judge Bench decision of this Court in DMRC | |
| Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357, | |
| the ground of patent illegality/perversity was delineated in the | |
| following terms: (SCC p. 376, para 39) | |
| “39. In essence, the ground of patent illegality is available for | |
| setting aside a domestic award, if the decision of the arbitrator |
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 19 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
| is found to be perverse, or so irrational that no reasonable | ||
|---|---|---|
| person would have arrived at it; or the construction of the | ||
| contract is such that no fair or reasonable person would take; | ||
| or, that the view of the arbitrator is not even a possible view. A | ||
| finding based on no evidence at all or an award which ignores | ||
| vital evidence in arriving at its decision would be perverse and | ||
| liabe to be set aside under the head of “patent illegality”. An | ||
| award without reasons would suffer from patent illegality. The | ||
| arbitrator commits a patent illegality by deciding a matter not | ||
| within its jurisdiction or violating a fundamental principle of | ||
| natural justice.” | ||
| Scope of interference with an arbitral award | ||
| 74. The aforesaid judicial precedents make it clear that while | ||
| exercising power under Section 34 of the 1996 Act the Court does | ||
| not sit in appeal over the arbitral award. Interference with an | ||
| arbitral award is only on limited grounds as set out in Section 34 of | ||
| the 1996 Act. A possible view by the arbitrator on facts is to be | ||
| respected as the arbitrator is the ultimate master of the quantity and | ||
| quality of evidence to be relied upon. It is only when an arbitral | ||
| award could be categorised as perverse, that on an error of fact an | ||
| arbitral award may be set aside. Further, a mere erroneous | ||
| application of the law or wrong appreciation of evidence by itself is | ||
| not a ground to set aside an award as is clear from the provisions of | ||
| sub-section (2-A) of Section 34 of the 1996 Act. | ||
| 75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd., | ||
| (2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court | ||
| held that courts need to be cognizant of the fact that arbitral awards | ||
| are not to be interfered with in a casual and cavalier manner, unless | ||
| the court concludes that the perversity of the award goes to the root | ||
| of the matter and there is no possibility of an alternative | ||
| interpretation that may sustain the arbitral award. It was observed | ||
| that jurisdiction under Section 34 cannot be equated with the | ||
| normal appellate jurisdiction. Rather, the approach ought to be to | ||
| respect the finality of the arbitral award as well as party's autonomy | ||
| to get their dispute adjudicated by an alternative forum as provided | ||
| under the law.” | ||
appropriate to reproduce the relevant clauses of the Agreement, which
are as follows:
I. Article 9.2 of the Agreement reads as follows:
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 20 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
“ Article 9.2: - Subject to the terms and conditions of this
Agreement the Concessionaire shall at its own cost and
expense:
I. Undertake the design, engineering, procurement and
construction and financing of the Project Highway in
accordance with this Agreement,
II. operate and maintain the Project Highway at all
times in conformity with this Agreement including but not
limited to the Specifications and standards set forth in
schedule 'D', Schedule 'L', the Maintenance Programme
and Good Industry Practice.
The concessionaire was obliged to provide a renewal coat of
BC on completion of five years from the date of construction
and as per the specifications given in the concession agreement
and MORTH, a minimum thickness of 40 MM is required to
be provided by the concessionaire. This renewal cot has to be
completed by end of five years from the date of construction
and second coat In Ten years from the date of construction,
which the concessionaire has failed to provide and has to pay
damages in terms of agreement.”
II. Relevant Clauses of Schedule L of the Agreement are as
follows:
“2.6 Operation and Maintenance Stage
2.6.1 This is applicable for the entire Operation Period for
the Project Highway during the entire Concession Period.
Various important activities to be carried out during this
stage are:
a) Regular periodic maintenance activities:
i. Renewal of the wearing surface of the road
pavement once every 5 years;
ii. Strengthening course to be provided on „as required‟
basis.
b) Maintenance activities arising out of the specific
need(s) on account of the site conditions are:
i. Strengthening course required on account of the
Benkelman Beam Deflection (B. B. D) values in
excess of the prescribed criteria obtained during
regular testing as per the Concession Agreement
requirement;
ii. Wearing course required on account of the IRI
values higher than the prescribed criteria obtained
during regular testing as per the Concession
Agreement requirement.
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 21 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
iii. Localized repairs in short lengths less than 500mm
on account of pot holes, cracking subsidence in
isolated spots or in structured area.
4.3 Periodic Maintenance of Pavement
The framework of activities relating to pavement
maintenance and rehabilitation in respect of flexible and
rigid pavement are given in the flowcharts in Appendix
3.1 and Appendix 3.2 respectively. The Concessionaire
shall set forth in the Operation and Maintenance Manual
the detailed procedures to be followed under each of these
activities and also those the operational and performance
criteria from the performance standards set forth in this
Schedule.
4.3.1 Pavement Riding Quality
i. The riding quality of the pavement shall be ensured
by satisfying the minimum requirements given
herein under, Surface roughness of the Project
Highway on completion of construction shall be
2000mm/km as measured by vehicle mounted Bump
Integrator.
ii. Surface roughness shall not exceed 3000mm/km
during the service life of pavement at any time. A
renewal coat of bituminous concrete shall be laid
every 5 years after initial construction or where the
roughness value reaches 3000mm/km whichever is
earlier to bring it to the initial value of 2000mm/km
4.3.2 Structural Condition of the Pavement
i. The structural condition of the flexible pavement of
the Project Highway shall be assessed every year by
taking Benkelman Beam Deflections and working
out characteristic deflections of homogenous
sections of the Project Highway as per IRC 81-1997,
wherever the characteristic deflection exceeds 1.2
mm a bituminous overlay shall be provided
appropriately designed according to IRC-81-1997 or
its latest versions or amendments to it.
ii. Recycling of existing crust using milling as an
option can be explored by the Concessionaire in
consultation with the IC to maintain the FRL at the
same level throughout the concession period.
However, while adopting such measures, the
residual strength of existing pavement shall be
estimated and equivalent thickness of new material
added before laying the designed overlay. The
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 22 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
design of profile with altered pavement treatments
shall be finalized in consultation with IC.
iii. In the case of cement concrete pavement, joint shall
be thoroughly inspected every year and the loss of
sealing compounds made good.”
III. Clause 1.6 of Schedule D of the Agreement reads as follows:
“ 1.6 All works related to the Project Highway shall
conform to the Guidelines and Special Publications as
applicable to National Highways and Ministry of
Shipping, Road Transport and Highway earlier Ministry of
Road Transport and Highways (MORT&H) specifications
and India Roads Congress (IRC) standards, Codes, with all
updates till 30 days before the date of bid submission by
the Concessionaire. In the absence of any definite
provisions on any particular issue related to the
Specifications and/or Standards, reference may be made to
the latest codes and Specifications of Bureau of Indian
Standards, British Standards, AASHTO, ASTM or any
other International Standard in that order. But, where even
these are silent, the construction and completion of the
works shall conform to sound engineering practice with
the approval of the Independent Consultant /NHAI.”
IV. Clause 7.3 of Schedule B of the Agreement reads as follows:
“7.3 Strengthening of the existing flexible pavement
Strengthening of the existing flexible pavement shall not
be less than 40mm Bituminous / Asphalt concrete and 125
mm Dense Bituminous Macadam (DBM) over profile
corrective course. The composition of profile corrective
course shall depend on its thickness as given below:
| <40mm | DBM |
|---|---|
| Up to 100mm | BM |
| Up to 150mm | 50mm DBM + l00mm BM |
| Up to 375mm | WMM, by scarifying the existing<br>BT |
| Up to 575mm | Granular overlay by scarifying the<br>existing BT |
| >575mm | New Construction |
If the concessionaire desires to use geo synthetics, geo
nets etc as part of strengthening of the existing
carriageway, the same shall be finalised in consultation
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 23 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
with IC before execution of work. The above-prescribed
minimum thickness for overlay shall be laid even with
such special provisions.”
31. After a perusal of the relevant clauses of the Agreement, the
pivotal question that arises for consideration before this Court is
whether the findings rendered by the learned Arbitral Tribunal are
beyond the scope of the Agreement, or a misinterpretation of the terms
of the Agreement. For the sake of clarity, the reasoning rendered by
the learned Arbitral Tribunal on issue number 1 is reproduced, which
is as follows:
“….
It is observed that the Claimant carried out BBD tests in February
2019 and again in February 2020, conducted by Sri Infotech in the
presence of representative of IE as well as the Respondent. Results
of the tests conducted during February 2019 have been submitted
by the Claimant in CD-VOL.4 at Page 155 to 315, which have
been certified by Central Road Research Institute vide its letter
dated 24.06.2019 at Page 316 of CD-IV. It is noted that report of
Benkelman Beam Deflection survey reveals that characteristic
deflection in the entire stretch of the highway is less than 1.2 mm.
The report on Bump Integrator survey reveals that roughness index
in the entire stretch of highway is less than 2000 mm / km. It
implies that the results of BBD and Surface roughness tests reveal
that the performance parameters are within the limits as provided
in Clause 4.3.1(ii) and Clause 4.3.2 (I). The test results clearly
indicate that structural condition of the pavement and pavement
riding quality parameters are within the prescribed limits in
February 2019. The flow chart in Appendix 3.1 of Schedule-L
clearly suggests that the project is not a candidate for strengthening
of the pavement by providing overlay as provided in Para 7.5 of
IRC-81 of 1997. As per Clause 4.3 periodic maintenance of
pavement frame work is given in Appendix 3.1 of Schedule-L,
which leads to conclusion that the project does not require any
periodic maintenance.
It is also noted that SRI INFOTECH again carried out report on
Bump Integrator Survey in February 2020 (Page 253 to 315 of CD-
IV) and Central Road Research Institute submitted calibration
report vide its letter dated 24.06.2019 (Page 316 of CD-IV). SRI
INFOTECH also carried out Benkelman Beam Deflection survey
in February 2020 (Page 318 of CD-IV to Page 437 of CD-V). It is
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 24 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
noted that test results of 2020 also reveals that characteristic
deflection in the entire stretch of the highway is less than 1.2mm /
km. and roughness index in the entire stretch of highway is less
than 2000mm / km. It implies that the results of BBD and Surface
roughness tests reveals that the performance parameters are within
the limits provided in the flow chart in Appendix 3.1 of Schedule-
L, which clearly suggests that the project is not a candidate for
strengthening of the pavement by providing overlay as provided in
Para 7.5 of IRC- 81 of 1997.
The test results indicate that there being no structural deficiency in
the entire project length as characteristic deflection was less than
1.2 mm therefore there was no requirement of Bituminous overlay
for structural strengthening. As Surface roughness was well below
2000 mm / km, there was no contractual requirement for overlay to
improve riding quality. However the Claimant was required to
provide renewal coat in accordance with Clause 4.3.1(ii) of
Schedule-L, which stipulates, as under:
“ Surface roughness shall not exceed 3000 mm/km during
the service life of pavement at any time. A renewal coat of
bituminous concrete shall be laid every 5 years after
initial construction or where the roughness value reaches
3000mm/km, whichever is earlier to bring it to the initial
value of 2000mm/km ”.
The test results conducted in February 2020 indicate that roughness
value was less than 2000mm/km on the entire stretch of the
highway indicating that pavement riding quality was within the
prescribed limits.
Clause 4.3.1 (ii) makes it mandatory to provide a renewal coat of
bituminous concrete on every 5 years after initial construction or
where the roughness value reaches 3000mm/km, whichever is
earlier to bring it to the initial value of 2000mm/km. The
Respondent has relied upon provisions of IRC-81-1997 Para 7.6
which stipulate that where structural deficiency is not indicated
from deflection values, thin surfacing may be provided to improve
the riding quality. The heading of this code is “Guidelines for
strengthening of flexible road pavement used Benkelman Beam
deflection technique. This is applicable if strengthening is required
due to assessment of the road by taking Benkelman Beam
deflection technique. Such a test was conducted and as the
characteristic deflection found to be less than 1.2mm and therefore
no bituminous overlay was required to be designed according to
IRC: 81-1997 and also the surface roughness was less than 2000
mm/ km. However 7.6 of IRC: 81-1997 stipulated as under:
7.6: Where structural deficiency is not indicated from
deflection values, thin surfacing may be provided to
improve the riding quality as required
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 25 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
Therefore IRC: 81-1997 itself states that if the characteristic
deflection is less than 1.2 and the roughness index is less than 2000
mm/ km, a thin layer can be laid. Para 7.5 of IRC: 81-1997 is not
applicable as no strengthening was required in the Road.
The contract does not provide for any specific thickness of renewal
coat, therefore, the Claimant has to fulfill its obligation as listed in
Clause 9.2 (ii) of CA which stipulates, as under:
“ Operate and maintain the project highway at all times in
conformity with this Agreement including but not limited
to the specifications and standards set forth in Schedule-
D, Schedule-L, the Maintenance programme and Good
Industry Practice ”.
Clause 1.6 of Schedule-D, provides that all works related to the
project highway shall conform to the guidelines and special
publication as applicable to National highways and MoRT&H
specifications and Indian Road Congress standards, codes with all
updates till 30 days before the date of bid submission by the
Concessionaire.
The Respondent has issued vide its letter dated 08.11.2002 (C-3,
Page 5 of CD-IV), revised guidelines of MoRT&H for periodic
renewal dated 26.09.2002, which is applicable in the present
matter. As per these guidelines, thickness of periodical renewal in
Para 4 (iv) (b), 25mm BC for high traffic roads shall be laid as a
wearing course. MoRT&H specification to be followed as per
Clause 1.6 of Schedule-D, Section 5.09 provides for specification
of BC, wherein Table 500-18 provides for layer thickness of 30 to
45mm when using nominal aggregate size of 13mm (Page 703 of
Vol. V). It is also noted that IRC-29-1988 provides for
specification for bituminous concrete wherein Para 2.3 and 4.2
provides for a compacted layer thickness of 25mm BC using
aggregate gradation as shown in Table-3 for Grading-1.
th
Respondent had submitted payment specialist report dated 8 May
2019 on the thickness of periodic renewal coat should (R-8/RD-
02). The other contention raised during argument is that pavement
specialist report is given in Exhibit C-7. It was argued that both I.
C. and Pavement Specialist took the same stand and therefore
according to them 40mm BC should be laid as Renewal Coat. The
Claimant response is as under:
(i) The Senior Pavement Specialist is one of the Personal of the I.
C. and not a third party.
(ii) The personal, pavement specialist did not examine the
Pavement layer to find out whether the layer laid / to be laid was in
accordance with the specifications in the contract.
Pavement specialist had, also observed that “Therefore, the laying
periodical renewal on regular basis be carried out mandatorily in
the entire project highway at the specified frequency of once in
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 26 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
every five years irrespective of whether the roughness index or
BBD is less than the prescribed limits given in the Concession
Agreement‟. The word „Renewal‟ used in Clause 2.6.1(a) (I) of
Schedule L of CA has been interpreted by the pavement specialists
as „Repetition‟ of the original „Wearing Surface of Road
Pavement‟ which had originally been laid with thickness of 40
MM and had held that the renewal coat of 40 MM thickness of
bituminous concrete is required to be laid every Five years.
Interpretation on a renewal was debated during course of
proceedings and it was apparent that the renewal does not mean
repeating the old surface as the intention of the contract agreement
by providing renewal quote coat was to ensure smooth riding
surface when there was no structural requirement for relaying or
overlaying as there had been no need for a strengthening keeping
in view the test results of BBD and deflection areas of rates have
been met fully what was required was to ensure that the riding
surface of the pavement continues to be one as per the only
requirement and the Wear and tear which is taking place in a
period of five years is made up by new layer.
Keeping in view the fact that Schedule B lays down the scope of
the project clearly specifying requirements for new construction as
well as for strengthening of the existing pavement and Schedule
„D‟ gives the specifications and standards for design of new works
and provisions of IRC 82 and IRC 37 are applicable for design of
new construction of highways and are not directly applicable for
the maintenance operations of highways; provisions which have
been detailed in schedule „L‟ of the Contact Agreement have to be
followed for renewal coat. When structural deficiency is found
recourse has to be taken to provisions of clause 7.3 of Schedule B.
AT members are of the considered opinion that the provisions of
contact agreement and the specifications standards mentioned
therein do not specify and require laying of 40 MM thickness of
Bituminous Concrete for renewal coat.
Therefore, against Issue No.1, the AT concludes that the thickness
of BC during Second Renewal Coat to be laid by the Claimant was
not to be 40mm.
…..”
32. This Court is conscious of the law laid down by a catena of
judgements that if the learned Arbitral Tribunal has taken one of the
two possible views and if the interpretation of the contractual clauses
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 27 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
by the Arbitrator was “a possible if not a plausible” interpretation, the
court would have no reason to interfere with the arbitral award.
33. In the present case, the Impugned Award would only merit
interference if the view taken by the learned Arbitral Tribunal is in
violation of the Principles of Reasonableness, meaning thereby that
the reasoning rendered is so unreasonable that no reasonable person
acting reasonably could have made it. This Court is also guided by the
judgment of the Apex Court in Rashtriya Ispat Nigam Ltd. v. Dewan
10
Chand Ram Saran .
34. A perusal of Schedule L indicates that it contemplates renewal
of the wearing surface at periodic intervals, without prescribing any
fixed thickness for such renewal. The emphasis is on maintaining the
prescribed riding quality and surface roughness parameters. The
learned Arbitral Tribunal has, therefore, correctly construed the
obligation as one relating to performance standards rather than rigid
structural specifications.
35. The contractual scheme, when read as a whole, draws a clear
distinction between routine maintenance activities and structural
strengthening. While renewal of the surface is a periodic maintenance
requirement, strengthening overlays are contemplated only when
structural deficiencies are detected on the basis of technical
parameters. Clause 7.3 of Schedule B, which forms the fulcrum of the
Petitioner‟s submission, pertains to strengthening the existing
pavement and prescribes a minimum thickness in that context. The
10
(2012) 5 SCC 306
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 28 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
learned Arbitral Tribunal has rightly held that this provision cannot be
read in isolation and applied to renewal coats governed by Schedule L.
36. The interpretation canvassed by the learned counsel for the
Petitioner would effectively obliterate the distinction between renewal
and strengthening, thereby rendering the specific provisions of
Schedule L redundant. The learned Arbitral Tribunal‟s construction,
on the other hand, preserves the internal coherence of the Agreement
and gives effect to each provision in its proper context.
37. The learned Arbitral Tribunal has also considered Clause 1.6 of
Schedule D, which incorporates MoRTH and IRC standards. It has
correctly appreciated that such standards operate within the
framework of the Agreement and supplement, rather than supplant,
the contractual provisions. The material placed before the learned
Tribunal indicated that, in the absence of structural deficiencies,
MoRTH specifications permit a thinner BC layer for renewal of the
wearing course. The reliance placed on such specifications is thus
consistent with the contractual scheme.
38. Importantly, the learned Arbitral Tribunal has returned a finding
of fact that the pavement did not exhibit structural deficiencies
warranting a strengthening overlay. This finding is based on technical
material and evidence on record. It is, therefore, not open to this
Court, in exercise of jurisdiction under Section 34, to reappreciate
such evidence or arrive at a different conclusion.
39. Once it is held that a 40 mm BC layer was not contractually
mandated, the further conclusion of the learned Arbitral Tribunal that
the additional 10 mm thickness was executed at the insistence of the
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 29 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
Petitioner follows as a logical consequence. The learned Arbitral
Tribunal has noted that the Respondent carried out the work under
protest and had reserved its right to claim compensation. The Award,
therefore, cannot be said to be arbitrary or unsustainable.
40. Learned counsel for the Petitioner has also sought to derive
support from the dissenting opinion rendered by the learned
Arbitrator, contending that the dissent correctly characterises a
“Renewal Coat” as a specialised intervention distinct from routine
maintenance and, therefore, necessitating a higher standard of
execution. This submission, however, fails to persuade this Court.
41. It is pertinent to note that a dissenting opinion, by its very
nature, does not constitute the binding determination of the learned
Arbitral Tribunal. The enforceable award is that of the majority, and
the scope of examination under Section 34 of the A&C Act is
confined to testing the validity of the majority award on the limited
grounds statutorily prescribed. The mere existence of a dissenting
view, even if plausible or persuasive, cannot be a ground to displace
the conclusions reached by the majority.
42. In the present case, the Majority Award has undertaken a
detailed analysis of the contractual framework, including the scheme
of Schedule L, and has drawn a clear distinction between renewal of
the wearing surface and structural strengthening. It has been
concluded that a renewal coat, as envisaged under the Agreement, is a
periodic activity linked to maintenance of riding quality and surface
parameters, and does not, in the absence of structural deficiency,
mandate the specifications applicable to strengthening overlays. This
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 30 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
interpretation is rooted in the text of the Agreement and supported by
the material placed before the learned Tribunal.
43. The reasoning adopted in the dissenting opinion essentially
reflects an alternative construction of the same contractual provisions
by attributing a more intensive and restorative character to the renewal
coat. While such a view may not be wholly implausible, it nonetheless
represents only one of the possible interpretations of the Agreement.
The settled position of law is that where two views are possible, and
the learned Arbitral Tribunal has adopted one such view, the Court
cannot interfere merely because another view, including that
expressed in a dissent, may appear preferable.
44. The reliance placed by the learned counsel for the Petitioner on
the conceptual distinction sought to be drawn in the dissent between
“ renewal ” and “ routine maintenance ” does not, therefore, advance its
case. The majority has not equated renewal coat with routine
maintenance in a simplistic sense; rather, it has interpreted the
contractual obligation in its proper context, distinguishing it from
strengthening measures that are triggered by structural deficiencies.
45. This construction, in the considered opinion of this Court,
cannot be said to be either perverse or contrary to the terms of the
Agreement.
46. In this regard, it bears reiteration that the jurisdiction under
Section 34 does not extend to substituting the Court‟s view for that of
the learned Tribunal or to choosing between competing interpretations
merely because one appears more attractive. The test is whether the
view adopted by the majority is a plausible and reasonable one. Once
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 31 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
that threshold is satisfied, as it is in the present case, no interference is
warranted.
47. Accordingly, the reliance placed on the dissenting opinion is
misplaced, and the same does not furnish any ground to interfere with
the Impugned Award.
48. The next limb of the challenge pertains to the issue of delay and
the imposition of damages. This Court deems it appropriate to extract
the relevant finding rendered by the learned Arbitral Tribunal, which
reads as follows:
“….
While discussing the issue number one it has been established that
the Claimant was not required to lay Bituminous Concrete of 40
MM thickness as part of contractual requirement for the renewal
course to be laid every five years. The contact agreement only
provides for laying of a thin layer of Bituminous Concrete for
improving the riding quality which is required to be laid every five
years irrespective of the fact whether the existing pavement was
meeting the deflection criteria and roughness prescribed criteria
stipulated in the specifications. The Claimant had proposed laying
of a thickness of 30 MM, keeping in view the MoRTH
specifications. AT has agreed with the contention of the Claimant
that laying a renewal course of Bituminous Concrete of 30mm
thickness was adequate in terms of the concession agreement and
improving the riding quality of the pavement was required to be
laid every five years. In view of this, the Claimant is entitled to
reimbursement of cost incurred by laying an extra 10 MM thick
bituminous concrete towards second renewal coat.
MoRT&H specifications (Fourth Revision) for Bituminous
Concrete in Section 5, stipulates minimum layer thickness of
30mm for nominal aggregate size of 13mm for bituminous
concrete pavement layers (Table 500 — 18, Page 703, CD Vol.V).
It is admitted position that the Claimant submitted its proposal for
30mm thick renewal coat as per good engineering practice right
from April 2019 till the date on 07.04.2020 (C-29, Page 440 CD-
Vol.V). The Team Leader vide its letter dated 07.04.2020 directed
the Claimant to provide 40mm thick renewal coat, The Claimant
vide its letter dated 14.04.2020 (C-30, Page 442 of CD-V),
objected the interpretation of Contract Clauses and direction issued
by the Respondent reserving its right to lodge claim for 10mm
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 32 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
thick BC (extra thickness) as per Clause XXXIX of Concession
Agreement. The Claimant had prepared and mobilized appropriate
resources to undertake laying of renewal coat from January 2020.
The Claimant did not agree to the interpretation
forced upon him by the Respondent and referred the dispute to
Team Leader of Independent Engineer for amicable settlement on
27.05.2020 (C-33, Page 454, Vol.V).
Claimant has submitted in one Volume (Volume -II), the detailed
breakup of the cost analysis of the Claim. The Respondent did not
specifically dispute the quantification as worked out by the
Claimant. The Respondent also did not provide any Counter rate
analysis. Further for the calculation of the Counter Claim, the
Respondent considered more rate of BC than the Claimant. It may
be pertinent to state that the Claimant has arrived the rate of BC as
Rs. 9238/- per cum (SOC Page N. 4 of Volume —Il) whereas, the
Respondent has considered Rs. 10342/- per cum in non-Municipal
limit and Rs. 10910/- per cum in the Municipal limit (SOD Page
No. 112).
In the absence of any mention of thickness of renewal coat in
Concession Agreement, MoRT&H guidelines, IRC Codes are to be
referred as provided in the Concession Agreement. Para 7.6 of
IRC-81-1997 stipulates that “Where structural deficiency is not
indicated from deflection values, thin surfacing may be provided to
improve the riding quality as required”. Therefore, MoRT&H
guidelines dated 08.11.2002 and IRC-29 — 1988, Para 4.2, Table-
3 have been relied upon by the Claimant, wherein 25mm thickness
of Bituminous Course for grading -1 size of aggregates is provided
for Bituminous Concrete.
MoRT&H specifications (Fourth Revision) for Bituminous
Concrete in Section 5, stipulates minimum layer thickness of
30mm for nominal aggregate size of 13mm for bituminous
concrete pavement layers (Table 500 — 18, Page 703, CD Vol.V).
It is admitted position that the Claimant submitted its proposal for
30mm thick renewal coat as per good engineering practice right
from April 2019 till the date on 07.04.2020 (C-29, Page 440 CD-
Vol.V). The Team Leader vide its letter dated 07.04.2020 directed
the Claimant to provide 40mm thick renewal coat, The Claimant
vide its letter dated 14.04.2020 (C-30, Page 442 of CD-V),
objected the interpretation of Contract Clauses and direction issued
by the Respondent reserving its right to lodge claim for 10mm
thick BC (extra thickness) as per Clause XXXIX of Concession
Agreement. The Claimant had prepared and mobilized appropriate
resources to undertake laying of renewal coat from January 2020.
The Claimant did not agree to the interpretation forced upon him
by the Respondent and referred the dispute to Team Leader of
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 33 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
Independent Engineer for amicable settlement on 27.05.2020 (C-
33, Page 454, Vol. V).
Keeping in view the provisions of Contract Agreement, the AT
concludes that the Claimant is entitled for payment of cost incurred
for 10mm extra thickness of Bituminous concrete towards second
renewal coat.
The Claimant has submitted total cost incurred towards this claim
for Rs.13,44,09,772/-, wherein the Claimant has provided detailed
working out of claim. The Claimant has given break-up of cost in
three parts i.e. (A), (B) and (C). Part—A is for extra 10 mm
thickness of Bituminous Concrete, Part-B is for Semi Dense
Bituminous Concrete in to Service Road (Additional Length) and
Part-C is for Tack Coat for additionally executed length of Slip
road and Service Road, costing. The AT has noted that the
Claimant in its pleading has claimed cost of extra 10mm thickness
of BC towards second renewal coat. There is no mention anywhere
in the pleadings regarding Semi Dense Bituminous Concrete
(SDBC) in additional length of Service Road or Tack Coat for
additional length of Slip Road/Service Road.
Therefore, the AT has taken in to consideration the cost pertaining
to extra thickness of 10mm BC only. The AT holds that the
Claimant is entitled for the cost of extra thickness of 10mm BC.
It is noted that the Respondent has not submitted anything
pertaining to quantification of this claim except the arguments that
the Respondent is not liable to pay claim No.(a) to the Claimant
towards extra thickness of 10mm Bituminous Concrete (BC) to be
laid for renewal coat.
The Claimant has claimed that it has executed total quantity of
12,765.88 cum towards extra thickness of 10 mm BC in second
renewal coat. The Claimant has submitted rate analysis for BC at
Page 4, of CD Vol. Il, according to which the rate of BC claim is
Rs.9238/- per cum. As against it the Respondent in its Counter
Claim (A) has considered rate of BC as Rs.10342/- per cum in
outside of municipal limits and Rs.10910/- per cum within the
municipal limits (C-28, Page 112 of Counter Claim 1, Vol. lll).
Derived rates of BC are as per SSR of the year 2020-21, and GST
@12% and Royalty / Seigniorage charges in the rate analysis for
BC have been added.
Keeping in view the fact that the some of the resources would be
same for both 40 mm thick BC and 30 mm thick BC, AT has
examined the rate analysis and corrected the same due to reasons
stated in Annexure-A attached with the Award, wherein rate
derived for BC comes to Rs..8639/- per cum. Since the Respondent
has not specifically contested the quantity of Bituminous Concrete
(for extra thickness of 10mm) i.e. 12765.88 cum, in its SOD, the
quantities worked out by Claimant have been adopted for
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 34 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
quantification of the Claim. Therefore, the Claimant is entitled to
Rs.12,35,18,570/- [12765.88 x 8639 x 1.12 (GST @ 12%)]
towards the cost of extra thickness of 10mm BC laid for second
renewal coat in the Project Highway. Issue No.2 is decided
accordingly. We award an amount of Rs. 12,35,18,570/- in favour
of Claimant against its claim of Rs. Rs.13,44,09,772/-.
….”
49. The Petitioner had initially raised the claim damages to the tune
of Rs. 1,92,58,192/- for the delay in execution of the renewal coat.
50. The Petitioner has sought to demonstrate that the learned
Arbitral Tribunal erred in computing the period of delay and wrongly
concluded that the Respondent was not liable to pay damages as
claimed.
51. However, a perusal of the Impugned Award indicates that the
learned Arbitral Tribunal has considered the contractual milestones,
the correspondence exchanged between the parties, and the sequence
of events leading to the completion of the renewal coat. On such
consideration, it has arrived at a finding that the delay was either
marginal or did not justify the imposition of damages to the extent
claimed by the Petitioner. This again is a finding of fact based on an
appreciation of evidence and is not open to interference unless shown
to be perverse, which has not been established in the present case.
52. The more substantial challenge of the Petitioner is directed
towards the interpretation of Clause 18.13 of the Agreement, which
provides for damages at the higher of two amounts, namely , Rs.
10,000 per day or 0.1% of the cost of repair. The learned Arbitral
Tribunal has examined this clause in the light of settled principles
governing liquidated damages and penalties. It has been concluded
that a stipulation requiring payment of the higher of two amounts,
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 35 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
without any clear nexus to the actual loss likely to be suffered, cannot
be regarded as a genuine pre-estimate of damages. Consequently, the
learned Arbitral Tribunal has treated the higher amount as penal in
nature and has restricted the damages to Rs. 10,000 per day as a
reasonable measure.
53. This approach is in consonance with the principles embodied in
Section 74 of the Indian Contract Act, 1872, which mandates that only
reasonable compensation may be awarded, irrespective of the amount
named in the contract. The learned Arbitral Tribunal has not rewritten
the contract but has instead harmonised the contractual stipulation
with the governing legal framework. Such an exercise falls squarely
within the jurisdiction of the learned Arbitral Tribunal and does not
call for interference.
54. The learned Tribunal has also accepted the contention of the
Respondent that the expression “repair” used in Clause 18.13(b) does
not encompass periodic renewal of the wearing surface. This
interpretation is supported by the internal structure of the Agreement,
which consciously distinguishes between maintenance, renewal, and
repair activities.
55. This Court finds that the aforesaid interpretation is not only
plausible, but is also consistent with the contextual usage of the terms
employed in the Agreement. Therefore, no infirmity can be found in
the findings rendered by the learned Arbitral Tribunal. Consequently,
the challenge raised by the Petitioner is devoid of merit and is
accordingly rejected.
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 36 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16
CONCLUSION:
56. In view of the foregoing analyses, this Court is of the
considered opinion that the learned Arbitral Tribunal has assigned
cogent, well-reasoned, and sustainable grounds in support of the
Impugned Award. No perversity, infirmity, or patent illegality has
been demonstrated by the Petitioner so as to warrant interference with
the Impugned Award.
57. Accordingly, the present petition, along with pending
application(s), if any, stands dismissed.
58. No orders as to cost.
HARISH VAIDYANATHAN SHANKAR, J.
APRIL 21, 2026/va
Signature Not Verified
O.M.P. (COMM) 195/2023 Page 37 of 37
Digitally Signed
By:NEERU
Signing Date:24.04.2026
10:46:16