M/S BHAGWATI ENTERPRISES vs RAJASTHAN STATE ROAD TRANSPORT CORPORATION
- Court
- Rajasthan High Court
[2026:RJ-JP:34779-DB]
HIGH COURT OF JUDICATURE FOR RAJASTHAN
BENCH AT JAIPUR
D.B. Civil Miscellaneous Appeal No. 76/2025
CNR: RJHC021100672024 | URN: CMA / 118U / 2025
M/s Bhagwati Enterprises, Through Its Power Of Attorney Holder
Shri M.s. Somani, S/o Shri M.l. Somani, 101, Classic Centre,
First Floor, 575, M.g Road, Indore Madhya Pradesh
----Appellant
Versus
Rajasthan State Road Transport Corporation, Through Its
Chairman And Managing Director, Address- Parivahan Marg,
Jaipur
----Respondent
Mr. R.K. Agarwal, Sr. Adv. Assisted by Mr.
For Appellant(s) :
Adhiraj Modi
Mr. Madhav Dadhich
Mr. Rachit Sharma
Mr. R.N. Mathur, Sr. Adv. Assisted by Mr.
For Respondent(s) :
Prateek Mathur
Mr. Utkarsh Dubey
HON'BLE MR. JUSTICE ARUN MONGA
HON'BLE MR. JUSTICE ASHUTOSH KUMAR
Judgment
Reportable
Pronounced on : 04/ 11/2026
Per: Arun Monga, J.
1. This appeal under Section 37 of the Arbitration and Conciliation
Act, 1996 (the Act of 1996) is directed against the order dated
08.11.2024 passed by the learned Commercial Court No. 4, Jaipur
Metropolitan II, vide which it allowed the objections of the respondent
under Section 34 of the Act of 1996. It set aside the arbitral award
dated 18.09.2011 rendered by the learned Sole Arbitrator. M/s Bhagwati
Enterprises is the appellant. It was the claimant before the learned
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(2 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
Arbitrator. The Rajasthan State Road Transport Corporation is the
respondent, referred to as RSRTC or the respondent.
2. The award was for a sum of Rs. 653.20 crores along with interest
at 12% per annum. The claim before the learned Arbitrator was for Rs.
2,970.56 crores (Rs.29.50 Billion). Against the said claim, the appellant
never carried out any work under the proposed arrangement which
never materialised. It did not carry a single parcel on a single bus. That
one fact colours the whole case. More of it later, in greater details.
THE FACTS
3. Succinctly put, the controversy pertains to disputes arising out of
the tender process initiated by the Rajasthan State Road Transport
Corporation (RSRTC) for appointment of a sole licensee to carry
domestic articles and small commercial goods on its fleet of
approximately 4,000 buses, pursuant to which the appellant’s bid was
accepted vide letter dated 31.01.2005. Even the before the work could
begin, the dispute arose between the parties in relation to the execution
of the formal agreement which led to the subsequent cancellation of the
work order dated 22.02.2005.
4. Salient features of the arrangement are tabulated as below:-
Date of Notice Inviting Tender 27.01.2005
Date of acceptance of appellant’s bid 31.01.2005
Monthly licence fee quoted by the
appellant
Rs. 6,66,786/-
Security deposit Rs. 6,66,786/-
Bank guarantee furnished Rs. 40,00,716/-
Date of issuance of Work Order 22.02.2005
Licence period as per Work Order 21.03.2005 to 20.03.2008
Date of signing of agreement by the
appellant
28.03.2005
Date of signing of agreement by RSRTC 29.03.2005
Date of cancellation of Work Order 16.04.2005
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(3 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
5. The claims preferred before the learned Arbitral Tribunal as per
statement of claim dated 10.02.2010 are tabulated as under:-
S.No
.
Particulars Amount
1. Claim No. 1: For refund of earnest money and
security deposit paid to respondent along with
interest @24% p.a. up to 31.12.2009
Rs. 1,47,20,592/-
(1.47 crore)
2. Claim No. 2: For establishment, overhead expenses
and administrative expenses upto June 2005 &
traveling expenses upto September 2005 with
interest @24% p.a. up to 31.12.2009
Rs. 57,38,076/-
(57.38 lakhs)
3. Claim No. 3: For legal expenses incurred towards
this case along with interest @ 24% p.a. up to
31.12.2009
Rs. 32,09,506/-
(32.09 lakhs)
4. Claim No. 4: For loss of profit @ 15% of contract
value along with interest @ 24% p.a. up to
31.12.2009
Rs.29,68,19,73,065/-
(2,968.19 crores)
The total claim preferred before the learned Arbitral Tribunal was for
Rs.2,970.56 crores. The arbitral proceedings culminated in an award,
whereby a sum of Rs. 653.20 crores along with interest at 12% per
annum from 10.01.2010 was awarded in favour of the appellant. Vide
the said award, Claim No. 4 was allowed and Claim Nos. 1 and 2 were
partly allowed, while Claim No. 3 was rejected. The counterclaim
preferred by RSRTC was rejected in toto.
6. The decision of the learned Tribunal on various claims is culled out
and tabulated as under:-
S.No
.
Particulars Decision Amount (in Rupees)
1. Claim No. 1: Refund of earnest
money and security deposit
Partly allowed Rs. 7,66,786/-
2. Claim No. 2: Administrative,
establishment and other expenses
Partly allowed Rs. 19,01,369/-
3. Claim No. 3: Legal, professional and Disallowed --
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(4 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
other expenses
4. Claim No. 4: Anticipated loss of
profit
Rs.6,52,94,18,212/-
i) On the basis of license fee payable
for three years
Allowed Rs. 2,64,84,744/-
ii) Incentive payable to RSRTC's
drivers/conductors
Allowed after
Rs.42,70,05,00,000/
reduction
-
iii) Rental for shops/offices at bus
stands and sub-depots
Allowed Rs. 9,07,20,000/-
iv) Loading/unloading charges Allowed after
Rs. 71,17,50,000/-
reduction
5. Total award Rs. 6,53,20,86,367/-
(653.20 crores)
Aside from the above, the learned Arbitral Tribunal awarded pendente
lite and future interest at the rate of 12% per annum on the awarded
amount from 10.01.2010 till realisation. It was further directed that the
parties would bear their own costs.
7. Adumbrating little more into the specifics, stripped of the
unnecessary details, it was in 2005 RSRTC invited tenders for a sole
licensee. The licensee was to carry domestic articles and small
commercial goods on its fleet of about 4,000 buses. Four bids came in.
The appellant's bid was the highest. RSRTC accepted it by letter dated
31.01.2005. The appellant was asked to deposit Rs. 6,66,786/- and to
furnish a bank guarantee of Rs. 40,00,716/-. The appellant itself calls
the deposit an advance monthly premium. It made the deposit on
09.02.2005. It furnished the bank guarantee on 16.02.2005. The bank
guarantee is exactly six times the monthly sum.
7.1 On 22.02.2005 RSRTC issued a letter, described as the work order.
It named the appellant sole licensee for the period 21.03.2005 to
20.03.2008. A letter dated 07.03.2005 repeated that period.
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(5 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
7.2 Clause 21 of the tender conditions dealt with the term. It provided
that the agreement would be for one year. It could be extended for two
more years after deliberation. Clause 31 of the tender conditions
required the successful bidder to sign a formal agreement. The format
was to be prepared by RSRTC in line with the tender conditions. Clause
32 of the agreement made the tender conditions binding.
7.3 On 19.03.2005 the appellant asked for the draft agreement. On
receiving it, the appellant wrote on 23.03.2005. It wanted Clauses 29
and 30 deleted. It also wanted a clause on goods permits. Clauses 29
and 30 kept some traffic outside the licence. That traffic included dak of
the Posts and Telegraph Department, parcels of the State Government
and stationery of RSRTC. The Suvidha Vahan buses were also kept
outside the licence.
7.4 The agreement bears the signature of the appellant's
representative dated 28.03.2005. It bears the signature of the then
Chairman and Managing Director of RSRTC dated 29.03.2005. It also
carries a handwritten note. The note says that Clauses 29 and 30 are
not accepted and that a valid goods permit is needed. RSRTC says the
note was not on the document when the file went up for signature. It
says the note was put in later. The Financial Advisor and the Executive
Director (Administration) were to sign as witnesses for RSRTC. They
never signed. No officer of RSRTC initialled the note.
7.5 On 31.03.2005 the appellant's representative was called to the
chamber of the Financial Advisor. He was told that the note was not
acceptable. He was asked to sign a fresh agreement in the prescribed
format. RSRTC then wrote to the appellant on 01.04.2005 and again on
06.04.2005. In substance this was RSRTC's counter offer. The appellant
was not willing to sign on those terms.
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(6 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
7.6 What the appellant did next matters a great deal. It did not press
RSRTC to let it start work. It asked RSRTC to refund its security. RSRTC
acted on that request and refunded the money. On 16.04.2005 RSRTC
cancelled the work order. The appellant never began work.
7.7. On 03.05.2005 the appellant asked for appointment of an
arbitrator. On 24.05.2005 RSRTC replied that its Chairman was the
named arbitrator. The appellant then moved this Court under Section
11. By order dated 22.05.2006 in S.B. Arbitration Application No.
15/2005, this Court appointed an Hon'ble retired Judge of High Court as
Sole Arbitrator. RSRTC carried the matter to the Supreme Court. Civil
Appeal No. 5137/2007 was dismissed on 10.12.2009. The appointment
stood. The question whether a concluded contract existed was left open
for adjudication.
7.8 The statement of claim was filed on 10.02.2010. Issues were
framed on 03.06.2010. The award dated 18.09.2011 granted Rs.
6,53,20,86,367/- with interest at 12% per annum from 10.01.2010.
7.9 RSRTC filed its objections under Section 34 on 24.12.2011. By the
impugned order dated 08.11.2024 the learned Commercial Court set
aside the award. Its reasons, in short, are three. First, the learned
Arbitrator ignored Clause 21 of the tender conditions and Clause 32 of
the agreement. He worked out loss for three years when the assured
term was one year. Second, compensation can be given only for loss
that is shown. The payments made, the period for which the agreement
ran, the date of cancellation and the fact that nothing was paid for the
second and third years were all relevant. They were ignored. Third, the
award does not give reasons as Section 31(3) of the Act of 1996
requires.
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(7 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
SUBMISSIONS ON BEHALF OF THE APPELLANT
8. Mr. R.K. Agarwal, learned Senior counsel for the appellant assisted
by Mr. Adhiraj Modi made these submissions. The scope of Section 34 is
narrow. The Court does not sit in appeal over an award. The arbitrator
is the master of the quantity and quality of evidence. A possible view
cannot be upset because another view is also possible. Reliance was
1
placed on Associate Builders v. Delhi Development Authority ,
2
MMTC Ltd. v. Vedanta Ltd. , Ssangyong Engineering and
3
Construction Co. Ltd. v. National Highways Authority of India
4
and Reliance Infrastructure Ltd. v. State of Goa . Section 5 of the
Act of 1996 was also pressed into service.
8.1 It was urged that the issue of concluded contract stands closed by
the order dated 03.08.2024, affirmed on 18.10.2024. RSRTC, it was
said, cancelled a concluded contract on a false plea of interpolation. The
agreement remained in RSRTC's own custody. No inquiry was held
against any officer. A concluded contract cannot be defeated by
unilateral cancellation. Reliance was placed on National Fertilizers
5
Ltd. v. Puran Chand Nangia .
8.2 On the term, it was argued that the contract was for three years.
Clause 4 of the agreement says so. The work order dated 22.02.2005
and the letter dated 07.03.2005 say so. The bank guarantee ran for
three years. The order dated 03.08.2024 and the order of this Court
dated 18.10.2024 record it. The one year theory, it was said, is outside
the lis.
1
(2015) 3 SCC 49
2
(2019) 4 SCC 163
3
(2019) 15 SCC 131
4
(2024) 1 SCC 479
5
(2000) 8 SCC 343
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(8 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
8.3 On damages, it was argued that a party who wrongly ends a
contract must pay for the profit the other side expected to earn. Proof
of actual loss is not needed. A broad evaluation is enough. Reliance was
6
placed on A.T. Brij Paul Singh v. State of Gujarat , Dwaarka Das v.
7
State of Madhya Pradesh and Mohd. Salamatullah v.
8
Government of Andhra Pradesh . The choice of formula is for the
arbitrator, as held in McDermott International Inc. v. Burn
9
Standard Co. Ltd. .
8.4 It was said that the claim for loss of profit was supported by bids in
later tenders of RSRTC. M/s Rachna Parcel Courier Agency, Kota offered
a licence fee of Rs. 402 lakhs per month with 10% yearly escalation. M/
s Yogesh Traders, Ujjain and M/s Annapurna Techno System Pvt. Ltd.,
Kota put forward yearly profits of Rs. 736.14 crores and Rs. 947.7
crores. The learned Arbitrator examined each head, allowed some and
rejected others. The award, it was said, is reasoned.
8.5 Lastly, it was argued that lack of reasons is not by itself a ground
under Section 34(2). If any part of the award is bad, it may be severed
10
under Gayatri Balasamy v. ISG Novasoft Technologies Ltd. .
SUBMISSIONS ON BEHALF OF THE RESPONDENT
9. Mr. R.N. Mathur, learned Senior counsel assisted by Mr. Prateek
Mathur representing RSRTC opposed the appeal. His first submission
was on the appellant's own conduct. The appellant signed the
agreement with a handwritten condition. That was not an unqualified
acceptance. It was a fresh proposal on the terms of the formal
agreement. RSRTC answered with its own terms. It asked for a fresh
6
(1984) 4 SCC 59
7
(1999) 3 SCC 500
8
(1977) 3 SCC 590
9
(2006) 11 SCC 181
10
2025 SCC OnLine SC 986
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(9 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
agreement in the prescribed format. That was the counter offer. The
appellant did not accept it. Instead it asked for its security back. RSRTC
acted on that request and refunded the money. The appellant thus
chose to walk away. Having taken its money back, it cannot now claim
three years of profit as if it had been kept out against its will.
9.1 His second submission was on the term. Clause 21 of the tender
conditions gave an assured term of one year only. Extension for two
more years depended on deliberation by RSRTC. Clause 32 of the
agreement made the tender conditions binding. The work order itself
made all tender conditions applicable. A renewal that depended on
performance could not be assumed when no work was done at all. The
award for three years thus rests on a right that never existed.
9.2 His third submission was on quantum. Section 73 of the Indian
Contract Act, 1872 allows compensation only for loss that arises
naturally from the breach. Remote and indirect loss is excluded. No loss
was proved. The appellant did not lead its accounts. The bids of third
parties in other tenders prove nothing about the appellant's profit. Many
documents were picked from the internet and no witness proved them.
An award of over Rs. 653 crores to a licensee who did no work shocks
the conscience. It is against the public policy of India. Reliance was
11
placed on Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. ,
12
Unibros v. All India Radio , Batliboi Environmental Engineers
13
Ltd. v. Hindustan Petroleum Corporation Ltd. and Delhi Metro
14
Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd. .
9.3 His fourth submission was on procedure and fairness. On
13.03.2011 RSRTC applied to place documents on record, including the
11
(2003) 5 SCC 705
12
2023 SCC OnLine SC 1366
13
(2024) 2 SCC 375
14
(2024) 6 SCC 357
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(10 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
appellant's balance sheets. The application was rejected. The very
documents that could test the claim for profit were shut out. That
offends Section 18 of the Act of 1996. He urged that the award also
misstates basic dates of the proceedings. It awards interest on the
deposit, though the tender conditions provided none.
9.4 His fifth submission was on Clauses 29 and 30. Under Section 66
of the Motor Vehicles Act, 1988 and the Rajasthan Motor Vehicles Rules,
1990, goods may be carried only in the manner permitted. The deluxe
Suvidha Vahan buses had no provision to carry goods. The clauses
reflected the law. The handwritten note made the acceptance
conditional. RSRTC was not bound to accept it. The appeal be thus
dismissed.
RELEVANT CONTRACTUAL PROVISIONS
10. Before adverting to the merits of the dispute, it would be apposite
to identify, with specificity, the contractual stipulations of the tender
conditions, work order dated 22.02.2005 and agreement dated
29.03.2005 which stand attracted in the light of the written submissions
and the passages extracted from the award and the objections as
already noticed in the record. The adjudication in hand require
consideration, inter alia , of the following clauses of the tender
conditions and agreement, along with their subject-heads:
S.
No.
Relevant Clauses/ Documents Particulars
1. Clause 21 of the Tender Conditions Term of Agreement and Extension
2. Clause 31 of the Tender Conditions Execution of Formal Agreement in the
Prescribed Format
3. Clause 4 of the Agreement Period of Agreement
4. Clause 29 of the Agreement Exclusion of Specified Categories of
Traffic from the Licence
5. Clause 30 of the Agreement Exclusion of Specified Categories of
Traffic, including Suvidha Vahan Buses,
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(11 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
from the Licence
6. Clause 32 of the Agreement Applicability of Tender Conditions
7. Work Order dated 22.02.2005 Appointment of the Appellant as Sole
Licensee and Stipulated Licence Period
QUESTIONS FOR DETERMINATION
11. We have heard learned counsel for both sides and gone through
the record. Basis thereof, the following questions arise for our
consideration :-
(i) What is the scope of interference in this appeal, and which law
governs the objections?
(ii) What is the effect of the appellant asking for, and receiving,
refund of its security after it refused RSRTC's counter offer?
(iii) Did the appellant have a right to a three year term?
(iv) Can the award of loss of profit stand when no work was done,
no loss was proved and the sum is out of all proportion to the
bargain?
(v) Can any part of the award be saved by severance?
QUESTION (i) SCOPE OF INTERFERENCE AND THE GOVERNING
LAW
12. We accept the general principles urged for the appellant. A Court
under Section 34 does not sit in appeal. It does not reweigh evidence. A
plausible view of the arbitrator must be respected. Under Section 37 the
appellate Court is narrower still. It examines whether the Section 34
Court stayed within its limits. This is settled by MMTC (supra) and
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(12 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
Punjab State Civil Supplies Corporation Ltd. v. Sanman Rice
15
Mills .
13. But limited review is not no review. One feature of this case is
easily missed. The objections were filed on 24.12.2011. That was well
before the amendment of 2015 came into force on 23.10.2015. In
Ssangyong Engineering (supra) Hon’ble the Supreme Court held
that the amended Section 34 applies only to applications filed on or
after that date. So the unamended Section 34 governs these objections.
The law on public policy is the law laid down in Saw Pipes , ONGC Ltd.
16
v. Western Geco International Ltd. and Associate Builders.
14. Under that law, an award is open to challenge on the ground of
public policy if it is patently illegal. It is open to challenge if it
contravenes the substantive law, the Act of 1996 or the terms of the
contract. It is open to challenge if it is so unfair and unreasonable that
it shocks the conscience of the Court. The fundamental policy of Indian
law includes a judicial approach, the principles of natural justice and the
test of reasonableness. A finding based on no evidence is perverse. So
is a finding that ignores vital evidence. So is a finding that rests on
irrelevant material. These are not appeals on merits, but rather the
recognised heads of challenge.
15. The question before us, then, is not whether we would have read
the evidence differently. It is whether the learned Commercial Court
was right in finding that the award falls within the recognized heads of
challenge. For the reasons that follow, we hold that it was.
15
2024 SCC OnLine SC 2632
16
(2014) 9 SCC 263
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(13 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
QUESTION (ii) THE APPELLANT'S OWN CONDUCT IN SEEKING
REFUND
16. We start with the conduct of the appellant, because it goes to the
root. We are not reopening the finding that a concluded contract came
into being. That finding is final and binds us. But a concluded contract
does not freeze the parties for all time. Parties who make a contract
may also end it. Section 62 of the Indian Contract Act, 1872 says so in
plain words. If the parties to a contract agree to substitute a new
contract for it, or to rescind or alter it, the original contract need not be
performed. Such agreement need not be in writing. It may be gathered
from conduct.
17. Now see what happened here. The appellant signed the formal
agreement with a condition written on it. Under Section 7 of the
Contract Act an acceptance must be absolute and unqualified. A
condition added at the time of signing is not acceptance of the offered
terms. It is a fresh proposal. RSRTC did not accept that proposal. It
called the appellant's representative on 31.03.2005. It wrote on
01.04.2005 and on 06.04.2005. It asked for a fresh agreement in the
prescribed format. That was RSRTC's counter offer.
18. The appellant had two courses open. It could accept the counter
offer and start work. Or it could insist on the earlier bargain, keep its
security in place and hold RSRTC to performance. It did neither. It asked
RSRTC to return its security. That request has only one sensible
meaning. The appellant was not willing to go ahead on the terms on
offer. It wanted out, and it wanted its money. RSRTC took the appellant
at its word. It refunded the money. Both sides thus acted on the footing
that the arrangement was over.
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(14 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
19. A licensee who asks for its security back is not a licensee who
stands ready and willing to perform. The security was the very
foundation of the licence. Without it the appellant could not have run
the licence for a day. By asking for it back, the appellant itself pulled
out that foundation. RSRTC's later letter of 16.04.2005 only recorded
what the parties had already done.
20. The law does not allow a party to blow hot and cold. In R.N.
17
Gosain v. Yashpal Dhir the Supreme Court held that a person
cannot approbate and reprobate. He cannot take a benefit under an
arrangement and then deny the basis on which he took it. The appellant
took the refund on the footing that the arrangement had ended. It
cannot now say that the arrangement ran on for three years and claim
the profit of all three.
21. This conduct was vital evidence. It bore directly on whether there
was any breach by RSRTC at all. It bore on whether the appellant was
ready to perform. It bore on whether any loss could be laid at RSRTC's
door. Any award of expected profit had first to reckon with it. The award
does not reckon with it in any real way. An award that leaves out vital
evidence is perverse under Associate Builders. The same principle
was applied in Delhi Metro Rail Corporation . This alone is enough to
sustain the impugned order.
22. There is one more aspect. The first head of claim was refund of the
security with interest. The security was refunded at the appellant's own
request. To award it again, with interest at 12%, would be to pay the
same money twice. To that extent the award is plainly unsustainable.
17
(1992) 4 SCC 683
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(15 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
QUESTION (iii) THE THREE YEAR TERM WAS NOT A MATTER OF
RIGHT
23. The appellant's entire claim for profit is worked out over three
years. That premise does not survive a reading of the contract as a
whole.
24. Clause 21 of the tender conditions is clear. The agreement was to
be for one year. It could be extended for two more years after
deliberation. Extension was thus a matter for RSRTC to decide after
seeing how the licensee performed. It was not a right that vested in the
bidder on day one. Clause 32 of the agreement made the tender
conditions binding. The appellant's own case is that, under Clause 31 of
the tender conditions, the formal agreement had to conform to the
tender conditions. The work order dated 22.02.2005, as RSRTC rightly
points out, itself made all tender conditions applicable.
25. The appellant relies on the tender conditions when it suits it. It
says Clauses 29 and 30 had to go because they were not in the tender.
It cannot then set aside Clause 21 of the same tender when it comes to
the term. A party cannot pick the terms it likes and discard the rest.
Read together, the documents yield one meaning. The period
21.03.2005 to 20.03.2008 mentioned in the work order and in Clause 4
of the agreement was the outer limit of the licence. One year was
assured. The next two years depended on renewal. Renewal depended
on performance and on deliberation by RSRTC.
26. The other material relied on by the appellant does not alter this. A
bank guarantee is security for the licensor. The fact that the guarantee
was kept valid for three years protected RSRTC if the licence ran its full
course. It did not enlarge the licensee's rights. The orders dated
03.08.2024 and 18.10.2024 dealt with whether a concluded contract
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(16 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
existed. They narrate the period stated in the work order. They do not
decide whether the second and third years were assured. That question
was not before them.
27. Section 28(3) of the Act of 1996 obliged the learned Arbitrator to
take the terms of the contract into account. He did not deal with Clause
21 and Clause 32 when he worked out profit for three years. Ignoring a
binding term of the contract is patent illegality. This was held in
Associate Builders and reiterated in State of Chhattisgarh v. Sal
18
Udyog Pvt. Ltd. .
28. There is a deeper flaw as well. Loss for the second and third years
could arise only if the licence would have been renewed. Renewal would
depend on performance. The appellant did not perform for a single day.
There was nothing on which RSRTC could judge it. So the claim for
those years rests on a hope stacked on a hope. Section 73 of the
Contract Act says compensation is not to be given for any remote and
indirect loss or damage sustained by reason of the breach. Profit for two
years that the appellant had no right to, and no record to earn, is
exactly such loss.
QUESTION (iv) DAMAGES WITHOUT WORK, WITHOUT PROOF
AND WITHOUT PROPORTION
29. We now come to the most troubling part of the award. It grants Rs.
6,53,20,86,367/- to a licensee who did no work, with interest at 12%
on top.
30. Section 73 of the Contract Act is the governing law. It allows
compensation for loss or damage caused by the breach. The loss must
be one that naturally arose in the usual course of things, or one the
parties knew would likely result. Remote and indirect loss is excluded.
18
(2022) 2 SCC 275
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(17 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
The Explanation adds that the means which existed of remedying the
inconvenience must be taken into account. The section thus speaks of
loss caused. It does not speak of windfalls. In this context, reference
may be had to another judgment rendered by Division Bench of this
Court, presided over by one of us (Arun Monga, J.) in D.B. Civil
Miscellaneous Appeal No. 1560/2025 , titled Jaipur Development
19
Authority v. Rohan Rahdeeo Rajasthan Infra Project Ltd. . The
relevant portion of the said judgment is reproduced hereinbelow:
“ (J) Disproportionality -
79. Dehors all that has been discussed in the preceding part, there is one
further, overarching aspect of the matter which, in our considered opinion,
independently vitiates the award, and which we consider it our duty to
record. The arithmetic of the award, when laid bare, speaks for itself.
Conceded case of the claimant/respondent is that the actual date of
completion of the work is 31.01.2013, on which date as per its own
calculations, as against the project cost of Rs. 150 crores, it incurred Rs.
207.87 crores. Thus, a cost overrun of Rs. 57.87 crores. After the actual
completion date, i.e., 31.01.2013, there was no further cost and it was all
revenue receipts against toll collection. Taken to its best, the claimant
could, at the most, seek compensation of Rs. 57.87 crores along with
interest, but that too not in monetary terms but by extension of time since
as per the contract, time was revenue.
79.1 However, we have already held that extension of time of 484 days
was granted and no further was asked for. The Project Cost stood
contractually frozen at Rs. 150 crores. On the respondent's own showing,
resting оп the certificates of its Chartered Accountants/Statutory Auditors,
the actual capital cost of the project upon completion was Rs. 207.85
crores. That is to say, the entire cost escalation which the respondent itself
asserted, and which the learned Tribunal accepted, was of the order of Rs.
57.87 crores. Upon this foundation of Rs. 57.87 crores, the learned
Tribunal awarded, under Claim 1 alone, a sum of Rs. 175.67 crores, the
principal escalation compounded at the so-called IRR of 20.33%, i.e.,
more than three times the escalation itself, and to this were added the
further claims, taking the aggregate award, as on the date of the
Statement of Claim, to Rs. 198.04 crores. The Corrigendum Award of
31.07.2023 then jumped even that ceiling, directing IRR at 20.33% until
actual realisation.
79.2 The consequence, as pointed out at the Bar and not disputed before
us, is that in the execution proceedings arising out of the award as
corrected, the respondent has laid a claim exceeding Rs. 500 crores.
In other words, an admitted cost escalation of about Rs. 57 crores has, by
the alchemy of a compounding "internal rate of return", been transmuted
into a demand of over Rs. 500 crores against the public exchequer,
roughly nine times escalation on which the entire claim was founded, and
more than three times the agreed cost of constructing the tunnel project
itself. Indeed, Claim No. 1 alone, at Rs. 175.67 crores, exceeds the
contractually frozen cost of the entire project; the "compensation" for an
incident of the project has outstripped the cost of the project.
19
2026:RJ-JP:30253-DB
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(18 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
80. Such a result seems to us, with due respect, rather preposterous, and
no process of reasoning consistent with law can sustain it. The law of
damages is compensatory, not punitive. Section 73 of the Contract Act
entitles a party only to compensation for loss or damage which naturally
arose, or which the parties knew to be likely to arise, from the breach, and
to nothing more.
80.1 An award mechanism under which the remedy grows, year upon year
and on a compounding basis, at a rate half as high again as the claimant's
own admitted cost of borrowing (13.5%), and continues to grow after the
award until realisation, does not just compensate a loss; In fact, it confers
a windfall, converts the arbitral award into a high-yield investment
against the State, and creates the perverse consequence that every day of
delay enriches the claimant beyond any loss it could conceivably have
suffered.
80.2 When the paying party is a statutory development authority and the
ultimate source of payment is public money collected from the citizens, the
award operates as unjust enrichment at the cost of the public exchequer.
Proportionality between the wrong (if any) and the remedy is an
elementary requirement of justice. An award which bears no rational
proportion to the loss found, indeed, in the present case, to a loss never
found, there being no finding of breach at all, shocks the conscience of the
Court. As held in Associate Builders (supra) and reiterated in Ssangyong
(supra) , an award which shocks the conscience of the Court conflicts with
the most basic notions of morality and justice within the meaning of
Explanation 1(iii) to Section 34(2)(b) (ii) of the Act of 1996, and this
ground, though to be applied sparingly, exists precisely for a case such as
the present.
81. We are conscious that inadequacy or excessiveness of the amount
awarded is not, by itself, a ground of challenge to the Award under Section
34, and that the Court does not sit in appeal over quantum. But that
principle presupposes an award whose measure of compensation is
anchored in the contract or in law.
81.1 In the case in hand, the very measure adopted is a notional,
compounding project appraisal rate (IRR) applied to claims which have
been allowed. That too, without a finding of breach. And as an icing on
the cake, unmoored by the corrigendum from any ceiling, which is itself
dehors to the contract. Moreover, it is contrary to Section 73 of the
Contract Act. It is contrary to the public policy reflected in the Interest
Act. It is contrary to Section 31(7) of the Act of 1996 and productive of a
result which is wholly unconscionable.
81.2 The vice is therefore not one of mere quantum but of the legal
foundation of the award itself, and squarely falls within Section 34(2)(b)
(ii) read with Explanation 1, as also Section 34(2A). This aspect, too,
wholly escaped the attention of the learned Commercial Court.
81.3 The award is liable to be set aside on this ground independently of,
and in addition to, the grounds recorded hereinabove.”
31. As held above, even in the case in hand we are of the same opinion
that, Dehors, what has been discussed in the preceding part of instant
judgment, disproportionality herein also is too overreaching, and that
aspect of the matter independently vitiates the entire award. In Kailash
20
Nath Associates v. Delhi Development Authority Hon’ble the
20
(2015) 4 SCC 136
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(19 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
Supreme Court held that damage or loss caused by the breach is a sine
qua non for compensation under the Contract Act. Where loss can be
proved, it must be proved. In Unibros (supra) , the Supreme Court
dealt with a claim for loss of profit in arbitration. It held that such a
claim needs credible evidence. Damages cannot as a matter of course
result in an award without proof of the claimant having suffered injury.
A formula cannot be applied in a vacuum. An award resting on no
evidence on this head was held to be patently illegal and in conflict with
the public policy of India. Batliboi Environmental (supra) is to the
same effect. The appellant itself cites it for the rule that damages
cannot be whimsical or disproportionate, and must rest on an intelligible
factual basis.
32. The appellant says the learned Commercial Court wrongly insisted
on actual loss. We do not read the impugned order that way. It does not
say that expected profit can never be awarded. It says that loss must
be shown on material, and that the payments made, the period for
which the agreement ran, the date of cancellation and the absence of
any payment for later years must be weighed. That is the very inquiry
Section 73 demands. It is the very inquiry Unibros and Batliboi
Environmental require.
33. The judgments relied on by the appellant do not help it. In Brij
Paul Singh the contractor had executed part of the work. Damages
were measured at 15% of the value of the balance work. In Dwaarka
Das damages were 10% of the contract value. In Mohd. Salamatullah
too a modest percentage was applied. All three were works contracts.
The contractor was to be paid a price. The expected profit was a small,
known slice of that price. Here the appellant was not to be paid
anything by RSRTC. It was to pay RSRTC a licence fee. Its profit
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(20 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
depended wholly on freight it might earn from a business it never
started. These cases support a broad evaluation of a reasonable margin.
They do not support an award of several hundred crores on bids made
by strangers.
34. McDermott International also does not assist. It holds that the
choice of formula is for the arbitrator. But every formula needs proven
inputs. In that case the work had been done and costs had been
incurred. Here the inputs are bids of third parties in other tenders. That
is a formula working in a vacuum, which Unibros forbids.
35. Let us also have a look at the evidence as well on which the profit
was awarded, since learned senior for the appellant would argue that it
is overwhelmingly in favour of appellant. Though of course we do not
agree with that. And for valid reasons. Evidence consists of nothing but
bids in later tenders. One bidder offered a licence fee of Rs. 402 lakhs
per month. A bid is a hope. It is not a profit. It tells us what a bidder
said it would pay or hoped to earn. It tells us nothing about what
appellant before us would have earned. No accounts of the appellant
were placed. No business plan was proved. No witness from those
bidders was examined. RSRTC’s stand is that many documents were
taken from the internet and no one proved them. The appellant has not
shown us otherwise. A figure of more than Rs. 900 crores a year, just
by carrying parcels on the State buses called for the closest scrutiny. It
received none.
36. The record does contain any firm figure on the value of this
bargain. It is what the appellant itself agreed to pay. The monthly sum
was Rs. 6,66,786/-. The bank guarantee of Rs. 40,00,716/- is exactly
six months of it. At that rate the appellant would have paid RSRTC
about Rs. 80,01,432/- a year, and about Rs. 2,40,04,296/- over three
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(21 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
years. The award is about 272 times that three year total. It is about
816 times one year's fee. That is before interest. Even if one were to
borrow the 10% to 15% yardstick of the cases cited by the appellant
and apply it generously, the figure would run into lakhs, not hundreds of
crores.
37. No reasonable person in the appellant's shoes would have bid Rs.
80 lakhs a year for a business expected to yield hundreds of crores a
year. Nor would any reasonable licensor have let it go so cheap. The
disproportion is not a matter of degree. It is of a different order
altogether. It shows that the award was not an estimate of loss caused,
but surely a windfall.
38. Impugned award thus fails because it awards an enormous sum on
no proof of loss, for a term that was never assured, to a party that did
no work and itself asked for its money back. Such an award is so unfair
and unreasonable that it shocks the conscience of the Court. That is the
very test laid down in Saw Pipes (supra) . It is in conflict with the
public policy of India. It is perverse in the sense explained in Associate
Builders . It is patently illegal for disregard of Section 73 of the
Contract Act and Section 28(3) of the Act of 1996.
QUESTION (v) SEVERANCE
39. Learned counsel for the appellant urged that, though in the
alternative, to sever the bad part and save the rest. In Gayatri
Balasamy (supra) it has been held that a Court may set aside part of
an award where the valid and invalid parts are truly separable.
However, it is also held that the power to modify an award is narrow.
The Court cannot reassess the merits or work out a fresh figure of its
own.
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(22 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
40. There is nothing here that can be cleanly separated and saved. The
security was refunded at the appellant's own request. The claim for
expenses rests on unproved bills after the appellant stepped away. The
claim for legal expenses was rejected by the learned Arbitrator himself.
The claim for profit rests on no proof of loss and on a term that was
never assured. Even a profit figure for the first year would have to be
worked out afresh. That is precisely what Gayatri Balasamy says a
Court cannot do. The award must therefore fall as a whole.
CONCLUSION
41. To sum up. The appellant, having refused RSRTC's counter offer,
itself asked for refund of its security. RSRTC acted on that request and
refunded the money. The appellant cannot now claim profit for a
contract it chose to leave. The three year term was not a matter of
right. Only one year was assured, and renewal depended on
performance that never took place. The award of Rs. 6,53,20,86,367/-
was made without any work being done, without any proof of actual
loss and on bids of third parties. It is wholly out of proportion to the
bargain. It ignores Section 73 of the Contract Act and the terms of the
contract. It shuts out relevant evidence. It is in conflict with the public
policy of India as the law stood when the objections were filed.
42. The learned Commercial Court did not reweigh evidence or
substitute its own view. It applied the recognised heads of challenge.
We find no error in the impugned order dated 08.11.2024. It does not
call for interference under Section 37 of the Act of 1996.
43. The appeal is accordingly dismissed. The order dated 08.11.2024
passed by the learned Commercial Court No. 4, Jaipur Metropolitan II,
Jaipur is upheld. The arbitral award dated 18.09.2011 stands set aside.
(Uploaded on 06/11/2026 at 07:12:19 PM)
(Downloaded on 06/11/2026 at 07:25:44 PM)
(23 of 23)
[2026:RJ-JP:34779-DB] [CMA-76/2025]
Pending applications, if any, stand disposed of. There shall be no order
as to costs.
(ASHUTOSH KUMAR),J (ARUN MONGA),J
72/Bijesh