M/S Annu Singh Construction and Suppliers Private Limited vs The State of Bihar

Court
Patna High Court

IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.16586 of 2026
CNR No. BRHC011089432026
======================================================
M/S Annu Singh Construction and Suppliers Private Limited through its
Director Balendra Kumar Singh, aged about 53 years, Male, Son of Krishna
Kumar Singh, resident of Village-Chhitri Gopalpur Neora, District-
Muzaffarpur having its office situated at Alkapuri Bhagwanpur, District-
Muzaffarpur.
... ... Petitioner/s
Versus
1. The State of Bihar through the Additional Chief Secretary, Planning and
Development Department, Bihar, Patna.
2. The Chief Engineer Planning and Development Department Local Area
Engineering Organization, Bailey Road, Patna.
3. The Executive Engineer, Local Area Engineering Organization Works
Division-02, Benipur, District- Darbhanga.
4. The Circle Officer, Ghanshyampur, District- Darbhanga.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s : Mr. Raju Kumar, Advocate
For the State : Mr. Rajeev Kumar Singh, GA-10
======================================================
CORAM: HONOURABLE MR. JUSTICE HARISH KUMAR
ORAL JUDGMENT
Date : 23-11-2026
Heard learned advocate for the petitioner and learned
advocate for the State.
2. The petitioner, being a Director of Construction and
Supplies Pvt. Ltd., has approached this Court seeking a direction
upon the respondent Executive Engineer, Local Area
Engineering Organisation, Works Division-02, Benipur,
Darbhanga, to issue an order for resumption of the construction
work of the Panchayat Sarkar Building at Budh Way Inayatpur
Panchayat, under Block-Ghanshyampur, District-Darbhanga,

Patna High Court CWJC No.16586 of 2026 dt.23-11-2026
2/4
pursuant to Agreement No. 03/SBD 2024-25 dated 04.09.2024,
or, in the alternative, to refund the security deposit and earnest
money deposited by the petitioner.
3. From the materials on record, it appears that the
petitioner entered into an agreement with the Executive
Engineer, Local Area Engineering Organisation, Works
Division-02, on 04.09.2024.
4. The petitioner, having been declared the successful
bidder, was directed to proceed with the execution of the
aforesaid work in accordance with the terms and conditions of
the contract. The construction work of the Panchayat Sarkar
Building, in terms of the Agreement dated 04.09.2024, was
required to be completed by 03.11.2025 from the date of
commencement. However, it is the specific contention of
learned Advocate for the petitioner that the work, in question,
could not be completed on account of severe waterlogging at the
proposed site, due to which, the construction work was brought
to a halt pursuant to Memo No. 433 dated 09.05.2025 issued by
the Circle Officer, Ghanshyampur.
5. The Executive Engineer, LAEO, Works Division,
sought clarification from the Circle Officer, Ghanshyampur,
vide Letter No. 864 dated 17.05.2025, with regard to the

Patna High Court CWJC No.16586 of 2026 dt.23-11-2026
3/4
execution of the work at the site. However, till date, no decision
has been taken regarding the resumption of the work. More than
two years have elapsed. In such circumstances, the petitioner
made a representation before the Executive Engineer, LAEO,
Works Division-02, Benipur, Darbhanga, requesting him either
to direct the resumption of the construction work or to cancel
the agreement and refund the security deposit and earnest
money. However, no final decision has been taken on the said
representation, hence, the present writ petition.
6. Learned Advocate for the State, however, prays for
a short adjournment to apprise this Court with regard to the
present factual position.
7. Considering the nature of the claim as raised in the
present writ petition, this Court finds it appropriate to dispose of
the same with the liberty to the petitioner to file a fresh
representation before the Executive Engineer, LAEO, Works
Division-02, Benipur, Darbhanga, preferably within a period of
two weeks.
8. In case, such a representation is filed, the concerned
respondent Executive Engineer, LAEO, Works Division-02,
Benipur, Darbhanga shall pass an appropriate order, in
accordance with law, within a further period of eight weeks.

Patna High Court CWJC No.16586 of 2026 dt.23-11-2026
4/4
9. With the aforesaid direction, the present writ
petition stands disposed of.

(Harish Kumar, J)