Vantage Integrated Securities Solution Pvt Ltd vs Spark Technologies Pvt Ltd

Court
Delhi High Court

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 27.07.2026
Judgment pronounced on: 05.08.2026
Judgment uploaded on: 05.08.2026
# CNR No. DLHC010331702026
+ FAO (COMM) 203/2026 and CM APPL. 47883/2026
VANTAGE INTEGRATED SECURITIES SOLUTION PVT
LTD .....Appellant
Through: Mr. Dhruv Tamta, Adv.

versus

SPARK TECHNOLOGIES PVT LTD .....Respondent
Through: None.

CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MS. JUSTICE SHAIL JAIN
J U D G M E N T
ANIL KSHETARPAL, J.:
1. Through the present Appeal, the Appellant assails the
correctness of the judgment dated 06.06.2026 [hereinafter referred to
as ‘Impugned Judgment’] passed by the learned District Judge
(Commercial Court)-01, Patiala House Courts, New Delhi [hereinafter
referred to as ‘Commercial Court’] in OMP (Comm.) No. 27/2021,
whereby the objections preferred by the Appellant under Section 34 of
the Arbitration and Conciliation Act, 1996 [hereinafter referred to as
‘1996 Act’], came to be dismissed and the arbitral award dated
27.10.2020 [hereinafter referred to as ‘award’] rendered by the learned
Sole Arbitrator in Arbitration Case No. DIAC/2297D/11-18 was
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 1 of 14

upheld.
2. The issue which arises for consideration in the present Appeal
is whether the learned Commercial Court committed any error in
declining to interfere, under Section 34 of the 1996 Act, with the
arbitral award dated 27.10.2020, so as to warrant interference by this
Court in exercise of its appellate jurisdiction under Section 37 of the
said Act.
FACTUAL MATRIX:
3. In order to appreciate the controversy involved in the present
Appeal, the relevant facts, in brief, are required to be noticed.
4. The Respondent is a company engaged in the business of
dealing in computer peripherals, networking products and allied
services. The Appellant is engaged in the business of design, supply,
installation, testing and commissioning of electronic security and
surveillance systems.
5. On 07.05.2015, the Appellant issued a Purchase Order in favour
of the Respondent for supply of certain networking products and
allied material required by the Appellant. Pursuant thereto, the
Respondent effected supplies under various invoices aggregating to
Rs.25,68,772/-. According to the Respondent, payments aggregating
to Rs.15,75,878/- were received from the Appellant, leaving an
outstanding balance of Rs.9,92,894/-, which formed the subject matter
of the claim before the learned Sole Arbitrator.
6. Alleging that despite repeated requests and notice dated
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 2 of 14

12.04.2017, the outstanding amount remained unpaid, the Respondent
invoked the provisions of the Micro, Small and Medium Enterprises
Development Act, 2006 [hereinafter referred to as ‘MSMED Act’] by
approaching the Micro and Small Enterprises Facilitation Council.
Upon failure of conciliation, the dispute was referred under Section
18(3) of the MSMED Act to the Delhi International Arbitration Centre
for adjudication in accordance with the provisions of the 1996 Act.
7. Before the learned Sole Arbitrator, the Respondent claimed
recovery of the outstanding principal amount of Rs.9,92,894/- together
with interest under the MSMED Act and other consequential reliefs.
The Appellant resisted the claim primarily on the ground that the
supplies were not made within the stipulated time, which allegedly
resulted in delay in execution of a separate project awarded to it by the
Reserve Bank of India [hereinafter referred to as ‘RBI’]. It was
asserted that the RBI consequently levied liquidated damages upon the
Appellant and, therefore, the outstanding amount payable to the
Respondent was liable to be adjusted against the losses so suffered.
The Appellant further pleaded that the Respondent had been informed
through contemporaneous correspondence that any liquidated
damages imposed by the RBI would be passed on to it.
8. Upon appreciation of the pleadings, documentary evidence and
oral testimony led by the parties, the learned Sole Arbitrator, by award
dated 27.10.2020, did not accept the defence raised by the Appellant
and substantially allowed the Respondent’s claim. The learned Sole
Arbitrator held, inter alia , that the Purchase Order did not stipulate
that time was the essence of the contract; there was no contractual
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 3 of 14

term or agreement entitling the Appellant to recover or adjust any
alleged liquidated damages; and the Appellant had failed to establish
that the Respondent had assumed any contractual liability in respect of
the liquidated damages allegedly imposed upon the Appellant under
its independent contract with the RBI.
9. The award also recorded that no counterclaim seeking recovery
of the alleged losses had been filed. Consequently, the Appellant was
directed to pay the outstanding principal amount of Rs.9,92,894/-,
interest under the MSMED Act as quantified in the award, costs and
further interest in terms thereof.
10. Aggrieved thereby, the Appellant instituted a petition under
Section 34 of the 1996 Act before the learned Commercial Court. By
the Impugned Judgment, the learned Commercial Court dismissed the
petition, holding that the findings recorded by the learned Sole
Arbitrator were based on appreciation of the contractual terms and the
evidence led by the parties, and did not suffer from patent illegality or
perversity so as to warrant interference within the limited scope of
Section 34 of the 1996 Act.
11. It is against the aforesaid judgment affirming the arbitral award
that the present Appeal has been preferred under Section 37 of the
1996 Act.
CONTENTIONS ON BEHALF OF THE APPELLANT:
12.1. It was submitted that both the learned Sole Arbitrator and the
learned Commercial Court committed a manifest error in proceeding
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 4 of 14

on the assumption that time was not the essence of the contract
between the parties. It was contended that the Purchase Order dated
07.05.2015 formed an integral part of a larger time-bound project
awarded by the RBI to the Appellant for installation of IP CCTV
surveillance systems at various offices of the RBI. The stipulated
delivery schedule contained in the Purchase Order had to be construed
in the backdrop of the principal contract, under which timely
completion was of paramount importance.
12.2. It was further submitted that the Respondent had failed to
adhere to the agreed delivery schedule and that such delay had a direct
bearing on the execution of the RBI project. It was submitted that the
contemporaneous correspondence exchanged between the parties,
particularly the emails dated 09.07.2015, 15.07.2015, 17.07.2015 and
26.08.2015, unequivocally demonstrated that the Respondent had
been repeatedly informed that the supplies were urgently required for
a time-bound Government project and that any liquidated damages
imposed by the RBI would be recovered from the Respondent.
12.3. It was further contended that the learned Sole Arbitrator failed
to appreciate that the RBI had, in fact, granted extension of time while
simultaneously imposing liquidated damages upon the Appellant.
Referring to the correspondence exchanged with the RBI, it was
submitted that the Appellant had established a direct nexus between
the Respondent’s delayed supplies and the financial loss suffered by
the Appellant.
12.4. It was also argued that the learned Sole Arbitrator erred in
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 5 of 14

holding that there was no contractual basis for adjustment of the
outstanding amount against the losses suffered by the Appellant.
According to him, even in the absence of an express clause providing
for recovery of liquidated damages, the Appellant was entitled to
claim compensation for breach of contract under Sections 55, 73 and
74 of the Indian Contract Act, 1872 [hereinafter referred to as
‘Contract Act’]. He submitted that the communication dated
26.08.2015 constituted sufficient notice under the third paragraph of
Section 55 of the Contract Act, thereby preserving the Appellant’s
right to recover compensation despite accepting delayed performance.
12.5. It was further contended that the learned Sole Arbitrator failed
to consider the defence of adjustment in its correct perspective and did
not adequately deal with the effect of the contemporaneous
correspondence, the admissions elicited during the cross-examination
of the witnesses and the documentary evidence relating to the levy of
liquidated damages by the RBI.
12.6. It was also submitted that the learned Sole Arbitrator acted
illegally in not permitting the Appellant to pursue its counterclaim
relating to the losses allegedly suffered on account of the liquidated
damages imposed by the RBI and consequently failed to adjudicate
the same. It was contended that the Appellant was thereby deprived of
an effective opportunity to establish its case and that such course of
action amounted to a violation of the principles of natural justice,
constituting an additional ground for setting aside the arbitral award.

Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 6 of 14

ANALYSIS & FINDINGS:
13. This Court has carefully considered the submissions advanced
on behalf of the Appellant and perused the material on record.
14. It is well settled that the scope of interference available to the
Court under Section 37 of the 1996 Act is even narrower than that
exercisable under Section 34 of the 1996 Act. While considering an
appeal under Section 37, this Court does not sit in appeal over the
arbitral award nor is it expected to undertake a fresh appreciation of
the evidence led before the learned Sole Arbitrator. Interference is
warranted only where the Appellant is able to demonstrate that the
Commercial Court has failed to apply the settled parameters
governing Section 34 or has committed a manifest error in refusing to
set aside an award which is vitiated by any of the grounds recognised
under the 1996 Act.
15. Equally well settled is the principle that an arbitral award
cannot be interfered with merely because another view on facts or
interpretation of the contractual terms is possible. The interpretation of
the terms of the contract, appreciation of documentary as well as oral
evidence and the findings of fact recorded by the learned Sole
Arbitrator ordinarily fall within the exclusive domain of the arbitral
tribunal. Unless such findings are shown to be patently illegal,
perverse or in conflict with the fundamental policy of Indian law, the
Court exercising jurisdiction under Sections 34 and 37 cannot
substitute its own view for that of the learned Arbitrator.
16. Examined in the aforesaid backdrop, this Court finds no
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 7 of 14

infirmity in the view adopted by the learned Commercial Court while
refusing to interfere with the arbitral award. A careful reading of the
award demonstrates that the learned Sole Arbitrator considered each
of the principal defences raised by the Appellant, namely, that time
was the essence of the contract, that the Respondent was liable to bear
the liquidated damages allegedly imposed by the RBI, and that the
outstanding amount payable to the Respondent stood validly adjusted
against the losses allegedly suffered by the Appellant. The learned
Sole Arbitrator recorded findings on each of these issues after
considering the contractual documents as well as the evidence
produced by the parties. The learned Commercial Court, while
exercising jurisdiction under Section 34 of the 1996 Act, found no
patent illegality or perversity in the aforesaid findings. Having
independently examined the record, this Court is in agreement with
the said conclusion.
17. The principal submission advanced on behalf of the Appellant
that both the learned Sole Arbitrator and the learned Commercial
Court erred in holding that time was not the essence of the contract,
does not merit acceptance. A perusal of the arbitral award reveals that
the learned Sole Arbitrator examined the terms of the Purchase Order
as well as the evidence adduced by the parties before arriving at the
conclusion that the contract between the Appellant and the
Respondent did not contain any stipulation declaring time to be the
essence of the contract. The learned Sole Arbitrator also noticed that
although specific delivery dates were mentioned in the Purchase
Order, there was no contractual provision making delayed delivery a
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 8 of 14

ground for fastening liability upon the Respondent or requiring the
Respondent to bear any liquidated damages in the event of delayed
supplies. The finding so recorded is essentially one based upon
construction of the contractual terms and appreciation of the evidence
on record.
18. Merely because the supplies procured by the Appellant were
intended to be utilised in the execution of another contract awarded by
the RBI would not, by itself, alter or rewrite the contractual
relationship between the Appellant and the Respondent. The
obligations and liabilities of the parties are required to be gathered
from the terms of the contract executed between them and not from
the conditions contained in a separate agreement entered into by one
of the contracting parties with a third party. Significantly, the
Appellant has not been able to point out any clause in the Purchase
Order whereby the Respondent agreed either that time would be the
essence of the contract or that it would be liable for any liquidated
damages which the Appellant might incur under its independent
contract with the RBI.
19. The Appellant has relied upon various emails and other
contemporaneous correspondence to contend that the Respondent had
been informed that the supplies were required for a time-bound project
and that any delay would expose the Appellant to liability before the
RBI. However, the mere exchange of correspondence reminding the
Respondent to expedite supplies or communicating the possible
consequences of delay cannot, in the absence of a contractual
stipulation accepted by both parties, create a fresh contractual
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 9 of 14

obligation or enlarge the liabilities originally undertaken by the
Respondent under the Purchase Order. Whether such correspondence
was sufficient to alter the contractual rights of the parties was a matter
squarely falling within the domain of the learned Sole Arbitrator. The
learned Sole Arbitrator considered the said correspondence and
declined to accept the interpretation sought to be placed thereon by the
Appellant. Such a view is undoubtedly a plausible view arising from
the material available on record and cannot be characterised as
patently illegal or perverse so as to warrant interference under
Sections 34 or 37 of the 1996 Act.
20. The next submission concerns the Appellant’s plea that it was
entitled to adjust the outstanding amount payable to the Respondent
against the liquidated damages allegedly imposed upon it by the RBI.
In support of this contention, learned counsel submitted that the
communication dated 26.08.2015 constituted sufficient notice within
the meaning of the third paragraph of Section 55 of the Contract Act
and, therefore, notwithstanding acceptance of the delayed supplies, the
Appellant had preserved its right to seek compensation.
21. This contention also does not persuade this Court to take a view
different from that adopted by the learned Sole Arbitrator. A perusal
of the award shows that the learned Sole Arbitrator examined the
Appellant’s plea that the outstanding dues payable to the Respondent
could be adjusted against the liquidated damages allegedly imposed
by the RBI. Upon consideration of the Purchase Order, the
correspondence exchanged between the parties and the evidence led
before him, the learned Sole Arbitrator found that there existed no
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 10 of 14

contractual stipulation or mutually accepted arrangement entitling the
Appellant either to recover such alleged damages from the
Respondent or to unilaterally adjust the admitted amount payable to it.
Once such a finding has been returned on appreciation of the
contractual documents and evidence, this Court, while exercising
jurisdiction under Section 37 of the 1996 Act, cannot reassess the
factual foundation of that conclusion merely because another view
may also be possible.
22. The correspondence relied upon by the Appellant, including the
communication dated 26.08.2015, was also taken into consideration
by the learned Sole Arbitrator. The said communication merely
conveyed the Appellant’s apprehension that liquidated damages might
be imposed by the RBI and its intention to recover the same from the
Respondent. Such communication neither formed part of the Purchase
Order nor constituted a contractual stipulation governing the rights
and liabilities of the parties. More importantly, there is nothing on
record to indicate that the Respondent accepted the said stipulation or
that the parties mutually agreed to modify the contractual terms. In the
absence of any contractual provision or subsequent mutual agreement
incorporating such liability, the learned Sole Arbitrator cannot be
faulted for concluding that the Appellant had failed to establish its
defence of adjustment.
23. The reliance placed by the Appellant upon Sections 73 and 74
of the Contract Act also does not advance its case. The very
foundation for claiming compensation from the Respondent, namely a
contractual obligation making the Respondent liable for the alleged
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 11 of 14

losses suffered by the Appellant, was found to be absent by the
learned Sole Arbitrator upon interpretation of the Purchase Order and
appreciation of the evidence. Once that foundational finding is held to
be a plausible view of the matter, no occasion arises for this Court,
while exercising jurisdiction under Section 37 of the 1996 Act, to re-
examine the Appellant’s entitlement to damages by undertaking a
fresh appreciation of the contractual documents or evidence.
24. Equally untenable is the submission that the learned
Commercial Court mechanically dismissed the objections without
independently examining the grounds urged by the Appellant. A
perusal of the Impugned Judgment reveals that the learned
Commercial Court adverted to each of the principal objections raised
under Section 34 of the 1996 Act and rightly concluded that the
Appellant was, in substance, seeking a re-appreciation of the evidence
and a fresh interpretation of the contractual terms. Having found that
the view adopted by the learned Sole Arbitrator was a plausible one
founded upon the material available on record, the learned
Commercial Court correctly declined to interfere in view of the settled
limitations governing proceedings under Section 34 of the 1996 Act.
25. The last submission advanced on behalf of the Appellant is that
the learned Sole Arbitrator failed to adjudicate upon its plea relating to
the losses allegedly suffered on account of the liquidated damages
imposed by the RBI and thereby violated the principles of natural
justice. This contention also deserves rejection. A perusal of the
arbitral award unmistakably shows that the learned Sole Arbitrator
examined at considerable length the Appellant’s contention that the
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 12 of 14

amount claimed by the Respondent was liable to be adjusted against
the alleged losses suffered by the Appellant. Upon consideration of
the Purchase Order, the contemporaneous correspondence and the oral
evidence, the learned Sole Arbitrator rejected the said plea on merits.
It cannot therefore be contended that the Appellant’s defence was not
considered.
26. The grievance now sought to be projected by the Appellant is,
in substance, an attempt to assail the findings recorded by the learned
Sole Arbitrator on the aforesaid defence. Even assuming that the
Appellant desired to pursue an independent claim against the
Respondent, the arbitral award does not disclose any failure to
consider the defence actually raised before the learned Sole Arbitrator
in answer to the Respondent's claim. The learned Sole Arbitrator
returned specific findings on the Appellant’s plea of adjustment and
rejected the same for want of any contractual or legal foundation.
Such findings, being findings on merits, based upon appreciation of
the contractual documents and the evidence on record, cannot be
recast as a violation of the principles of natural justice or as a
procedural infirmity warranting interference under Sections 34 or 37
of the 1996 Act.
27. This Court is, therefore, of the considered opinion that none of
the findings recorded by the learned Sole Arbitrator can be said to
suffer from patent illegality, perversity or conflict with the
fundamental policy of Indian law. The learned Commercial Court
rightly appreciated the limited scope of interference available under
Section 34 of the 1996 Act and correctly declined to interfere with a
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 13 of 14

well-reasoned arbitral award. The Appellant has failed to demonstrate
any jurisdictional error or perversity in the Impugned Judgment
warranting interference by this Court in exercise of its appellate
jurisdiction under Section 37 of the 1996 Act.
CONCLUSION:
28. In view of the aforesaid discussion, this Court finds no merit in
the present Appeal. The Impugned Judgment passed by the learned
Commercial Court does not suffer from any infirmity warranting
interference in exercise of appellate jurisdiction under Section 37 of
the Arbitration and Conciliation Act, 1996. Consequently, the arbitral
award dated 27.10.2020, as affirmed by the learned Commercial
Court, calls for no interference.
29. Accordingly, the present Appeal, along with the pending
application, is dismissed.
ANIL KSHETARPAL, J.

SHAIL JAIN, J.
AUGUST 05, 2026
jai/pal
Signature Not Verified
Signed By:SAVITA
PASRICHA
Signing Date:05.08.2026
12:18:02
FAO(COMM) 203/2026 Page 14 of 14