National Highways Of India vs Gr Infraprojects Limited

Court
Delhi High Court

$~9
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC010224812026
+ ARB. A. (COMM.) 40/2026, I.A. 13905/2026 & I.A.
13906/2026

NATIONAL HIGHWAYS OF INDIA .....Petitioner
Through: Dr. Diya Swamy, Mr.
Yagwalkya Singh, Ms. Akriti
Singh, Ms. Akriti Singh, Mr.
Rishav Ranjan, Mr.
Yashoverman Chandel, Mr.
Anubhav Agrawal, Mr. Shikhar
Rusia, Advs.

versus

GR INFRAPROJECTS LIMITED .....Respondent
Through: Mr. H. S. Chandhoke, Mr.
Pradyuman Dubey and Ms.
Astha Dhawan, Advs.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT(ORAL)
% 17.09.2026
1. The present appeal has been filed by the Appellant under
1
Section 37 of the Arbitration and Conciliation Act, 1996 , directed
against the order passed by the learned Arbitral Tribunal under
Section 17 of the Act whereby the learned Tribunal has restrained the
Appellant from invoking and encashing the Performance Bank
Guarantee furnished by the Respondent.

2. The learned Tribunal has, at the same time, directed the
ARB. A. (COMM.) 40/2026 Page 1 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

Respondent to keep the Performance Bank Guarantee alive during the
pendency of the arbitral proceedings.

3. The dispute arises out of an EPC (Engineering, Procurement,
and Construction) Agreement dated 21.08.2018 executed between the
parties for construction and maintenance of a 4-lane NH-56 bypass
forming part of the Varanasi Ring Road.

4. A Provisional Certificate was issued with effect from
21.10.2021 followed by a Completion Certificate with effect from
24.01.2022. Thereafter, recognition of the pavement was introduced.

5. However, dispute arose after the concerned highway, though
provisionally certified on 21.10.2021 and subsequently granted a
Completion Certificate with effect from 24.01.2022, allegedly began
showing excessive rutting and pavement deterioration from around
March 2022.

6. According to the Appellant, the deterioration was attributable to
the deficiency in construction and maintenance undertaken by
Respondent.

7. The controversy intensified when the Appellant issued the Final
Notice dated 28.03.2025 seeking approximately Rs.102.49 crores
towards the cost of rehabilitation and consequential damages
following which the Respondent invoked arbitration challenging its

1
“Act” hereinafter
ARB. A. (COMM.) 40/2026 Page 2 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

liability for the pavement failure and deficiency.

8. The Respondent disputed the aforesaid attribution. According to
Respondent the deviation was principally on account of excessive
overloading.

9. The Respondent also questioned the adequacy of the contractual
specification as, according to him, the same was inadequate, which led
to deterioration of the pavement and other deficiencies and sought to
attribute the pavement failure to practice beyond its contractual
responsibility.

10. The disputes were referred to arbitration.

11. During the pendency of the arbitration proceedings, the
Appellant sought to move the entire Performance Bank Guarantee
furnished by the Respondent under the Agreement.

12. Being aggrieved, the Respondent approached the learned
Tribunal under Section 17 of the Act.

13. By the impugned order, learned Tribunal restrained the
Appellant from invoking any specific Performance Bank Guarantee
and directed the Respondent to keep the guarantee alive during the
pendency of the arbitral proceedings.

14. The Appellant has challenged this order of the Arbitral Tribunal
ARB. A. (COMM.) 40/2026 Page 3 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

whereby they were restrained from invoking the Performance Bank
Guarantee.

15. Learned Counsel appearing for the Appellant submits that the
Performance Bank Guarantee is unconditional and irrevocable and is
payable on the Appellant’s first written demand, without demur and
without requiring proof of any breach under the underlying contract.

16. Reliance is also being placed on Clauses 7.3.1 and 26.1.4 of the
subject agreement which according to the Appellant expressly
contemplate appropriation of the Performance security upon default
by the contractor not withstanding the pendency of the arbitral
proceedings.

17. It is further submitted that the Respondent failed to undertake
the requisite strengthening and overlay works.

18. Consequently, the Appellant was constrained to engaged a new
agency under agreement dated 24.10.2025 to execute the work at the
Respondent’s risk and cost.

19. It is contented that the learned Arbitral Tribunal failed to take
into account the continuing expenditure being incurred by the
Appellant towards the rehabilitation of the highway as its obligation to
ensure safe and uninterrupted traffic.

20. Per contra , learned counsel for the Respondent, submits that
ARB. A. (COMM.) 40/2026 Page 4 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

invocation of the PBG was itself unjustified since, under Clause 7.3.1
of the EPCA, occurrence of a “Contractor’s Default” is a prerequisite
to invocation, whereas no such default under Clause 23.1 has been
established and the contractual conditions permitting risk and cost
remedial works under Clauses 14.7 and 17.4 are also stated not to
have been satisfied.

21. It is submitted that the pavement deterioration was not
attributable to defective construction or maintenance but arose
principally from persistent excessive overloading and allegedly
deficient traffic and pavement specifications prescribed under the
EPCA.

22. It is further contended that the Respondent had constructed the
Project Highway in accordance with the approved designs, and quality
requirements, which is evidenced by the issuance of the Provisional
and Completion Certificates.

23. Learned Counsel for the Respondent also alleges that the
strengthening and overlay works proposed by the Appellant materially
exceed the pavement thickness prescribed under the original EPCA
and therefore amount, in substance, to an upgradation/change of scope
rather than rectification of any Contractor’s Default.


24. It further relies upon the fact that the Appellant initially sought
extension of the PBG in September 2025 and thereafter invoked it on
08.10.2025, only shortly before expiry of the Defect Liability Period,
ARB. A. (COMM.) 40/2026 Page 5 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

contending that the invocation was coercive and inconsistent with the
earlier stated basis for seeking extension.

25. Lastly, it is submitted that no prejudice is caused to the
Appellant because the Performance Bank Guarantee has been
extended and is required to remain alive during the arbitration,
whereas immediate encashment, while the Appellant’s counterclaim
on the very same liability remains pending adjudication, would cause
irretrievable prejudice and unnecessary multiplicity of proceedings.

26. I have heard both sides and perused the record.

27. The only short issue which arises for consideration is whether
the Tribunal was justified in restraining encashment of the
unconditional and irrevocable Performance Bank Guarantee.

28. The law on the aspect of encashment of unconditional PBG is
settled.

29. The division bench of this court in Black Gold Resources
2
Private Limitada v. International Coal Ventures Pvt. Ltd. ,
recognised the exceptions that are; i) egregious fraud of which the
bank has notice and which vitiates the foundation of the guarantee,
and (ii) special equities where encashment would result in irretrievable
harm or injustice.


2
FAO(OS)(COMM) 211/2025
ARB. A. (COMM.) 40/2026 Page 6 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

30. In view of this Court, even assuming every allegation made by
the Respondent regarding deficient specifications etc. these merely
establish a substantive dispute concerning responsibility for pavement
failure.

31. According to this Court, the learned Arbitral Tribunal erred in
warranting restraint on invocation of the Performance Bank
Guarantee, as the guarantee was unconditional and irrevocable and
constituted an independent contract between the issuing bank and the
Appellant beneficiary.


32. The disputes raised by the Respondent regarding the cause of
pavement deterioration, are matters for adjudication in the pending
arbitration.

33. Such contractual disputes, even if substantial, do not by
themselves furnish a legal basis to interdict an unconditional bank
guarantee.

34. It is undisputed that the nature of the Performance Bank
Guarantee was unconditional.

35. The mere fact that the invocation of the Performance Bank
Guarantee may cause a financial burden upon the Respondent or that
the Respondent may ultimately succeed in the arbitration, cannot
constitute irreparable harm in the legal sense required to justify
interdiction of an unconditional bank guarantee.
ARB. A. (COMM.) 40/2026 Page 7 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

36. Indeed, the very purpose of performance security is to secure
the beneficiary against the financial consequences of a Contractor’s
default. The possibility of financial prejudice to the contractor upon
invocation is, therefore, the inherent consequence of the security and
cannot, in the absence of circumstances of an exceptional nature, be
elevated into a ground for issuing its invocation.

37. The fact that the Appellant continues to incur expenditure
towards rehabilitation of the highway also assumes significance.


38. While the Court is not required to determine, at this stage,
whether the Respondent is ultimately liable for such expenditure, the
existence of continuing expenditure and the Appellant’s obligation to
maintain the highway do not detract from its Contractor’s right to
invoke the Performance Bank Guarantee in accordance with its terms.

39. Consequently, the impugned order in so far as it restrained the
Appellant from invoking any specific Bank Guarantee and is
accordingly set aside.

40. The appeal is allowed in the aforesaid terms.

41. It is clarified that nothing contained in this order has expression
of opinion on the merits of the claims or counter-claims arising out of
the underlying agreement.

ARB. A. (COMM.) 40/2026 Page 8 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25

42. All such issues are left open for determination by the learned
Arbitrator in accordance with law.

OM PRAKASH SHUKLA, J
SEPTEMBER 17, 2026/at
ARB. A. (COMM.) 40/2026 Page 9 of 9


Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:30.09.2026
18:39:25