THE BOARD OF MAJOR PORT AUTHORITY FOR THE SHAMA PRASAD MOOKERJEE PORT, KOLKATA AND ANR. vs HARYANA MICRO AND SMALL ENETERPRISES FACILITATION COUNCIL (HMSEFC), PANCHKULA AND ORS.
- Court
- Calcutta High Court
IN THE HIGH COURT AT CALCUTTA
(Constitutional Writ Jurisdiction)
APPELLATE SIDE
Present:
The Hon’ble Justice Krishna Rao
W.P.A. No. 26463 of 2025
The Board of Major Port Authority for the Syama Prasad
Mookerjee Port, Kolkata & Anr.
Vs.
Haryana Micro and Small Enterprises Facilitation
Council (HMSEFC), Panchkula & Ors.
Mr. Kishore Datta, Sr. Adv.
Mr. Ashok Kumar Jena
....For the petitioners.
Hearing Concluded On : 22.09.2026
Judgment Delivered On : 05.10.2026
Judgment Uploaded On : 05.10.2026
Krishna Rao, J.:
1. The petitioners have filed the present writ petition challenging the
jurisdiction of the Haryana Micro and Small Enterprises Facilitation
2
Council (hereinafter referred to as “HMSEFC”) to make the reference
rd
and in issuing the letter dated 3 July, 2025 by the respondent no.3 on
behalf of the respondent no.2 by invoking Section 18(1) of the MSMED
Act, 2006.
th
2. The petitioners floated an E-tender notice on 18 August, 2021 for
engagement of architect for comprehensive architectural services
towards interior and exterior modification of Jawahar Tower Complex
and its allied areas at Haldia Township, HDC, Haldia and
comprehensive architectural services towards beautification of the road
from helipad crossing to Port House via Jawahar Tower at Haldia
Township and beautification of lock area along with erection of
electronic display board, HDC, Haldia.
th
3. The respondent no.4 submitted his bid on 8 September, 2021. After
th
submission of E-Tender, the respondent no. 4 by a letter dated 4
th
October, 2021 and 24 November, 2021, submitted additional required
th
information regarding technical bid. By a letter dated 6 April, 2022,
the respondent no. 4 extended the validity of his offer for the subject
th
work up to 30 April, 2022, retaining the terms and conditions of the
offer without any change.
st
4. The petitioners have issued work order to the respondent no. 4 on 21
April, 2022 for carrying out subject work at Rs. 12,50,000/- plus
applicable GST put to tender and without any variation in contract
nd
price. The respondent no.4 by his letter dated 2 May, 2022, informed
3
the petitioners that the advisor of the respondent no. 4 visited the site
th th
on 28 April, 2022 and 29 April, 2022 and requested for drawing and
document which are required for preparation of concept drawing. On
receipt of the documents, the respondent no. 4 submitted revised
th
concept of drawing including PPT presentation on 18 June, 2022. The
respondent no. 4 submitted only two options of floor plan layout of
Jawahar Tower floor and other items of scope of work were not
submitted as per Appendix 1 of the tender document.
5. Series of correspondences were made between the petitioners and the
th th
respondent no. 4 from 20 June, 2022 to 17 November, 2022 as to
the discussion of various issues to revise design of the main gate,
certain modification of drawing were suggested by the respondent no. 4
including internal sitting arrangements, internal detailing and layout of
individual floors of Jawahar Towers.
6. Mr. Kishore Datta, Learned Senior Advocate, representing the
petitioners submits that without resolving the issues as per suggestion
of the respondent no.4, the respondent no.4 submitted its first R.A Bill
for Rs. 2,95,000/- i.e. 20% of total contractual value of Rs. 12,50,000/-
th
plus applicable GST on 10 February, 2023. The petitioners have paid
the sum of Rs. 2,95,000/- as per the first R.A bill raised by the
respondent no.4 in terms of Clause 6.7.2 of the tender document.
7. Mr. Datta submits that the designs and drawings submitted by the
respondent no. 4 were reviewed and commented from the end of the
4
petitioners and modifications and corrections were carried out. The
respondent no. 4 has not submitted many deliverables as per
requirement of the tender but requested for release of payment. The
respondent no. 4 was again requested to comply with the provisions of
tender documents but the respondent no. 4 has not submitted many
deliverables as per requirement of tender but demanding payment.
th
8. Mr. Datta submits that the respondent no. 4 by an email dated 16
October, 2024, agreed to revise the deliverables and submit the
estimate within 45 to 60 days. Immediately after acceptance of the
scheme by the competent authority, the respondent no. 4 was informed
about the same. The respondent no. 4 was again requested to submit
detailed estimate and other deliverables as per the tender document
within four (4) months from the date of acceptance of the scheme. The
respondent no. 4 submitted only estimate of Lock Area that too
defective. The respondent no. 4 was requested to revise the estimate to
match with actual site otherwise it will not be possible to execute the
construction work by Haldia Dock Complex.
9. Mr. Datta submits that the respondent no. 4 denied to revise the
estimate and outrightly rejected to address the issues raised by the
petitioners. The petitioner no. 2 was compelled to issue show cause
th
notice to the respondent no. 4 dated 17 February, 2025. He submits
that till the receipt of the show cause notice, no further or final R.A bill
was submitted by the respondent no. 4 after receipt of the payment of
the first R.A bill. The respondent no. 4 submitted the reply to the show
5
cause notice by denying the allegations. On receipt of the show cause
reply, the petitioners do not find any justification to the demands
claimed by the respondent no. 4 and there is no reason to pay any
balance amount to the respondent no. 4.
10. Mr. Datta submits that as the reply submitted by the respondent no. 4
was not satisfactory and accordingly, the petitioner no. 2 has issued an
th
order of termination dated 25 March, 2025. The respondent no. 4 has
not challenged the order of termination before any forum. He submits
that there is no amount is due and payable by the petitioners to the
respondent no. 4 in terms of the contract or in terms of the provisions
of Section 17 and 18 of the MSMED Act, 2006.
11. Mr. Datta submits that the respondent no. 4 failed to execute the order
th
and having not challenged the order of termination dated 25 March,
2025 and has approached before the Micro and Small Enterprises
Facilitation Council, Panchkula, Haryana by filing an application under
sub-section (1) of Section 18 of the MSMED Act, 2006, claiming for a
sum of Rs. 18,40,800/-, though no amount is due and payable and no
final R.A bill was submitted prior to receiving of the show cause
notices, the application filed under Section 18(1) of the MSMED Act,
2006, is not maintainable.
12. Inspite of several notices, issued by the petitioners to the respondents
none appears on behalf of the respondents in the present writ petition.
6
13. Scope of work is defined in Clause 6.2 of Special Conditions of
Contract, which reads as follows:
“ 6.2 SCOPE OF WORK:
1. comprehensive architectural design which
includes architectural modifications of the
existing structures both internal and
external including creation of modular office,
air-conditioning, electrical modification and
decorative lighting arrangements including
firefighting system, landscaping and
development works like internal roads,
construction and modification of Main gate,
boundary wall, car and two wheeler
parking, fountain, rotary, sewage and
water supply system and allied works
inside Jawahar Tower premises. The
Jawahar Tower Complex consist of
Jawahar Tower, Connector building, Annex
Building, Garage with solar roof, Canteen
Building, Pond behind Annex building,
Internal roads, landscape areas etc.
2. Part-A: Beautification of the road from
Helipad crossing to Port House via Jawahar
Tower
The scope of work shall be preparation
of comprehensive architectural design
which includes architectural plan of
proposed face lifting and beautification of
the road from Helipad crossing to Port
House via Jawahar Tower, up-gradation of
the Boulevard, setting up of Planter Box on
either sides of the road, other allied
beautification work of the road, electrical
works, facilities for CCTV surveillance and
decorative lighting arrangements of
entrance gate building with security room,
Part-B: Beautification of Lock area along
with erection of electronic display board
The scope of work shall include
preparation of comprehensive architectural
design which includes architectural plan of
7
proposed beautification of Lock area along
with landscaping of the entire area both
working and non-working side of Lock
barrel, erection of electronic display board
at Lock area, structural design and
drawing, detailed estimate and
specifications.
All the items of works as detailed above shall have
to be carried out as per specification and as
detailed in the "Price Schedule".”
14. The private respondent filed a claim petition before the MSMED Council
under Section 18(1) of the MSMED Act, 2006. Section 18(1) of the
MSMED Act, 2006, reads as follows:
“ 18. (1) Notwithstanding anything contained
in any other law for the time being in force, any
party to a dispute may, with regard to any amount
due under section 17, make a reference to the Micro
and Small Enterprises Facilitation Council.”
15. Section 2(d) of the MSMED Act, 2006, defines buyer which reads as
follows:
“ 2(d) means whoever buys any goods or
receives any services from a supplier for
consideration” .
16. Section 2(f) of the MSMED Act, 2006, defines “goods” which means
every kind of movable property other than actionable claims and
money.
17. Section 2(n) of the MSMED Act, 2006, defines “supplier” which read as
follows:
“2(n) “supplier” means a micro or small
enterprise, which has filed a memorandum with the
8
authority referred to in sub-section (1) of section 8,
and includes,—
(i) the National Small Industries Corporation,
being a company, registered under the Companies
Act, 1956 (1 of 1956);
(ii) the Small Industries Development
Corporation of a State or a Union territory, by
whatever name called, being a company registered
under the Companies Act, 1956 (1 of 1956);
(iii) any company, co-operative society, trust or
a body, by whatever name called, registered or
constituted under any law for the time being in
force and engaged in selling goods produced by
micro or small enterprises and rendering services
which are provided by such enterprises.”
18. Section 15 of the MSMED Act, 2006, reads as follows:
“ 15. Liability of buyer to make payment.—
Where any supplier, supplies any goods or
renders any services to any buyer, the buyer shall
make payment therefor on or before the date
agreed upon between him and the supplier in
writing or, where there is no agreement in this
behalf, before the appointed day:
Provided that in no case the period agreed
upon between the supplier and the buyer in writing
shall exceed forty-five days from the day of
acceptance or the day of deemed acceptance.”
19. Section 17 of the MSMED Act, 2006, reads as follows:
“17. Recovery of amount due.—
For any goods supplied or services rendered
by the supplier, the buyer shall be liable to pay the
amount with interest thereon as provided under
section 16.”
9
20. The respondent no. 4 has not completed the work as per the scope of
work awarded to the respondent no. 4. The respondent no. 4 is not a
buyer and has not supplied any goods to the petitioners. There is no
claim raised by the respondent no. 4 against the petitioners. The
respondent no. 4 has not completed the work. Accordingly, the work
awarded to the respondent no. 4 was terminated. The order of
termination has not challenged by the respondent no. 4. The
respondent no. 4 has filed the claim before the MSMED Council
claiming an amount of Rs. 18,40,800/- but there is no due payable by
the petitioners as the respondent no. 4 has not raised any claim before
the petitioners before filing of an application under Section 18(1) of the
MSMED Act, 2006.
21. Considering the above, this Court finds that the petitioners have not
challenged the order of termination before any court of law and the
MSMED Council is not the authority to decide with regard to the
termination of the contract. The respondent no. 4 has not raised any
final R.A bill or any dues are payable against the respondent no. 4,
thus, the proceeding initiated by the respondent no. 4 against the
petitioners before the MSMED Council under Section 18(1) of the
MSMED Act, 2006, is set aside and quashed.
22. WPA No. 26463 of 2025 is thus allowed .
Parties shall be entitled to act on the basis of a server copy of the
Judgment placed on the official website of the Court.
10
Urgent Xerox certified photocopies of this judgment, if applied for,
be given to the parties upon compliance of the requisite formalities.
(Krishna Rao, J.)