M/S MVV SATYANARAYANA THROUGH ITS AUTHORISED SIGNATORY NIEL KAKASAHEB PATIL vs THE GENERAL MANAGER CENTRAL RAILWAY AND OTHERS

Court
Bombay High Court
Case type
Writ Petition
Decided on
27-03-2026
<div> <b>2026:BHC-AUG:13099-DB</b><br /> 606-26-WP.odt<br /> {1}<br /> IN THE HIGH COURT OF JUDICATURE AT BOMBAY<br /> BENCH AT AURANGABAD<br /> WRIT PETITION NO. 606 OF 2026<br /> M/s. MVV Satyanarayan<br /> A registered Partnership Firm,<br /> Through its Authorized Signatory,<br /> Mr. Niel S/o. Kakasaheb Patil,<br /> Age: 42 years, Occu.: Project Manager,<br /> R/o.C/o.6-1-136/3M, Flat No.101<br /> Meher Ratna Complex, Balram Colony,<br /> Padmarraonagar, Secunderabad-500025 … Petitioner<br /> VERSYUS<br /> 1. The General Manager,<br /> Central Railway, D.N. Road,<br /> Mumbai CSMT - 400001<br /> 2. The Chief Administrative Officer (Const.),<br /> Central Railway, New Administrative Building<br /> th<br /> 6 Floor, D.N. Road, <br /> Mumbai, CSMT – 400001.<br /> 3. The Chief Engineer/C/Central CSMT<br /> Chief Administrative Officer (c)’s Office<br /> Central Railway, New Administrative Building<br /> th<br /> 6 Floor, D.N. Road, <br /> Mumbai, CSMT -400001 … Respondents<br /> …...<br /> Mr. Prasadrao Vemulapalli, Advocate h/f Mr. A.A. Fulfagar,Advocate for <br /> Petitioner<br /> Mr. N.S. Salunke, Advocate for Respondents No.1 to 3<br /> …...<br /> CORAM : SMT. VIBHA KANKANWADI AND<br /> HITEN S. VENEGAVKAR, JJ.<br /> RESERVED ON : 13 MARCH, 2026<br /> PRONOUNCED ON : 27 MARCH,2026<br /><br /> 606-26-WP.odt<br /> {2}<br /> JUDGMENT/ORDER [Per Hiten S. Venegavkar, J.] :-<br /> 1. Rule. Rule is made returnable forthwith. With the consent of the<br /> parties, the petition is taken up for final disposal.<br /> 2. The present Writ Petition is filed under Article 226 of the<br /> Constitution of India by a partnership firm, M/s. MVV Satyanarayan,<br /> registered at Hyderabad, acting through its authorized signatory<br /> (hereinafter referred to as &#x27;the petitioner&#x27;), against Respondent No.1 –<br /> the General Manager, Central Railway; Respondent No.2 – the Chief<br /> Administrative Officer (Construction), Central Railway; and Respondent<br /> No.3 – the Chief Engineer (Construction)/Central, Chhatrapati Shivaji<br /> Maharaj Terminus, Mumbai (hereinafter collectively referred to as &#x27;the<br /> respondent railway authorities&#x27;).<br /> 3. By way of the present petition, the petitioner challenges the<br /> communication dated 13.11.2025 issued by Respondent No.3, whereby<br /> a decision was taken to part terminate the contract/agreement dated<br /> 17.08.2024, and further challenges the termination notice dated<br /> 02.12.2025, on the grounds that the said actions are arbitrary, illegal,<br /> and contrary to the principles of natural justice. The petitioner has also<br /> prayed for a direction permitting it to complete the balance work as per<br /> the petitioner&#x27;s letter dated 6th December 2025 and for a further<br /> direction to the respondents to release the payments for the work<br /> executed by the petitioner till date.<br /><br /> 606-26-WP.odt<br /> {3}<br /> 4. The factual matrix as pleaded by the petitioner in its memo of<br /> petition is as follows. The petitioner is a duly registered partnership firm<br /> based at Hyderabad and has been carrying on business since<br /> 03.09.1984. The petitioner claims to have been engaged in the field of<br /> civil contract works for Indian Railways, both Central and various State<br /> Governments and their instrumentalities, for over four and a half<br /> decades, with what it describes as an immaculate track record in<br /> meeting exact specifications and completing work within targeted<br /> timelines. In the process, it is stated that the petitioner has acquired<br /> specialized skills in the construction of bridges and other works for<br /> Indian Railways.<br /> 5. It is the case of the petitioner that Respondent No.2 had invited<br /> tenders for the construction of balance minor and major bridges at<br /> various places, construction of Road Under Bridges (RUBs) and drain<br /> works in connection with the Ahmednagar–Beed–Parli Vaidyanath New<br /> Broad Gauge Line Project, by issuing a Tender Notice dated 19.01.2024.<br /> The petitioner&#x27;s tender was accepted by Respondent No.3, who issued a<br /> Letter of Acceptance dated 30.04.2024. Thereafter, an agreement came<br /> to be executed between Respondent No.2 and the petitioner on<br /> 17.08.2024. As per the terms of the Letter of Acceptance, the initial<br /> value of the work was Rs.3,74,65,7193/- (Rupees Thirty Seven Crores<br /><br /> 606-26-WP.odt<br /> {4}<br /> Forty Six Lakhs Fifty Seven Thousand One Hundred and Ninety Three<br /> only). The work was to be completed within twelve calendar months<br /> from the date of the Letter of Acceptance, making the completion date<br /> on or before 29.04.2025. Upon completion of the work, the petitioner<br /> was also obligated to provide a maintenance period of twelve calendar<br /> months, including through the monsoon season, under the defect<br /> liability clause.<br /> 6. The petitioner further states that in terms of the Letter of<br /> Acceptance, the Earnest Money Deposit (EMD) of Rs.20,66,500/-<br /> submitted by the petitioner along with the tender document was to be<br /> retained by the respondents as part payment of security deposit until<br /> the liability period was over. In addition, the respondents were entitled<br /> to deduct and recover an amount equivalent to 6% of each running bill<br /> until the amount so deducted and recovered reached 5% of the contract<br /> value towards the balance security deposit. The petitioner contends<br /> that, as a consequence of these deductions, the respondents hold a sum<br /> of approximately Rs.2.66 crores belonging to the petitioner. The<br /> petitioner has also furnished a Bank Guarantee towards a Performance<br /> Guarantee for an amount of Rs.1,87,32,859.67 issued by the Bank of<br /> Maharashtra, the validity of which, according to the respondents, has<br /> been extended up to 25.06.2026.<br /><br /> 606-26-WP.odt<br /> {5}<br /> 7. The petitioner submits that upon receipt of the Letter of<br /> Acceptance, it mobilized and deployed the necessary men, machinery,<br /> and material to the site and commenced work with due earnestness so<br /> as to complete it within the agreement period. It is further submitted<br /> that during the execution of the work, due to prevailing site conditions,<br /> certain additional quantities and extra items became necessary, on<br /> account of which two supplemental agreements were entered into<br /> between the parties, whereby the value of the work was increased to<br /> Rs.54,85,03,233.53/- (Rupees Fifty Four Crores Eighty Five Lakhs Three<br /> Thousand Two Hundred and Thirty Three and paise Fifty Three),<br /> representing an increase of approximately 46 to 50% over the original<br /> contract value. Consequent upon the increase in quantities and the<br /> change in the scope of work, coupled with prevailing site conditions, the<br /> completion period was also extended from time to time without the<br /> imposition of any penalty, and the agreement was stated to be valid<br /> through 31.03.2026. The petitioner contends that the extension of time<br /> without any penalty is itself indicative of the fact that the delay in<br /> completion of work was not attributable to the petitioner but was on<br /> account of factors beyond its control.<br /> 8. As per the case of the petitioner, work to the tune of<br /> approximately Rs.46 crores has been executed, out of which the<br /><br /> 606-26-WP.odt<br /> {6}<br /> petitioner has been paid an amount of Rs.38,95,69,185/- and that work<br /> valued at approximately Rs.7.5 crores is yet to be measured, recorded<br /> and paid for. The petitioner further contends that during the execution<br /> of work, without the consent of the petitioner and without any formal<br /> amendment to the agreement, certain works forming part of the scope<br /> of work under the agreement dated 17.08.2024 were awarded by the<br /> respondents to other agencies. Some of these offloaded works,<br /> according to the petitioner, were crucial for the completion of the<br /> petitioner&#x27;s own scope, including the laying of the deck slab on the<br /> major bridge. While the work was in progress, the petitioner alleges<br /> that for extraneous reasons, Respondent No.3 issued a series of show-<br /> cause and adverse notices in order to arm-twist and compel the<br /> petitioner not to raise complaints about the unauthorized offloading of<br /> works to what the petitioner describes as &#x27;blue-eyed boys&#x27;, without<br /> entering into formal agreements with those agencies.<br /> 9. It is the case of the petitioner that without regard to the<br /> prevailing site conditions and the progress of work, a communication<br /> dated 13.11.2025 was issued by Respondent No.3 through which the<br /> administration took a decision to &#x27;part terminate&#x27; the work awarded to<br /> the petitioner, which the petitioner describes as unheard of in the annals<br /> of contract management. A Seven Days&#x27; Notice was issued on<br /><br /> 606-26-WP.odt<br /> {7}<br /> 19.11.2025, followed by a 48-Hours&#x27; notice on 27.11.2025, and finally<br /> the agreement was terminated by way of a Termination Notice dated<br /> 02.12.2025. The petitioner submits that the managing partner was out<br /> of the country at the relevant time and returned only on 29.11.2025,<br /> which is stated to be one of the reasons for not replying to the show-<br /> cause notices. Feeling aggrieved by what it terms an illegal termination,<br /> the petitioner has approached this Court invoking its jurisdiction under<br /> Article 226 of the Constitution of India.<br /> 10. The learned Advocate appearing on behalf of the petitioner has<br /> advanced the following arguments in support of the petition. It is firstly<br /> argued that the reasons assigned in the communications dated<br /> 13.11.2025 and 02.12.2025 are absolutely contrary to the actual site<br /> conditions and hence cannot be sustained. It is further argued that as on<br /> 13.11.2025, the petitioner still had more than 140 days remaining to<br /> complete the balance work, and even as on the date of issuance of the<br /> final termination notice on 02.12.2025, there were more than 100 days<br /> remaining, which made the action of part termination and eventual<br /> termination completely unwarranted and deserving of interference by<br /> this Court. It is also submitted that since certain works were offloaded<br /> by the respondents to other agencies without the consent of the<br /> petitioner, the failure of those other agencies to complete the offloaded<br /> work cannot be fastened as a liability upon the petitioner.<br /><br /> 606-26-WP.odt<br /> {8}<br /> 11. The learned Advocate for the petitioner further argues that the<br /> allegations made in the letters dated 13.11.2025 and 02.12.2025 are<br /> trivial in nature and that most of the works were actually in progress at<br /> the relevant point of time, and hence did not warrant either part<br /> termination or full termination. He argues with vehemence that both<br /> the communications dated 13.11.2025 and 02.12.2025 were issued in<br /> gross violation of the principles of natural justice as the petitioner was<br /> never afforded an adequate opportunity of being heard before the<br /> impugned decisions were taken. He contends that the petitioner had<br /> sufficient time remaining to complete the contracted work within the<br /> extended period of validity of the agreement, namely, 31.03.2026, and<br /> therefore the impugned communications are bad in law. He further<br /> argues that some of the works offloaded to third agencies were a pre-<br /> condition for the petitioner to take up and complete its allotted work,<br /> and therefore, the non-completion of the offloaded work by those third<br /> agencies cannot be attributed to the petitioner, nor can the petitioner be<br /> held liable for any resultant delay. He submits that even at the time of<br /> filing of the present petition, sufficient time remained for the balance<br /> contract work to be completed, and if permitted by this Court, the<br /> petitioner is ready and willing to complete the work within the balance<br /> days. In support of this submission, he draws the attention of this Court<br /> to the letter dated 06.12.2025 addressed by the petitioner to the<br /><br /> 606-26-WP.odt<br /> {9}<br /> respondent authorities expressing its desire to complete the work within<br /> the balance period.<br /> 12. On the question of maintainability of the writ petition, the<br /> learned Advocate for the petitioner acknowledges that the contract<br /> agreement contains an arbitration clause but argues that the reliefs<br /> sought in the present petition are declaratory and consequential in<br /> nature, and if relegated to arbitration, it would consume substantial<br /> time, during which the material already present at the site would get<br /> damaged and rendered unusable, thereby causing irreparable harm to<br /> the petitioner. He also argues that the primary challenge in the present<br /> petition is to the termination order on the grounds of violation of the<br /> principles of natural justice, which is a public law remedy and is<br /> cognizable by this Court under Article 226 of the Constitution. In<br /> support of the maintainability of the writ petition, the learned Advocate<br /> places heavy reliance on the judgment of the Hon&#x27;ble Supreme Court of<br /> India in the case of Union of India &amp; Ors. v. Tantia Construction Pvt.<br /> Ltd., (2011) 5 SCC 697, which is also a railway contract case, wherein<br /> the Hon&#x27;ble Apex Court has held that an alternative remedy, including<br /> the existence of an arbitration clause in a contract, is not an absolute<br /> bar to the invocation of the writ jurisdiction of the High Court or the<br /> Supreme Court, and that such a petition is maintainable.<br /><br /> 606-26-WP.odt<br /> {10}<br /> 13. The learned Advocate appearing for the respondent railway<br /> authorities has advanced arguments in support of the action taken and<br /> in support of the impugned orders. He submits that the termination<br /> order dated 02.12.2025 has been issued strictly in accordance with the<br /> terms and conditions of the contract agreement and after duly following<br /> the process of law as contemplated therein. He states that the<br /> respondents had invited tenders for the completion of the subject work<br /> and, after accepting the tender of the petitioner, issued a Letter of<br /> Acceptance as per standard procedure and thereafter executed the<br /> contract agreement in accordance with the General Conditions of<br /> Contract (GCC). The completion period, maintenance period, retention<br /> of EMD amount, deduction of security deposit, and the performance<br /> guarantee are all strictly in terms of the contract agreement and the<br /> Letter of Acceptance dated 30.04.2024. He further states that the<br /> validity of the performance guarantee in the form of a Bank Guarantee<br /> of the Bank of Maharashtra has been extended up to 25.06.2026.<br /> 14. The learned Advocate for the respondents further submits that it<br /> was the sole and primary responsibility of the petitioner to deploy the<br /> requisite manpower, machinery, and material at the site for<br /> commencement and continuous progress of the work. He contends that<br /> the respondents wrote to the petitioner on several occasions pointing<br /><br /> 606-26-WP.odt<br /> {11}<br /> out the slow progress of work and the non-deployment of requisite<br /> manpower at the site. Regular meetings were held with the petitioner,<br /> and the minutes of meetings dated 06.01.2025 and 13.06.2025 record<br /> that target dates for completion of various works were provided to the<br /> petitioner, but the same were never adhered to or achieved. Owing to<br /> site conditions, additional quantities and additional items were<br /> incorporated into the existing scope of work in agreement with the<br /> petitioner, and variations were processed accordingly, for which the<br /> petitioner also submitted numbered claim certificates. The first<br /> extension of time was granted to the petitioner up to 30.09.2025, at the<br /> request of the petitioner vide its communication dated 28.04.2025. A<br /> second extension was thereafter granted up to 31.03.2026, again on the<br /> specific request of the petitioner. Thus, according to the respondents,<br /> the original timeline of twelve months has been extended by a further<br /> eleven months, representing an extension of approximately 91% of the<br /> original completion period, while the variation in the original contract<br /> amount is approximately 46%.<br /> 15. The learned Advocate for the respondents submits that even<br /> after the grant of extensions, the petitioner was unable to complete the<br /> work, and after reviewing the progress, it was found that there was no<br /> activity at the site for the casting of the deck slab. Accordingly, a Seven<br /><br /> 606-26-WP.odt<br /> {12}<br /> Days&#x27; Notice was issued to the petitioner on 19.11.2025. Even after the<br /> said notice, the petitioner failed to mobilise the necessary resources. A<br /> 48-Hours&#x27; Notice was therefore issued on 27.11.2025, but there was still<br /> no improvement. The part termination notice dated 13th November<br /> 2025 was issued in accordance with Annexure XIII of the contract<br /> agreement, due to the urgency of completing the work before a<br /> scheduled inspection by the Commissioner of Railway Safety (CRS), and<br /> the poor performance and planning on the part of the petitioner had<br /> resulted in the delay of the CRS inspection by four months. The<br /> termination of the agreement on 02.12.2025 was accordingly a<br /> culmination of a long process during which the petitioner was given<br /> ample opportunity but repeatedly failed to comply.<br /> 16. With regard to the payments claimed by the petitioner, the<br /> learned Advocate for the respondents submits that the amounts claimed<br /> in the petition are incorrect, as the petitioner has not submitted the<br /> details of measurements along with the technical site registers duly<br /> signed by the railway officials in respect of the balance work.<br /> Measurements for the balance work have not been initiated by the<br /> petitioner till date, and therefore the payments in respect of such work<br /> remain outstanding solely on that account. He further submits that the<br /> action taken by the respondents is in strict accordance with the terms<br /><br /> 606-26-WP.odt<br /> {13}<br /> and conditions of the contract, which expressly reserves the right of the<br /> railway to alter, omit, or get executed any part of the work through<br /> other agencies.<br /> 17. On the question of maintainability of the writ petition, the<br /> learned Advocate for the respondents strongly argues that, in view of<br /> Clauses 63 and 64 of the General Conditions of Contract, all disputes<br /> between the parties are required to be resolved by way of arbitration.<br /> He submits that once the parties have consciously adopted an<br /> arbitration mechanism for resolution of disputes arising out of the<br /> contract, there is no warrant for invoking the extraordinary jurisdiction<br /> of this Court under Article 226 of the Constitution of India. He further<br /> submits that the issues raised by the petitioner are essentially disputed<br /> questions of fact, requiring the recording of evidence and proof, which<br /> is a function that cannot be performed in a writ petition but can only be<br /> adjudicated before an arbitrator. In support of his contentions, he relies<br /> upon the judgment of the Hon&#x27;ble Supreme Court in (i) State of U.P. &amp;<br /> Ors. v. Bridge &amp; Roof Co. (India) Ltd., (1996) 6 SCC 22, (ii) Kerala<br /> State Electricity Board &amp; Anr. v. Kurien E. Kalathil &amp; Ors., (2000) 6 SCC<br /> 293 and (iii) Joshi Technologies International Inc. v. Union of India &amp;<br /> Ors., (2015) 7 SCC 728.<br /><br /> 606-26-WP.odt<br /> {14}<br /> 18. We have heard the learned Advocates for both the parties at<br /> length and have carefully perused the material on record, including the<br /> documents annexed to the petition and the reply filed by the<br /> respondents, and have given our earnest consideration to the citations<br /> relied upon by both sides. We are now called upon to adjudicate upon<br /> the maintainability of the present writ petition and the merits of the<br /> challenge mounted by the petitioner against the impugned orders.<br /> 19. Before we advert to the facts of the case, it would be apposite to<br /> set out the legal framework governing the invocation of writ jurisdiction<br /> by a High Court under Article 226 of the Constitution in matters arising<br /> out of contractual disputes between a contractor and a State or its<br /> instrumentality. The law on this aspect is well-settled through a catena<br /> of pronouncements of the Hon&#x27;ble Supreme Court of India, and the<br /> principles emerging therefrom may be briefly summarised. The power<br /> of this Court under Article 226 of the Constitution is undoubtedly<br /> plenary and wide. It is also well settled that the existence of an<br /> alternative remedy, including an arbitration clause in a contract, does<br /> not absolutely and invariably foreclose the exercise of writ jurisdiction<br /> by a High Court. At the same time, however, it is equally well settled<br /> that writ jurisdiction under Article 226 is discretionary in nature, and<br /> the exercise of such extraordinary jurisdiction has to be calibrated with<br /><br /> 606-26-WP.odt<br /> {15}<br /> care and caution, having regard to the nature of the dispute, the<br /> availability of an efficacious alternative remedy, and the question of<br /> whether the dispute essentially involves contested questions of fact that<br /> cannot be adjudicated in writ proceedings.<br /> 20. The Hon&#x27;ble Supreme Court, in State of U.P. &amp; Ors. v. Bridge &amp;<br /> Roof Co. (India) Ltd. (supra), laid down the foundational principles<br /> governing this field in clear and emphatic terms. In that case, the Apex<br /> Court held that a contract between the parties is in the realm of private<br /> law and is governed by the provisions of the Contract Act. Any dispute<br /> relating to the interpretation of the terms and conditions of such a<br /> contract cannot be agitated, and could not have been agitated, in a writ<br /> petition; that is a matter either for arbitration, as provided by the<br /> contract, or for the civil court, as the case may be. The Court further<br /> held that where the contract itself contains a clause providing for<br /> settlement of disputes by reference to arbitration, there is no reason<br /> why the parties should not follow and adopt that remedy, and that the<br /> existence of an effective alternative remedy, in such case provided in the<br /> contract itself, is a good ground for the Court to decline to exercise its<br /> extraordinary jurisdiction under Article 226 of the Constitution of India.<br /> The Hon’ble Apex Court pointedly observed that Article 226 of the<br /> Constitution of India was not meant to supplant the existing remedies<br /><br /> 606-26-WP.odt<br /> {16}<br /> at law but only to supplement them in certain well-recognized<br /> situations.<br /> 21. The principle enunciated in Bridge &amp; Roof Co. (supra) was<br /> affirmed and elaborated by the Hon&#x27;ble Supreme Court in Kerala State<br /> Electricity Board &amp; Anr. v. Kurien E. Kalathil &amp; Ors. (supra), wherein the<br /> Apex Court, speaking through a Bench of two learned Judges, reiterated<br /> with clarity that every act of a statutory body need not necessarily<br /> involve an exercise of statutory power, and that statutory bodies, like<br /> private parties, have the power to contract or deal with property, and<br /> such activities may not raise any issue of public law. The Court held that<br /> the contract between the parties therein was in the realm of private law<br /> and not a statutory contract, and that disputes relating to the<br /> interpretation of the terms and conditions of such a contract could not<br /> have been agitated in a petition under Article 226 of the Constitution. It<br /> was further held that whether any amount is due to the contractor and,<br /> if so, how much, and whether the refusal of the authority to pay it is<br /> justified or not, are not matters which could have been agitated and<br /> decided in a writ petition. The Court emphasized that the proper forum<br /> for such adjudication is a civil court or, where the contract provides for<br /> it, arbitration.<br /><br /> 606-26-WP.odt<br /> {17}<br /> 22. The Hon&#x27;ble Supreme Court in Joshi Technologies International<br /> Inc. v. Union of India &amp; Ors., reported in (2015) 7 SCC 728, further<br /> clarified the position by holding that the law has developed through a<br /> catena of judgments, and from a reading of those judgments it emerges<br /> that in pure contractual matters, the extraordinary remedy of writ<br /> under Article 226 or Article 32 of the Constitution cannot be invoked.<br /> The Court held that such a remedy is available only in a limited sphere,<br /> namely, when the non-Government contracting party is able to<br /> demonstrate that it is a public law remedy which it seeks to invoke, as<br /> contra-distinguished from the private law remedy simpliciter available<br /> under the contract. This principle constitutes a clear and authoritative<br /> statement of the law on the interface between writ jurisdiction and<br /> contractual disputes.<br /> 23. We have given careful consideration to the judgment of the<br /> Hon&#x27;ble Apex Court in Union of India &amp; Ors. v. Tantia Construction Pvt.<br /> Ltd. (supra), upon which the learned Advocate for the petitioner has<br /> placed heavy reliance. The Hon’ble Apex Court, in that case, upheld the<br /> maintainability of the writ petition filed by a railway contractor<br /> challenging an order requiring it to execute enlarged and altered work<br /> at the same rates as originally tendered, and held that the existence of<br /> an arbitration clause in the agreement does not absolutely bar the<br /><br /> 606-26-WP.odt<br /> {18}<br /> parties from invoking the writ jurisdiction of the High Court or the<br /> Supreme Court. The Court reiterated the rule that the exclusion of writ<br /> jurisdiction on account of an alternative remedy is a rule of discretion<br /> and not one of compulsion. We have no quarrel with the aforesaid legal<br /> proposition. However, the Tantia Construction judgment must be read<br /> in its correct context. In that case, the dispute was not merely a factual<br /> dispute regarding slow progress or breach of contractual obligations;<br /> rather, it involved a fundamental question of whether the Railway was<br /> entitled to require the contractor to execute a substantially and<br /> qualitatively altered scope of work, amounting in substance to a new<br /> project, at the rates originally tendered, which raised a significant<br /> public law issue pertaining to the exercise of contractual power<br /> arbitrarily and beyond the four corners of the agreement. The factual<br /> matrix of the present case is materially different, as we shall presently<br /> demonstrate.<br /> 24. Before examining whether the disputes in the present case are<br /> essentially factual in nature, we must address the principal ground<br /> urged by the petitioner, namely, the alleged violation of the principles of<br /> natural justice. The petitioner&#x27;s learned Advocate has vehemently<br /> contended that the impugned communications dated 13.11.2025 and<br /> 02.12.2025 were issued without affording the petitioner any<br /><br /> 606-26-WP.odt<br /> {19}<br /> opportunity of being heard. We find this submission to be factually<br /> unsustainable in the present case. From the record before us, it is<br /> evident that the respondent railway authorities had issued multiple<br /> show-cause notices and adverse progress reports to the petitioner over a<br /> prolonged period, spanning several months prior to the issuance of the<br /> part termination notice. The minutes of meetings held on 06.01.2025<br /> and 13.06.2025, and the communications between the parties, establish<br /> beyond any doubt that the petitioner was made fully aware of the<br /> concerns of the respondents regarding the slow progress of the work<br /> and the non-deployment of adequate manpower and machinery at the<br /> site. The petitioner was not only present at those meetings but was also<br /> given specific target dates for completion of various items of work.<br /> Seven Days&#x27; Notices were issued to the petitioner on at least five<br /> separate occasions and 48-Hours&#x27; Notices were also issued repeatedly,<br /> all of which were received by the petitioner.<br /> 25. In this background, The work assigned to the petitioner was of<br /> national importance, and therefore completion of the said project<br /> within time was absolutely necessary for the public at large and also for<br /> the nation. The respondents, being public authorities involved in<br /> essential services like Railways, have a primary duty towards the<br /> citizens of this nation, and therefore the targeted completion of the<br /><br /> 606-26-WP.odt<br /> {20}<br /> work was not only necessary but rather mandatory. The record shows<br /> that the respondent authorities have constantly raised their concern<br /> with the petitioner regarding the slow progress of the work and have,<br /> from time to time, issued instructions and directions to the petitioner to<br /> expedite the work and complete the same within the allotted time as<br /> well as the extended time. It will, therefore, be incorrect to characterize<br /> the impugned action as one taken behind the back of the petitioner<br /> without any opportunity of being heard. The communication dated<br /> 13.11.2025 and the subsequent termination notice dated 02.12.2025<br /> were not the first communications from the respondents; they were the<br /> culmination of a long chain of notices, meetings, and communications,<br /> all of which afforded the petitioner more than adequate opportunity to<br /> explain its position, mobilize resources, and remedy the defaults<br /> complained of. The submission of the petitioner that its managing<br /> partner was abroad and therefore could not respond is, in our<br /> considered view, an afterthought that cannot be elevated to the level of<br /> a valid legal ground of natural justice violation. The petitioner is a<br /> partnership firm, capable in law of acting through its authorized<br /> representative or any other partner, and the absence of the managing<br /> partner from the country does not create a legal vacuum that would<br /> nullify the actions taken by the respondents after following the due<br /> contractual process. The principles of natural justice do not require the<br /><br /> 606-26-WP.odt<br /> {21}<br /> respondents to wait indefinitely for a response or to maintain the status<br /> quo until such time as it suits a contracting party to engage with the<br /> notices issued to it.<br /> 26. Turning now to the crux of the matter, we are of the considered<br /> view that the disputes sought to be agitated in the present writ petition<br /> are essentially and overwhelmingly disputes involving contested<br /> questions of fact. The petitioner alleges, on one hand, that the works<br /> were in progress and that the extension of time without penalty is<br /> indicative of the absence of any default on its part. The respondents, on<br /> the other hand, have specifically averred that the progress of work was<br /> consistently unsatisfactory, that the petitioner repeatedly failed to<br /> adhere to contractual milestones, that no activity was observed at the<br /> site for the casting of the deck slab despite repeated notices, and that<br /> the Commissioner of Railway Safety&#x27;s inspection was delayed by four<br /> months on account of the petitioner&#x27;s poor performance and planning.<br /> The petitioner has alleged that certain works were offloaded to other<br /> agencies without its consent, which prevented it from completing its<br /> own work. The respondents have denied that such offloading was<br /> improper or beyond the scope of the contractual power reserved to the<br /> railway. The petitioner has claimed that a sum of approximately Rs.7.5<br /> crores is yet to be paid for work already executed, while the<br /><br /> 606-26-WP.odt<br /> {22}<br /> respondents have submitted that the measurements and technical<br /> documentation required to process payment for the balance work have<br /> not been submitted by the petitioner.<br /> 27. It is manifest that each and every one of these contentions raises<br /> a disputed question of fact that cannot be examined, evaluated, or<br /> adjudicated in a proceeding under Article 226 of the Constitution. A<br /> writ court does not record evidence, examine witnesses, or scrutinize<br /> technical specifications and site records. The determination of whether<br /> the work was progressing satisfactorily or not, whether the offloading of<br /> certain works was in accordance with or contrary to the terms of the<br /> contract, whether the petitioner is entitled to additional time for<br /> completion, whether any amount is due and payable to the petitioner,<br /> whether the default in completion is attributable to the petitioner or to<br /> other agencies appointed by the respondents, and whether the<br /> termination was for bona fide reasons related to public interest and the<br /> operational requirements of the railway — all of these are questions<br /> that can only be resolved through a detailed examination of evidence,<br /> including technical site records, minutes of meetings, correspondence<br /> between the parties, measurement books, and the opinions of experts, if<br /> any. The appropriate forum for such an exercise is the Arbitral Tribunal<br /> as specifically agreed upon by the parties under Clauses 63 and 64 of<br /> the General Conditions of Contract.<br /><br /> 606-26-WP.odt<br /> {23}<br /> 28. We are also of the view that the petitioner has failed to<br /> demonstrate the existence of any element of public law that would<br /> justify the exercise of the extraordinary jurisdiction of this Court under<br /> Article 226 of the Constitution. The rights sought to be enforced by the<br /> petitioner are purely contractual rights arising from the agreement<br /> dated 17.08.2024. The petitioner&#x27;s grievance, at its core, is that the<br /> respondent authorities terminated the contract before the expiry of the<br /> extended completion period, and that the reasons given for termination<br /> are factually incorrect or insufficient. This is a private law dispute<br /> arising in the realm of contract and is not a matter involving the<br /> violation of any fundamental right or any statutory right that requires<br /> the intervention of this Court under Article 226. As the Hon&#x27;ble<br /> Supreme Court observed in Kerala State Electricity Board v. Kurien E.<br /> Kalathil (supra), not every action of a statutory body or instrumentality<br /> of the State raises a public law issue, and where the dispute is purely in<br /> the domain of private law, the appropriate remedy is before a civil court<br /> or an arbitrator, as the case may be.<br /> 29. We have also considered the submission of the petitioner&#x27;s<br /> learned Advocate that if the petitioner is relegated to arbitration, the<br /> material at the site would get damaged and become unusable, thus<br /> causing irreparable harm. While we are sensitive to this concern, we<br /><br /> 606-26-WP.odt<br /> {24}<br /> find that this submission does not, by itself, create a ground for<br /> invoking the writ jurisdiction of this Court. The Arbitration and<br /> Conciliation Act, 1996 itself provides adequate mechanisms for<br /> obtaining interim relief, including under Section 9 of the Act, where a<br /> party may approach the competent court for interim measures of<br /> protection pending arbitration proceedings. The petitioner is at liberty<br /> to avail of those statutory remedies. The availability of interim relief<br /> through the arbitration framework further reinforces our conclusion<br /> that the present writ petition is not the appropriate vehicle for the<br /> adjudication of the petitioner&#x27;s grievances.<br /> 30. Having regard to the foregoing analysis, we are of the<br /> considered view that the present writ petition is not maintainable for<br /> the following principal reasons. First, the disputes raised in the petition<br /> are essentially disputes involving contested questions of fact arising out<br /> of the execution of a works contract, which are incapable of<br /> adjudication in a writ proceeding and must be resolved through the<br /> mechanism of arbitration as contractually agreed upon between the<br /> parties. Second, the petitioner has failed to make out any case of<br /> violation of the principles of natural justice, inasmuch as the respondent<br /> railway authorities had issued multiple notices, held numerous<br /> meetings, and provided the petitioner with ample and repeated<br /><br /> 606-26-WP.odt<br /> {25}<br /> opportunities over a prolonged period to respond, mobilize resources,<br /> and remedy the alleged defaults before issuing the impugned<br /> communications. Third, the petitioner has not demonstrated the<br /> infringement of any fundamental right or statutory right that would<br /> attract the extraordinary jurisdiction of this Court under Article 226 of<br /> the Constitution. Fourth, both parties, having agreed to the mechanism<br /> of arbitration under Clauses 63 and 64 of the General Conditions of<br /> Contract for the resolution of all disputes arising out of the contract, it<br /> would be wholly inappropriate for this Court to permit a party to bypass<br /> the agreed dispute resolution mechanism and invoke the extraordinary<br /> jurisdiction of the writ court to adjudicate upon essentially contractual<br /> grievances. Fifth, the law laid down by the Hon&#x27;ble Supreme Court in<br /> State of U.P. v. Bridge &amp; Roof Co. (India) Ltd. (supra), and Kerala State<br /> Electricity Board v. Kurien E. Kalathil (supra), read together with the<br /> principles enunciated in Joshi Technologies International Inc. v. Union<br /> of India (supra), fully supports the conclusion that this Court ought to<br /> exercise its discretion to decline to entertain the petition and to relegate<br /> the parties to the arbitral forum agreed upon by them.<br /> 31. The judgment in Union of India v. Tantia Construction Pvt. Ltd.<br /> (supra) does not assist the petitioner in the facts of the present case. As<br /> we have already observed, the factual matrix of Tantia Construction<br /><br /> 606-26-WP.odt<br /> {26}<br /> involved a qualitatively different and more fundamental challenge,<br /> namely, the question of the railway&#x27;s entitlement to alter the entire<br /> design of a project and compel the contractor to execute a substantially<br /> new and different project at the original tendered rates, which raised a<br /> pure public law issue of arbitrary exercise of statutory power. In the<br /> present case, in contrast, the petitioner&#x27;s challenge is to the termination<br /> of a contract on the ground of slow progress and non-completion, which<br /> is a matter squarely within the domain of contract law and is subject to<br /> the arbitration clause agreed upon by the parties. The principle laid<br /> down in Tantia Construction (supra) that an alternative remedy is not<br /> an absolute bar to the exercise of writ jurisdiction is a rule of discretion,<br /> and in the exercise of that discretion, having regard to the nature of the<br /> dispute, the adequacy of the alternative remedy, and the essentially<br /> factual character of the controversy, we decline to entertain this<br /> petition.<br /> 32. Before parting with this order, we deem it appropriate to record<br /> that by dismissing the present writ petition, we have not adjudicated<br /> upon the merits of the dispute between the parties, and our<br /> observations on the facts contained in this judgment are solely for the<br /> purpose of determining the maintainability of the petition and shall not<br /> prejudice either party in any future proceedings. The petitioner shall be<br /> at liberty to raise all its claims and contentions, including the legality of<br /><br /> 606-26-WP.odt<br /> {27}<br /> the termination, the question of payments due, the alleged offloading of<br /> works without consent, and any other grievance, before the Arbitral<br /> Tribunal constituted in accordance with the provisions of the General<br /> Conditions of Contract. It is further clarified that the security deposit,<br /> the EMD amount retained by the respondents, and the Bank Guarantee<br /> submitted by the petitioner shall continue to be maintained and shall<br /> not be forfeited, encashed, or acted upon by the respondents pending<br /> the initiation and conclusion of the arbitration proceedings, for a period<br /> of twelve weeks from today, to enable the petitioner to initiate<br /> arbitration proceedings.<br /> 33. In view of the above, the Writ Petition stands dismissed. Rule<br /> discharged. There shall be no order as to costs. <br /> 34. The observations made herein above shall not prejudice the<br /> rights of either party before the Arbitral Tribunal. <br /> 35. The protection granted by way of interim order, if any, subsisting<br /> as on date shall stand vacated subject to the aforesaid direction with<br /> respect to the security deposit, EMD, and Bank Guarantee. <br /> [ HITEN S. VENEGAVKAR ] [ SMT. VIBHA KANKANWADI ]<br /> JUDGE JUDGE<br /> S P Rane</div>