Ms. Sai Industry Through Sarita Sharma vs The State Of Madhya Pradesh
- Court
- Madhya Pradesh High Court
- Decided on
- 09-03-2026
NEUTRAL CITATION NO. 2026:MPHC-IND:6234
1 W.P. No. 7864/2026
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE
BEFORE
HON'BLE SHRI JUSTICE JAI KUMAR PILLAI
WRIT PETITION No. 7864 of 2026
M/s SAI Industries, Khargone M.P.
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance :
Shri Savya Sachi Saxena – Advocate for the petitioner.
Shri Ayushman Choudhary - Government Advocate for the
respondents/State.
Reserved on : 27/02/2026
Post on : 09/03/2026
__________________________________________________
ORDER
Signature Not Verified
Signed by: JAGADISHAN
AIYER
Signing time: 09-03-2026
17:45:51
NEUTRAL CITATION NO. 2026:MPHC-IND:6234
2 W.P. No. 7864/2026
By way of the present Writ Petition preferred under Article
226 of the Constitution of India, the petitioner invokes the
extraordinary writ jurisdiction of this Court to challenge the alleged
arbitrary and high-handed action of respondent No.3 in forcibly
dispossessing the petitioner from its Industrial Land. The petitioner
specifically prays for the issuance of an appropriate writ, order, or
direction for the quashment of the impugned notice dated
17.02.2026 issued by respondent No.3.
2. The petitioner is a Proprietorship Concern carrying on
Industrial Activities. The respondent department allotted industrial
land bearing part of Plot Nos.32 and 45, situated at Industrial Area,
Indore Road, Barwaha, District Khargone (M.P.) to the petitioner
vide a registered Lease-Deed dated 09.06.2009 for a period of 30
years (valid up to 08.06.2039). The adjoining portion of land,
forming another part of Plot Nos.32 and 45 was separately allotted
to a distinct unit namely, M/s Ramkrishna Industries. The
respondent Authorities initiated lease cancellation proceedings
against M/s Ramkrishna Industries and allegedly prepared a
Panchnama on 08.05.2025 for taking possession of the said
adjoining unit. It is the case of the petitioner that under the garb of
the proceedings initiated exclusively against M/s Ramkrishna
Industries, the respondent Authorities have unlawfully dispossessed
Signature Not Verified
Signed by: JAGADISHAN
AIYER
Signing time: 09-03-2026
17:45:51
NEUTRAL CITATION NO. 2026:MPHC-IND:6234
3 W.P. No. 7864/2026
the petitioner from its lawfully allotted portion without initiating
any independent lease cancellation proceedings against the
petitioner.
3. Learned counsel for the petitioner submitted that the action of
the respondents is wholly illegal, arbitrary and without the
Authority of law, as the petitioner’s registered lease-deed remains
valid and subsisting. It was contended that M/s Ramkrishna
Industries is a separate and distinct legal entity having no common
identity with the petitioner. Therefore, the respondents acted in
excess of their jurisdiction by dispossessing the petitioner based on
proceedings initiated against a third party. The petitioner further
argued that no show cause notice was issued to them, nor was any
opportunity of hearing afforded. Furthermore, no proper
demarcation of the land was conducted in the petitioner's presence
to distinguish between the respective allotments of the two units.
Accordingly, it was submitted that the impugned action violates the
principles of natural justice and infringes upon the petitioner’s
fundamental and constitutional rights guaranteed under Articles 14,
19(1)(g), and 300-A of the Constitution of India, resulting in
irreparable financial loss.
Signature Not Verified
Signed by: JAGADISHAN
AIYER
Signing time: 09-03-2026
17:45:51
NEUTRAL CITATION NO. 2026:MPHC-IND:6234
4 W.P. No. 7864/2026
4. Per contra, the respondents vehemently opposed the petition.
It was submitted on behalf of the State that the petition is entirely
misconceived and premature. The respondents contended that no
action has been taken against the petitioner’s leasehold rights and
the proceedings in question were strictly confined to the lease
cancellation of M/s Ramkrishna Industries.
5. Heard the respective contentions of the parties and carefully
perused the pleadings and the record available.
6. Upon a careful examination of the facts of case in hand, this
Court finds that the present writ petition is premature. It is an
admitted position on record that no show-cause notice or
independent order regarding the cancellation of the petitioner's
lease deed dated 09.06.2009 has been issued or passed by the
respondent Authorities against the present petitioner.
7. The grievance raised in this petition is fundamentally rooted
in mere apprehension. The petitioner's fear of dispossession stems
solely from the lease cancellation proceedings and the subsequent
Panchnama prepared against a separate and distinct legal entity,
namely M/s Ramkrishna Industries. An apprehension, without a
concrete adverse order or specific notice of dispossession directed
Signature Not Verified
Signed by: JAGADISHAN
AIYER
Signing time: 09-03-2026
17:45:51
NEUTRAL CITATION NO. 2026:MPHC-IND:6234
5 W.P. No. 7864/2026
at the petitioner, does not furnish a sufficient cause of action to
invoke the extraordinary jurisdiction of this Court at this stage.
8. Even otherwise, if any notice has been issued to the
petitioner, the same shall be dealt with by the Department of Micro,
Small and Medium Enterprises (MSME), Government of Madhya
Pradesh, strictly in accordance with law and by duly applying the
principles of natural justice.
9. In view of the aforesaid observations, as the petition is
premature, no interference is warranted with the impugned notice
dated 17.02.2026, at this juncture. Consequently, the Writ Petition
stands dismissed.
10. Pending applications, if any, shall be disposed of accordingly.
(Jai Kumar Pillai)
Judge
Aiyer*PS