Steel Authority Of India Limited (Sail) vs M/S Primetals Technologies India Pvt. Limited

Court
Delhi High Court

$~19
* IN THE HIGH COURT OF DELHI AT NEW DELHI

# CNR No. DLHC010220622026
+ FAO(OS) (COMM) 131/2026
STEEL AUTHORITY OF INDIA LIMITED (SAIL)
.....Appellant
Through: Mr. Jayant Mehta, Senior Advocate
with Mr. Ashish Tiwari, Mr. Anurag
Tiwari, Ms. Mansvini Jain and Mr.
Sahib Patel, Advs.

versus

M/S PRIMETALS TECHNOLOGIES INDIA PVT. LIMITED
.....Respondent
Through: Mr. Rajesh Markanda, Mr., Keshri
Kumar, Mr. Arshdeep Singh, Advs.

CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA

O R D E R
% 14.09.2026
This matter is being taken up today as 11.09.2026 was declared holiday
on account of BRICS Summit.

MANMEET PRITAM SINGH ARORA, J.
FAO(OS)(COMM)- 131/2026
1. The appeal arises from a contractual dispute concerning the recovery
of shortfall in the minimum CENVAT Credit under a contract between the
Appellant, a PSU operating Bhilai Steel Plant [‘BSP’], and the Respondent.
The Appellant challenges the judgment dated 23.02.2026 [‘impugned
judgment’] passed by the learned Single Judge in OMP(COMM) No.
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 1 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

297/2024 [‘Section 34 petition’], whereby the arbitral award dated 24.05.2024
rejecting the Respondent’s claims was set aside on the ground of patent
illegality.
FACTS IN BRIEF
2. In 2006, the Appellant issued an NIT for ‘Installation of the Power
Supply Facility (Package-II) for 700 TDP ASU-4 in Oxygen Plant No. II’.
The Respondent emerged as the successful bidder, pursuant to which a formal
contract was executed on 12.10.2007 [‘the contract’]. Under the contract, the
facilities were to be installed and commissioned within 15 months.
2.1 A material term of the contract was Article 2.1, under which the
Respondent had quoted a Contract Price of INR 18,45,54,310/- which
1
included CENVAT of INR 2,16,42,894/-. The said Article stipulated that
Respondent shall pass on minimum amount of INR 2,16,42,894/- to the
Appellant as CENVAT credit. According to the Appellant, the promise of
minimum CENVAT credit was an important factor in tender evaluation and
selection of the successful bidder. The Appellant further relies upon Clause
14.6 of the General Conditions of Contract [‘GCC’], which prescribed the
procedure for adjustment of the Contract Price, at the instance of the
Respondent, in case of variation in taxes and duties [‘Excise Duty and
Counter Veiling Duty’].
2.2 It is stated that although the contractual period was 15 months, the
Commissioning Certificate was issued only on 20.06.2012, with outstanding
items remaining to be completed, and liquidated damages were consequently
imposed. The Performance Guarantee Certificate [‘PGC’] was issued on

1
Central Value Added Tax
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 2 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

16.07.2013 and the Final Acceptance Certificate [‘FAC’] was issued on
12.12.2013. The Appellant therefore states that the contract stood concluded
in 2013, after a delay of more than four (4) years.
2.3 Thereafter, the Appellant informed the Respondent, by communication
dated 17.05.2014, of its decision to recover the shortfall, if any, in the
minimum CENVAT amount and imposition of liquidated damages. The
Appellant asserts that the Respondent acknowledged this communication
without objection. Thus, when the Respondent subsequently raised its
outstanding final invoices in 2018 and 2019, the Appellant adjusted INR
1,07,61,378/- towards the shortfall of the Respondent in passing on the
minimum CENVAT credit stipulated in Article 2.1 of the contract and paid
the balance amount.
2.4 The Respondent issued a conciliation notice dated 26.05.2021. After
conciliation failed, the Respondent sought arbitration on 28.12.2021, claiming
INR 1,07,61,378/- towards recovery of the amount adjusted by the Appellant
for shortfall of the minimum CENVAT credit, along with interest.
2.5 It is admitted that during the execution of the contract, duty rates were
reduced leading to lesser payment of duty by the Respondent to the statutory
authorities. Also, consequently in the invoices raised by the Respondent on
the Appellant, the duty claimed was lower. The Respondent raised a claim of
reimbursement towards duty for INR 1,08,81,516/-, recovered the same from
the Appellant and passed on the CENVAT credit for the aforesaid amount of
INR 1,08,81,516/-. However, in this process there was a shortfall of the
minimum CENVAT credit stipulated in Article 2.1 to the extent of INR
1,07,61,378/-, which is the subject matter of the dispute.
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 3 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

2.6 The Respondent contended that it is not liable to pay INR 1,07,61,378/-
to the Appellant as an assured benefit, and any amount towards shortfall
CENVAT credit could have been deducted only if the Respondent had failed
to provide the necessary documentation, which is not the case in hand. The
Respondent stated that it is not liable to pay INR 1,07,61,378/- as an assured
benefit. The Appellant has however submitted that CENVAT credit shortfall
of INR 1,07,61,378/- is not dependent on the rate of duty collected by
statutory authority but is an independent assured sum payable by the
Respondent.
2.7 The learned Arbitrator by its award dated 24.05.2024, rejected the
Respondent’s claim for recovery after considering, inter alia, Article 2.1 and
Clause 14.6 of the GCC. It held that the minimum CENVAT credit stipulated
in Article 2.1 was an assured benefit to the Respondent and in case of any
shortfall in the said minimum CENVAT credit passed on to the Appellant,
even if on account of lowering of duty by the statutory authority, the
Respondent was liable to make good the said shortfall by suffering a
deduction in a Contract Price.
2.8 Aggrieved by the arbitral award, the Respondent filed a petition under
Section 34 of the Act, being OMP(COMM) No.297/2024. By the impugned
judgment, the learned Single Judge allowed the petition and set aside the
arbitral award, on the finding that there was no clause in the contract which
stipulated deduction, from the invoices payable to the Respondent as per the
Contract Price, in case of a shortfall in the minimum CENVAT credit passed
on to the Appellant, due to actual lowering of duty by the statutory
authorities. Learned Single Judge rejected the submission that there was
assured benefit promised to the Appellant under Article 2.1 independent of
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 4 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

the CENVAT credit.
2.9 The present appeal under Section 37 challenges the aforesaid judgment
seeking restoration of the arbitral award principally on the ground that the
learned Single Judge exceeded the limited scope of interference under Section
34 of the Act.
SUBMISSIONS BY THE APPELLANT
3. The Appellant submitted that the learned Single Judge erred in setting
aside the arbitral award dated 24.05.2024, as the learned Arbitrator had
adopted a plausible interpretation of the contractual provisions, particularly
Article 2.1 and Clause 14.6 of the GCC, and substituted his own interpretation
for that of the learned Arbitrator.
3.1. The Appellant submitted that under Article 2.1 of the contract, the
Respondent had expressly guaranteed a minimum CENVAT credit of INR
2,16,42,894/- as part of the Contract Price of INR 18,45,54,310/-; the
guaranteed minimum amount was admittedly quoted by the Respondent and
formed part of the contractual arrangement.
3.2. The Appellant submitted that the contract specifically contemplated
variations in taxes and duties and prescribed a detailed mechanism under
Clause 14.6 of the GCC for seeking corresponding adjustment in the Contract
Price, subject to production of supporting documentary evidence. The
Respondent, however, never invoked the said contractual mechanism or
produced the requisite evidence to establish that any variation in taxes and
duties had caused the alleged shortfall in CENVAT Credit.
3.3. The Appellant submitted that the FAC was issued on 12.07.2014,
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 5 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

whereafter the contract stood concluded. Despite this, the Respondent did not
raise its pending PG/FAC invoices for several years and submitted the
relevant bills only in 2018-2019. At the time of making the final payment, the
Appellant adjusted the liquidated damages and INR 1,07,61,378/- towards the
shortfall in the minimum CENVAT credit and released the balance amount.
3.4. The Appellant submitted that the learned Arbitrator, after considering
Clause 14.6, which contemplated adjustment of the Contract Price for
variation in taxes upon production of supporting evidence, as well as Article
2.1 concerning the minimum CENVAT credit, correctly dismissed the claims
of the Respondent.
3.5. The Appellant submitted that the Arbitrator’s view was a possible and
plausible interpretation of the contractual provisions and was neither perverse
nor such as would shock the conscience of the Court, therefore, there was no
permissible ground under the narrow scope of Section 34 for the learned
Single Judge to interfere with the arbitral award.
3.6. The Appellant submitted that the learned Single Judge erred in holding
that Article 2.1 merely provided for passing on the minimum CENVAT credit
without specifying the consequence of a shortfall. According to the Appellant,
such interpretation ignores the expression ‘minimum’ in Article 2.1 and
renders Clause 14.6 redundant, whereas the Arbitrator had harmoniously
construed the contractual provisions.
3.7. The Appellant submitted that the learned Single Judge incorrectly
concluded that the Arbitrator had travelled beyond the contractual provisions,
however, it was the learned Single Judge who effectively substituted his own
interpretation of Article 2.1 and Clause 14.6 for the plausible interpretation
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 6 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

adopted by the Arbitrator, which was impermissible within the limited
jurisdiction under Section 34 of the Act.
3.8. The Appellant submitted that therefore the impugned order dated
23.02.2026 suffers from a jurisdictional error, as it interferes with a reasoned
arbitral award on the basis of a different interpretation of the contract. The
Appellant consequently seeks setting aside of the impugned order and
restoration of the arbitral award dated 24.05.2024.
SUBMISSIONS BY THE RESPONDENT
4. The Respondent submitted that the contracts involved in FAO (OS)
(COMM) 130/2026 and FAO (OS) (COMM) 131/2026 contain mirror-image
provisions, particularly Article 2, the Summary Price Schedule, Clause 11.2
of the GCC and Clause 14.5.2 relating to CENVAT Credit. However, the two
arbitral tribunals rendered contradictory findings on the same issue, leading
the learned Single Judge to uphold one award while setting aside the award
challenged in the present petition, i.e., FAO (OS) (COMM) 131/2026.
4.1. The Respondent submitted that the two arbitral tribunals adopted
contrary interpretations despite considering substantially identical contractual
clauses. In FAO (OS) (COMM) 130/2026, the Arbitrator held that the
contract did not entitle the Appellant to deduct the shortfall and that the only
contractual consequence was non-reimbursement of the relevant amount. In
FAO (OS) (COMM) 131/2026, however, the Arbitrator proceeded on the
basis that CENVAT credit was a benefit to be passed on to the Appellant and
that any shortfall could therefore be deducted from the amount payable to the
Respondent.
4.2. The Respondent submitted that the Appellant’s contention that any
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 7 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

shortfall in CENVAT credit automatically entitled it to deduct the shortfall
from the Respondent’s dues is contrary to the contractual terms. According to
the Respondent, the contractual consequence of a shortfall was only that the
corresponding amount would not be reimbursed, thereby reducing the total
Contract Price to that extent. There was no contractual provision authorising
the Appellant to make a separate deduction from the Respondent’s invoices
on account of such shortfall.
4.3. The Respondent submitted that, the learned Single Judge correctly
found that Clause 14.5.2 dealt with the consequence of failure to furnish
documents for claiming CENVAT, namely non-reimbursement, but contained
no provision permitting deduction of the shortfall in minimum CENVAT
credit from the Respondent’s invoices. The learned Single Judge accordingly
held that no such term could be read into the contract.
4.4. The Respondent submitted that the learned Single Judge correctly
observed that the contract value represented the amount payable for the work
executed and was inclusive of taxes and duties, whereas the minimum
CENVAT credit was not a sum payable for the work itself but related to
reimbursement of duty actually paid. It is submitted that the amount of such
duty could vary owing to factors such as changes in tax rates and prices of
items.
4.5. The Respondent submitted that there was no contractual basis for
deducting the shortfall in minimum CENVAT credit from the invoices. The
Arbitrator effectively proceeded on the basis of a term/clause which did not
exist in the contract and thereby travelled beyond the contractual provisions,
and such an approach amounted to adding a term to the contract, which was
impermissible.
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 8 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

4.6. The Respondent submitted that the learned Single Judge correctly held
that an Arbitrator is required to decide the dispute within the four corners of
the contract and cannot create or introduce a contractual provision providing
for deduction of minimum CENVAT credit shortfall when no such provision
exists.
4.7. The Respondent submitted that, since the Arbitrator travelled beyond
the contractual terms and founded the award on a non-existent provision
permitting deduction of the minimum CENVAT credit shortfall, the award
suffered from patent illegality and was rightly set aside by the learned Single
Judge.
FINDINGS AND ANALYSIS
5. We have heard the counsels for the parties and perused the record.
6. Before proceeding further, it would be relevant to reproduce Article 2.1
of the Contract and Clauses 11.1, 11.2, 11.2.1, 14.5.2, 14.6.1, 14.6.2 and
14.6.3 of the GCC relied upon by the parties:
The Contract

“2.1 Contract Price (Reference GCC Clause 11 & Appendix-1)
The Employer hereby agrees to pay to the Contractor the Contract Price
in consideration of the performance by the Contractor of its obligations
hereunder. The Contract Price shall be Rs. 18,45,54,310/- (Rupees
eighteen crore forty-five lakh fifty-four thousand and three hundred ten
only), or such other sums as may be determined in accordance with the
terms and conditions of the Contract. A minimum amount of
Rs.2,16,42,894/- (Rupees two crore sixteen lakh forty-two thousand and
eight hundred ninety-four only) is to be passed on to BSP as CENVAT
credit .

GENERAL CONDITIONS OF CONTRACT

11. Contract Price
11.1 The Contract Price shall be as specified in Article 2 (Contract Price
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 9 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

and Terms of Payment) of the Contract Agreement. The break-up of the
Contract Price is given in the Appendix-1 to the Contract Agreement.

11.2. Price Basis
11.2.1 The Contract Price shall be for the entire scope of the Facilities
including spares, oils, grease, lubricants, flushing liquor, chemicals for
pickling etc. required till commissioning of the Facilities, imported
surplus material and scrap in any form generated in side the plant
premises. The contract price shall be inclusive of all taxes and duties
and comprise inter-alia of Basic price, excise duty, sales tax, VAT
including sales tax/VAT on works contract / Works Contract Tax),
octroi, Turn Over Tax (TOT), Entry Tax, Service Tax, Education Cess
and any other duties, taxes and levies, as may be applicable and
prevailing on the base date of the contract and insurance. The payment
of duties, taxes, levies, etc. will be reimbursed (on actual) against
documentary evidence to be produced by the contractor, subject to a
ceiling indicated in the price schedule of the contract .

In no case the reimbursement towards duties and taxes etc., shall exceed
the amount indicated in Appendix-1 towards duties, taxes, levies, etc.
except as indicated in Sub-Clause 14.6.1, hereof.

14.5 CENVAT Credit
14.5.2 The Contractor shall submit the necessary documents required by
the Employer to avail the CENVAT Credit. In case the Contractor fails to
submit the required document for claiming the CENVAT Credit by the
Employer in respect of certain plant & equipment, the amount of Excise
Duty on such indigenous plant & equipment and Counter Veiling Duty
on such imported plant & equipment, shall not be paid by the Employer
to the Contractor.

14.6 Variations in Taxes & Duties
14.6.1 For the purpose of the Contract, it is agreed that the 'Contract
Price' specified in Article 2 ("Contract Price" & "Terms of Payment") of
the Contract Agreement is based on the taxes, duties, levies and charges
prevailing on Base date (hereinafter called "Tax" in this Sub-Clause 14.6
hereof). If any rate of tax is increased or decreased, a new tax is
introduced, an existing tax is abolished, or any change in interpretation or
application of any tax occurs in the course of the performance of
Contract, which was or will be assessed on the Contractor, Sub-
Contractors or their employees in connection with performance of the
Contract, an adjustment of the Contract Price shall be made as per Sub-
Clauses 14.6.2 & 14.6.3, hereof, by addition to the Contract Price or
deduction therefrom, as the case may be.

14.6.2 The adjustment in the Contract Price towards variation in the taxes
shall be made by the Employer on production of the documentary
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 10 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

evidences by the Contractor.

14.6.3 The Contract Price shall be adjusted towards variations in taxes in
respect of only finished equipment supplied by the Contractor to the
Employer. No adjustment in the Contract price shall be made for
variations in the taxes on raw materials, parts, component/ intermediate
components, assemblies/sub-assemblies, etc.”
[Emphasis Supplied]

I. Findings in the impugned Arbitral Award
7. The impugned arbitral award was in favour of the Appellant and
against the Respondent. The said award was impugned by the Respondent in
the Section 34 petition and has been set aside by the learned Single Judge by
the impugned judgment.
7.1. The challenge in Section 34 petition was to the rejection of
Respondent’s Claim for recovery of INR 1,07,61,378/- from the Appellant.
The said Claim was covered by the decision rendered under Issue Nos. 3 and
4 in the arbitral award. Issue No. 3 was whether the Appellant’s deduction of
the INR 1,07,61,378/- on account of shortfall of minimum CENVAT credit
was bad in law, and Issue No. 4 was that whether the Respondent was entitled
to the reimbursement of such deduction.
7.2. With respect to the issue of minimum CENVAT credit, the learned
Arbitrator noted that the contract contemplated three possible situations: (i)
actual CENVAT credit equalling the guaranteed amount; (ii) actual credit
being less than the guaranteed amount; and (iii) actual credit exceeding the
guaranteed amount. It held that where the actual credit [passed on] was less
than the guaranteed credit, the Claimant was required to make good the
shortfall; where it exceeded the guaranteed amount, the excess benefit was to
be shared equally between the parties.
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 11 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

7.3. The learned Arbitrator rejected the Respondent’s contention that since
the shortfall in CENVAT credit had resulted from variation in taxes, the
reduction was liable to be adjusted from the [Gross] Contract Price under
Clause 14.6 of the GCC.
7.4. The learned Arbitrator held that the contractual provisions expressly
contemplated variations in taxes during the execution of the contract and,
also, separately provided for obligation to pass on minimum CENVAT credit.
He held that since the rates of duty during performance of the contract were
lowered by the Government than those prevailing on the base date, the
resulting shortfall in passing on minimum CENVAT credit to the Appellant,
had to be borne by the Respondent herein in terms of the contractual
arrangement. He further held that the quantum of minimum CENVAT credit
was a benefit ‘assured’ to the Appellant under Article 2.1 of the contract and
was a fundamental component of the contractual arrangement, as the
Respondent had expressly guaranteed passing on the specified minimum
CENVAT credit while submitting its bid. He held therefore Respondent
herein could not subsequently avoid the contractual liability by characterising
the recovery of the shortfall, by the Appellant, as unjust enrichment.
7.5. The learned Arbitrator acknowledged that the arbitral tribunal is a
creature of contract and therefore, is bound by the terms of the contract
agreement. He held that neither party could selectively rely upon favourable
contractual provisions while disregarding others, and that the arbitral tribunal
could not rewrite or travel beyond the contractual bargain. He therefore
concluded that the Appellant had rightly deducted the shortfall from the
invoices of the Respondent. Accordingly, while deciding Issue Nos. 3 and 4,
the learned Arbitrator upheld the Appellant’s deduction of INR 1,07,61,378/-
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 12 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

from the Respondent’s invoices on account of the shortfall in passing on the
minimum CENVAT credit recorded in Article 2.1 of the contract. He rejected
the Respondent’s claim for a declaration that the deduction was bad in law
and for reimbursement of the said amount.
II. Findings in the Impugned Judgment
8. Learned Single Judge by the impugned judgment has set aside the
arbitral award on the finding of patent illegality by holding that the
determination of the learned Arbitrator as regards the entitlement of the
Appellant to make the deduction of INR 1,07,61,378/- from the invoices of
the Respondent, is beyond the terms of the contract.
8.1. Learned Single Judge held that Article 2.1 of the contract required the
Respondent to ensure passing on of the stipulated minimum CENVAT credit
to the Appellant, however, the contract contained no provision permitting
deduction of the amount to any ‘shortfall’ in minimum CENVAT credit from
the Respondent’s invoices.
8.2. Learned Single Judge at paragraph 18 of the impugned judgment has
observed that the learned Arbitrator has wrongly upheld the deduction of INR
1,07,61,378/- by the Appellant from the Respondent’s invoices even though
there was no clause in the contract which permitted such a recovery and/or
deduction. He held that, therefore the award was beyond the terms and
conditions of the contract and is thus vitiated on the ground of patent
illegality. He also held that Clause 14.6.2 has to be read with Clause 14.6.3 of
the GCC and the said clauses are inapplicable in the facts of this case.
8.3. Learned Single Judge held that the impugned arbitral award suffered
from patent illegality, as the learned Arbitrator had failed to act within the
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 13 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

contractual framework, and by allowing deductions had in effect added terms
to the contract. The relevant paras of the judgment read as under:
“13. The contention of the learned counsel for the respondents that
Article 2.1 of the contract shall override the terms of the GCC is of no
avail. Article 2.1 provides for MGCC to be passed on but it does not deal
with the consequences in case of a shortfall.

14. The contract value is an amount payable to the petitioner for the work
executed and is inclusive of taxes and duties. The MGCC is not a sum
due for the work done but is a reimbursement of the duty paid which may
vary consequent to several factors including variation in the rate of taxes
and change in the price of items.

15. The matter needs to be considered from another angle. The gross
contract value was Rs.18,45,54,310/-. After giving credit of
Rs.2,16,42,894/- towards MGCC, the work would cost the respondents
Rs.16,29,11,416/- (Net Contract Value). The position remained
unchanged despite the shortfall in MGCC. The reimbursement of duty
paid was Rs.1,08,81,516/- for which the respondents shall get CENVAT
credit. By not reimbursing the shortfall in MGCC the respondents
retained the balance amount of Rs.1,07,61,378/- and the net cost of the
contract remained Rs.16,29,11,4161/-. In other words, for getting an
MGCC of Rs.2,16,47,894/- the respondents had to pay Rs.18,45,54,310/-
but upon reimbursement of excise duty of Rs.1,08,81,516/-, the
respondents paid a sum of Rs.17,37,92,932/- i.e., Rs.1,07,61,378/- less
than the gross contract value. Consequently, the net contract price
payable for the work done remained unaffected by the shortfall in MGCC
as it was not reimbursed and the amount remained with the respondents.

16. Whether variation in the rate of tax resulted in shortfall in MGCC and
if contract price could be adjusted as per clause 14.6.1 for variation in
rate of taxes on raw materials, components etc., need not be dilated upon.
The arbitrator rightly held that the shortfall in MGCC shall not be
reimbursed but there cannot be deduction for such shortfall thereby
rendering the reasons for shortfall to be inconsequential. For this very
reason, non-compliance of clause 14.6.2 shall not be fatal to the claim of
the petitioner.

17. The arbitrator rightly took into account that the MGCC formed the
basis of the tender valuation but failed to consider that despite the
shortfall in MGCC, the net value of the contract remained unchanged.

18. The arbitrator travelled beyond the terms of the contract to reject the
claim. To justify the conclusion arrived at, reference was made to a non-
existing clause in the contract that 50% benefit of CENVAT would go to
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 14 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

the petitioner. At the cost of repetition there is no clause for deducting
the shortfall in MGCC from the invoices. It is a trite law that an arbitrator
has to decide the dispute within the four corners of the terms and
conditions of the contract. The venture of the arbitrator beyond the terms
and conditions vitiates the award by patent illegality.
…….

19. The law is well settled that the parties are bound by the terms of the
contract and the arbitrator cannot go into the fairness of the terms and
conditions. In the case in hand in absence of a clause providing for
deduction on account of shortfall in MGCC, the arbitrator proceeded on
the basis that the petitioner had to make good the shortfall in MGCC but
failed to point out the clause for providing such deduction .

20. The arbitrator erred in holding that the tax component formed part of
the contract price and not the MGCC, whereas MGCC was the credit of
excise duty paid which was part of the contract price.

21. The arbitrator relying upon clauses 11.2.1 and 14.5.2 of GCC and
Article 2.1 of the contract rightly concluded that the petitioner had to
ensure MGCC. However, while referring to clause 14.6.2 the arbitrator
overlooked that no clause in the contract provides for deduction of
shortfall in MGCC. On the contrary, under clause 14.5.2 in case of
failure of the petitioner to submit documents enabling the respondents to
avail CENVAT credit, the duty paid to that extent was not to be
reimbursed. Moreover, clause 14.6.2 cannot be pressed into service in
isolation and is to be read along with clauses 14.6.1 and 14.6.3. Clause
14.6.3 states that the adjustment in contract price would be made only for
variation in taxes in respect of finished equipment supplied by the
petitioner and not for variation in taxes on raw material, parts,
component, intermediate components, assemblies, subassemblies etc.,
and is not applicable in facts of the present case .

22. The arbitrator while holding that the net outgoing would be the
contract price reduced by MGCC, failed to consider that the net outflow
of the respondents was not affected by any shortfall in MGCC. There was
no basis to hold that the shortfall in MGCC could be deducted from the
invoices and this tantamounts to adding terms to the contract between
the parties which is not permissible in law.”
[Emphasis Supplied]

III. Scope of Interference on the grounds of patent illegality
9. Prior to analysing the rival contentions of the parties, it would be
apposite to refer to the scope of interference by this Court under Section 37 of
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 15 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

the Act, particularly where the arbitral award has been set aside by the learned
Single Judge under Section 34 on the ground of patent illegality.
2
10. In Ramesh Kumar Jain v. Bharat Aluminium Company Limited ,
the Supreme Court has held that Section 37 of the Act provides for a limited
appellate remedy against an order either setting aside or refusing to set aside
an arbitral award passed by the Court under Section 34 of the Act. It held that
interference in an arbitral award by the Appellate Court in exercise of
jurisdiction under Section 37 of the Act cannot travel beyond the restrictions
laid down in Section 34 of the Act.
11. Thus, while the scope of review of an arbitral award under Section 37
of the Act remains narrow and co-extensive with Section 34 of the Act, it
certainly extends to examine whether the Court which passed the order under
Section 34 of the Act interfering in the award has correctly applied the test of
patent illegality to the award or not; and where the impugned award, on a
proper application of that test, indeed suffers from an illegality going to its
root, then no interference under Section 37 of the Act would be made out in
the order passed by the Court under Section 34 of the Act.
12. In the facts of this case, the learned Single Judge has set aside the
arbitral award under Section 34 on the ground of patent illegality. In such a
case, the Appellate Court under Section 37 is required to examine whether the
finding of patent illegality in the impugned judgment of the learned Single
Judge is sustainable within the statutory parameters of Section 34(2A) of the
Act.
IV. The impugned arbitral award suffers from patent illegality

2
2025 SCC OnLine SC 2857, at paragraph 29
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 16 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21


13. In Ramesh Kumar Jain v. BALCO (supra) the Supreme Court, in
paragraphs 33 and 34, clarified that the patent illegality must be one which
goes to the root of the award; illustrations include ignoring a binding
precedent or a clear prohibition contained in the contract, or a finding based
on no evidence. The Supreme Court further explained that patent illegality
may arise where the award travels beyond the contract or the submission to
arbitration, contravenes substantive law or the Arbitration Act, is contrary to
the terms of the contract, or is so irrational or unreasoned as to disclose an
error apparent on the face of the award.
“33. In 2015, by way of the Arbitration and Conciliation (Amendment)
Act a new sub-section (2A) to section 34 of A&C Act was inserted which
in addition to statutorily recognizing the ‘patent illegality’ ground for
setting aside a domestic arbitral award made it an independent and
distinct ground from ‘public policy’ under section 34. The proviso to the
newly inserted clause further provided that an award “ shall not be set
aside merely on the ground of an erroneous application of the law or by
reappreciation of evidence”. The legislative intent behind insertion of
this proviso was to avoid excessive intervention to arbitral award by the
courts under the ground of ‘patent illegality’. However, the Amendment
clarified that “an erroneous application of the law” or “re-appreciation of
evidence” does not fall under patent illegality. Hence, the courts are not
to treat every factual error or every divergent interpretation as an
illegality. The illegality must be of a kind that strikes at the heart of the
award's validity. For instance, if an arbitrator ignores a binding precedent
or a clear prohibition in the contract, that may be patent illegality.
Likewise, a finding based on no evidence at all can be said to be perverse
and thus patently illegal. But where there is some evidence and a
reasonably plausible inference has been drawn by the arbitrators, the
courts should ordinarily refrain themselves from supplanting the views
arrived by the arbitrator as that would be the true import of the legislative
intent inherent in the Amendment Act.
34. Thereafter, this court elucidated the meaning of the expression
22
‘patent illegality’ in Ssangyong Engg. & Construction Co. Ltd. v. NHAI
while taking into consideration the amendment act of 2015 and held it as
a glaring, evident illegality that goes to the root of the award. This
includes : (a) an award deciding matters outside the scope of the
arbitration (beyond the contract or submission); (b) an award
contradicting the substantive law of India or the Arbitration Act itself; (c)
an award against the terms of the contract; and (d) an award so
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 17 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

unreasoned or irrational that it manifests an error on its face.”
[Emphasis supplied]
14. Mr. Jayant Mehta, learned senior counsel for the Appellant has
contended that the phrase ‘minimum’ as it appears in Article 2.1 has to be
given due effect to and the learned Arbitrator rightly held that the shortfall of
INR 1,07,61,378/- in passing on the minimum CENVAT Credit was
recoverable by the Appellant from the invoices raised by the Respondent. He
states on instructions that the shortfall of INR 1,07,61,378/- occurred due to
lowering of rate of duty by the Government during the execution of the
contract and not due to any act or omission of the Respondent. He states that
however, under Clause 14.6 of the GCC, in case of variation in taxes and
duties, Respondent had to approach the Appellant with documentary proof of
the variation so that the [Gross] Contract Price could be adjusted. He states
however the Respondent did not approach the Appellant and therefore the
[Gross] Contract Price mentioned in Article 2.1 and Summary Price Schedule
remained unchanged.
15. We are unable to accept the submission of the Appellant.
16. It is a matter of record that the Gross Contract Price was INR
18,45,54,310/-, which included CENVAT credit of INR 2,16,42,894/-. The
Respondent had agreed to pass on the said CENVAT credit to the Appellant
by furnishing all requisite documents so as to enable the Appellant to avail the
CENVAT credit. Thus, the Net Contract Price after deducting the CENVAT
credit payable to the Respondent was INR 16,29,11,416/-.
17. The promise of the Respondent recorded in Article 2.1 is that it shall
pass on minimum CENVAT credit of INR 2,16,42,894/- to the Appellant.
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 18 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

This figure of INR 2,16,42,894/- is duly reflected in the Summary Price
Schedule and is reflective of the value of duty which the parties estimated
would be payable to the Government, at the time of the formation of the
contract. The parties contemplated that Respondent during the execution of
the contract would be liable to pay duty amount of INR 2,16,42,894/- to the
Government and seek reimbursement of the duty amount from the Appellant,
and the Respondent undertook to pass on the CENVAT credit equal to INR
2,16,42,894/- to the Appellant.
18. However, since the rate of the duty was lowered, the duty levied on the
goods manufactured by the Respondent and invoiced to the Appellant was
reduced resulting in a levy of a lower amount INR 1,08,81,516/- only. So, the
Respondent raised invoices claiming reimbursement of duty from the
Appellant for the lowered sum of INR 1,08,81,516/- only. There is no dispute
that Respondent as per clause 14.5.2 of the GCC provided all necessary
documents, including proof of deposit of duty to the Appellant for claiming
CENVAT credit of INR 1,08,81,516/- from the government and therefore
Appellant reimbursed the said duty amount to the Respondent.
19. The effect of lowering of the rate of duty was that Appellant instead of
paying and/or reimbursing the initially estimated INR 2,16,42,894/- in the
[Gross] Contract Price towards the duty to the Respondent, reimbursed lower
amount of INR 1,08,81,516/- to the Respondent.
The Appellant, therefore, in fact, at the outset, saved INR 1,07,61,378/-
from the [Gross] Contract Price due to the lowering of the rates of duty. In
other words, the Appellant was never out of pocket for the sum of INR
1,07,61,378/- which otherwise was part of the [Gross] Contract Price
stipulated in Article 2.1 of the contract and Summary Price Schedule. There
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 19 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

was therefore no ‘shortfall’ in the CENVAT credit, which was actually
recoverable by the Appellant and this notion of ‘shortfall’ is itself
misconceived. To sum it up, under the contract the Appellant reimbursed duty
equal to INR 1,08,81,516/- to the Respondent and duly received CENVAT
credit equal to INR 1,08,81,516/-.
20. Learned Single Judge has, at paragraph 15 of the impugned judgment,
correctly illustrated the fact that, due to the lowering of the rate of duty, the
CENVAT amount which formed part of the Gross Contract Price in the
Summary Price Schedule stood correspondingly reduced and the Appellant,
having not incurred the liability of CENVAT to the extent of INR
1,07,61,378/- had their monetary interest protected, and were unaffected by
the reduction of the passing on of the CENVAT credit. In fact, during
arguments learned senior counsel for the Appellant has been unable to rebut
the aforesaid finding of the learned Single Judge.
We find no error in the findings recorded by the learned Single Judge at
paragraph 15, as these are evident on a bare reading of the Summary Price
Schedule, which is an admitted document forming part of the contract.
21. As noted above, Mr. Jayant Mehta learned senior counsel during
arguments has only relied upon Article 2.1 of the contract and Clause 14.6 of
the GCC to justify the deduction and recovery from the invoices.
We find no merit in this submission of the Appellant as neither Article
2.1 nor Clause 14.6 of GCC entitles the Appellant to recover alleged shortfall
of the minimum CENVAT credit from the invoices. This cannot even be
implied intention of this contract as the promise of minimum CENVAT credit
in Article 2.1 is not a ‘cash discount’ offered by the Respondent. We are of
the opinion that the view canvassed by the Appellant is not even a plausible
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 20 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

interpretation of Article 2.1 of the contract.
22. Additionally, the submission of the Appellant gives a myopic emphasis
to the word ‘minimum’ in Article 2.1 but fails to give any meaning to the
words ‘CENVAT credit’ in the clause. Whereas the said Article 2.1 has to be
read with Clause 14.5.2 which contemplates that if the Respondent fails to
furnish requisite documents to the Appellant so as to enable the Appellant to
claim CENVAT credit, then the Appellant has the right to deny
reimbursement of duty. Thus, upon reading of Article 2.1 of the Contract and
Clause 14.5.2 of the GCC, we find that the intent of the parties was that
Respondent undertook to pass on to the Appellant CENVAT credit of INR
2,16,42,894/-. However, this was on the understanding that in the first place
Respondent expected to deposit, with the Government, duty amount equal to
INR 2,16,42,894/- and recover the said amount from the Appellant by
providing all requisite documents and proof so as to enable the Appellant the
claim to CENVAT credit. However, due to the lowering of the rate of the duty
the Respondent deposited and recovered from the Appellant a lower sum of
INR 1,08,81,516/- only towards duty, and it duly passed on CENVAT credit
equal to the said amount INR 1,08,81,516/- to the Appellant.
23. We therefore concur with the findings of the learned Single Judge that
the learned Arbitrator wrongly held that Appellant was entitled to make
deductions from the invoices for recovery of the alleged shortfall in the
minimum CENVAT credit recorded in Article 2.1 of the contract, though the
contract did not stipulate any such recovery. We therefore find that the
learned Single Judge rightly set aside the award on the ground of patent
illegality.
V. Inconsistent views of arbitral tribunals on interpretation of the same
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 21 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

contractual stipulation cannot be simultaneously upheld by the Court in its
jurisdiction under Section 34 and Section 37 of the Act

24. We note that between the same parties in different contracts, the
identical issue of alleged ‘shortfall’ in passing on of the minimum CENVAT
credit and its recovery by the Appellant by making deduction from the
invoices led to disputes and was referred for adjudication to different arbitral
tribunals. The clauses of the contract and the GCC are identical. In the other
3
case , the arbitral tribunal held in favour of the Respondent and rejected the
claim of the Appellant for deduction relying on the same Article 2.1, and the
arbitral award has been upheld by the Court under Section 34 of the Act in
4 5
OMP(COMM) No. 451 of 2023 and also by us in the appeal filed by the
Appellant herein under Section 37 of the Act. We have in fact concluded in
this appeal and the other appeal that the view canvassed by the Appellant is
not even a plausible interpretation of Article 2.1 of the contract.
25. In this regard, we find it apposite to rely on the dicta in the judgment of
6
National Highway Authority of India v Progressive- MVR (JV) by the
Supreme Court wherein it was held that, because conflicting arbitral awards
had interpreted the same clause of the contract differently, the ordinary rule of
non-interference with a plausible arbitral view under Section 34 of the Act,
could not be mechanically applied. The relevant paragraph reads as follows:
“40. Once we interpret the formula in the manner indicated above, the
necessary consequences would be to hold that the Arbitral Tribunal(s) did
not decide the cases with the correct application of the formula and further
that the claim for price adjustment in respect of bitumen laid by the
contractors was not correct. Therefore, it can be held that the Award(s) are
contrary to the contractual terms. At the same time, this outcome poses a
dilemma inasmuch as in these cases, the Arbitral Tribunal has taken a

3
Steel Authority of India Limited (SAIL) v. M/S Primetals Technologies India Pvt. Ltd.
4
Arbitral Award dated 02.05.2023.
5
FAO(OS) (COMM) 130 of 2026
6
(2018) 14 SCC 688 at paragraph 40
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 22 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

particular view and when this was a plausible view, keeping in mind the
parameters of judicial review of the Court in exercise of powers under
Section 34 of the Act, normally the Court would not interfere with such
Awards. However, as already indicated above, such a situation has arisen
because of conflicting Awards given by the Arbitral Tribunals themselves,
which has provoked this Court to take a final view in the matter,
necessitated by the aforesaid reason. If one takes into consideration the
theory that one applies the principle mechanically i.e. that a plausible view
is not to be interfered with, then it may lead to very anomalous situation. In
such an eventuality, view taken by a particular Arbitral Tribunal in favour of
the Contractor would be upheld as plausible view. Likewise, the Court will
have to uphold the view taken by a particular Arbitral Tribunal in favour of
NHAI as well, as a plausible view. Therefore, the purpose is to avoid such a
situation which cannot be permitted as it would result in upholding both
kinds of arbitral awards interpreting the same clause, whether they go in
favour of the employer or they go in favour of the contractor. When the
exercise is done keeping in view these considerations and outcome thereof
is not determined, interest of justice would also demand that this result has
to be applied to the pending cases, which have not attained finality.
Therefore, in these peculiar circumstances, we hold that the principle of
issue estoppel will apply only in those cases where matters have attained
finality and no judicial proceedings are pending. In all those cases, including
the present one, where awards are challenged on this particular aspect, this
judgment will govern the outcome.”
[Emphasis Supplied]


26. In our considered opinion, the view expressed by the Supreme Court
in the aforesaid judgment is relevant to the facts of this case. Since we have
upheld the view of the arbitral tribunal that Article 2.1 of the contract does not
entitle the Respondent to recover monies from the invoices on account of
‘shortfall’ in CENVAT credit in the arbitral proceedings forming subject
matter of FAO(OS)(COMM) 130/2026, it would be appropriate that we
implement the same interpretation for Article 2.1 in this proceeding. The
parties are same; the contractual clauses relied upon by the parties are
identical and the fact which gave rise to the dispute of alleged ‘shortfall’ in
the CENVAT credit are also identical.
27. If we uphold the impugned arbitral award, we would be accepting a
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 23 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

diametrically different interpretation of identical Article 2.1 of the contract,
having contrary results, which is opposed to all judicial canons.
28. Separately, we have already observed that the interpretation given by
the learned Arbitrator in the impugned arbitral award to Article 2.1 is
implausible.
29. We therefore find no merit in this appeal. The impugned judgement is
upheld.
30. Pending applications, if any, are disposed of.

MANMEET PRITAM SINGH ARORA, J.



C.HARI SHANKAR, J.
SEPTEMBER 14, 2026/ dsn/AM
Signature Not Verified
FAO(OS) (COMM) 131/2026 Page 24 of 24

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21