JAIPUR DEVELOPMENT AUTHORITY vs ROHAN RAJDEEP RAJASTHAN INFRA PROJECT LIMITED

Court
Rajasthan High Court

[2026:RJ-JP:30253-DB]
HIGH COURT OF JUDICATURE FOR RAJASTHAN
BENCH AT JAIPUR
D.B. Civil Miscellaneous Appeal No. 1560/2025
CNR: RJHC020268382025 | URN: CMA / 2660U / 2025
1. Jaipur Development Authority, Through Executive
Engineer (PDC-1) Indira Circle, Jawaharlal Nehru Marg,
Jaipur, Rajasthan
2. Urban Development And Housing Department (UDH),
Government Of Rajasthan, Through Its Secretary, Food
Building, Secretariat, Jaipur 302015, Rajasthan
----Appellants
Versus
Rohan Rajdeep Rajasthan Infra Project Limited, Through
Director, Suhas K. Lunkad, 1, Modibaug, CTS No. 2254,
Bhamburde, Ganeshkhind Road, Pune 441016, Maharashtra
----Respondent
For Appellant(s) : Mr. Rajendra Prasad, AG
Mr. Tanay Goyal, Adv.
Mr. Sheetanshu Sharma, Adv.
Ms. Harshita Thakar, Adv.
Ms. Dhriti Sharma, Adv.
For Respondent(s) : Mr. Sudhir Gupta, Sr. Adv.
Ms. Sweta Chauhan, Adv.
Mr. Tarak Ahuja, Adv.
Mr. Ishan Khanna, Adv.
Mr. Aditya Shandilya, Adv.
Mr. Rachit Somani, Adv.
HON'BLE MR. JUSTICE ARUN MONGA
HON'BLE MR. JUSTICE SANDEEP TANEJA
Judgment
INDEX
1. Introduction___________________________________________ 02
2. Factual background______________________________________ 05
3. Arguments on behalf of the appellants_______________________ 14
4. Written submission on behalf of the appellants________________ 18
5. Arguments on behalf of the respondent______________________ 20
6. Written submission on behalf of the respondent_______________ 23
7. Discussion and findings __________________________________ 29
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 2 of 76 ) [CMA-1560/2025]
A. Questions for determination____________________________ 30
B. Relevant Contractual Clauses & Statutory Provisions_________ 31
C. Scope of interference u/s 34 & 37 of the Act_______________ 33
34
D. Case set up by the appellants___________________________
E. Case set up by the respondent___________________________ 37
8. Our View______________________________________________ 38
F. Re:Question (i) _______________________________________
38
41
G. Re:Question (ii)______________________________________
G. Re:Question (iii)_____________________________________ 57
H. Re:Question (iv)______________________________________ 66
I. Re:Question (v)_______________________________________ 68
J. Disproportionality_____________________________________ 68
K. Our view on submissions of the respondent ________________ 72
L. Conclusion___________________________________________ 74
M. Answers to the legal questions __________________________ 74
N. Summary ___________________________________________ 74
9. O. Order______________________________________________ 76
Reportable
Pronounced on :- 17/08/2026
Per: Arun Monga, J.
I. INTRODUCTION:
1. Appeal herein is directed against the order dated 27.01.2025
passed by the learned District Judge, Commercial Court, Jaipur,
whereby the objection petition preferred by the appellants under
Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as "the Act of 1996"), assailing the arbitral award dated
25.06.2023 and the corrigendum award dated 31.07.2023, was
dismissed.
2. The controversy pertains to disputes, arising out of a Tripartite
Concession Agreement dated 27.11.2009 executed between the
Government of Rajasthan, Jaipur Development Authority and the
respondent-concessionaire in relation to the construction, operation and
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 3 of 76 ) [CMA-1560/2025]
maintenance of an alternate route to “Ghat Ki Guni”, through a tunnel in
the Jhalana Hills to connect with NH-11 (Agra Road), Jaipur on Build,
Operate and Transfer (BOT) basis.
3. Salient features of the work scope are tabulated as below:
Project Cost as per Bid Docs. Rs. 150 Crores
*
Project Cost as quoted by Respondent Rs. 150 Crores
Date of Letter for agreement of Award 13.10.2009
Date of signing of Agreement 27.11.2009
Concession Period w.e.f .commencement
date
13 years 05 months 20 days
IRR As per Cash Flow Projection of
claimant
20.33%
Proposed Commencement date 01.12.2009
Actual commencement date 15.12.2010
Stipulated date of completion 14.06.2013
Actual date of completion 31.01.2013
4. The claims preferred before the learned Arbitral Tribunal as per
statement of claim dated 15.02.2019 are tabulated as under:-
S. No. Particulars Amount
1. Claim No. 1: For increase in project cost 175.67 crores
2. Claim No. 2: For loss of toll 188.02 crores
3. Claim No. 3: For compensation of toll loss due to
delay in achieving the Commercial Operations Date
(COD)
40.71 crores
4. Claim No. 4: For revenue loss on account of denial
of use of right of way for displaying advertisements
8.49 crores
Besides above, declaratory reliefs and Internal Rate of Return (IRR)
@20.33% and arbitral costs were also sought.
The arbitral proceedings culminated in an award, whereby Claim No. 1
and Claim No. 4 were allowed, Claim No. 2 was partly allowed, and
Claim No. 3 was rejected.
*
Revised Project Cost as on 13.01.2013 (completion date) due to additional
Scope - Rs. 207.87 crores (as per claimant/respondent)
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 4 of 76 ) [CMA-1560/2025]
5. The decision of the learned Arbitral Tribunal on various claims is
culled out and tabulated as under:
S.No. Particulars Decision Amount (in
Rupees)
1. Claim No. 1: Increase in Project Costs allowed in toto 175.67 crores
2. Claim No.2 Loss of Toll
i). On account of leakage of traffic
through old GKG road.
allowed 12.20 crores
ii). On account of diversion of traffic
through Kho-Nagoriyan road after
accident on 6th June, 2017
disallowed --
iii). On account of demonetization allowed 1.68 crores
iv). On account of traffic leakages
through other competing roads.
disallowed --
3. Compensation of toll loss of 7 months due
to delay in achieving COD
disallowed --
4. Loss of revenue due to prohibition to use
ROW for Advertisements
allowed 8.49 crores
5. Total award (as on date of filing
statement of claim on 16.02.2019)
198.04 crores
6. Costs on account of payment of arbitral
fee, legal expenses etc.
23,66,061/-
Aside above, the learned Arbitral Tribunal also awarded IRR @
20.33% per annum on the allowed claims, up to the date of the Award.
It was further directed that, in the event the awarded amount was not
paid within a period of 90 days from the date of the Award, the same
would carry post-award interest @12% per annum until its actual
payment.
6. Subsequently, vide a corrigendum award dated 31.07.2023, also
assailed herein, the learned Sole Arbitrator, exercising powers under
Section 33 of the Act of 1996, allowed the Respondent-Claimant's
application for correction of clerical errors. The Corrigendum, inter alia ,
deleted the words "amounting to Rs. 198.04 Crores", ( i.e. sum total of
the award) from paragraph 141 and made the original Award dated
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 5 of 76 ) [CMA-1560/2025]
25.06.2023 without any upper cap, by adding IRR @20.33% on
compounding basis per annum.
7. Apropros the award, the respondent is stated to have instituted
execution proceedings, wherein, recovery is sought for a sum of
Rs.544.43 crores which is calculated as per Rs. 198.04 crore along with
the IRR @20.33% w.e.f 31.01.2019, plus additional 12% w.e.f.
01.08.2023. The learned Executing Court, vide its order dated
09.01.2026, had directed issuance of a warrant of recovery under Order
XXI Rule 30 of the Code of Civil Procedure, 1908, for recovery of Rs.
544.43 crore.
8. However, pursuant to an order dated 22.01.2026 passed by this
Court, the execution proceedings were stayed. Since the appellants
challenge not only the conclusions drawn by the learned Sole Arbitrator
but also the approach of the learned Commercial Court in refusing
interference within the framework of Section 34 of the Act of 1996, it
becomes necessary to set out the factual backdrop in some greater
details.
II. FACTUAL BACKGROUND:
8.1. The project in question originated from a Notice Inviting Tender
dated 04.08.2009, which was later amended on 17.08.2009. A pre-bid
meeting was held on 08.09.2009. The minutes thereof were circulated
on 14.09.2009. The respondent participated in the bidding process and,
was declared the successful bidder. It was issued a Letter for agreement
of Award dated 13.10.2009. Thereafter, on 27.11.2009, a Tripartite
Concession Agreement was executed between the Government of
Rajasthan, Jaipur Development Authority and the respondent, a Special
Purpose Vehicle incorporated for implementation of the project.
8.2. Under the Concession Agreement, the respondent was entrusted
with the concession to investigate, design, engineer, finance, construct,
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 6 of 76 ) [CMA-1560/2025]
operate and maintain the project. The project thus stood structured on
a Design- Build- Finance- Operate- Transfer/Build -Operate- Transfer
(DBFOT/BOT) model. The rights and obligations of the parties, the
standards governing execution, the risk allocation between the authority
and the concessionaire, and the remedies available were all intended to
be regulated by the contractual framework, i.e., concession agreement.
8.3. In pursuance of the agreement, the respondent is stated to have
taken financial exposure by entering into a term loan agreement with
Punjab National Bank in March 2010. It is further the respondent's case
that, in the wake of subsequent revisions and escalations, an additional
term loan was sanctioned in April 2011 and formalized in July 2011.
The financial structure initially rested on an approved project cost of Rs.
150 crores, with the term loan and equity infusion being arranged on
that basis. According to the respondent, the situation altered once
execution commenced and the project allegedly encountered serious
deficiencies in the Detailed Project Report (DPR), alignment-related
issues, site constraints and additional instructions issued by the
authority.
8.4. The central factual dispute, i.e., cost escalation (first claim),
between the parties commenced with the respondent's allegation that
the DPR supplied by the department was not merely imperfect but
fundamentally defective in material particulars affecting the structural
and engineering feasibility of the tunnel alignment. The respondent's
case before the learned Tribunal was that, upon transfer of the
alignment on the ground and upon conducting surveys in December
2009 and February 2010, it was discovered that the natural overburden
over the tunnel tubes at material chainages shown in DPR was grossly
inadequate from the standpoint of structural safety, and that the tunnel,
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 7 of 76 ) [CMA-1560/2025]
if executed on the alignment indicated in the DPR, would not conform to
minimum engineering norms. The respondent accordingly treated the
DPR as the source of a foundational defect that compelled redesign and
generated cost consequences.
9. In elaboration of the above, the respondent relied upon its
communications dated 28.04.2010 and 12.05.2010, by which it
highlighted discrepancies in the DPR and proposed alternative solutions.
One option suggested construction of a cut-and-cover tunnel in a
specified valley portion. The other involved lowering the finished road
level to ensure compliance with minimum overburden requirements.
The matter was also referred for technical evaluation, and according to
the respondent, the expert inputs revealed serious concerns regarding
water diversion, forest clearance, slope instability, risk of landslides,
formation of weak junctions, and the need for substantial alteration in
gradient, tunnel length and embankment profile. On that basis, the
respondent asserted that revision in vertical and horizontal alignment
was unavoidable and that the cost implication of the proposed changes
alone was estimated at about Rs. 29 crores.
10. The respondent further asserted that these deficiencies were
eventually acknowledged within the departmental setup. Reliance is
placed on a sequence of communications dated 28.04.2010,
06.09.2010, 20.09.2010, 04.10.2010 and 20.10.2010, and on the
department's agenda note, to contend that the revised horizontal and
vertical alignment submitted by the respondent was approved on
20.10.2010. The respondent also relied upon material to suggest that
the consultant associated with the earlier DPR was debarred for a period
of two and a half years and that the services of its Project Head were
terminated, which, according to the respondent, constituted
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 8 of 76 ) [CMA-1560/2025]
contemporaneous administrative recognition of the defects in the
original report.
11. According to the respondent, even after approval of the revised
alignment on 20.10.2010, further disruption occurred owing to the
presence of Baba Balaknath Samadhi at chainage 0+650, which
allegedly fell within the proposed right of way. It is the respondent's
case that local resistance to removal of the Samadhi compelled
stoppage of work and necessitated a further revision in alignment on
the instructions of the authority itself. Reference is made to letters
dated 14.06.2011 and 18.08.2011, and to subsequent approvals dated
16.11.2011 and 23.04.2012, to assert that repeated redesign had to be
undertaken before work could effectively proceed.
12. The respondent also relies on the statement/cross-examination of
the appellants' witness i.e. Executive Engineer, JDA, to assert that the
encumbrance at chainage 0+650 was not removed and that the
Samadhi fell within the right of way proposed by the claimant.
According to the respondent, this evidence fortified its case that the
delays and design modifications were not self-generated but arose from
site conditions and institutional decisions attributable to the authority.
13. Apart from the alignment issue, the respondent alleged that the
project cost escalated because certain additional works, not originally
envisaged in the bid or base design, had to be executed at the instance
of the authority. These included provision of a truck lay-bye between
chainages 1990 to 2100, a slip road at chainage 2750 for merging
traffic from Goner side, redesign and widening of the rotary, and
widening of connecting roads on both sides of the rotary. The
respondent's case is that these interventions were not voluntary
betterments made for its own commercial convenience, but were
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 9 of 76 ) [CMA-1560/2025]
directed by the authority in the course of project supervision and traffic
management, and therefore generated compensable cost overrun.
14. The respondent further asserts that the rotary works themselves
suffered delay because existing electric cables were not rerouted in time
by the authority. It is also the respondent's case that, during a site visit
on 30.11.2012 by members of the Empowered Committee, DCP Traffic,
JDC and other JDA officials, revision in the approved geometry of the
rotary was suggested, leading to redesign, fresh approval, widening of
the carriageway, and execution of work within an expedited time frame
before inauguration. According to the respondent, all such works were
beyond the original scope and directly impacted project cost and
construction planning.
15. The respondent additionally alleges that it was burdened with
expenditure on facilities provided to the Independent
Consultant/Independent Engineer at the insistence of the authority,
despite there being no contractual provision obliging it to bear such
costs. In support, reliance is placed on the fact that the authority (JDA),
by letter dated 21.04.2010, demanded deposit of an amount of
approximately Rs. 1.799 crores for the Independent Consultant, and
that although the respondent disputed the demand, it was eventually
constrained, in the interest of project completion, to provide office
space, furniture, clerical staff, office boys, vehicles, mobile connections
and other logistical support over a prolonged period. According to the
respondent, this constituted extra-contractual expenditure incurred in
good faith and liable to reimbursement.
16. Yet another factual branch of the controversy pertains to forest
clearance, site availability and encumbrance removal. The respondent's
case is that, at the stage of bidding, it had been represented that land
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 10 of 76 ) [CMA-1560/2025]
acquisition was in process and that the project land would be made
available free from encumbrances prior to commencement of work
under the agreement. However, according to the respondent, forest
clearance remained a live operational difficulty even after award of
work; restrictions on working hours were communicated by the Forest
Department; and by letter dated 06.01.2010, the respondent expressed
its inability to work at full capacity and requested relaxation of time
restrictions. The respondent thus treats delayed or conditional forest
clearance, along with incomplete site readiness, as another cause of
idling, disruption and cost increase.
17. In support of the project cost claim, the respondent also relied on
evidence from Punjab National Bank to show that the original term loan
had been sanctioned after technical vetting of project details, estimates
and traffic survey, and that an additional term loan was later considered
and sanctioned only after the escalated cost component was again
technically vetted. The respondent accordingly sought to estalish that
the escalation in project cost was not hypothetical or self-certified, but
had undergone scrutiny by the lending institution, technical consultants
and the lender's internal mechanisms.
18. The appellants, however, dispute the entire basis of the
respondent's claim for enhanced project cost. Their case, simply put is
that the project stood awarded on a DBFOT basis, under which the
concessionaire had undertaken to conduct its own investigations,
surveys and design development, and could not subsequently shift the
consequences of its own technical or financial decisions onto the
authority. It is further their case that the DPR was appended only as a
reference document and that the governing standards were those
prescribed in the Concession Agreement, the Indian Roads Congress
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 11 of 76 ) [CMA-1560/2025]
norms and MoRTH specifications. According to the appellants, the
respondent was contractually expected to verify the project site, identify
risks and shape its bid accordingly.
19. The appellants also take the factual position that large portions of
the site had been made available, that encumbrances were either
negligible or timely resolved. That the respondent exaggerated the
effect of such issues on the progress of the work. They aver that the
respondent itself delayed action on stretches where approvals had
already been granted and that, in any event, the respondent had
already been substantially compensated through extension of the
concession period. According to the appellants, once such extensions
had been granted under the contractual mechanism, the respondent
could not seek a fresh money decree for the very same causes.
20. The second major head of claim relates to loss of toll revenue.
The respondent asserts that traffic was diverted or leaked through
alternate routes, including the old Ghat Ki Guni road and other
competing roads, and that this affected the toll potential of the project.
The respondent also claims that, owing to demonetisation and toll-
suspension related directions, toll collections were adversely impacted
and loss was caused. These assertions are opposed by the appellants,
who dispute both the existence and extent of any enforceable obligation
on their part and the computation methodology adopted by the
respondent for estimating toll loss.
21. The third claim pertains to compensation for toll loss allegedly
arising from delay in achieving the Commercial Operation Date. The
respondent sought to connect delayed completion with acts or
omissions attributable to the appellants, whereas the appellants denied
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 12 of 76 ) [CMA-1560/2025]
liability and disputed the maintainability of the claim on contractual and
factual grounds.
22. The fourth claim concerned alleged revenue loss resulting from
denial of permission to use the right of way for displaying commercial
advertisements. According to the respondent, the concession
arrangement envisaged commercial advertising opportunities and the
refusal to permit such use caused measurable loss. The appellants, on
the other hand, resisted the claim on grounds including safety,
contractual limitation and limitation in law.
23. As the disputes remained unresolved, the respondent invoked the
arbitration clause contained in the Concession Agreement. By order
dated 28.09.2018 passed by this Court under Section 11 of 1996, the
learned Sole Arbitrator was appointed to adjudicate the disputes
between the parties.
24. During the arbitral proceedings, the appellants also questioned
the arbitrability of the disputes by contending that the Concession
Agreement envisaged a multi-stage dispute resolution mechanism
requiring amicable settlement before recourse to arbitration. The
learned Sole Arbitrator rejected the objection by holding that the plea
had not been raised within the time contemplated by Section 16 of the
Act of 1996 and was therefore liable to be rejected.
25. Upon adjudication, the learned Sole Arbitrator rendered the award
dated 25.06.2023. As already noted, the claims preferred before the
learned Tribunal included are as
(i) Claim No. 1 for increase in project cost quantified at Rs. 175.67
crores,
(ii) Claim No. 2 for loss of toll quantified at Rs. 188.02 crores,
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 13 of 76 ) [CMA-1560/2025]
(iii) Claim No. 3 for compensation of toll loss due to delay in achieving
COD quantified at Rs. 40.71 crores,
(iv) Claim No. 4 for revenue loss on account of denial of use of right of
way for displaying advertisements quantified at Rs. 8.49 crores, besides
declaratory reliefs, return at the rate of IRR and arbitral costs.
By the award, Claim No. 1 was allowed, Claim No. 2 was partly allowed,
Claim No. 3 was rejected, and Claim No. 4 was allowed.
25.1 Thereafter, a corrigendum award dated 31.07.2023 came to be
issued on an application under Section 33(1)(a) of the Act of 1996,
culminating into the instant appeal in hand. Relevant paragraphs of
corrigendum are as below:
"9. From the perusal of the whole award, it is clear that the intention of
the Arbitrator was not to restrict the award amount to Rs.198.04 crores
till the date of the award. Rs.198.04 crores is the amount awarded only
till the date of filing of the claim petition and the said amount does not
include the amount awarded for the period between filing of the claim
petition and the date of the award. The intention of the Arbitrator was to
award the claim till the date of the award. Therefore, "amounting to Rs.
198.04 Crores" has been wrongly mentioned in Para 141 on Page 106
and requires correction. The said correction is only
typographical/clerical.
10. I find that other corrections sought by the Claimant are merely
spelling/typographical errors. I deem it appropriate to allow the
application of the Claimant. The corrigendum for correction of
typographical/ clerical errors in the award dated 25.06.2023 shall be
treated as part of the award. The corrections to be made to the award are
as under:
S.No. Para and Page
of the Award
To Be Replaced/deleted Corrected
Portion/Deleted
Part
1. Para 141 on
Page 106
amounting to Rs. 198.04 Crores Deleted
2. Page 1 Mr. Rajan Khandoliya Mr. Rajan
Khandoliya
3. Para 2 on Page
2
Arbitraion Case No.31 of 2018 S.B. Civil
Arbitration
Application No.
31 of 2018
4. Para 46 on
Page 32
13.5% per annum 12% per annum
5. Para 77 on
Page 61
Annexure C-59 Annexure C-20
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 14 of 76 ) [CMA-1560/2025]
6. Para 74 on
Page 71
Rs.20.787.16/- Lakhs Rs.20.787.16/-
Lakhs
7. Para 98 on
Page 79
letter dated 08.01.2017 letter dated
18.01.2017
8. Page 108 Place of Arbitration: Jabalpur Place of
Arbitration:
Jaipur
11. The application of the Claimant is allowed. No orders on cost."
III. ARGUMENTS ON BEHALF OF THE APPELLANTS:
26. Learned Advocate General for the State, Mr. Rajendra Prasad,
Senior Advocate assisted by Mr. Sheetanshu Sharma, Mr. Tanay Goyal,
Ms. Harshita Thakar, and Ms. Dhriti Sharma, appeared for the
appellants. He argued on the lines of the written submissions handed
over in the course of court hearing. The oral submissions are noted
hereunder, and the written submissions are thereafter reproduced
verbatim:-
26.1 Elaborating the written submissions, Learned senior counsel for
the appellants submitted that the impugned order of the learned
Commercial Court, together with the arbitral award dated 25.06.2023
and the corrigendum award dated 31.07.2023, are contrary to the facts
and the law and deserve to be set aside in their entirety. It is contended
that the award suffers from patent illegality, perversity and irrationality,
and is opposed to the fundamental policy and public policy of India as
reflected in the Limitation Act, the Indian Contract Act, the Interest Act,
and the Rajasthan Road Development Act, 2002 and the Rules framed
thereunder.
26.2 It is further submitted that the learned Sole Arbitrator failed to
test each of the claims against the applicable law of limitation and that,
had such exercise been undertaken, the claims would have been held to
be ex facie time-barred. According to him, this objection went to the
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 15 of 76 ) [CMA-1560/2025]
very root of the adjudication, yet neither the award nor the order under
Section 34 contains a proper or independent determination thereon.
26.3 In relation to Claim No. 1, learned senior counsel for the
appellants submited that the learned Sole Arbitrator fundamentally
misconstrued the status of the Detailed Project Report under the
Concession Agreement. It is urged that, under the contractual scheme,
the governing standards were those prescribed by the Indian Roads
Congress and MoRTH specifications, whereas the DPR was appended
only for reference. He would also rely upon the pre-bid clarification,
especially the response to the bidder's query regarding whether the DPR
was required to be followed, to contend that the non-binding character
of the DPR was made explicit even prior to bid submission.
26.4 He would further contend that the revised alignment had in fact
been placed before and approved by the Empowered Committee
constituted under the Act of 2002. Once such approval was granted,
deviation from the original DPR could not by itself furnish a cause for
monetary compensation against the authority. It is also submitted that
the learned Sole Arbitrator failed to identify any positive contractual
obligation breached by the appellants, and instead proceeded on
assumptions not borne out by the agreement.
26.5 It is next contended that under the scheme of the Concession
Agreement, the ordinary contractual method of compensating the
concessionaire, save in a case of termination payment, was by
extension of concession period and not by grant of cash compensation.
Learned senior counsel would submit that extensions aggregating 484
days (which in money terms yielded additional revenue of Rs. 120
crores to the respondent) had already been granted by the Empowered
Committee. Thus, the learned Sole Arbitrator could not have
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 16 of 76 ) [CMA-1560/2025]
superadded monetary compensation for the same causes. According to
him, the award thereby defeats the negotiated risk allocation embedded
in the contract.
26.6 He would also submit that the learned Sole Arbitrator committed a
manifest error in equating the Internal Rate of Return of 20.33 with an
interest rate payable by the appellants. It is urged that IRR is merely an
internal financial metric relating to the respondent's investment model
and cannot be mechanically converted into an interest entitlement
against the JDA. It is further contended that additional loan
arrangements between the respondent and Punjab National Bank were
private financial arrangements, to which the appellants were not
parties, and that the contractual bar against fastening such financing
consequences upon the authority was ignored.
26.7 He would further argue that the computation of increased project
cost is itself unsustainable. According to him, inasmuch as, components
such as interest during construction, survey expenses, loan processing
fees and allied items were the respondent's own contractual
responsibility. It is also urged that the award failed to account for the
fact that, on account of deviation from the original DPR, the tunnel
length allegedly reduced from 3.70 km to 2.8 km, thereby resulting in
de-scoping and cost saving which ought to have been adjusted against
any escalated claim.
26.8 In relation to Claim No. 2, learned senior counsel for the
appellants would submit that the appellants had undertaken only to
restrict heavy vehicular traffic, namely buses and trucks, from the old
Ghat Ki Guni road, and had never undertaken to ban all tollable traffic,
as was allegedly assumed in the award. It is submitted that the
commitment made by the appellants was honoured through the gazette
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 17 of 76 ) [CMA-1560/2025]
notification dated 31.01.2013 and by erection of physical barriers, and
that any residual flow of other vehicles could not translate into a
contractual claim for damages.
26.9 As regards the demonetisation component of Claim No. 2, it is
submitted that the same was allowed without the mandatory
certification by the Steering Group and verification by the Chief
Engineer, JDA/UDH, allegedly required under the contract. It is further
contended that demonetisation caused no material adverse effect of the
kind claimed, particularly when the toll denominations were below the
affected currency values and when the project road did not fall within
the category of National Highways to which certain tolling directions
were addressed.
26.10 With respect to Claim No. 4, learned senior counsel for the
appellants would contend that the learned Sole Arbitrator recorded no
sustainable finding either on whether the proposal for advertisements
compromised road safety or on whether the quantified loss of Rs. 8.49
crores was proved in accordance with law. The appellants also assail the
grant of costs. He would also submit that the corrigendum award
exceeded the limited jurisdiction available under Section 33 of the Act of
1996 by making a substantive alteration under the guise of clarification.
26.11 Lastly, it was argued that the learned Commercial Court failed to
discharge the jurisdiction vested in it under Section 34 of the Act of
1996. According to learned senior counsel for the appellants, the
Commercial Court proceeded on an unduly narrow understanding of its
powers, mechanically reproduced the restrictive principles governing
Section 34 review, and failed to independently examine the specific
grounds of patent illegality, contractual infraction and public policy
violation raised in the objections petition.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 18 of 76 ) [CMA-1560/2025]
26.12 WRITTEN SUBMISSIONS ON BEHALF OF THE APPELLANTS
(reproduced verbatim):-
Apart from the arguments addressed before the Court, written
submissions on behalf of the appellants were also tendered during the
course of hearing. For ready reference relevant portion of written
submission thereof are reproduced hereinbelow:-
“ POINTS OF SUBMISSIONS
I.The Agreement was a DBFOT concession providing only for extension
of the concession period, and no cash compensation; the award ofcash
compensation amounts to re-writing of the contract.
Award: Arbitrator has taken a contrary stand on this by allowing
Claim 1 and denying Claim 3 in Para 130
Relevant Docs: Concession Agreement (Vol II) Cl. 10, 12.
II. Article 16 (disclaimer) expressly allocated the design-risk and
waswrongly nullified on misapplied precedents
Claimant entered into the contract with open eyes and therefore
could not dispute its obligations and the terms made under it (RIICO
vs Diamond and Gem, (2013) 5 SCC 470 – Para 23)
Disclaimer clause was not in teeth of any provision of the Indian
law (Para 71 @ Pg 52 of the Award)
Board of Trustees for the Port of Calcutta vs. Engineers-De-Space
Age, (1996) 1 SCC 516 and the Delhi High Court in Simplex Concrete
Piles (India) Ltd. vs. Union of India, 2010 SCC OnLine Del 821 both
authorities were misapplied and are clearly distinguishable on facts
Ignored binding precedent in the case of Ramnath International
Construction (P) Ltd. vs. Union of India, (2007) 2 SCC 453.
III. The DPR was a reference document only; treating it as
mandatoryreference contradicts Clauses 2.1, 5.1, Article 7 and
Schedule-A.
Under the DBFOT scheme, investigation and design were the
Concessionaire’s exclusive responsibility
Relevant Docs: Query No. 99 of the Pre-Bid Meeting (An. C3)
Award passed clearly contrary to the contract and evidence.
IV. No breach by the Appellants was found; damages without breach
goesagainst Sections 54/55/73 of the Contract Act.
Learned Arbitrator does not any breach of contractual obligation

attributable to the Appellants
Kailash Nath Associates vs Delhi Development Authority, (2015) 4
SCC 136.
V. The 484-day extension already compensated the Respondent;
theaward therefore directs double recovery.
Initial extension in the concession period for 379 days awarded for
any extra cost that might have accrued to the Claimant at the start of
the project due to change in alignment
Second extension of 105 days was granted for hindrances and
encumbrances leading to delay in the Project.
VI. Para 124 contradicts the allowance of Claims 1, 2(i), 2(iii) and 4
andvitiates the award.
Para 123 (Pg 96) - The Contract between the parties shows the

joint intent of both the parties and has to be interpreted holistically
(previously contrarily and erroneously holding that design faults are
the Appellants’ fault while the obligation was on the Claimant)
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 19 of 76 ) [CMA-1560/2025]
While denying Claim 2(iv), in para 124 Ld Arbitrator observes that
the agreement does not provide for cash compensation but only
extension, therefore the claim for cash compensation is rejected
This observation renders the award internally contradictory which
makes it patently illegal and liable to be set aside.
VII. IRR was wrongly equated with interest, inflating the claim and
theinterest rate (20.33%).
IRR is defined as the discount rate that makes an investment’s net
present value of cash flows equal to zero; it is used to see the viability
of an investment
IRR assumes that any cash payouts received during the investment
are immediately put back as re-investment which is clearly not the case
herein
IRR was part of a Feasibility Study of the Agreement and was not
an admitted or agreed upon term (An. C7 Vol II Pg 152)
Claimant’s argument would mean that IRR is a guarantee of
returns, which is clearly contrary to the entire framework of the
Agreement. IRR is an entirely fictional measure based on estimates to
see probable profitability of an investment.
Reliance on State of Maharashtra vs. Khare & Tarkunde
Infrastructure Pvt. Ltd., 2021 SCC OnLine Bom 220, by the
Arbitrator is misplaced as there the High Court upheld interest
reflecting the actual bank rate the contractor was paying its lenders.
All Claims have also been grossly inflated based on the
compounding nature of IRR
When applied as interest by the Arbitrator, it is without any
analysis as to reasonability and in absolute non-consideration of
relevant factors applicable while calculating interest.
VIII. Claim 2(i); there was no obligation to ban all tollable traffic, and
the Appellants in fact issued the 31.01.2013 notification.
Consistent with the pre-bid assurance, the Appellants in fact issued
a gazette notification on 31.01.2013 banning heavy vehicles on the old
GKG road, diverted that traffic to the project road, and erected
barriers. The Appellants thus performed the only obligation they had
undertaken (DOC).
IX. Claim 4 elevated private profit over user safety and ignored
theEmpowered Committee’s safety rejection.
Article 17.3 permitted advertising subject to user safety. The
Empowered Committee, vide its meeting dated 06.02.2015, rejected the
advertising proposal precisely because the serpentine alignment
rendered roadside advertising unsafe. (Award Para 137, 138)
X. Ld. Arbitrator, without holding the safety rejection unjustified, simply
accepted the Claimant’s figure of Rs. 8.49 crore and faulted the
Appellants for an alleged “lack of concern for the profit-earning
opportunity” of the Claimant, thereby elevating private profit over
public safety, which is arbitrary, perverse and beyond the contract.
XI. Claim for any escalation in cost is barred by Limitation.
Work Completed on 31.03.2013, hence, no additional costs to
accrue after this date; therefore, limitation has to run from this date –
3 years as per Art. 55/113.
Relevant Docs: Para 4.9 Claim @ Pg 36; Work Completion
certificate An C-11A Vol III Pg 495.
XII. The corrigendum award exceeded Section 33 by granting
[email protected]% not granted in the original award.
The allowance of deletion of “amounting to Rs. 198.04 cr.”
changes the entire quantum of the award and grants a subsequent
substantial relief which is not a clerical or typographical error
permitted to be corrected under Section 33.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 20 of 76 ) [CMA-1560/2025]
XIII. The impugned order is non-reasoned and failed to apply
therecognised Section 34 tests.
Ld. Commercial Court merely re-iterates the arguments of the
parties and holds that it does not have appellate power under Section
34 and since it is a detailed and reasoned award it cannot be set aside
Ld. Commercial Court fails to test the arguments against the
parameters enshrined in Section 34.
Therefore, it is most respectfully prayed, that the present appeal may
be allowed and the impugned order dated 27.01.2025 passed by the
Learned Commercial Court and the impugned awards dated
25.06.2023 and 31.07.2023 may kindly be quashed and set aside."
IV. ARGUMENTS ON BEHALF OF THE RESPONDENT:
27. Au contraire, Mr. Sudhir Gupta, Senior Advocate, assisted by Mr.
Tarak Ahuja, Ms. Sweta Chauhan, Mr. Ishan Khanna, Mr. Aditya
Shandilya and Mr. Rachit Somani, argued in favour of upholding the
impugned award, canvassing rather strenuously that, this Court must
dismiss the appeal, given the limited scope under Section 37 of the Act
of 1996, which is far more circumscribed than Section 34 itself. Apart
therefrom, he addressed arguments on merits of the award and also
tendered written submissions in support of his arguments.
27.1 In course of his arguments, learned senior counsel for the
respondent would rather vigorously urge that the learned Sole
Arbitrator undertook a detailed examination of the pleadings, the
documentary record, the correspondence exchanged between the
parties, the contractual framework, and the oral evidence led before the
learned Arbitral Tribunal, and thereafter returned a reasoned award
which did not warrant interference under Section 34 of the Act of 1996
and thus the instant appeal be also dismissed.
27.2 On merits, learned senior counsel for the respondent would
submit that the Detailed Project Report supplied at the inception
contained material deficiencies which directly affected the structural
feasibility and safe execution of the project. According to the
respondent, the revision in horizontal and vertical alignment was
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 21 of 76 ) [CMA-1560/2025]
compelled by engineering realities and site conditions, and not by any
unilateral commercial preference of the concessionaire. It is urged that
the subsequent approval of the revised alignment, the departmental
agenda notes, and the action taken against the consultant associated
with the DPR all support the respondent's case that the original report
was defective and that the resulting redesign generated compensable
consequences.
27.3 It is further submitted that the respondent had
contemporaneously brought the discrepancies to the notice of the
appellants, furnished alternative technical options, disclosed the cost
implications thereof, and proceeded only upon administrative approval.
According to the learned senior counsel for the respondent, the chain of
correspondence and approvals clearly demonstrates that the redesign,
the additional alignment work, and the consequential delay were within
the knowledge of and accepted by the appellants.
27.4 He also contended that the presence of Baba Balaknath Samadhi,
the non-removal of the encumbrance at chainage 0+650, and the
resulting need for further revision in alignment were matters
attributable to the appellants and not to the respondent. He relied upon
the material noticed in the award to submit that the encumbrance was
not removed and that corrective measures had to be taken in
consequence thereof.
27.5 As regards additional works, he would submit that the provision of
truck lay-bye, slip road, redesign of the rotary, widening of the rotary
and adjoining roads, and provision of facilities to the Independent
Consultant were all either specifically directed by the appellants or
necessitated by the manner in which the project was supervised and
modified during execution. According to him, these were not cost items
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 22 of 76 ) [CMA-1560/2025]
already internalized in the original project estimate and hence the
learned Sole Arbitrator rightly treated them as contributing to the
increase in project cost.
27.6 He would further submit that issues concerning forest clearance,
restricted working hours, site encumbrances and delayed availability of
an unhindered work front materially affected execution and contributed
to delay and escalation. It was urged that the lending arrangements,
additional technical vetting and sanction of additional finance by the
bank corroborate the existence of actual cost overrun and demolish the
appellants' suggestion that the claim was speculative or unsupported.
27.7 In relation to Claim No. 2, the learned senior counsel for the
respondent would submit that the communications issued by the
Government, the traffic restrictions and the actual traffic conditions on
the ground adversely affected toll collection and that the learned Sole
Arbitrator assessed the loss on the basis of material placed before him.
It is also the respondent's case that the impact of demonetisation on
tolling revenue was real and was duly appreciated in the award.
27.8 As regards Claim No. 4, it is submitted that denial of permission
to commercially use the right of way for advertisements caused
measurable revenue loss and that the award on this issue rests on a
valid appreciation of the contractual arrangement and the evidence led.
27.9 Learned senior counsel for the respondent lastly reiterated that
the learned Commercial Court correctly appreciated the limited scope of
interference under Section 34 of the Act of 1996. The Court exercising
jurisdiction under Section 34 does not sit in appeal over the award and
cannot reappreciate evidence or substitute one plausible interpretation
of the contract for another, he would urge. It is therefore urged that
once the view taken by the learned Sole Arbitrator was a possible and
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 23 of 76 ) [CMA-1560/2025]
reasoned view, the learned Commercial Court rightly declined
interference and this Court, while examining the appeal, ought not to
unsettle that conclusion save on the recognized grounds available in
law.
27.10 WRITTEN SUBMISSIONS ON BEHALF OF THE RESPONDENT
(reproduced verbatim):-
"Submissions: -
Vide the present Appeal, the Appellant has made averments and raised
grounds against the Award and Order passed by the Commercial Court,
which are totally beyond the scope of Section 37.
1. The contours of jurisdiction vested in this Hon’ble Court by virtue of
Section 34 and 37 of the Act are settled by a plethora of decisions of the
Hon’ble Supreme Court and reiterated by several Hon’ble High Courts
including this Hon’ble Court, whereby it has been held as under:
i. Jurisdiction under Sections 34 and 37 is not akin to appellate
jurisdiction and arbitral awards cannot be interfered with in a cavalier
or casual manner by re-appreciation of evidence.
ii. Construction of the terms of the contract is primarily for an arbitrator
to decide and if an Arbitrator construes a term of the contract in a
reasonable manner, it cannot be set aside.
iii. When a view taken by the Arbitrator is a plausible view, no
interference under Section 34 is warranted.
iv. Mere illegality or irregularity is not sufficient to invite interference
under Section 34, rather it has to be demonstrated that the illegality is
‘patent’ which goes to the root of the matter.
v. Fresh grounds and pleas which were not taken by a party before the
arbitrator, cannot be taken for the first time in proceedings under Section
34 or 37 of the 1996 Act.
2. The plea of limitation in the present Appeal was not raised before the
Arbitrator, hence barred from being taken for the first time in the present
proceedings. It is settled proposition of law that the limitation is a mixed
question of fact and law. Adjudication of this ground would require re-
appreciation of evidence.
3. The Project was implemented in DBFOT mode, constructed by the
Respondent with its own funds along with the funds borrowed from the
financial institution(s).No amount has been paid by the Appellant either
towards cost of construction or towards compensation awarded by the
Arbitral Tribunal.
4. The grounds taken by the Appellant are not permissible within the
limited scope of Sections 34 and 37 of the A&C Act.
5. It is a settled proposition of law, in case an Arbitral Award has been
upheld under Section 34 of the Act, the Appellate Court must be
extremely cautious and slow to disturb such concurrent findings as the
scope of intervention under Section 37 is even narrower than Section 34.
6. Various grounds raised by the Appellant are devoid of any substance
and merit and are not sustainable as per settled proposition of law. The
Grounds are of such a nature as would entail review on merits of the
matter by reappreciation of evidence, which cannot be permitted.
The matter has been heard by this Hon’ble Court on 03.07.2026,
06.07.2026, 07.07.2026 & 08.07.2026 and the judgement has been
reserved for order.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 24 of 76 ) [CMA-1560/2025]
Detailed Submissions made by the Respondent in response to the various
contentions/grounds raised by the Appellant during the course of hearing
are briefly stated hereunder, for ready reference:
A.1 New Grounds (Not raised before the Arbitral Tribunal and / or
Ld. Commercial Court):
A.2 Grounds raised by Appellant: Ld. Commercial Court / Arbitrator
has not dealt with the barrier of Limitation.
Reply:
Appellant has failed to raise this ground before the Arbitral
Tribunal and is deemed to have been waived off nor did the Appellant
address oral arguments on the said ground before the Ld. Commercial
Court. Increase in project cost could only be ascertained only at
Commercial operations Date (COD) i.e. 31.01.2013. Thereafter, the
Respondent invoked dispute resolution mechanism as per Article 15 in
2014. The Appellant itself recognizes that the final decision in the said
regard was taken in 2015. Since, the decision in regard to failure of
amicable settlement was only taken on 22.06.2015 (R-1, Pg.99; Reply to
SoC). Therefore, considering 2015 as the year of breaking point/
rejection of the claim of the Respondent gave cause of action to the
Respondent and accordingly, arbitration was invoked within 3 years by
the Respondent on 18.09.2017. The cause of action for each of claims
allowed by the Arbitrator have been provided below in a tabulated
form:-
Claim.
No
Claim Particulars Cause of Action Remarks as
to Limitation
01 Increase in Project
Cost amounting to Rs
175.67 Cr
11.09.2015 Well within
limitation period
of 3 years
02 Loss of Toll:
Old GKG Road leakage Rs
12.20 Cr Demonetization Rs
1.68 Cr
Continual in
nature 02.12.2016
NA
Well within
Limitation period
of 3 years
03 Advertisement Rs8.49 Cr Empowered
Committee
meeting on
22.06.2015
Well within
limitation period
A.3 Grounds raised by Appellant: Award of IRR of 20.33%
compounding annually is in contradiction of S. 31(7) of the Arbitration
Act. At the most Arbitrator could have awarded interest as per S. 31(7).
Reply:
Appellant has never raised this ground before Ld Commercial
Court and has been pleaded for the first time. Noteworthy, Appellant has
also never disputed the computation of claims submitted by the
Respondent. There is no contravention of Section 31(7) of the
Arbitration Act. The Arbitral Tribunal has examined in depth the concept
of IRR in paras 72, 73, 74, 75, 84 and 141, and has accordingly granted
IRR on the Claim amount which forms part of the cash flow statement
contained in Annexure A of the Concession Agreement (CA). Lastly, IRR
being a financial arithmetic term by the very nature demonstrates
annually compounded financial return. The Arbitral Tribunal as per
Section 31
(7) of A&C Act, granted 12% p.a. interest on the awarded amount for the
future period only, if in case the awarded amount is not paid within 90
days from the date of the Award.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:18 PM)

[2026:RJ-JP:30253-DB] ( 25 of 76 ) [CMA-1560/2025]
A.4 Grounds raised by Appellant: Arbitrator failed to take cognizance
of extension of concession period by 484 days thereby compensating
more than 120 Cr by way of toll collection.
Reply:
This ground was never raised before the Arbitrator, and was raised for
the first time in S 34 Proceedings.
st
1 Grant of 379 days was ought to be given on account of change in
commencement date, as recorded vide MoM dt.05.01.2012 (R-24(Colly),
Pg. 53; Reply to Rejoinder). Later on instead of changing the
commencement date, extension of concession period was granted. In
essence compensation was for delay not for increase in project cost.
nd
2 grant of 105 days was granted vide 22-06-2015 against
Concessionaires claim of 210 days incurred during the end of
construction period.
Respondent had made separate claims for Increase in Project Cost &
Extension of Concession Period. Appellant had only granted extension of
Concession.Period and denied the Claim for Increase in Project Cost
citing that there exists no provision for compensation of Increase in
Project Cost.
Total Concession period comprised of Construction (Implementation)
period and Operation Period. Delays incurred were in the construction
period and accordingly same were granted. However, this has not
resulted into additional revenue generation, whatsoever, for the
Concessionaire as this merely affected extension of COD.
Other Grounds:
4 Grounds raised by Appellant: Deletion of “amounting
to Rs 198.04 Cr” in the corrigendum award enlarging Award amount
from 198.04 Cr to Rs 457 Cr, amounting to modification of award.
Reply:
Para 141 cannot be read in isolation to infer that amount of Award was
restricted to 198.04 Cr. This has to be read with para 139 citing
operative part of the Award that clearly shows the amounts of claim
allowed till the date of reference i.e. 31.01.2019, against individual
claims, which when added reached to Rs 198.04 Cr.
Hence, reading the Award as a whole necessarily implies that the words
“ amounting to Rs 198.04 Cr ” have been inserted erroneously. Ld. Sole
Arbitrator in Corrigendum Award, clearly includes the rationale behind
correction of this peripheral mistake / error in para 6 of the
corrigendum award.
4 Grounds raised by Appellant: Award of Monetary
Compensation along with IRR is against the basic framework of CA, as
grant of Concession Period was the sole criteria for bidding and any
remedy thus could have been sought only in terms of Concession Period.
Reply:
Although, sole criteria for bidding was the grant of Concession Period,

the Cash flow projections in the format provided by the Appellant forms
the part of CA. The Cash Flow Projections forms the very basis of
arriving at the grant of Concession Period and thus cannot be plainly
rejected as beyond the framework of CA. Had cash flow projections &
IRR been of no relevance, Appellant would not have included the same
in its own format as part of the CA.
CA framework contemplates compensation by way extension of
Concession Period only as could be made out by the provisions of Art
10.3, Art 11.5, Art 13.2, but has failed to cite any provision in the CA
that expressly bars for compensation in cash. In absence of such
provision in CA, Concessionaire cannot be left deprived of any remedy.
The Ld. Sole Arbitrator in paras 71, 72 and 80 has given the rationale
for award of monetary compensation in absence of any bar in CA for
seeking compensation.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 26 of 76 ) [CMA-1560/2025]
All the above provisions in CA providing for the extension of
Concession Period are pertaining to the specific event that may occur
during the tenure of the Project; however, do not deal with breach of
contract for the peculiar reasons in this Contract.
Appellant has never denied Increase in Project Cost by 57.85 Cr;
however, the Appellant has rejected Concessionaire’s request on the
basis that Project Cost could not be more than 150 Cr citing the its
definition and further stating that there exists no provision in CA for
Increase in Project Cost (Lt. 30.01.2015, C-39,Pg.684, Vol-5;SoC))
Ld. Sole Arbitrator vide para 80 of the Award has held that “ CA is
silent with regard to payment of damages/ compensation in the event
of breach of Contract” while allowing monetary compensation as the
same are not explicitly barred in the CA. Noteworthy, Arbitrator has
also in the same para observed that “situation would have been
different had there been a prohibitory clause barring payment of
compensation”
Moreover, pursuant to the passing of the Corrigendum Award, the
Appellantshad unilaterally and illegally invoked Respondent’s Bank
Guarantee amountingto Rs 3.00 Cr on 27.11.2024 for effecting
recovery of dues, thereby not onlyexplicitly relying upon but also acting
upon the cash said flow projections Pg.359, Vol-2 of SoC in the
Concession Agreement in pursuance of whichpayment of Rs 3.42 Cr
was required to be made by the Respondent on any dayin April 2021 to
the Appellant.
4 Grounds raised by Appellant: Award is made without taking into
cognizance ‘Article 16.2 – Disclaimer’ and its applicability in DBFOT
projects .
Reply:
Art 16.2 starts as ‘without prejudice to any express provisions
contained in this Agreement ….’ meaning thereby that the provisions of
the said disclaimer clause are subject to any express provision in the
Agreement including the Schedules appended thereto.
Appellant in NIT has declared the “Alignment and other parameters
are duly approved by JDA” leaving no room for any doubt upon
error/mistake as claimed vide Disclaimer Clause of 16.2. Further, as
Clause 2.5 of Annexure I to Schedule A expressly provides that
horizontal and vertical alignment of the DPR are the minimum
standards and only deviation therefrom is permitted with a view to
enhance the standard of safety and mobility, the DPR would be covered
within the expression ‘Without prejudice to any express provision
contained in this Agreement’ occurring in the opening sentences of
Clause 16.1.
Also, disclaimer vide Article 16.2, explicitly provides for the nature
and extent of difficulties, risk and hazards which the concessionaire is
likely to face during performance of its obligations under the
Agreement. By no stretch of imagination it was likely that the
Concessionaire would have foreseen difficulties that were faced on
account of faulty DPR.
The Ld. Sole Arbitrator in para 66, 67 of the Award has given its

rationale qua the same.
4 Grounds raised by Appellant: Arbitrator considered the DPR as an
important document which actually was provided as a reference
document.
Reply:
Alignment, cross sections and other parameters provided in the DPR

was included as it is in the Concession Agreement at Appendix A-1, Vol
3 schedule.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 27 of 76 ) [CMA-1560/2025]
NIT at Pg. 81 Vol-1 of SoC expressly declares that “Alignment and
other parameters are duly approved by JDA” leaving no room for any
doubt upon error/mistake as claimed vide Disclaimer Clause of 16.2
Appellant on one hand has termed this as reference document allowing
concessionaire to adopt its own design and on the other has made
certain minimum/design requirements set forth in Schedule A of Annex I
of the CA, by virtue of which finished top level of the road cannot be
changed.
DPR was defective to such an extent that Appellant debarred the DPR

consultants and terminated the services of Advisor (RRP)-Project
Head-Member Secretary of the Project.
Arbitrator in para 65 of the Award has discussed the relevancy and
importance of DPR in DBFOT project.
4 Grounds raised by Appellant: Arbitrator allowed entire Project
cost. At the most he could have granted change of scope as per Art 10.
Reply:
Art 10 applicable for Change of Scope has to be initiated by GOR by
providing COS order, provided that:
4..a It does not require expenditure exceeding / reducing 10% of
Project Cost i.e Rs 15 Cr; and
4..a It does not adversely affect the Scheduled Project
completion date
Art 10.3 casts duty upon Appellant to determine the increase / reduction
in the Concession Period only in event of COS Order being issued has
impact of more than 2% of the Project Cost.
In present case, GOR did not issue any COS order as the Change in
Project cost were not required by GOR as contemplated under Art 10,
but, the change in project cost was compelled beyond 10% on account
of blatant deficiencies in tunnel alignment and other parameters.
Hence, the Project contemplated under the CA Schedule A was
completely overturned to significant extent beyond 10% project cost
and the Project Completion Date was also adversely affected .
4 Grounds raised by Appellant: Arbitrator has made contradictory
findings in the Award as to the grant of monetary compensation.
Reply:
Ld. Sole Arbitrator has rejected monetary compensation for claims No
3 vide para 124, stating that “ claimant having not asked for extension
cannot make out claim” .
The aforesaid finding is not contradictory; rather is complying with the
CA provisions which include the decisions taken in pre-bid meetings.
Arbitrator has discussed reply to the relevant pre-bid query No.6 in
para 122 for competing roads observing that “Any change in
concession period because of development of future requirement would
be addressed by the Committees under Art 15.1 of CA”. Gathering joint
intent of the parties therefrom to seek remedy on such account in the
form of extension of concession period Tribunal had rejected the
monetary compensation.
However, in case of Claim No 1 Increase in Project Cost, Claim No 2
(i) Old GKG road Cl No 2 (iii) Demonetization & Claim No 4 for
Advertisement, Arbitrator has inferred grant of monetary compensation
as the CA is silent upon the remedy in case of breach of Contract as
observed vide para 80 of the Award.
Grounds raised by Appellant: IRR as a concept is completely
4
foreign to the CA and is an internal mechanism of the Concessionaire.
Arbitral Award of IRR @ 20.33% is equated to interest.
Reply:
IRR being included in cash flow projections form part of CA and
cannot be termed as foreign to CA.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 28 of 76 ) [CMA-1560/2025]
IRR is a finance term regularly used in financial analysis to estimate
the commercial viability of potential investments. IRR is a discount rate
that makes the net present value (NPV) of all cash flows equal to zero
in a discounted cash flow analysis
Ld. Sole Arbitrator vide paragraph 72, 73, 74, 75, 84 and 141 of the
Award has discussed the concept of IRR and its relevance into cash
flow projections and compared with the ordinary levy of interest
observing that as and when the project becomes profitable, IRR
increases.
All the investments being made by Concessionaire were agreed to
generate IRR of 20.33% as contemplated under Cash Flow Projections.
As there happened to be increase in Project cost by Rs 57.87 Cr,
requiring Concessionaire to additionally invest this amount,
Concessionaire is legitimately entitled to recover the additional
investments made at an IRR of 20.33%.
4 Grounds raised by Appellant: Arbitrator failed to appreciate
definition of Project Cost & Art 9.2 ‘Amendments to financing
documents.
Reply:
Appellant has neither disputed the Project Cost to Rs 207.85 Cr nor
objected the Statutory Auditors certificate certifying Project Cost of
207.85 Cr.
Definition of Project cost cannot be viewed in isolation and has to be
strictly viewed in correlation with the definition of Project.
Project as defined in CA is as described in Schedule A, has completely
changed on account of facts witnessed during the course of execution.
The tunnel length, that was the heart of project, increased from 647 to
875 mtrs along with many other variations on account of various
deficiencies found in the DPR but also majorly due to additional works
undertaken as clearly depicted in the comparative statement vide
Annex. C-23, Pg. 547, Vol-3 of SoC.
Ld. Sole Arbitrator vide para 80 of the Award held that the “ Project
Cost has rendered otiose or futile in view of a project has suffered a
complete overturn ”
Ld. Sole Arbitrator vide para 85 of the Award held that it has of
hesitation in accepting the certificate of Chartered Accountant more
particularly because the Appellant has cross examined CW 2 & 3.
Art.9.2. has limited applicability only in the event of Termination.
4 Ground raised by Appellant: Arbitrator failed to appreciate that
Appellant has fulfilled its obligation by issue of Notification for Banning
of tollable vehicles through Old Ghat ki Guni Road:
Reply:
Appellant had expressly promised vide Pre bid reply query that the Old
GKG route will be totally banned/restricted by all tollable vehicles.
(Refer to Pre-Bid query nos. 9,66,85,92)
Appellant through Police Dy. Commissioner – Traffic had issued

Gazette Notification dt.31-01-2013 banning of tollable traffic through
Old GKG Road, however, took no effective measures to implement the
same.
Even after Respondents repeated requests to conduct joint survey,
Appellant failed to undertake such surveys to ascertain factually the
leakage of traffic through Old GKG Road.
Ground raised by Appellant : Claim No 4 On account of Denial to
4
use ROW for Displaying Commercial Advertisement
Reply:
Art 17.3 of the CA, Concessionaire was entitled to display
advertisements, display or hoarding such on the Project site, subject to
it does not affect the safety of the users of the Project Road while
driving.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 29 of 76 ) [CMA-1560/2025]
Concessionaire submitted the tentative locations to put up hoardings;
however, Appellant plainly rejected the same without assigning any
reason on 22.06.2015 (MoM 31.07.2015, R-1, Pg.98; Reply to SoC),
thereby depriving Respondent of its legitimate right to earn revenue
through display of Commercial Advertisement.
Apart from the above submissions, the Respondent herein below apprises
this Hon’ble Court of the subsequent developments and present status of
Project Concession Agreement after the pronouncement of Award
(including corrigendum Award) and during the pendency of present
proceedings:
A.1 The Concession Agreement has come to an end on 11.10.2024 by
efflux of grant of concession period and its extension.
Thereafter, Respondents reliably understand that Appellants have
A.2
appointed private toll collection contractor for a period of 6 years and
are earning revenue of approximately around Rs 895 Cr Approx.
therefrom by way of equated monthly installments.
A.3 Appellants had unilaterally and illegally invoked Respondents
Bank Guarantee amounting to Rs 3.00 Cr on 27.11.2024 by explicitly
relying upon and acting upon the cash flow projections Pg. 359, Vol-2 of
SoC in the Concession Agreement in pursuance of which payment of Rs
3.42 Cr was required to be made by the Respondent on any day in April
2021 to the Appellant. On one hand, the Appellant before this Hon’ble
Court denies the relevancy of DPR as reference document, as well as
applicability of Cash flow projections and IRR included therein as
merely estimates, and on the other hand the Appellant takes unilateral
coercive action of invoking Respondent’s Bank Guarantee for effecting
recovery of dues by explicitly relying upon and acting upon the very
same DPR & Cash flow Projections which form part of CA and
envisages the payment of Rs.3.42 Cr. by the Respondent to the
Appellant."
V. DISCUSSION AND FINDINGS
28. Heard learned counsel for the parties at length and perused the
entire record, including the impugned order dated 27.01.2025, the
arbitral award dated 25.06.2023, the Corrigendum Award dated
31.07.2023, the Concession Agreement dated 27.11.2009 together with
its Schedules, the minutes of the pre-bid meeting dated 14.09.2009,
and the written submissions filed on behalf of both sides. In light
thereof we shall now proceed to render our opinion based on the
discussion and analysis recorded here in after in the light of the settled
principles governing judicial interference with arbitral awards.
29. Before we proceed further, apt it is to observe that the principal
ground taken in the objections, as noticed by the Commercial Court,
was that the award was contrary to the public policy of India, contrary
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 30 of 76 ) [CMA-1560/2025]
to the terms of the contract, and vitiated by patent illegality. The
respondent resisted the objections by supporting the reasoning of the
award and by submitting that the learned Sole Arbitrator had rendered
a detailed and reasoned decision on the basis of the pleadings,
documents and evidence led in the arbitral proceedings.
30. The Ld. Commercial Court upheld, in substance, the resistance to
interfere in the award, as canvassed by the claimant and inter alia held
that the scope of interference under Section 34 of the Act of 1996 is
limited, that reappreciation of evidence is impermissible, and that the
findings returned by the learned Sole Arbitrator on Claim Nos. 1, 2 and
4 were reasoned, plausible and supported by material on record.
A. QUESTIONS FOR DETERMINATION
31. Even though there is no requirement of framing any questions of
law in exercise of appellate jurisdiction under Section 37 of the Act of
1996, however, for our own clarity and convenience of structuring our
judgment, and to distill the arguments of both parties, we feel that the
following core questions arise for determination:-
(i) Whether the claim petition of the respondent was ex facie
barred by limitation?
(ii) Whether the arbitral award dated 25.06.2023, as modified by
the corrigendum award dated 31.07.2023, suffers from patent
illegality or is in conflict with the public policy of India.
(iii) Whether the learned Sole Arbitrator traversed beyond the
scope of the Concession Agreement, thus rendering the award
unsustainable in law.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 31 of 76 ) [CMA-1560/2025]
(iv) Whether the corrigendum award dated 31.07.2023 exceeds the
permissible scope of Section 33 of the Act of 1996.
(v) Whether the learned Commercial Court failed to exercise
jurisdiction vested in it under Section 34 of the Act of 1996 while
declining interference with the award.
B. RELEVANT CONTRACTUAL CLAUSES AND STATUTORY
PROVISIONS
a) Contractual Stipulations of the Concession Agreement
32. Before adverting to the merits of the issues framed hereinabove,
it would be apposite to identify, with specificity, the contractual
stipulations of the Concession Agreement which stand attracted in the
light of the written submissions and the passages extracted from the
award and the objections as already noticed in the record.
The issues canvassed by the parties require consideration, inter
alia , of the following clauses of the Concession Agreement, along with
their subject-heads:
S. NO. Relevant Clauses Particulars
1. Clause 1.1 Definitions
2. Clause 2.1 Grant of Concession
3. Clause 2.2 Concession Period
4. Clause 2.3 Acceptance of Concession
5. Clause 2.6 Environmental Clearance
6. Clause 4.1(a) Right to Levy, Demand, Collect and
Appropriate Fee
7. Clause 5.1 General Obligations of the
Concessionaire
8. Clause 7.1 Preparation of Drawings
9. Clause 9.2 Amendments to Financing
Documents
10. Article 10 Change of Scope
11. Clause 11.5 Force Majeure and Consequential
Relief/Extension
12. Clause 11.6(d) Certification / Verification in relation
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 32 of 76 ) [CMA-1560/2025]
to Force Majeure consequences
13. Clause 12.1(b) Notice of Breach
14. Clause 12.2 (b) (2) Termination Payment
15. Clause 13.2 Change in Law
16. Clause 15.1(a) and
Clause 15.1(c)
Dispute Resolution / role of the
Empowered Committee and
expressly stated contractual
departures
17. Clause 15.2 Arbitration
18. Clause 16 / Clause
16.2
Disclaimer / Independent
Evaluation / Acceptance of Risk of
Error
19. Clause 17.7 Amendment only in the manner
provided in the Agreement
20. Schedule A Project Description and Broad
Particulars
21. Annexure I to
Schedule A, Clause
1.1
Alternative Design / Cross-Sections /
Lowering of Formation Level in case
of apparent DPR errors
22. Annexure I to
Schedule A, Clause
2.5
Minimum Parameters for Horizontal
and Vertical Alignment.
b) The Statutory Framework
33. Insofar as the statutory framework is concerned, the issues would
require consideration of, among others, Section 11, Section 31, Section
33, Section 34 and Section 37 of the Act of 1996. The challenge to the
corrigendum award would fall to be considered in the context of Section
33 thereof. The scope of judicial interference with the award, and with
the order passed under Section 34, would necessarily be examined in
the light of Sections 34 and 37 of the Act of 1996.
34. The appellants have additionally invoked the Limitation Act in
support of their objection that the claims, or some of them, were barred
by time.
35. The controversy concerning grant of compensation and the nature
of contractual breach would also require reference to the relevant
provisions of the Indian Contract Act, including the principles embodied
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 33 of 76 ) [CMA-1560/2025]
in Sections 54, 55 and 73, as relied upon by the appellants, and the
broader contractual law principles governing claim for damages during
subsistence of contract as noticed by the courts below. The plea
concerning award of interest would also have to be examined in the
light of the Interest Act and the principles governing arbitral discretion
in awarding interest.
36. The Rajasthan Road Development Act, 2002 and the role of the
Empowered Committee constituted thereunder, the extent and legal
effect of approvals granted by such authority may also require
examination, depending upon the issue under consideration.
C. Scope of interference under Sections 34 & 37 of the Act, 1996
37. Before adverting to the rival submissions, it is apposite to remind
ourselves of the contours of jurisdiction. It is well settled, and is not in
dispute between the parties, that a Court exercising jurisdiction under
Section 34 of the Act of 1996, does not sit in appeal over the arbitral
award; it does not re-appreciate evidence; and where the learned
Arbitrator has taken a view which is a possible or plausible one on a fair
construction of the contract, no interference is warranted. The
jurisdiction under Section 37 is narrower still. This position stands
crystallised by the judgments of the Hon'ble Supreme Court in
1
Associate Builders v. DDA , Ssangyong Engineering &
2
Construction Co. Ltd. v. NHAI , Delhi Airport Metro Express (P)
3
Ltd. v. DMRC , and Konkan Railway Corporation Ltd. v. Chenab
4
Bridge Project Undertaking (relied upon by the respondent itself).
38. Equally well settled, however, is the converse: the ground of
“patent illegality” under Section 34(2A) is squarely attracted where the
1
(2015) 3 SCC 49
2
(2019) 15 SCC 131
3
(2022) 1 SCC 131
4
(2023) 9 SCC 85
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 34 of 76 ) [CMA-1560/2025]
learned Arbitral Tribunal (i) decides the dispute in disregard of, or
contrary to, the terms of the contract, in the teeth of Section 28(3) of
the Act of 1996; (ii) construes the contract in a manner which no
reasonable or fair-minded person could adopt, i.e., takes a view which
is not even a possible view; (iii) ignores vital evidence or binding
precedent, thereby offending the “judicial approach” limb of
fundamental policy of Indian law; (iv) renders findings which are
internally contradictory and hence perverse; or (v) awards relief without
any legal foundation, in contravention of the substantive law of the
land. An award which re-writes the bargain between the parties is not
saved by the deference ordinarily shown to arbitral adjudication —
Ssangyong (supra) ; PSA Sical Terminals (P) Ltd. v. Board of
5
Trustees , V.O. Chidambranar Port Trust ; Indian Oil Corporation
6
Ltd. v. Shree Ganesh Petroleum ,. Judicial restraint under Sections
34 and 37 does not translate into judicial abdication. It is on this
touchstone that the submissions of the parties fall to be examined.
D. CASE SET UP BY THE APPELLANTS
39. Though the written submissions of the appellants are elaborate,
but on analysis thereof we deem it appropriate to crystallise the same
into the following eight submissions:
Submission I-
The claims, in particular the claim for escalation/increase in project
cost, were barred by limitation, the work having been completed on
31.03.2013 and the Statement of Claim having been filed only on
16.02.2019 and the plea of limitation being available at any stage.
Submission II-
5
(2023) 15 SCC 781
6
(2022) 4 SCC 463
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 35 of 76 ) [CMA-1560/2025]
The Concession Agreement, being a DBFOT/BOT concession awarded on
the sole bid criterion of concession period under the Rajasthan Road
Development Act, 2002, contemplated restoration of the
concessionaire's economic position only by adjustment (extension) of
the concession period and made no provision for cash compensation
except a Termination Payment under Clause 12.2(b)(2); the award of
cash compensation amounts to re-writing the contract; the extension of
484 days already granted by the Empowered Committee fully
compensated the respondent, rendering the award one of double
recovery; and paragraph 124 of the award, rejecting sub-claim 2(iv) on
the ground that the Agreement provides only for change of concession
period, is irreconcilable with the allowance of Claims 1, 2(i), 2(iii) and 4,
rendering the award internally contradictory.
Submission III-
Article 16.2 (Disclaimer), an express allocation of design risk, was
wrongly nullified by the learned Sole Arbitrator on the strength of
misapplied and distinguishable precedents ( Simplex Concrete Piles ,
Board of Trustees for the Port of Calcutta v. Engineers-De-
7
Space-Age , Asian Techs , G. Ramchandra Reddy , NHAI v.
8
Shillong Expressway ) , while ignoring the binding judgment of the
Hon'ble Supreme Court in Ramnath International Construction (P)
9
Ltd. v. Union of India , .
Submission IV-
The DPR was, under the express terms of Schedule- A/Annexure-I read
with Query No. 99 of the pre-bid meeting, only a reference document;
the learned Tribunal's treatment of the DPR as a document of
7
(1996) 1 SCC 516
8
2018 SCC OnLine Del 12342
9
(2007) 2 SCC 453
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 36 of 76 ) [CMA-1560/2025]
“paramount importance” and as the benchmark of design contradicts
Clauses 2.1 and 5.1, Article 7 and Schedule-A of the Agreement.
Submission V-
The award records no finding of breach of any identified contractual
obligation by the appellants; compensation in the absence of breach is
contrary to Sections 54, 55 and 73 of the Indian Contract Act, 1872 and
10
to Kailash Nath Associates v. DDA .
Submission VI-
The learned Tribunal erred in equating the IRR of 20.33%, a project-
appraisal metric contained in the cash flow projections, with
interest/assured return, and in awarding all claims together with IRR at
20.33% on a compounding basis, in misapplication of State of
11
Maharashtra v. Khare & Tarkunde and without any of the
considerations mandated by Vedanta Ltd. v. Shenzen Shandong
12
Nuclear Power Construction Co. Ltd. .
Submission VII-
Claims 2(i), 2(iii) and 4 were allowed beyond the terms of the contract:
there was no obligation to ban all tollable traffic on the old GKG road
and the notification dated 31.01.2013 banning heavy vehicles was in
13
fact issued ( MSK Projects (India) (JV) Ltd. v. State of Rajasthan ;
the Force Majeure costs on account of demonetisation were allowed
without the certification of the Steering Group and verification by the
Chief Engineer mandated by Clause 11.6(d); and Claim 4 was allowed
by elevating the respondent's profit-earning opportunity above user
safety, without holding the Empowered Committee's safety-based
10
(2015) 4 SCC 136
11
1992 SCC OnLine Bom 16
12
(2019) 11 SCC 465
13
(2011) 10 SCC 573
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 37 of 76 ) [CMA-1560/2025]
rejection dated 06.02.2015 to be unjustified and without scrutiny of the
quantum of Rs. 8.49 crores.
Submission VIII-
The Corrigendum Award dated 31.07.2023 travelled beyond Section 33
by effecting a substantive enhancement of the award through deletion
of the words “amounting to Rs. 198.04 crores” in paragraph 141; and
the impugned order of the learned Commercial Court is a non-reasoned
order which failed to apply the recognised Section 34 tests to the
objections actually raised.
E. CASE SET UP BY THE RESPONDENT
40. The respondent, per contra, has supported the award and the
impugned order, and as understood by us, pre dominantly on five
planks which are summed up as below:
(i) The narrow scope of Sections 34 and 37 and the
impermissibility of re- appreciation of evidence.
(ii) That several grounds, including limitation and the plea of
double recovery through the 484-day extension, are new grounds
not raised before the learned Tribunal.
(iii) That the cash flow projections and the IRR of 20.33% form
part of the Concession Agreement and therefore the award of IRR
is intra-contractual;
(iv) That the Concession Agreement is silent on the remedy for
breach and does not expressly bar cash compensation, and hence
the learned Tribunal rightly awarded damages, the award being a
plausible view.
(v) That the findings on the faulty DPR, the Balaknath Samadhi
encumbrance, traffic leakage and demonetisation are findings of
fact based on evidence.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 38 of 76 ) [CMA-1560/2025]
OUR-VIEW:
F. Re:question (i)
Whether the claim petition of the respondent was ex facie
barred by limitation?
a. Submission I — Plea of limitation
41. The plea of limitation must be examined first, for if it were to
succeed, a substantial part of the claims would logically fail at the
threshold. Learned Senior Counsel for the appellants contended that the
work stood completed on 31.03.2013, the Completion Certificate dated
12.09.2013 fixing the COD as 01.02.2013, and that no additional cost
could accrue thereafter; that limitation for the claim of
escalation/increase in project cost therefore began to run from that
date under Articles 55/113 of the Schedule to the Limitation Act, 1963;
and that the Statement of Claim filed on 16.02.2019 was hopelessly
beyond three years. Reliance was placed on State of Chhattisgarh v.
14
Sal Udyog (P) Ltd. , Narne Rama Murthy v. Ravula
15 16
Somasundaram , R. Nagaraj v. Rajmani and allied decisions for
the proposition that a plea of limitation, being a plea of law which goes
to the root of jurisdiction, can be raised at any stage.
42. Having given our anxious consideration to the submission, we are
unable to accept it, for the following reasons:
42.1 First , the plea in the form now canvassed was admittedly not
raised before the learned Arbitral Tribunal. The award does not reflect
any issue of limitation having been framed or pressed qua the claims.
The only threshold objection pressed before the learned Tribunal, as the
award records, was the objection founded on the multi-tier dispute
14
(2022) 2 SCC 275
15
(2005) 6 SCC 614
16
2025 SCC OnLine SC 762
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 39 of 76 ) [CMA-1560/2025]
resolution mechanism, which was rejected with reference to Section
16(2) of the Act of 1996. It is trite that limitation is a mixed question of
law and fact: the date of accrual of the cause of action for each claim,
when the increase in project cost crystallised, when each demand was
made and rejected, whether the losses on account of traffic leakage
were continuing in nature, are all questions which required pleadings
and evidence before the learned Tribunal. A plea which cannot be
adjudicated without a fresh investigation into facts cannot be permitted
to be raised for the first time in proceedings under Section 34, much
less in an appeal under Section 37, for its adjudication would entail
precisely the re- appreciation of evidence which Section 34 forbids.
42.2 Secondly , the judgments relied upon by the appellants do not
carry their case further. In Sal Udyog (supra) and other authorities
cited on limitation, the plea permitted to be raised was a pure plea of
law apparent on the face of the award and the admitted record,
requiring no further evidence. That principle, which we shall ourselves
invoke later in this judgment in a different context, has no application
where the plea of limitation is fact- dependent. The present plea does
not appear ex facie from the award. On the contrary, the admitted
documents on record point the other way, as noticed hereinafter.
42.3 Thirdly , even if the plea were to be examined on merits on the
admitted documents, it must fail. The Concession Agreement, by Article
15, prescribed a mandatory multi-stage mechanism of amicable
resolution through the Steering Group and the Empowered Committee,
the latter a statutory authority under the Rajasthan Road Development
Act, 2002 and described in Clause 15.1(c) as the final dispute-
settlement authority, before recourse to arbitration. The admitted List of
Dates shows that the respondent raised its consolidated demand for
extension of the concession period and compensation against increase
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 40 of 76 ) [CMA-1560/2025]
in project cost by letter dated 21.07.2014, sought reference of the
disputes to the Steering Committee on 22.12.2014, approached the
Empowered Committee on 12.03.2015, and the Empowered Committee
took its final decisions on 22.06.2015, granting only an extension of
105 days (communicated on 11.09.2015) while declining the monetary
claims. It is upon this rejection, the “breaking point” in the parties'
negotiations conducted under a contractually mandated mechanism,
that the cause of action to invoke arbitration can be said to have finally
accrued, on the principle recognised by the Hon'ble Supreme Court in
Geo Miller & Co. (P) Ltd. v. Rajasthan Vidyut Utpadan Nigam
17
Ltd. The notice invoking arbitration under Section 21 was issued on
18.09.2017, well within three years of 22.06.2015/11.09.2015. By
virtue of Section 21 read with Section 43 of the Act of 1996, the arbitral
proceedings commenced on 18.09.2017, and the subsequent filing of
the Statement of Claim on 16.02.2019 is within time for computing
limitation.
42.4 Fourthly , so far as the remaining claims are concerned, the
position is even clearer. The claim on account of demonetisation relates
to the period 09.11.2016 to 02.12.2016. The claim on account of denial
of advertising rights arises from the rejection of the respondent's
proposal in the Empowered Committee's decision of 2015; and the
claim on account of leakage of traffic through the old GKG road was, in
its nature, founded on a continuing state of affairs. Each of these is
comfortably within three years of the Section 21 notice dated
18.09.2017.
43. For these reasons, Submission II fails and the plea of limitation
raised on behalf of the appellants is rejected. We hasten to add,
17
(2020) 14 SCC 643
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 41 of 76 ) [CMA-1560/2025]
however, that the rejection of this plea does not advance the
respondent's case on the merits of the award, to which we now turn.
G. Re:Question (ii):
Whether the arbitral award dated 25.06.2023, as modified by
the corrigendum award dated 31.07.2023, suffers from
patent illegality or is in conflict with the public policy of India
(a) Submission II — Award of cash compensation contrary to
the scheme of the Concession Agreement
44. The Concession Agreement is a tripartite DBFOT concession
awarded, under the regime of the Rajasthan Road Development Act,
2002, on the sole bid criterion of the lowest concession period. The
respondent was selected on its quoted concession period of 13 years, 5
months and 20 days for a tentative Project Cost of Rs. 150 crores. The
definition of “Project Cost” in Article 1 pegs it to the lowest of (a) Rs.
150 crores, (b) the actual capital cost as certified by the Statutory
Auditors, and (c) the Project Cost set forth in the financing documents.
The language deployed in the Concession Agreement is throughout
consistent and unambiguous. Article 10 (Change of Scope)
contemplates that changes in scope shall be addressed through a
prescribed Change of Scope procedure and adjustment of the
concession period; Clause 10.3 (capacity augmentation) thereof
contemplates change of the concession period by a supplemental
agreement whereas, Clause 13.2 restores the concessionaire's financial
position upon a Change in Law by extension or reduction of the
concession period. Pertinently, the solitary provision for payment of
money to the concessionaire is the Termination Payment under Clause
12.2(b)(2), payable upon termination for an event of Government’s
default, an event which admittedly never occurred.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 42 of 76 ) [CMA-1560/2025]
44.1 Aforesaid, relevant Articles of CA are reproduced hereinbelow for
ready reference:-
“ARTICLE 10
CHANGE OF SCOPE
X-X-X-X-X
10.3 Capacity Augmentation of the Project V
(a) The GOR may following a detailed traffic study conducted by it, at
any time after COD decide to augment / increase the capacity of the
Project (Capacity Augmentation) with a view to provide the desired level
of service to the users of the Project Facility.
(b) The GOR shall invite proposals from eligible Persons for Capacity
Augmentation. The Concessionaire shall have option to submit its
proposal for Capacity Augmentation.
(c) The bid document for Capacity Augmentation shall specify a
Termination Payment to be made to the Concessionaire in case the
Concessionaire chooses not to submit its proposal or fails or declines to
match the preferred offer as mentioned in sub-article (e)- below.
(d) In case the Concessionaire, after participating, in the bidding
procedure, fails "to give the lowest offer, the Concessionaire shall be
given the first right of refusal to match the preferred offer. If the
Concessionaire matches the preferred offer Parties shall enter into a
suitable agreement supplemental to this Agreement to give effect to the
changes in scope of the Project, Concession Period and all other
necessary and consequential changes. in such event the Concessionaire
shall pay to the bidder who had made the lowest an offer a sum of Rs.-
0.1% of the estimated project cost of maximum of Rs. 10 lacs which shall
be indicated in the bid document-towards bidding costs incurred by such
bidder.
(e) In case the Concessionaire
(1) chooses not to submit its proposal for Capacity Augmentation or
(II) is not the preferred bidder and also fails or declines to match the
preferred offer.
GOR shall be entitled to terminate this Agreement upon payment to the
Concessionaire of the Termination Payment GOR may also cause the
payment to be made by the new concessionaire.
(f) The Termination Payment referred to in the preceding sub-articles (c)
and (e) above snail be the amount equivalent to the amount of
Termination Payment set out in Article 12.2(b).
X-X-X-X-X
ARTICLE 11
FORCE MAEJURE
X-X-X-X-X
11.5 Effect of Force Majeure Event.
Upon occurrence of any Force Majeure Event. the following shall apply:
(a) There shall be no Termination of this Agreement
(b) Where the Force Majeure Event occurs before. COD, the dates set
forth in the Project Completion Schedule, and the Concession Period
shall be extended by the period for which such Force Majeure Event
shall subsist;
(c) Where a Force Majeure Event occurs after COD, the Concessionaire
shall continue to make all reasonable efforts to operate the Project and /
or to collect Fee, but if it is unable or prevented from doing so, the
Concession Period shall, having due regard to the extent of the impact
thereof as determined by the Steering Group, be extended by the period
for which collection of Fee remains affected on account thereof, and
(d) Costs arising out of or concerning such Force Majeure Event shall be
borne in accordance with the provisions of the Article 11.6 hereinafter.
X-X-X-X-X
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 43 of 76 ) [CMA-1560/2025]
ARTICLE 12
EVENTS OF DEFAULT AND TERMINATION
X-X-X-X-X
12.2. Termination due to Event of Default
(b) Termination for GOR Events of Default
(1) The Concessionaire may upon the occurrence and continuation of any
GOR Event of Default terminate. this Agreement by issuing Termination
Notice to GOR
(2) Upon Termination of this Agreement by the Concessionaire due to a
GOR Event of Default, the Concessionaire shall be entitled to receive
from GOR, by way of Termination Payment a sum equal to assessed
value of the work (Project cost or the value assessed by Superintending:
Engineer whichever is less) / assets available reduced by the amount
already collected as fee till such termination is effected and an additional
sum upto 10% thereon as recommended by the Steering Group, as
approved by GOR.
X-X-X-X-X
ARTICLE13
CHANGE IN LAW
X-X-X-X-X
13.2 Extension of Concession Period
The Chief Engineer shall upon being notified by the Concessionaire
/UDHAIDA Engineer of the Change in Law and the proposed
amendments to this Agreement, assess the change in the financial
position as a result of such Change of Law and determine the extension/
reduction to the Concession Period so as to put the Concessionaire in the
same financial position and recommend the same to GOR. GOR shall,
within 30 days of receipt of such recommendation, extend / reduce the
concession period, as it may deem fit.”
X-X-X-X-X
45. The scheme of Concession Agreement is neither accidental nor
unusual. In a BOT/DBFOT concession in which the concession period is
itself the bid variable, the parties consciously stipulate that the
concessionaire's economic equilibrium shall be restored through time
adjustment of the concession period, and not through money from the
public exchequer. That is precisely how the parties themselves acted.
The Empowered Committee, by its decision of 07.12.2011
(communicated on 16.05.2012), extended the concession period by 379
days expressly to compensate the concessionaire for any additional cost
that may have accrued on account of the revised alignment and by its
decision of 2015 it granted a further extension of 105 days on account
of hindrances and encumbrances. The respondent accepted and enjoyed
both extensions.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 44 of 76 ) [CMA-1560/2025]
46. Against this contractual matrix, the learned Sole Arbitrator
awarded cash compensation of Rs. 198.04 crores (Claims 1, 2(i), 2(iii)
and 4), together with IRR at 20.33%. In doing so, the learned Tribunal
did not rest its conclusion on any provision of the Agreement entitling
the concessionaire to money payments. It proceeded on the footing,
recorded in paragraph 80 of the award, that the Agreement “is silent
with regard to payment of damages/compensation in the event of
breach of contract” and that the situation would have been different
“had there been a prohibitory clause barring payment of compensation”.
With respect, this reasoning invert seems to the correct approach to a
commercial concession of this nature. Where the contract provides a
specific, exhaustive and carefully calibrated remedy, adjustment of the
concession period, for every category of supervening event (change of
scope, force majeure, change in law), the absence of an express
prohibition on cash compensation cannot be treated as an implied
entitlement to it. The learned Arbitrator, being a creature of the
contract, was bound by Section 28(3) of the Act of 1996 to decide in
accordance with its terms; an award which substitutes a remedy the
parties never agreed upon effectively re-writes the contract, such a
course is impermissible, see Indian Oil Corporation Ltd. v. Shree
Ganesh Petroleum (supra) ; PSA Sical Terminals (supra) ;
Rajasthan State Mines & Minerals Ltd. v. Eastern Engineering
18
Enterprises .
Also, a subsequent judgment rendered by Hon'ble Supreme Court of
India by decision dated 11.12.2006 in Ramnath International
19
Construction Pvt. Ltd. v. Union of India , wherein, reiterating
18
(1999) 9 SCC 283
19
AIR 27 SC 509 : 2007(2)SCC 453
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 45 of 76 ) [CMA-1560/2025]
Associated Engineering Co. v. Government of Andhra Pradesh
20
and Anr. , it was held as under:
"12. We are fortified in this view by several decision of this Court. We
may refer to two of them. In Associated Engg. Co. v. Govt. of A.P. this
Court was concerned with an appeal which related to similar claims
based on delays in execution. The High Court had held (State of A.P. v.
Associated Engg. Enterprises²) thus:
"26. Applying the principle of the above decision to the facts
of the case before us, it must be held that clause 59 bars a
claim for compensation on account of any delays or
hindrances caused by the department. In such a case, the
contractor is entitled only to extension of the period of
contract. Indeed, such an extension was asked for, and
granted on more than one occasion. (The penalty levied for
completing the work beyond the extended period of contract
has been waived in this case.) The contract was not avoided
by the contractor, but he chose to complete the work within
the extended time. In such a case, the claim for compensation
is clearly barred by clause 59 of the A.P. DSS which is
admittedly, a term of the agreement between the parties."
This Court noticed that the claims were set aside by the High Court on
the ground that those claims were not supported by any agreement
between the parties, and that the arbitrator had travelled outside the
contract in awarding those claims. This Court held that the said claims
were not payable under the contract and that the contract does not
postulate, in fact prohibits, payment of any escalation under those heads.
It affirmed the decision of the High Court setting aside the award of
those claims."
(emphasis supplied)
47. What places the matter beyond the pale of a merely being
erroneous, or even a plausible, is the learned Tribunal's own
construction in paragraph 124. While rejecting sub-claim 2(iv), the
learned Tribunal held:
“The dispute resolution mechanism provides only to the extent of seeking
change in the Concession Period, the Claimant having not asked for
extension, cannot make out a claim and therefore is not entitled to claim
under this head.”
This finding, which, in our considered view, correctly reflects the
scheme of the Agreement, is wholly irreconcilable with the allowance, in
the very same award and on the very same contractual matrix, of cash
compensation under Claims 1, 2(i), 2(iii) and 4. The learned Tribunal
has thus taken two mutually contradictory views on the self-same
question in the self-same award. An award which is internally
contradictory on the central question of entitlement is perverse and
20
(1991) 4 SCC 93
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 46 of 76 ) [CMA-1560/2025]
irrational, and falls foul both of the “patent illegality” grounds under
Section 34(2A). See also, Associate Builders (supra) .
48. There is a further and independent vice. The Empowered
Committee had already compensated the respondent for the very
causes underlying Claim 1, the revised alignment and the site
hindrances, by extensions aggregating 484 days. On the respondent's
own cash flow projections, an additional operational period of that order
carried very substantial toll revenue. The appellants have quantified
revenue generation for those 484 days at upwards of Rs. 119 crores
against an alleged cost increase of Rs. 57.87 crores. Pertinently, said
figure of Rs. 119 crore as revenue receipt is not disputed by the
respondent. Whether or not that precise quantification is accepted, the
award nowhere accounts for, set off, or even advert to the
compensation already received in the form of extended concession
period while awarding cash for the same causes. The result is double
compensation for a single loss, arrived at by ignoring vital and admitted
material on record, a recognised facet of perversity. The respondent's
answer that the first extension of 379 days was referable only to delay
in the commencement date is belied by the record noticed above, which
shows the Empowered Committee's decision to have been expressly
relatable to the additional cost on account of revised alignment.
49. Submission I is accordingly accepted.
(b) Submission III — Nullification of Article 16.2 (Disclaimer)
50. Article 16.2 of the Agreement embodies an acknowledgment by
the concessionaire of the risks of adequacy, mistakes or errors in or
relating to the matters set forth in the Agreement, in substance, an
express contractual allocation of the investigation and design risk to the
concessionaire, entirely consonant with the DBFOT character of the
concession under which investigation, study, design and engineering
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 47 of 76 ) [CMA-1560/2025]
were the concessionaire's exclusive domain (Clause 2.1). Relevant
extract of Article 16.2 is reproduced hereinbelow:-
“16.2 Disclaimer
(a) Without prejudice to any express provision contained in this.
Agreement, the Concessionaire acknowledges that prior to the execution
of this Agreement the Concessionaire has after a complete and careful
examination made an independent evaluation of the traffic volumes,
Specifications and Standards. Project Site and all the information
provided by GOR, and has determined to the Concessionaire's
satisfaction the nature and extent of such difficulties, risks and hazards
as are likely to arise or may be faced by the Concessionaire in the course
of performance of its obligations hereunder
(b) The Concessionaire further acknowledges and hereby accepts the risk
c adequacy mistake or error in or relating to any of the matters set forth
in (an above and hereby confirms that GOR shall not be liable for the
same in are manner whatsoever to the Concessionaire.”
The learned Tribunal declined to give effect to this clause, holding
it to be an exclusionary clause which could not operate over Section 73
of the Contract Act, relying upon G. Ramchandra Reddy , Asian
Techs (supra) , Board of Trustees for the Port of Calcutta v.
Engineers-De-Space-Age (supra) and the judgments in Simplex
and NHAI v. Shillong Expressway (supra) . In our considered
opinion, each of these authorities was misapplied as elaborated
hereafter.
50.1 Board of Trustees (supra) dealt with a Clause in the contract
barring the departmental authority from entertaining a claim for
pendente lite interest. The Hon'ble Supreme Court held that a fetter on
the departmental authority was not a fetter on the learned Arbitrator's
power to award interest. The decision is an authority on pendente lite
interest and the reach of a clause addressed to a departmental officer.
It lends no support to the proposition that a risk- allocation/disclaimer
clause consciously bargained between commercial parties can be
disregarded by the learned Arbitrator.
50.2 Asian Techs (supra) turned on its peculiar facts i.e. the
Department had assured payment to the contractor, and it was that
assurance which precluded the Department from invoking the disclaimer
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 48 of 76 ) [CMA-1560/2025]
clause. No comparable assurance exists here. On the contrary, the pre-
bid clarification to Query No. 99 (noticed hereinafter) was to the
opposite effect.
50.3 G. Ramchandra Reddy (supra) concerned damages in a post-
termination scenario. Admittedly, there was no termination in the
present case, nor any finding of breach as discussed and held under
submission V in later part of our order. The decision was therefore
applicable herein.
50.4 NHAI v. Shillong Expressway (supra) is distinguishable on the
learned Tribunal's own reasoning. The deficiencies in the DPR
necessitated acquisition of additional land which was delayed by NHAI.
In the present case, it is nobody's case that the revision of alignment
necessitated acquisition of additional land as the project was executed
within the available right of way.
50.5 Most significantly, the judgment of the Hon'ble Supreme Court
in Ramnath International Construction (P) Ltd. v. Union of
21
India , which upholds a contractual stipulation confining the
contractor's remedy for delay to extension of time and excluding claims
for compensation, was specifically brought to the notice of the learned
Tribunal, and indeed stands acknowledged in the very judgment of the
Delhi High Court in Simplex on which the learned Tribunal relied. The
learned Tribunal nonetheless preferred the view of a High Court over the
binding pronouncement of the Hon'ble Supreme Court, without
distinguishing the latter. Disregard of a binding precedent of the Hon'ble
Supreme Court, brought to the learned Tribunal's notice is against the
fundamental public policy of law on the first principles of “stare
decision” and constitutes patent illegality.
21
(2007) 2 SCC 453
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 49 of 76 ) [CMA-1560/2025]
51. One cannot also lose sight of the fact that the respondent, a
commercial entity, entered into the Agreement with open eyes after due
inspection of the site between 04.08.2009 and 14.09.2009 and after
seeking and obtaining clarifications in the pre-bid meeting. A party
which accepts a contract with a conscious allocation of risk could not be
relieved of its obligations under that bargain by the learned Arbitrator.
22
See:- RIICO v. Diamond & Gem Development Corporation Ltd.
and Indian Oil Corporation Ltd. v. Shree Ganesh Petroleum
(supra) . Submission III is thus accepted.
(c) Submission IV — The DPR was a reference document
52. The entire edifice of Claim 1 rests on the learned Tribunal's finding
that the DPR was of “paramount importance” and constituted the
minimum design requirement, deficiencies wherein visited the
appellants with liability. The express terms of the Agreement do not
admit of such an interpretation construction. Under Clause 2 of
Annexure-I of Schedule-A, the codes and standards governing design
were those of the Indian Roads Congress and the MoRTH Specifications.
Building works were to conform to Rajasthan PWD Specifications.
Geometric design standards were to follow IRC guidelines applicable to
National Highways. The DPR, prepared by M/s SPAN Consultants, was
furnished merely as a reference. The word “may” preceding its mention
does not make it binding. That aside, tellingly, the possibility of
apparent errors in the DPR was itself expressly acknowledged in the bid
documents. The DPR was excluded from the defined expression
“Specifications and Standards”. Clause 2 of Annexure-I of Schedule-A is
reproduced hereinbelow for ready reference:-
"2.0
CODES AND STANDARDS
22
(2013) 5 SCC 470
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 50 of 76 ) [CMA-1560/2025]
The codes and standards applicable for the design of the Project and
Project Facilities are:
(i) Indian Road Congress (IRC) Codes and Standards; and
(ii) Ministry of Road Transport and Highways (MORTH)
Specifications
Both as applicable to National Highways and shall include policy
circulars, guidelines and special publications, issued in respect thereof
by IRC or MORTH, as the case may be, from time to time and shall
incorporate all amendments and/or modifications to such codes and
standards which are available to public 30 days before the Proposal Due
Date unless otherwise specified in this Schedule.
The terms 'Ministry of Surface Transport' and 'Ministry of Road
Transport, Highways' and 'Ministry of Shipping Road Transport and
Highways' shall be considered as synonymous to each other.
A list of IRC/MORTH codes is provided in Appendix C
2.2 Where the aforesaid codes, standards and specifications are silent on
any aspect, the following standards in order of preference shall be
adopted in consultation with the JDA, unless otherwise specified in this
Schedule:
(a) Bureau of Indian Standards (BIS)
(b) American Association of State Highway and Transport officials
(AASHTO)
(c) Geometric Design Standards for Ontario Highways
(d) American Society of Testing Materials (ASTM)
(e) British Standards (BS)
(f) Suitable specification/standard devised by the JDA
(g) Any other standard proposed by the Concessionaire
2.3 All items of building works shall conform to Rajasthan Public Works
Depatment (UDH/JDA)
specifications for Class 1 building works and standards given in the
National Building Code (NBC). To the extent specific, provisions for
building works are provided in IRC/MORTH specifications, the same
shall prevail over the UDH/JDA/NBC provisions. For this purpose,
building works shall be deemed to include road furniture, roadside
facilities, landscape elements and/or any other works incidental to the
building works.
2.4 The Geometric Design Standards for the. Project/Project Facilities
shall be as per IRC Guidelines as applicable to the National Highways,
urban arteries
2.5. The designed parameters for horizontal and vertical alignments
shown in the DPR are the minimum requirements to be maintained for
the project. The concessionaire may adopt better standards for enhancing
the requirements of safety and mobility."
53. Any residual doubt stands dispelled by the minutes of the pre-bid
meeting dated 14.09.2009, which, by common consent, form part of
the Agreement. Query No. 99 raised by the bidders was: “the
concessionaire is not required to follow the Detailed Project Report
(DPR) given in Vol-IV, please specify”. The answer given to all bidders
was “Yes, but there would not be any impact on concession period and
cost.” The bidders were thus told, in unequivocal terms, two things at
once, i.e., (i) that the DPR was not binding, and (ii) that deviation from
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 51 of 76 ) [CMA-1560/2025]
it would have no impact on the concession period or the cost. The
respondent gave its bid on that footing. The learned Arbitral Tribunal's
conclusion that the DPR was nonetheless the benchmark whose
deficiencies rendered the appellants liable in money is a construction
which the contract, read as a whole, cannot reasonably bear. That
conclusion ignores the express dispensation in Schedule-A and the pre-
bid clarification altogether. A construction which no fair-minded or
reasonable person could adopt on the contract read as a whole is not a
plausible or even a “possible view” attracting deference. With respect, it
is a case of patent illegality. Submission IV is thus also accepted.
(d) Submission V — Compensation without a finding of breach
54. Compensation under Section 73 of the Contract Act presupposes a
breach of contract. Whereas Sections 54 and 55 presuppose,
respectively, reciprocal promises and a time-bound obligation
undertaken by the party in default. As held in Kailash Nath
23
Associates v. DDA , damages are payable only upon breach being
established. On a careful reading of the award, we find that the learned
Tribunal has nowhere identified the contractual provision which obliged
the appellants to furnish a workable design or an error-free DPR, nor
recorded a finding that any identified obligation of the appellants was
breached. Indeed, no such obligation could have been identified, as
under the DBFOT allocation (Clause 2.1 read with Clause 5.1 and Article
7) the investigation, study, design and engineering of the project were
the exclusive responsibility, and at the exclusive cost, of the
concessionaire. Clauses 2.1, Clause 5.1 and Article 7 is reproduced
hereinbelow for ready reference:-
"2.1 Grant of Concession
23
(2015) 4 SCC 136
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 52 of 76 ) [CMA-1560/2025]
Subject to and in accordance with the terms and conditions set forth in
this Agreement, GOR hereby grants and authorizes exclusively the
Concessionaire to investigate, study, design, engineer, procure, finance,
construct, operate and maintain the Project / Project Facility and to
exercise and / or enjoy the rights, powers, privileges authorizations and
entitlements (including limited ownership for concession period) as set
forth in this Agreement, including but not limited to the right to levy,
demand, collect end appropriate Fee from vehicles and Persons liable to
payment of Fee for using the Projects/ Project Facility or any other part
thereof (collectively "the Concession").
X-X-X-X-X
5.1 General Obligations of the Concessionaire
The Concessionaire shall at its own cost and expense:
(1) Investigate, study, design, construct, operate and maintain the Project
Assets / Project Facility in accordance with the provisions of this
Agreement, Good Industry Practice and Applicable Laws;
(II) Obtain all Applicable Permits in conformity with the Applicable
Laws and be in compliance with thereof at all times during the
Concession Period,
(III) 'Procure and maintain in full force and effect, as necessary,
appropriate proprietary rights, licenses, agreements and permissions for
materials, methods, processes and systems used in or incorporated into
the Project;
(IV) Ensure and procure that each Project Agreement contains provisions
that would entitle GOR or a nominee of GOR to step into such agreement
at GOR's discretion, in place and substitution of the Concessionaire in
the event of Termination pursuant to the provisions of this Agreement;
(V) Provide all assistance to UDH/JDA Engineer and Steering Group as
they may reasonably require for the performance of their duties and
services under this Agreement;
(VI) Provide to the Steering Group reports or a regular basis during the
implementation. Period and the Operations Period in accordance with
the provisions of this Agreement;
(VII) Appoint, supervise, monitor and control the activities of
Contractors under their respective Project Agreements as may be
necessary and develop, implement and administer a surveillance and
safety program for the Project / Project Facility and the users thereof and
the Contractors personnel engaged in the provision of any services under
any of the Project Agreements including correction of safety violations
and deficiencies, and taking of all other actions necessary to provide a
safe environment in accordance with Applicable Laws and Good Industry
Practice.
(VIII) Take all reasonable precautions for the prevention of accidents on
or about the Project Site / Project Facility and provide all reasonable
assistance and emergency medical aid to accident victims;
(IX) Not to place or create nor to permit any Contractor or other person
claiming through or under the Concessionaire to create or place any
Encumbrance over all or any part of the Project Assets, or on any rights
of the Concessionaire therein, save and except as expressly set forth in
this Agreement;
(X) Make its own arrangements for quarrying, if necessary, and observe,
and fulfill the environmental and other requirements under the
Applicable Laws and Applicable Permits;
(XI) Be responsible for safety, soundness and durability of the-Project
Facility (Including toilet, parking way as specified) including all
structures forming part thereof and their compliance with the
Specifications and Standards;
(XII) Ensure that the Project Site remains free from all encroachments
and take all steps necessary to remove encroachments, if any:
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 53 of 76 ) [CMA-1560/2025]
(XIII) Make payment to Police Department or any Government Agency, if
required, for provision of such services as are not provided in the normal,
course or are available only on payment;
(XIV) Operate and maintain the Project at all times during the
Operations. Period in conformity with this Agreement including but not
limited to the Specifications and Standards, the Maintenance Programme
and Good Industry Practice;
(XV) Remove promptly according to Good industry Practice, from the
Project Site, all surplus construction machinery and materials, waste
materials (including, without imitation, hazardous materials and waste
water), rubbish and other debris (including without limitation accident
debris) and keep the Project Site in a neat and clean condition and in
conformity with the Applicable Laws and Applicable. Permits.
X-X-X-X-X
7.1 Preparation of Drawings. The Concessionaire shall, at its cost,
charges and expenses, cause Drawings to be prepared in accordance
with the Specification and Standards. The Concessionaire may, for this
purpose, adopt with or without any modifications the Drawings, if any,
any, made available by GOR, provided, notwithstanding such adoption,
the Concessionaire shall be solely responsible for the adequacy of the
Drawings.
7.2 Review and Approval of Drawings.
(a) The Concessionaire shall promptly and in such sequence as is
consistent with the Project Completion Schedule, submit a copy each of
all Drawings to the Superintending Engineer and the Steering Group.
(b) By forwarding the drawings pursuant to sub-article (a) above, the
Concessionaire represents that it has determined and verified that the
design and engineering including field construction criteria related
thereto are in conformity with the Specifications and Standards-
(c) Within 15 (fifteen) days of the receipt of the Drawings, Superintending
Engineer shall review the same and convey comments / observations, if
any, thereon to the Concessionaire with particular reference to the
conformity or otherwise with the Specifications and Standards. GOR
shall not be liable for The adequacy of the Drawings and that the
Concessionaire shall solely be responsible therefore and shall not be
relieved or absolved in any manner whatsoever of its obligation, duties
and liabilities as set forth in this Agreement.
(d) If the Superintending Engineer does not object to the Drawings
submitted to it by the Concessionaire within a period stipulated in above
sub-article(c) the Concessionaire shall be entitled to proceed with the
Project.
(e) The Concessionaire shall be responsible for delays in Project
Completion and consequences thereof caused by reason of any Drawings
not being in conformity with the Specifications and Standards and shall
not be entitled to seek any relief in this regard from GOR.
(f) Within 90 (ninety) days of the COD, the Concessionaire shall furnish
to GOR three copies of as built Drawings duly veiled by the Executive
Engineer or a firm of consultants reflecting the Project as actually
designed, engineered and Constructed, including without limitation an as
built survey illustrating the layout of the Project and-setback lines, if any.
of the buildings and structures forming part of Project Facility."
In light of the above, the learned Tribunal has, in effect,
presupposed an obligation of the appellants which the Agreement does
not contain. It thus proceeded to award damages for its supposed
breach without establishing any actual, either the obligation or its
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 54 of 76 ) [CMA-1560/2025]
breach or actual damages. An award of compensation dehors any
finding of breach of an identified contractual obligation is contrary to the
substantive provisoins contained in Sections 54, 55 and 73 of the
Contract Act. It is thus patently illegal. Accordingly, submission V is
accepted.
(e) Submission VI — IRR of 20.33% equated with interest
55. The Internal Rate of Return is, by definition, as we have
understood, is the discount rate at which the net present value of the
projected cash flows of an investment equals zero. It is a tool of project
appraisal. It is an ex ante , estimated measure of the anticipated
viability of an investment. It is premised, inter alia , on the assumption
of reinvestment of interim cash flows. It is neither a promised return
nor a rate of interest. The figure of 20.33% appears in the cash flow
projections forming part of the feasibility material annexed to the bid.
There is nothing in the Agreement which converts that IRR projection
into a guaranteed return, much less into a contractual rate of interest
on the claims raised by the respondent. The admitted position on record
is that the respondent's actual cost of borrowing from its lenders was
13.5%.
56. The learned Tribunal nevertheless awarded every allowed claim
together with IRR at 20.33%, on a compounding basis, from accrual,
treating the IRR as the measure of the respondent's entitlement as if it
were the rate of the interest which was agreed by the appellant. The
reliance on State of Maharashtra v. Khare & Tarkunde(supra) is
misplaced. There, the rate upheld reflected the actual rate of interest
the contractor was paying to its bankers, which the banks had declined
to reduce. The decision is no authority for adopting a notional appraisal
metric as the rate of return on an award. Nor does the award reflect any
consideration of the factors governing the award of interest recognised
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 55 of 76 ) [CMA-1560/2025]
in Vedanta Ltd. v. Shenzen Shandong (supra) , or of the settled
position that compound interest/interest upon interest is not to be
awarded absent contractual or statutory sanction ( State of Haryana v.
24
S.L. Arora & Co. D. Khosla & Co. v. Union of India ).
56.1 The adoption of 20.33% compounding IRR inflates every claim
exponentially, on the respondent's own showing, it is this element which
swells the award from Rs. 198.04 crores to a figure in the region of Rs.
544.43 crores as on 28.02.2025 (date of execution petition). This
element of the award is without contractual foundation, without reasons
addressing reasonableness, and vitiates the quantification of each claim
in its entirety. Submission VI is also accepted.
(f) Submission VII — Claims 2(i), 2(iii) & 4 beyond the contract
57. Claim 2(i) — leakage of traffic through the old GKG road (Rs.
12.20 crores). The learned Tribunal has not referred to any provision of
the Concession Agreement obliging the appellants to ban all tollable
traffic on the old GKG road. The pre-bid assurance, on the record as we
read it, extended to restricting the entry of heavy vehicles, buses and
trucks, on the old road. In consonance therewith, a gazette notification
dated 31.01.2013 was, in fact, issued banning heavy traffic on the old
GKG road. That traffic was diverted to the project road, and even
barriers were erected. The appellants thus performed the only
obligation they had undertaken. To hold the appellants liable in
damages for not banning other categories of traffic they never
undertook to ban amounts to enforcing an obligation which the contract
does not contain. The judgment of the Hon'ble Supreme Court in MSK
25
Projects (India) (JV) Ltd. v. State of Rajasthan , where a claim
for loss of toll was negatived notwithstanding the issue of a toll
24
(2010) 3 SCC 690
25
(2011) 10 SCC 573
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 56 of 76 ) [CMA-1560/2025]
notification restricting heavy vehicles, applies with full force and was
not noticed by the learned Tribunal.
58. Claim 2(iii)- demonetisation (Rs. 1.68 crores). The claim was
allowed as Force Majeure costs. Clause 11.6(d) of the Agreement,
however, mandates that Force Majeure costs be certified by the Steering
Group and thereafter verified by the Chief Engineer, JDA/UDH.
Admittedly, no such certification or verification was ever undertaken.
The learned Tribunal accepted the figures on the strength of the
respondent's own material. The contractual machinery for quantification
was thus bypassed altogether. Further, the office orders suspending toll
relied upon by the respondent were issued by the Public Works
Department and NHAI for roads under their respective jurisdictions. No
order of the appellants directed suspension of toll on the project road,
which is not a National Highway. The respondent, in fact, continued
collecting toll on 9, 10 and 11 November 2016. Nor was any Material
Adverse Effect of the demonitisation event pleaded. The O&M expenses
and interest-repayment obligations allowed under this head bear no
direct correlation with the Force Majeure event as envisaged under
Article 11. The claim was thus allowed both beyond the terms of the
Agreement and in disregard of its mandatory machinery and its
mechanism.
59. Claim 4 — denial of advertising rights (Rs. 8.49 crores). Article
17.3 permits advertising on the project site subject to the safety of the
users of the project road. Article 17.3 is reproduced hereinbelow for
ready reference:-
"Article 17.3- Advertising on the Project Site:
The Concessionaire shall not undertake or permit any form of
commercial advertising, display or hording at any place on the Project
site if such advertising, display or hording shall affect the safety of users
of the Project facility while driving. Provided, however, that this sub-
article shall not apply within the rest areas on the Project Site, which the
concessionaire may/may allow to operate".
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 57 of 76 ) [CMA-1560/2025]
The Empowered Committee, in its meeting of 06.02.2015, rejected the
advertising proposal on the express ground that the serpentine
alignment of the road rendered roadside advertising unsafe. The
learned Tribunal has not recorded any finding that this safety-based
rejection was unjustified, colourable or contrary to Article 17.3. Instead,
it faulted the appellants for a “lack of concern for the profit earning
opportunity” of the respondent. With respect, in a contest between a
statutory authority's assessment of road-user safety and a
concessionaire's profit expectation, the contract itself, through its Article
17.3, subordinates the latter to the former. Even otherwise, the learned
Tribunal accepted the quantum of Rs. 8.49 crores as claimed to be
gospel, without any scrutiny of its computation. The allowance of Claim
4 is thus both beyond the contract and perverse. Submission VII is
accepted.
G. Re:Question (iii):
Whether the learned Sole Arbitrator traversed beyond the
scope of the Concession Agreement, thus rendering the
award unsustainable in law
60. We now turn to question (ii), i.e., whether the learned Arbitrator
travelled beyond the scope of the Concession Agreement. At the outset,
a caveat is necessary, lest the respondent form the impression that we
intend to re-appreciate the evidence or freshly interpret the terms of
the commercial contract. We propose to do neither. Our sole inquiry is
whether the learned Sole Arbitrator, being a creature of the contract,
exceeded the bounds of the Concession Agreement. We shall not,
therefore, either delve into the merits of the evidence, or examine the
merits of the underlying dispute, or reinterpret the contract executed
between the parties, or even undertake any independent assessment of
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 58 of 76 ) [CMA-1560/2025]
the merits of the award. With this limitation in mind, we proceed to
analyse the three claims allowed by the learned Arbitral Tribunal.
(a) Reasoning on Claim No. 1 (Increase in Project Cost)
61. The challenge laid by the appellants to Claim No. 1 proceeds, in
the first instance, upon the contractual structure of the project as a
DBFOT concession. Reliance in this context is placed upon Clause 2.1
under the head ‘Grant of Concession’, Clause 2.3 under the head
‘Acceptance of Concession’, Clause 5.1 under the head ‘General
Obligations of the Concessionaire’, and Clause 7.1 under the head
‘Preparation of Drawings’ which are already reproduced in Para
54(supra) in the preceding part.
Upon a conjoint reading of these stipulations, the position which
emerges is that the concessionaire had expressly undertaken to
investigate, survey, design and execute the project at its own cost and
risk, and that the drawings, even where adopted from departmental
material, remained the sole responsibility of the concessionaire. This
contention of the appellants, in our considered opinion, merits
acceptance. Once the parties had consciously allocated the risk of
investigation, survey and design to the concessionaire under the
aforesaid clauses, the learned Sole Arbitrator could not have invoked
the mandate of Section 28(3) of the Act of 1996 and thus, fastened the
financial consequences of redesign upon JDA without first locating a
contractual stipulation displacing burden of that allocation. The award
identifies no such stipulation, and the effective transfer of the design
risk from the respondent to the appellants runs counter to the express
terms of the Concession Agreement.
62. Furthermore, the appellants contention is that the DPR was only a
referential document and not a binding design code. This plea, in fact,
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 59 of 76 ) [CMA-1560/2025]
stands substantiated on a plain reading of Schedule A under the head
‘Project Description and Broad Particulars’, (Annexure-I to Schedule A),
Clause 1.1 under the head ‘Alternative Design / Cross-Sections /
Lowering of Formation Level’ in case of apparent DPR errors (Annexure-
I to Schedule A), Clause 2.5 under the head ‘Minimum Parameters for
Horizontal and Vertical Alignment’. Clause 2 of Schedule A prescribed
the Indian Roads Congress norms and Ministry of Road Transport and
Highway (MoRTH) specifications as the governing standards. Whereas,
the DPR stood appended only for reference. The pre-bid clarification
issued in response to the specific query as to whether the DPR was
required to be followed showing the non-binding character of that
document beyond doubt even prior to submission of bids. In such a
contractual setting, the DPR could not have been elevated into a binding
design mandate, and the learned Tribunal’s finding to the contrary
amounts to rewriting the bargain between the parties, which is
impermissible.
63. The contrary reasoning recorded in the award, namely that the
DPR and the alignment parameters shown therein constituted minimum
design requirements and that deviation therefrom was permissible only
upon demonstration of apparent error and sound durable design, does
not, in our view, amounts to rewriting the terms of concession
agreement. Annexure I to Schedule A, Clause 1.1 itself contemplates
adoption of alternative design, cross-sections and lowering of formation
level in the event of apparent errors in the DPR. The contract thus
foresaw the possibility of imperfections in the DPR and cast the burden
of devising a sound and durable design upon the concessionaire as part
of its own obligations under Clause 7.1, rather than converting every
such imperfection into a compensable event against the authority. By
reading Clause 7.1, Annexure I to Schedule A, Clause 1.1 and Annexure
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 60 of 76 ) [CMA-1560/2025]
I to Schedule A, Clause 2.5 as fastening upon the appellants the
consequences of the very errors whose correction the contract
entrusted to the concessionaire, the learned Sole Arbitrator went way
beyond the contractual scheme. Thus, we cannot concur with such an
approach as it does not appear to be reasonable to us, thereby
attracting the vice of patent illegality.
64. The appellants also contend that the revised alignments had been
placed before and duly approved by the Empowered Committee. This
submission is referable to Clause 15.1(c) under the head Dispute
Resolution / role of the Empowered Committee and expressly stated
contractual departures, read with the Rajasthan Road Development Act,
2002. Clause 15.1(c) is reproduced hereinbelow for ready reference:-
"(c) Stage 3: If the dispute is not settled within 6 months, the
concessionaire may refer the dispute to Empowered Committee for final
settlement.”
Apropos, the revised alignment was admittedly placed before and
approved by the Empowered Committee constituted under the Act of
2002. Once such statutory approval was granted through the
mechanism which the contract and the statute themselves
contemplated, the deviation from the DPR could not, by itself, be
attributed as a breach on the part of the appellants or be converted into
a foundation for monetary compensation. We are of the view that the
award, inasmuch as, treating the very approvals granted in the
respondent's favour as circumstances fastening liability upon the JDA,
falls foul of the legal effect of those approvals. The appellants'
contention on this score, therefore, must be accepted.
65. Equally weighty is the appellants' argument founded upon Clause
16 / Clause 16.2 under the head Disclaimer / Independent Evaluation /
Acceptance of Risk of Error. Under Article 16, the concessionaire
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 61 of 76 ) [CMA-1560/2025]
acknowledged that it had made an independent evaluation of the site,
the specifications, the standards and the traffic, and had accepted the
risk of adequacy, mistake or error in the information supplied, with the
further stipulation that the authority would not be held liable in respect
thereof. The alleged deficiencies in the DPR fall squarely within the field
occupied by this provision. Clause 16 is a considered risk-allocation
clause negotiated between commercial parties to a concession of this
magnitude, and it directly barred the respondent from claiming
damages on account of any error in the bid documents, including the
DPR. The contention of the appellants that the claim was contractually
excluded therefore deserves acceptance.
66. The submission that the learned Sole Arbitrator wrongly discarded
the protection flowing from Article 16, and erred in applying
precedent/case law to dilute its effect, must also succeed. Said
submission falls for out consideration against the same contractual head
of Disclaimer / Independent Evaluation / Acceptance of Risk of Error.
Pertinently, Article 16 is not a clause exempting the authority from the
consequences of its own breach. It is a clause allocating, in advance,
the risk of adequacy, mistake or error in the information supplied to the
bidders. The exclusionary clauses considered in the reported decisions
relied upon in the Award stand on a materially different footing. Their
ratio could not have been invoked to efface an express risk-allocation
stipulation. Impugned Award thus disregards the binding term of the
contract which is contrary to mandate of Section 28(3) of the Act of
1996. It is vitiated by patent illegality on that count also.
67. The appellants' plea that there was no identified contractual
breach, and that compensation could not be awarded merely on broad
notions of unfairness, is also well founded when tested against Clause
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 62 of 76 ) [CMA-1560/2025]
2.3 under ‘Acceptance of Concession’, Clause 5.1 under ‘General
Obligations of the Concessionaire’, Clause 7.1 under ‘Preparation of
Drawings’, and Clause 12.1(b) under ‘Notice of Breach’. No positive
obligation regarding provision of designs and drawings lay upon the
appellants. The same being the concessionaire's own responsibility
under the DBFOT structure. No notice of breach under Clause 12.1(b)
was ever issued. The award does not identify any specific contractual
obligation of the appellants which stood violated. Compensation under
Sections 54, 55 and 73 of the Contract Act presupposes an obligation
and established breach of an identified obligation. In its absence, the
grant of damages which rests upon considerations of perceived
unfairness is alien to the contract. Learned Arbitrator, being creation of
contract adjudicatory forum, is equally bound by the agreement. The
finding on liability under Claim No. 1 is, for this reason as well,
unsustainable.
68. The appellants' central submission that the contract contemplated
extension of concession period, and not cash compensation, for non-
termination situations also commends acceptance. Same is borne out
from a combined reading of Article 10 under Change of Scope, Clause
11.5 under Force Majeure and Consequential Relief/Extension, Clause
13.2 under Change in Law, Clause 12.2(b)(2) under Termination
Payment, and Clause 12.1(b) under Notice of Breach. These contractual
clauses have already reproduced in Para 44(supra). The contractual
scheme, save and except the case of termination payment, recognized
extension of the concession period as the compensatory mechanism for
the events pleaded, and extensions aggregating 484 days had in fact
been granted by the Empowered Committee for the very causes
underlying the claim. Having received that relief translated in money
terms as Rs. 119 crore, which the contract itself provided by way of
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 63 of 76 ) [CMA-1560/2025]
extention of time, the respondent could not have been granted a
superadded money claim for the same causes. In allwoing that claim,
the learned Sole Arbitrator substituted a compensatory regime of it’s
own making for the negotiated risk allocation embedded in the
agreement, thereby travelling beyond the contract.
69. The appellants' objection to the reliance placed by the respondent
on additional term loan arrangements, enhanced project cost and
financing documents likewise deserves acceptance, having regard to
Clause 9.2 under the head ‘Amendments to Financing Documents’,
Clause 17.7 under the head ‘Amendment only in the manner provided in
the Agreement’, and the definitional provisions of Clause 1.1. The
additional term loan of Rs. 23.72 crores was a private arrangement
between the respondent and Punjab National Bank, to which the
appellants were not parties. Qua with which they had no privity. Clause
9.2 regulated amendments to financing documents, and Clause 17.7
mandated that the Concession Agreement could be amended only in the
manner provided therein. No amendment binding the JDA, or enhancing
the approved project cost as against the JDA, could be inferred dehors
this express contractual machinery. The award thus errs in treating the
enhanced financing as if it enlarged the appellants' obligations.
70. For the same reasons, the appellants' contention that no
monetary consequence could flow from the additional financing
arrangements, and that the express bar under Clause 17.7 prevented
any deemed amendment of the bargain, must be upheld. In taking the
enhanced project cost, the additional borrowing and the projected
return as the measure of the appellants' liability, the learned Sole
Arbitrator effectively restructured the project cost, return and
compensation payable under the concession, an exercise which neither
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 64 of 76 ) [CMA-1560/2025]
Clause 9.2 under Amendments to Financing Documents nor Clause 17.7
under Amendment only in the manner provided in the Agreement
permits. An Arbitral Tribunal, being a creature of the contract, cannot
remake or rewrite the contract for the parties, and the award, insofar as
it proceeds upon such deemed restructuring, travels outside the four
corners of the agreement.
71. The appellants' submission that the learned Sole Arbitrator
wrongly treated IRR at 20.33 as if it were an enforceable rate of interest
or return against the appellants is also merited. The Internal Rate of
Return is an internal financial metric employed by the concessionaire
and its lenders for appraisal of the investment model reflected in
Schedule A and the financing framework. It is not a contractual promise
by the authority to assure any particular return. Neither the Concession
Agreement nor the applicable legal framework permits the mechanical
transposition of such a projection into a money decree, or into a rate of
interest, against the authority. The adoption of IRR at 20.33 as the
measure of recovery is without contractual foundation and constitutes a
further facet of the patent illegality vitiating the award on Claim No. 1.
(b) Reasoning on Claim No. 2 (Loss of Toll Revenue)
72. In relation to Claim No. 2, the entitlement asserted by the
respondent rests upon Clause 4.1(a) under the head Right to Levy,
Demand, Collect and Appropriate Fee. That clause confers upon the
concessionaire the right to levy, demand, collect and appropriate the fee
from users of the project facility. It does not, by its terms, amount to a
guarantee by the authority of any particular volume of tollable traffic,
nor an indemnity against leakage or diversion of traffic through the old
Ghat Ki Guni road or other routes. The award proceeds upon the
premise that the entitlement to collect toll carried with it an enforceable
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 65 of 76 ) [CMA-1560/2025]
assurance of traffic, a premise which finds no support in the language of
Clause 4.1(a). To the extent, the award elevates a contractual right to
collect fee into a warranty of revenue against the authority and the
appellants' objection is well taken.
73. The appellants' plea that they had undertaken only to restrict
heavy vehicles, and not all tollable traffic, must equally be accepted on
a consideration of Clause 4.1(a), the pre-bid minutes relied upon by the
parties, and the contractual matrix governing toll entitlement. The
commitment reflected in the pre-bid minutes concerned buses and
trucks only, and that commitment stood honoured through the gazette
notification dated 31.01.2013 and the erection of physical barriers. The
assumption in the award that the appellants had undertaken to ban all
tollable traffic from the old road enlarges the appellants' obligation
beyond anything found in the contract or the pre-bid record, and the
residual movement of other categories of vehicles could not, in law,
translate into a contractual claim for damages. The finding on this
component of Claim No. 2 therefore rests upon an obligation which
never existed.
74. Insofar as the component of Claim No. 2 founded on
demonetisation is concerned, the matter is governed by Clause 11.5
under Force Majeure and Consequential Relief/Extension and Clause
11.6(d) under Certification/Verification in relation to Force Majeure
consequences. Clause 11.6(d) made certification by the Steering Group,
and verification by the Chief Engineer, JDA/UDH, a mandatory
precondition to the allowance of force majeure costs. Admittedly, no
such certification or verification preceded the allowance of the
demonetisation component. The grant of relief in the absence of an
express condition precedent stipulated by the parties is not a matter of
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 66 of 76 ) [CMA-1560/2025]
appreciation of evidence but a departure from the contractual
machinery itself, and the appellants' contention that this component
could not have been allowed without compliance with Clause 11.6(d)
must be accepted.
(c) Reasoning on Claim No. 4 (Advertisement Rights)
75. As regards Claim No. 4, relating to compensation for denial of use
of the right of way for advertisements, the claim was required to be
established with reference to the provisions of the Concession
Agreement and Schedule A dealing with commercial exploitation and
advertisement rights. The award records no sustainable finding on
whether the proposal for advertisements compromised road safety,
which was the ground on which permission was declined, nor does it
contain an assessment, in accordance with law, of the quantified loss of
Rs. 8.49 crores, and the objections founded on contractual limitation
and limitation in law remained unaddressed. An award of compensation
which neither anchors the entitlement in an identified contractual
provision nor records proof of the loss claimed cannot withstand
scrutiny, and the appellants' challenge to the finding on Claim No. 4
accordingly succeeds.
H. Re:Question (iv):
Whether the corrigendum award dated 31.07.2023 exceeds
the permissible scope of Section 33 of the Act of 1996
Submission VIII —
76. Section 33(1)(a) of the Act of 1996 permits correction of
computation errors, clerical or typographical errors or errors of a
similar nature. Upon the respondent's application dated 29.07.2023,
the learned Tribunal, by the Corrigendum Award dated 31.07.2023,
deleted the words “amounting to Rs. 198.04 crores” occurring in
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 67 of 76 ) [CMA-1560/2025]
paragraph 141 of the award. The effect of the deletion, as the
respondent's own note before us demonstrates, is to unshackle the
direction for payment of IRR at 20.33% from the ceiling of the
aggregate figure and to enlarge the operative award from Rs. 198.04
crores to a figure in the region of Rs. 457 crores. A deletion which
multiplies the award more than twofold is not the correction of a
clerical, typographical or computational error; it is a substantive
modification of the award and the grant, after the award, of a relief not
granted in the award, a course wholly outside Section 33, after which
the learned Tribunal stood functus officio: State of Arunachal
26
Pradesh v. Damani Construction Co. ; Gyan Prakash Arya v.
27
Titan Industries Ltd. . The Corrigendum Award is unsustainable on
this short ground alone.
77. We are of the considered opinion that, in relation to the
corrigendum award, the jurisdiction under Section 33(1)(a) of the Act of
1996,is confined to the correction of computation, clerical, typographical
or similar errors, and does not extend to substantive modification of the
award. By granting interest at 20.33 under the guise of clarification,
when the original award, read with the financing and compensation
clauses of the Concession Agreement noticed above, furnished no basis
for such relief, the corrigendum effected a substantive alteration of the
award. The appellants' contention that the corrigendum award dated
31.07.2023 exceeded the permissible scope of Section 33 of the Act of
1996 is therefore accepted, and the corrigendum cannot survive
independently of the award which it purported to clarify.
Submission VIII is accordingly, accepted.
26
(2007) 10 SCC 742
27
(2023) 1 SCC 153
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 68 of 76 ) [CMA-1560/2025]
I. Re:Question (v):
Whether the learned Commercial Court failed to exercise
jurisdiction vested in it under Section 34 of the Act of 1996
while declining interference with the award
78. As regards the impugned order dated 27.01.2025, we regret to
observe that the learned Commercial Court, though correctly extracted
the statutory tests under Section 34 and the case-law delineating them,
but it did not thereafter apply those tests to the specific objections
raised. It also disregarded SC judgment in Ramnath (supra). The
adoption of IRR as interest, the bypassing of Clause 11.6(d) and the
scope of Section 33 was also given a short shift. The operative
reasoning of the learned Commercial Court is, in substance, that the
award is “detailed and reasoned” and that the Court “does not have
appellate jurisdiction” and therefore “cannot delve into the merits”. The
limited nature of Section 34 jurisdiction is not a warrant for declining to
exercise it at all. Where objections squarely invoking patent illegality
and conflict with public policy are raised, the Commercial Court is bound
to test the award against those parameters and record its own reasons.
Failure to do so is a failure to exercise jurisdiction vested in it.
(J) Disproportionality -
79. Dehors all that has been discussed in the preceding part, there is
one further, overarching aspect of the matter which, in our considered
opinion, independently vitiates the award, and which we consider it our
duty to record. The arithmetic of the award, when laid bare, speaks for
itself. Conceded case of the claimant/respondent is that the actual date
of completion of the work is 31.01.2013, on which date as per its own
calculations, as against the project cost of Rs. 150 crores, it incurred
Rs. 207.87 crores. Thus, a cost overrun of Rs. 57.87 crores. After the
actual completion date, i.e., 31.01.2013, there was no further cost and
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 69 of 76 ) [CMA-1560/2025]
it was all revenue receipts against toll collection. Taken to its best, the
claimant could, at the most, seek compensation of Rs. 57.87 crores
along with interest, but that too not in monetary terms but by extension
of time since as per the contract, time was revenue.
79.1 However, we have already held that extension of time of 484 days
was granted and no further was asked for. The Project Cost stood
contractually frozen at Rs. 150 crores. On the respondent's own
showing, resting on the certificates of its Chartered
Accountants/Statutory Auditors, the actual capital cost of the project
upon completion was Rs. 207.85 crores. That is to say, the entire cost
escalation which the respondent itself asserted, and which the learned
Tribunal accepted, was of the order of Rs. 57.87 crores. Upon this
foundation of Rs. 57.87 crores, the learned Tribunal awarded, under
Claim 1 alone, a sum of Rs. 175.67 crores, the principal escalation
compounded at the so-called IRR of 20.33%, i.e., more than three
times the escalation itself, and to this were added the further claims,
taking the aggregate award, as on the date of the Statement of Claim,
to Rs. 198.04 crores. The Corrigendum Award of 31.07.2023 then
jumped even that ceiling, directing IRR at 20.33% until actual
realisation.
79.2 The consequence, as pointed out at the Bar and not disputed
before us, is that in the execution proceedings arising out of the award
as corrected, the respondent has laid a claim exceeding Rs. 500 crores.
In other words, an admitted cost escalation of about Rs. 57 crores has,
by the alchemy of a compounding “internal rate of return”, been
transmuted into a demand of over Rs. 500 crores against the public
exchequer, roughly nine times escalation on which the entire claim was
founded, and more than three times the agreed cost of constructing the
tunnel project itself. Indeed, Claim No. 1 alone, at Rs. 175.67 crores,
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 70 of 76 ) [CMA-1560/2025]
exceeds the contractually frozen cost of the entire project; the
“compensation” for an incident of the project has outstripped the cost of
the project.
80. Such a result seems to us, with due respect, rather preposterous,
and no process of reasoning consistent with law can sustain it. The law
of damages is compensatory, not punitive. Section 73 of the Contract
Act entitles a party only to compensation for loss or damage which
naturally arose, or which the parties knew to be likely to arise, from the
breach, and to nothing more.
80.1 An award mechanism under which the remedy grows, year upon
year and on a compounding basis, at a rate half as high again as the
claimant's own admitted cost of borrowing (13.5%), and continues to
grow after the award until realisation, does not just compensate a loss;
In fact, it confers a windfall, converts the arbitral award into a high-
yield investment against the State, and creates the perverse
consequence that every day of delay enriches the claimant beyond any
loss it could conceivably have suffered.
80.2 When the paying party is a statutory development authority and
the ultimate source of payment is public money collected from the
citizens, the award operates as unjust enrichment at the cost of the
public exchequer. Proportionality between the wrong (if any) and the
remedy is an elementary requirement of justice. An award which bears
no rational proportion to the loss found, indeed, in the present case, to
a loss never found, there being no finding of breach at all, shocks the
conscience of the Court. As held in Associate Builders (supra) and
reiterated in Ssangyong (supra) , an award which shocks the
conscience of the Court conflicts with the most basic notions of morality
and justice within the meaning of Explanation 1(iii) to Section 34(2)(b)
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 71 of 76 ) [CMA-1560/2025]
(ii) of the Act of 1996, and this ground, though to be applied sparingly,
exists precisely for a case such as the present.
81. We are conscious that inadequacy or excessiveness of the amount
awarded is not, by itself, a ground of challenge to the Award under
Section 34, and that the Court does not sit in appeal over quantum. But
that principle presupposes an award whose measure of compensation is
anchored in the contract or in law.
81.1 In the case in hand, the very measure adopted is a notional,
compounding project- appraisal rate (IRR) applied to claims which have
been allowed. That too, without a finding of breach. And as an icing on
the cake, unmoored by the corrigendum from any ceiling, which is itself
dehors to the contract. Moreover, it is contrary to Section 73 of the
Contract Act. It is contrary to the public policy reflected in the Interest
Act. It is contrary to Section 31(7) of the Act of 1996 and productive of
a result which is wholly unconscionable.
81.2 The vice is therefore not one of mere quantum but of the legal
foundation of the award itself, and squarely falls within Section 34(2)(b)
(ii) read with Explanation 1, as also Section 34(2A). This aspect, too,
wholly escaped the attention of the learned Commercial Court.
81.3 The award is liable to be set aside on this ground independently
of, and in addition to, the grounds recorded hereinabove.
82. We may also add here that as regards the corrigendum of the
award, since the main award has not be found tenable by us, on that
ground alone the sequel thereof i.e. corrigendum award is liable to be
set aside, though, of course, in the preceding part we have dilated on
its merits also and given independent reasons for its un-sustainability.
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 72 of 76 ) [CMA-1560/2025]
K. Our view on submissions of the respondent
83. The submissions advanced on behalf of the respondent, though
attractively presented by Sh. Sudhir Gupta, learned Senior Advocate, do
not, in our considered opinion, salvage the award. Let us see how.
83.1 Narrow scope of Sections 34/37; plausible view.
The propositions of law are unexceptionable, and we have kept
them in the forefront of our consideration. But the deference owed to a
plausible arbitral construction presupposes that the construction is one
which the contract can reasonably bear. For the reasons recorded under
Submissions I, IV and VI, the learned Tribunal's construction, that a
contract whose every provision channels relief through the extension of
concession period nonetheless permits cash compensation with a
compounding return of 20.33%, and that a DPR expressly furnished for
reference with an express acknowledgment of possible error was
nonetheless the binding benchmark, is not a possible view on the
Agreement read as a whole. The vices found by us, re-writing of the
contract, internal contradiction, disregard of binding precedent and of
vital evidence, compensation without breach, and an out-of-jurisdiction
corrigendum, are the very grounds which Sections 34(2A) and 34(2)(b)
(ii) recognise; interference on these grounds is not re-appreciation of
evidence.
83.2. New grounds.
The objection is not borne out by the record. The award itself
records (inter alia in the discussion of Claim 1) the appellants'
submissions before the learned Tribunal on the absence of any enabling
provision for compensation, on the definition of Project Cost, on Clause
9.2, on Article 16, on the pre-bid queries and on the incorrectness of
the 20.33% IRR. The pleas of internal contradiction and of the
corrigendum exceeding Section 33 could, in the nature of things, arise
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 73 of 76 ) [CMA-1560/2025]
only after the award and the corrigendum respectively. In any event, a
patent illegality appearing on the face of the award, and each of the
vices found by us so appears, can be examined by the Court, as held in
Sal Udyog (supra) , the very decision the parties cite. The plea of
double recovery rests on the Empowered Committee's decisions, which
were part of the record before the learned Tribunal.
83.3 Cash flow projections and IRR form part of the Agreement.
Even accepting that the cash flow projections in the prescribed
format formed part of the bid documents, their incorporation does not
transmute an estimated appraisal metric into a guaranteed return. The
projections were the basis on which the concession period was quoted
and evaluated. The Agreement's chosen mechanism for preserving the
economics so projected was, again, adjustment of the concession
period, a remedy the respondent sought and obtained. The submission
proves, if anything, the appellants' case.
83.4 Silence of the contract.
The contention that the Agreement, being silent on damages for
breach and containing no express bar on cash compensation, left the
field open to the learned Tribunal, is answered by what we have held
under Submissions I and V. To sum up, the contract is not silent, it
prescribes a specific and exhaustive remedy and in any event no breach
of any identified obligation of the appellants was found. The learned
Tribunal's own paragraph 124 accepts the correct position.
83.5 Findings of fact on the faulty DPR etc.
The deficiencies in the DPR, the debarment of the DPR consultant,
and the presence of the Balaknath Samadhi may all be accepted as
facts. They do not answer the anterior legal questions, upon whom the
Agreement placed the design and investigation risk, and what remedy
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 74 of 76 ) [CMA-1560/2025]
the Agreement provided, which the learned Tribunal answered contrary
to the contract.
83.6 Concurrent findings.
The caution against disturbing concurrent findings under Section
37 presupposes that the Section 34 Court in fact examined the
objections. For the reasons recorded in paragraph 80 above, it did not.
Where the first Court fails to exercise its jurisdiction, the appellate
Court under Section 37 must correct the error rather than compound it.
84. The aforesaid submissions of the respondent are accordingly
rejected.
L. Conclusion
85. Findings on the respective rival submissions are thus :
(i) the plea of limitation raised by the appellants (Submission II) is
rejected for the reasons recorded in paragraphs 40 to 42 above;
(ii) Submissions I and III to VIII of the appellants are accepted;
(iii) the submissions of the respondent are all rejected.
M. ANSWERS TO THE LEGAL QUESTIONS
86. In light of the discussion on the applicable law and the outcome
thereof as recorded in the preceding part, the answers to the all the
four legal ponis as framed in para -30 are in the affirmative.
N. SUMMARY
87. To summarise:
(i). The arbitral award dated 25.06.2023, as modified by the
Corrigendum Award dated 31.07.2023, in so far as it allows
Claims 1, 2(i), 2(iii) and 4 with IRR at 20.33% and costs, suffers
from patent illegality appearing on its face and is in conflict with
the fundamental policy of Indian law and the basic notions of
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 75 of 76 ) [CMA-1560/2025]
justice, within the meaning of Section 34(2)(b)(ii) read with
Explanations 1 and 2 and Section 34(2A) of the Act of 1996:
(ii). it travels beyond and re-writes the terms of the Concession
Agreement; it is internally contradictory; it disregards the vital
admitted material;
(iii). it awards compensation without any finding of breach; it
adopts a rate of return foreign to the contract;
(iv). it inflates an admitted escalation of about Rs. 57.87 crores
into a liability now claimed in execution at over Rs. 500 crores
(plus other claims), a result which shocks the conscience of the
Court;
and
(v). the corrigendum exceeds the jurisdiction conferred by Section
33 of the Act of 1996.
88. The infirmities noticed above are not confined to any severable
part of the award. The misconstruction of the contractual scheme
infects the entitlement under every allowed claim. Furthermore, the
adoption of IRR at 20.33% infects the quantification of every allowed
claim.
89. This is, therefore, not a case in which any portion of the impugned
award dated 25.06.2023 can be salvaged by severance on the principles
recognised in Gayatri Balasamy v. ISG Novasoft Technologies
28
Ltd. . The impugned award, to the extent it allows the claims, must
therefore, fail as a whole. Equally, the impugned order dated
27.01.2025, passed by the learned Commercial Court, having failed to
test the award on the statutory parameters, cannot be sustained.
28
(2025) 7 SCC 1
(Uploaded on 17/08/2026 at 07:59:14 PM)
(Downloaded on 18/08/2026 at 12:37:19 PM)

[2026:RJ-JP:30253-DB] ( 76 of 76 ) [CMA-1560/2025]
O. ORDER
90. Upshot of our analysis leads us to pass the following resultant
order:
(i) The appeal is allowed.
(ii) The order dated 27.01.2025 passed by the learned District
Judge, Commercial Court No. 2, Jaipur Metropolitan-II in
Objection Application No. 85/2024 is set aside.
(iii) The arbitral award dated 25.06.2023 and the Corrigendum
Award dated 31.07.2023 passed by the learned Sole Arbitrator
are set aside.
(iv) The amounts, if any, deposited by or recovered from the
appellants in execution or otherwise pursuant to the award,
including any amount realised by invocation of bank guarantee
referable to the award, shall abide by such restitution as the
parties may be entitled to in accordance with law.
(v) In the circumstances of the case, the parties shall bear their
own costs. All pending applications stand disposed of.