+ W.P.(C) 568/2024
DR OM PRAKASH KHARBANDA & ANR. .....Petitioners
Through: Mr Akhilesh Kumar Dixit along with
Sonu Narwal, Advs.
versus
ADM/LAC, DISTT. NORTH AND ANR .....Respondents
Through: Mr. Prashant Diwan, Adv.
CORAM:
JUSTICE PRATHIBA M. SINGH
JUSTICE MADHU JAIN
Prathiba M. Singh, J. (Oral)
1. This hearing has been done through hybrid mode.
2. The Petitioners have filed the present petition seeking release of their
st
withheld payments in terms of Award no. 16/03-04 dated 1 October, 2003
th
Supplementary Award No. 16A/04-05 dated 27 October, 2004, along with
interest from due date of payment till actual realisation.
3. The case of the Petitioners is that accumulated land of 445 Bigha 18
Biswas of Village Holambi Kalan was acquired vide notification issued on
rd
23 May, 2002.
4. The jointly owned land of the Petitioners falls in Khasra No. 32/7 (4-
16), 32/8 (3-3) and 32/6 (4-16) ad-measuring 12,856 sq. yards (approx.)
(hereinafter, ‘the subject land’ ). The details of the Petitioners are as under:
Petitioner No. 1-
Dr. Om Prakash Kharbanda S/o Late Shri C R Kharbanda
R/o B-43, Mohan Park, Navin Shahdara, Delhi – 110032
Signature Not Verified
W.P.(C) 568/2024 Page 1 of 4
Signed By:RENUKA
NEGI
Signing Date:24.04.2026
19:35:05

Petitioner No. 2-
Hans Kumar (HUF) Karta Hans Kumar Gupta S/o Late Shri
A P Gupta
R/o 72, Defence Enclave, Delhi-110092
5. Award no. 16/2003-2004 was passed under the Land Acquisition Act,
th
1894 on 1st October, 2003 and the same was reviewed on 14 July, 2004
wherein the compensation payable to the beneficiaries, including the
Petitioners was reduced.
th
6. A Supplementary Award No. 16A/2004-2005 was also passed on 27
October, 2004.
7. The review award, however, came to be challenged before the High
Court, and thereafter before the Supreme Court. The Supreme Court, in Civil
Appeal no 6637/ 6638 of 2010 , vide order dated 17th October, 2019, set aside
the said review award dated 14th July, 2004.
8. In the same Civil Appeal no 6637/ 6638 of 2010 before the Supreme
Court, a contempt petition was filed by another land owner/ bhumidar bearing
Contempt 545/546 of 2020 and notice was issued to the Respondents.
9. In the said contempt petition, there was a document which was
th
circulated as the minutes of meeting dated 4 January, 2021 and the details of
the affected persons in respect of the said review award no. 16/2003-2004 was
set out. The said is extracted below:
Signature Not Verified
W.P.(C) 568/2024 Page 2 of 4
Signed By:RENUKA
NEGI
Signing Date:24.04.2026
19:35:05

10. The case of the Petitioners is that their share is reflected at Sl. No. 4 of
the above table and the amount in terms of the above table has not been paid
to them.
11. The LAC has filed a counter affidavit before this Court as per which,
th
some amount has already been paid on 29 March, 2022 to the tune of Rs.
6,38,798/-. The relevant portion of counter affidavit is set out below:
“2. That the prayer of the present Writ Petition has
already being satisfied by the office of respondent
no. 1 before institution of the present petition as no
payment is due to both the petitioners in terms of
Award No.16/2003-04also in terms of
supplementary Award No. 16A/2004-05 of 16/2003-
04 whereby the balance/adjusted amount
i.e.Rs.6,38,798/- was paid to petitioner no. 1 vide
Cheque no. 284684 and Rs.6,38,798/- was paid to
petitioner No. 2 vide Cheque no. 284683 both dated
29.03.2022 respectively in accordance with the
original Award no. 16/2003-04, Therefore the
present Writ Petition has became infructuous as the
main prayer of Writ petition has already being
Signature Not Verified
W.P.(C) 568/2024 Page 3 of 4
Signed By:RENUKA
NEGI
Signing Date:24.04.2026
19:35:05

satisfied”
12. The submission of the ld. Counsel for the Respondents is that the
Petitioners did not fairly disclose the payment of the amount.
13. Ld. Counsel for the Petitioners, on the other hand submits that much
more amount is due to the Petitioners in terms of the LAC’s own minutes of
meeting which is placed on record in the contempt petition.
14. Under these circumstances, this Court is of the view that firstly,
Petitioners chose not to disclose all the true facts in respect of receipt of
compensation.
15. However, even the LAC is silent about the amount which was
mentioned in the table filed in the contempt petition as being due to the
Petitioners.
16. Under these circumstances it is directed that the amounts due to the
Petitioners, if any, be released by the LAC within two months from the date
of this order.
17. If the same is not released within two months in terms of the Minutes
th
dated 4 January, 2021, higher interest would be liable to be directed.
18. The petition, along with pending applications, if any, are disposed of.
19. Liberty is granted to the Petitioners to file an application, if the amount
is not paid.
PRATHIBA M. SINGH
JUDGE
MADHU JAIN
JUDGE
APRIL 23, 2026/ prg/ss
Signature Not Verified
W.P.(C) 568/2024 Page 4 of 4
Signed By:RENUKA
NEGI
Signing Date:24.04.2026
19:35:05