M/S K.B. Enterprises vs Hindustan Prefab Limited
- Court
- Delhi High Court
$~15
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: November 20 , 2026
# CNR No. DLHC010591802023
+ W.P.(C) 752/2024
M/S K.B. ENTERPRISES .....Petitioner
Through: Mr. Susmit Pushkar, Mr.
Gaurav Sharma, Ms. Naina
Agarwal & Ms. Deepali
Poddar, Advs.
versus
HINDUSTAN PREFAB LIMITED .....Respondent
Through: Mr. Varun Nischal, Ms. Saira
Tagra, Advs. Mr. Mukesh
Legal Incharge, Mr. S.K. Dass,
DGM-HPL & Mr. Munshi
Ram, HPL.
CORAM:
HON'BLE MR. JUSTICE AMIT MAHAJAN
AMIT MAHAJAN, J. (Oral)
1. The present petition has been filed essentially seeking a
direction to the Respondent – Hindustan Prefab Limited, to release the
Security Deposit of ₹6,55,545/- along with interest @18% and the
Performance Bank Guarantee of ₹7,42,500/-, furnished by the
Petitioner in connection with the work awarded to it, namely,
“ Construction of 06 Nos. Single Offr accn (G+II) in 01 Block with
allied Services and development works for AR Transit Camp
Minuthong (Manipur) ”.
2. Succinctly stated, the Petitioner claims that the Respondent had
issued a Notice Inviting Tender dated 03.01.2019 for the aforesaid
Signature Not Verified
W.P.(C) 752/2024 Page 1 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
work. Pursuant thereto, a Letter of Intent dated 19.02.2019 was issued
in favour of the Petitioner for its quoted bid of ₹1,48,40,682/-.
3. In lieu thereof, the Petitioner furnished a Performance Bank
Guarantee bearing No. 0208GBR0000319 of ₹7,42,500/- dated
14.03.2019. Acceptance dated 20.04.2019 was addressed by Petitioner
to the Respondent inter alia accepting the terms of the Letter of Intent,
GCC, SCC and all other terms and conditions of the LOI/NIT/Tender
documents. Thereafter, an Agreement dated 20.04.2019 was executed
between the parties for construction of the project.
4. It is claimed that the work was completed on 28.04.2021. The
Board of Officers of Assam Rifles inspected the work on 28.06.2021
and opined that “the construction has been completed in all respect
and should be taken from Hindustan Prefab Limited and to be entered
in the building register.” The project was handed over to Inspector
General of Assam Rifles/Client vide Handing/Taking Over Memo
dated 30.06.2021, recording that the work had been completed to the
extent of 100% and taken over.
5. By several communications, the Petitioner requested the
Respondent to release the Performance Bank Guarantee. It was also
stated that since 1 year defect liability period has elapsed and no
defects were observed, the Security Deposited is liable to be returned.
6. ‘No Defect Certificate’ dated 20.07.2022 was also issued by the
concerned officer of Assam Rifles, certifying that the work had been
executed and completed and had been handed over on 30.06.2021, and
that no defects had been noticed during the defect liability period and
all defects having been rectified.
Signature Not Verified
W.P.(C) 752/2024 Page 2 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
7. Thereafter, the Petitioner addressed a letter dated 29.08.2022,
along with requisite documents and certificates, to the Respondent
stating that security deposit has been released by Assam Rifles/Client
in the Respondent’s account and thus, requesting the Respondent to
release the Security Deposit. The Petitioner also sent a reminder
correspondence 12.09.2022 seeking release of the Performance Bank
Guarantee. However, the Respondent continued to retain the same.
8. In these circumstances, the Petitioner approached this Court by
way of the present petition.
9. Notice was issued in the present petition on 05.02.2024.
10. Learned Counsel for the Petitioner submits that the Petitioner
duly completed the contractual work, which was inspected and taken
over by Assam Rifles/Client. It is submitted that the completion of the
work and absence of any outstanding defects stand established by the
Handing/Taking Over Memo dated 30.06.2021 and the No Defect
Certificate dated 20.07.2022. The defect liability period also expired
on 30.06.2022. Thus, the Security Deposit and the Performance Bank
Guarantee are liable to be returned upon recording of the completion
of the work by the competent authority.
11. It is further submitted that the Respondent issued a
communication dated 29.02.2024, raising certain claims, only after
notice was issued in the present petition on 05.02.2024 and the same is
an afterthought intended to justify their inaction. It is contended that
the Respondent cannot justify the retention by subsequently raising
allegations of an outstanding GST liability and an alleged excess
payment as, the GST liability pertains to an earlier and unrelated
Signature Not Verified
W.P.(C) 752/2024 Page 3 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
contract and cannot be adjusted against the amounts payable under the
present agreement. The allegation of excess payment is also denied.
He further submits that the Respondent did not communicate any
subsisting objection or liability when the Petitioner initially sought
release of the Security Deposit and Performance Bank Guarantee.
12. It is further submitted that the Respondent has though relied
upon Clause 29A – Lien in respect of claims in other Contracts, to
claim that it is under this provision the amount has been retained
stating that the same provides that amount due under any other
contract also can be retained/withheld till the time the same is either
mutually settled or determined by the arbitration clause, however, the
sum of money was never notified to the Petitioner, and this point has
been raised only during the oral arguments, before this Court, after 3
years of completion of work, and was never raised in communication
addressed by the Respondent. The said action is unjust as the
Petitioner has already performed to the satisfaction of their client.
13. Per contra, learned counsel for the Respondent opposes the
petition, primarily on the ground that the dispute arises out of a
commercial contract and involves disputed questions of fact and
accounts, which ought not to be adjudicated in proceedings under
Article 226 of the Constitution of India and the parties should be
directed to avail the alternate and efficacious remedy.
14. He submits that upon examination of the Petitioner's accounts,
the Respondent discovered that an excess payment of ₹14,82,054/-
had inadvertently been released to the Petitioner. The Respondent, by
a communication dated 29.02.2024, called upon the Petitioner to remit
Signature Not Verified
W.P.(C) 752/2024 Page 4 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
the excess payment amount and also to clear the outstanding GST
liability arising out of Tax Invoice No. 01/2017-18 dated 08.09.2017.
It is submitted that the GST authorities had raised a demand against
the Respondent in respect of the said liability and that the Petitioner
was responsible for the same. Reliance is placed upon Clause 29A
providing provision for creating a lien on claims arising out of other
contracts.
15. He further submits that that the Performance Bank Guarantee
has already been released in favour of the Petitioner and the same has
not been retained. However, the Petitioner is required to indemnify the
Respondent against statutory dues, taxes and other demands arising in
connection with the work. Thus, as regards the retention of security
deposit is concerned, the Respondent is entitled to create a lien upon
the same.
16. Hence, it is urged that the present petition, involving disputed
contractual claims and an available alternative remedy, is liable to be
dismissed.
17. I have heard learned counsel for the parties and perused the
record.
18. At the outset, it is apposite to note that the hon’ble Apex Court
in, ABL International Ltd. v. Export Credit Guarantee Corporation
of India, (2004) 3 SCC 553 , while examining the scope of jurisdiction
under Article 226 in contractual matters, has held that merely because
a dispute arises out of a contractual obligation or involves certain
disputed questions of fact or there exits an alternate remedy, the same
would not constitute an absolute bar to the exercise of writ
Signature Not Verified
W.P.(C) 752/2024 Page 5 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
jurisdiction. It was further held that where the action of a State
instrumentality is alleged to be arbitrary, unfair or unreasonable, the
contractual nature of the dispute does not, by itself, exclude judicial
review under Article 226.
19. Thus, the objection of the Respondent that the present petition
involves disputed questions of fact and that the Petitioner ought to be
relegated to an alternate remedy, does not, in the facts of the present
case, persuade this Court to decline interference, when the petition has
remained pending since 2024. Further, the nature of the dispute, as it
emerges from the record placed before this Court, does not require
detailed examination of evidence or cross-examination.
20. Adverting to the merits, there is no dispute that the work
awarded to the Petitioner was completed in April 2021 and handed
over in June 2021. The one-year defect liability period also admittedly
stood completed by 30.06.2022. The record further contains the No
Defect Certificate certifying that no defects had been noticed during
the defect liability period and that all defects had been rectified was
also issued in the July 2022.
21. The Petitioner thereafter repeatedly sought release of the
Performance Bank Guarantee and the Security Deposit. As per the
case set out by the Petitioner the very first communication seeking
return of the Performance Bank Guarantee was in October 2021 and
the first communication seeking release of Security Deposit was in
July 2022, followed by reminder letters.
22. In order to ascertain how the requests were processed internally
by the Respondent, this court vide order dated 09.10.2026 had directed
Signature Not Verified
W.P.(C) 752/2024 Page 6 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
the Respondent to produce the relevant record with respect to the
demand raised by the Petitioner on 05.07.2022 seeking release of
security deposit. The record has been produced and perused.
23. Notably, the record of the GST proceedings, reveals that the
Notice in FORM GST ASMT-10 was issued on 05.05.2022 to the
Respondent, informing them about the utilization of the in-eligible
ITC for the Tax period 2017-18 and asking them to furnish reasons for
the same, which was done on 03.06.2022. Thus, the Respondent had
knowledge of the discrepancies/liabilities pointed by the GST
Authorities in May 2022.
24. Now, we may advert to the Noting/comments. The Noting dated
13.09.2022 pertains to the proposal for release of Performance Bank
Guarantee (₹7,42,500) and Security Deposit of (₹6,55,545). It records
that the work had been completed in accordance with the agreement
and the defect liability period had expired. The proposal for release
was supported by the contractor's request, No Defect Certificate,
labour clearance certificate, prescribed release format and
recommendation of the DGM (Engineering), Guwahati. The Accounts
Department had examined the supporting documents and
recommended release of the PBG and Security Deposit, following
which the proposal was submitted to the competent authority for
approval.
25. Handwritten Noting/comments dated 29.09.2022 raises four
queries regarding the proposal for release of the PBG and Security
Deposit: (i) the note submitted by RO, Guwahati does not clarify
whether any defects were observed during the defect liability period;
Signature Not Verified
W.P.(C) 752/2024 Page 7 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
(ii) the date on which the defect liability period was completed has not
been specified; (iii) RO, Guwahati had recommended release of the
Security Deposit only, and clarification was sought as to whether a
separate recommendation for release of the PBG was required; and
(iv) the status of the final bill was sought.
26. The matter was accordingly referred back for clarification, with
an email dated 04.10.2022 sent to RO, Guwahati, and the
correspondence was placed on file on 11.10.2022.
27. Thereafter note dated 11.10.2022, issued by the Regional
Office, Guwahati, Hindustan Prefab Limited, provides clarification in
response to the queries raised by the Head Office regarding release of
the Security Deposit and PBG. It states that the defect liability period
was completed on 30.06.2022; the client (Assam Rifles) had issued an
official certificate confirming zero defects on 20.07.2022; and the RO,
Guwahati had recommended release of both the Security Deposit of
₹6,55,545 and PBG of ₹7,42,500, stating that the completed PBG
document had already been forwarded to HPL Headquarters on
06.10.2021. It further clarifies that, as per the contract agreement, the
PBG and Security Deposit could be released only after release of the
final bill, which had been done by the Regional Office. The proposal
was accordingly submitted for approval.
28. Following the same, the handwritten comment dated
11.10.2022 beneath reveals that the FA&CAO mentioned “ check
account status ”.
29. Significantly, none of the above-mentioned notings/comments
highlight any issue of GST liability despite the Notice being served in
Signature Not Verified
W.P.(C) 752/2024 Page 8 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
May, 2022 or payment of any excess amount.
30. It is only the handwritten noting dated 10.02.2023, which for
the first time, merely referred to the pending GST action, which reads
as “Before the release of dues, reconcile the account statement in view
of the pending GST action ”.
31. There is no noting fastening any sort of liability upon the
Petitioner.
32. It further emerges that, since no satisfactory response was
received by the GST Authorities, the Respondent was issued Show
Cause Notice dated 30.01.2023, to show cause why Ineligible ITC
amounting to approximately Rs. 17 lakhs and the interest and penalty
thereon should not be demanded and recovered. The Order in Original
dated 22.12.2023 records that the Respondent had initially stated that
an amount of ₹4,12,336/- out of the disputed ITC of ₹17,61,073/-
pertained to Petitioner – M/s K.B. Enterprises, however, in its
subsequent reply stated the same to be only ₹1,12,210/-. The ITC of
₹1,12,210/- was claimed from the Tax Invoice K.B. Enterprises,
which was under 5 lakhs, and was rejected for non-submission of the
prescribed supplier certificate under the Circular. Thus, the same
formed part of the confirmed demand of Rs. 4,53,051/- (reduced from
17 lakhs on account of payment of Rs. 13,08,022/- certified by CA as
paid by M/s RK Fortune Developers i.e. another supplier) however, no
individual liability of the Petitioner was determined. The appeal
against this Order in Original has also been rejected vide Order dated
08.01.2025.
33. Without commenting on the merits of the claim and liability,
Signature Not Verified
W.P.(C) 752/2024 Page 9 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
this Court finds that despite the Respondent having been aware of the
GST proceedings and having actively contested the same, there is no
contemporaneous communication on record to demonstrate that, at the
time when the Petitioner sought release of the Security Deposit and
Performance Bank Guarantee, the Petitioner was informed that the
amounts were being withheld on account of any GST liability or
alleged excess payment.
34. The first communication, placed on record, raising these claims
was issued only on 29.02.2024 with Subject as Recovery of Excess
Payment , after the present proceedings had already been instituted and
notice had been issued, justifying the retention principally on the basis
of an alleged excess payment of ₹14,82,054/- and an outstanding GST
liability of ₹2,06,624/-.
35. The Respondent has claimed that creating a lien is permissible
under the contractual conditions and the security deposit can be
retained towards claims arising under another contract. There is no
quarrel with respect to the above proposition. It would be apposite to
reproduce Clause 29A pertaining Lien in respect of claims in other
contracts , which reads as under: -
" Clause 29A- Lien in respect of claims in other contracts
Any sum of money due and payable to the contractor
( including the security deposit returnable to him ) under
the contract may be withheld or retained by way of lien by
the Engineer-in-Charge or the Government or any other
contracting person or persons or through Engineer-in-
Charge against any claim of the Engineer-in-Charge of
Government or such other person or persons in respect of
payment of a sum of money arising out or under any other
contract made by the contractor with the Engineer-in-
Charge or of the Government or with such other person or
persons.
Signature Not Verified
W.P.(C) 752/2024 Page 10 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
It is an agreed term of the contract that the sum of money so
withheld or retained under this clause by the Engineer-in-
Charge or the Government will be kept withheld or
retained as such by the Engineer-in- Charge or the
Government or till his claim arising out of the same
contract or any other contract is either mutually settled or
determined by the arbitration clause or by the competent
court, as the case may be and that the contractor shall
have no claim for interest or damages whatsoever on this
account or on any other ground in respect of any sum of
money withheld or retained under this clause and duly
notified as such to the contracto r."
36. A bare perusal of the above clause, in the opinion of this court
reflects that firstly , there is right to withhold/retain the sum due
(including security deposit), by creating a lien; secondly , the amount
withheld under the clause shall remain withheld until the claim is
mutually settled or determined through arbitration or by a competent
court; and lastly, the contractor shall have no claim for interest or
damages in respect of an amount withheld under the clause and duly
notified to him.
37. Though the Respondent may have been entitled to exercise the
power under Clause 29A where an identified claim was in existence,
however, the existence, identification and communication of such a
claim would be a necessary precursor to withholding the amount by
way of lien.
38. Identification and Communication of the lien under Clause 29A
is also essential because it triggers the contractor's right to challenge
the withholding before the Dispute Redressal Committee or in
arbitration under Clause 25. The communication should clearly
specify the exact amount being withheld, the details of the other
Signature Not Verified
W.P.(C) 752/2024 Page 11 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
contract from which the claim arises, and the nature of the pending
claim or recovery. It must state which specific dues are being retained
under the lien. Proper intimation puts the contractor on notice,
allowing them to respond, settle the claim, or initiate dispute
resolution.
39. In the present case, neither any claim was identified, nor was
any demand towards any dues raised against the Petitioner prior to the
filing of the present petition and thus, no payment was actually
refused as no amount was ever claimed or communicated to the
Petitioner, as evident from their own internal notings.
40. Thus, it emerges that the amount was mechanically retained,
unilaterally in anticipation of a future or uncrystallised claim and
particularly without communicating the same to the Petitioner.
41. Further, the right contemplated under Clause 29A is one of
retention of the amount by way of lien and does not create an
automatic right to appropriate/adjust the amount towards such a claim.
The retention is also permissible till the claim is mutually settled/
determined by arbitral proceedings/competent court. However,
despite completion of work in the year 2021, no such steps were taken
by the Respondent to get any claim adjudicated. Rather, it is only after
the filing of this Petition that the parties had explored the possibility of
amicable settlement which failed. The Respondent, being an
instrumentality of the state, is expected to act fairly and reasonably.
[ Ref: ABL International Ltd. v. Export Credit Guarantee
Corporation of India, (2004) 3 SCC 553 and Unitech Limited and
Ors. v. Telangana State Industrial Infrastructure Corporation and
Signature Not Verified
W.P.(C) 752/2024 Page 12 of 13
Signed By:SANJAY
KUMAR
Signing Date:25.11.2026
20:21:01
Ors, (2021) 16 SCC 35 ].
42. Thus, this Court finds that when the claim was raised by a
belated communication, after filing of the writ, the Petitioner had at
that stage, already become entitled to release of the amount of
Security Deposit and the Performance Bank Guarantee.
43. In the peculiar facts of the present case, the continued retention
of the Petitioner’s Security Deposit is unjust.
44. The Respondent is directed to release the Security Deposit and
the Performance Bank Guarantee (if not already done) to the
Petitioner within a period of four weeks from today.
45. Needless to say, if the Respondent has any independently
enforceable claim against the Petitioner, including but not confined to
GST liability or payment of any excess amount, it shall be open to the
Respondent to pursue the same in accordance with law and the
contractual mechanism governing such claim and seek recovery of the
amounts due, if any.
46. The petition stands disposed of in the aforesaid terms. Pending
applications, if any, also stand disposed of.
AMIT MAHAJAN, J
NOVEMBER 20, 2026
“SK”
Signature Not Verified
W.P.(C) 752/2024 Page 13 of 13