Union Of India vs Satish Kumar Mittal
- Court
- Delhi High Court
$~18
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 25.11.2026
# CNR No. DLHC010471942024
+ FAO (COMM) 152/2024 & CM APPL. 44534/2024
UNION OF INDIA .....Appellant
Through: Mr. Sanjay Kumar Aggarwal &
Mr. Vikram Aggarwal, Advs.
versus
SATISH KUMAR MITTAL .....Respondent
Through: Mr. Ankkit Guptha, Mr. N.D.
Pandey & Ms. Aakanksha
Gupta, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
HON'BLE MS. JUSTICE SHAIL JAIN
AVNEESH JHINGAN, J. (ORAL)
1. This appeal is filed against the judgement dated 15.03.2024
passed by the Commercial Court, South-East District, Saket Courts
(hereinafter referred to as ‘Commercial Court’) whereby the petition
filed by the appellant under Section 34 of the Arbitration and
Conciliation Act, 1996 (in short ‘the Act’) challenging the arbitral
award dated 28.02.2019 was dismissed.
2. The brief facts are that the parties entered into a contract
agreement no. CEWAC/PAL-29/2012-13WE/PM/S-22/2013-14 for
‘Addition/Alteration to storm drain along with perimeter wall at AF
Station, Faridabad’. The contract valued at Rs.41,59,417.64 was
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 1 of 7
awarded to the respondent vide letter dated 04.06.2012. The stipulated
period for completion of the work was six months. The work
commenced on 20.06.2012 and was to be completed by 19.12.2012.
2.1 The extensions of time were granted thrice up to 30.09.2015.
Disputes arose over rectification of defects, removal of excavated
material, execution of additional work, payment of the final bill,
timely handover of sites, delays in approval of deviation orders,
finalization of star rates and release of payments.
2.2 The work was completed on 15.09.2015 and a completion
certificate was issued by the appellant vide letter dated 21.09.2015.
The respondent submitted the final bill vide letter dated 11.01.2016
alleged to be signed under protest on 06.06.2017.
2.3 The arbitration was invoked at the instance of the respondent.
The arbitrator was initially appointed on 14.08.2014 but upon
superannuation resigned on 29.02.2016. Thereafter a sole arbitrator
was appointed on 29.06.2016 and entered upon the reference on
26.07.2016.
2.4 The respondent raised ten claims amounting to Rs.55,78,525/-,
while the appellant preferred two counterclaims amounting to
Rs.4,30,160/-. The arbitral proceedings culminated in the award dated
28.02.2019. The arbitrator partly allowed the claims of the respondent
and awarded a total sum of Rs.8,00,516/- along with interest @9% per
annum. The counterclaims preferred by the appellant were rejected in
entirety.
2.5 Aggrieved by the award, the appellant preferred a petition under
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 2 of 7
Section 34 of the Act. The Commercial Court vide judgment dated
15.03.2024 dismissed the petition. Hence, the present appeal.
3. Learned counsel for the appellant argues that for quantifying the
amount awarded in Claim no. 2 the arbitrator erred in relying upon the
rates mentioned under Item 13 of Schedule A Part I of the contract for
assessing the value of old steel posts/ old expanded metal. It is
contended that Item 13 of Schedule A Part I of the contract provides
measurement on per-meter basis and not in kilograms(Kg).
4. Per contra , the award and the impugned judgment is defended
stating that the scope of interference under Section 37 of the Act is
limited and a plausible and well-reasoned view does not call for
interference.
5. Heard the learned counsel for the parties and perused the record
with their able assistance.
6. The only issue under challenge relates to the quantification of
Claim no.2 as the respondent could not retrieve the demolition
material described under Item nos. 13 and 14 of Schedule A Part I of
the contract since the material was not made available at the site.
7. Before proceeding further, it would be fruitful to reproduce
Item no. 13 and 14 of Schedule A Part I of the contract: -
“
Srl.
No.
Description
of Item of
Work
Drg
No.
or
ref
to
List
of
Unit No. of
unit
required
Rate Per
Unit (in
words &
figure
both)
Total
Amount
Period of
competition of
individual item
(s) after date of
commencement
of work as per
WO No 1
Remarks
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 3 of 7
Drgs
13. Dismantling
posts or
strut (wood,
steel or
RCC) any
section,
including
taking out
embedded
portion and
making
good
disturbed
ground and
removing of
site
complete all
as specified
and
directed.
RM 200 Rs. 3/-
(Rupees
three
only)
Rs.
600/-
14. Dismantling
expanded
metal, any
thickness or
mesh of any
weight
fixed with
steel or
wood fillet
complete all
as specified
and directed
Sq
m
660 Rs.2.50/-
(Rupees
Two &
Paise
fifty
only)
Rs.1650
/-
”
8. Item no.13 deals with the removal of posts and struts and Item
no.14 deals with the removal of expanded metal. As per Item nos. 13
and 14 the contractor was required to remove old posts or structure
made of wood, steel or concrete including the portions fixed
underground and old expanded metal sheets or mesh fixed to wooden
or steel frames respectively and clear the removed material from the
site.
9. The Commercial Court upheld the award of Rs.1,76,100/- under
Claim no.2. It was noted that the work was carried out in a restricted
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 4 of 7
area and the respondent could not have removed the demolished
material without obtaining the requisite authorisation from the
appellant. The issue of gate pass was raised but despite repeated
directions, the appellant failed to issue gate passes. The respondent
pleaded pilferage of items and the arbitrator during site visit on
02.02.2015 noted that a portion of wall where the material was stored
was broken.
10. The Claim no.2 was not quantified on the rates prescribed under
Item nos.13 and 14 of Schedule A Part I. The items were referred to
only to identify the source of the material namely, old steel
posts/structs retrieved from demolition under Item 13 and old
expanded metal retrieved from work under Item 14. The Schedule of
Credit provided recovery rates of Rs.2.25 per Kg for old steel
posts/structs and Rs.2.47 for expanded metal. The scrap value was
taken at Rs.30 per kg being 50% of the voucher rate of Rs.60 per kg.
After deducting the applicable recovery rates, the arbitrator calculated
Rs.92,188.55 for old steel posts/struts and Rs.83,911.99 for expanded
metal, totalling Rs.1,76,100.
11. The Claim no.2 was accepted and a concurrent finding in the
award and impugned judgment under Section 34 of the Act was
recorded that the work carried out was in a restricted area, the
respondent was not in a position to remove any item without the
permission of the appellant. Despite instructions to issue gate passes
for removal of the material the needful was not done by the appellant.
The respondent was entitled to make a claim for the old steel retrieved
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 5 of 7
from demolition carried out as per the contract. The amount awarded
was quantified on the basis of the scrap value of the material, after
deducting the applicable recovery rates.
12. The law is well settled that the proceedings under Section 34
and 37 of the Act are not akin to regular appeal. The court cannot sit
in appeal to re-appreciate the evidence for another possible view.
Reference is to the following judgments of the Supreme Court:
12.1 In Punjab State Civil Supplies Corpn. Ltd. v. Sanman Rice
Mills, 2024 SCC OnLine SC 2632 it was held:
“ 16. It is seen that the scope of interference in an appeal
under Section 37 of the Act is restricted and subject to
the same grounds on which an award can be challenged
under Section 34 of the Act. In other words, the powers
under Section 37 vested in the court of appeal are not
beyond thescope of interference provided under Section
34 of the Act.
21. It must also be remembered that proceedings under
Section 34 of the Act are summary in nature and are not
like a full-fledged regular civil suit. Therefore, the scope
of Section 37 of the Act is much more summary in nature
and not like an ordinary civil appeal. The award as such
cannot be touched unless it is contrary to the substantive
provision of law; any provision of the Act or the terms of
the agreement.”
12.2 In Larsen Air Conditioning & Refrigeration Co. v. Union of
India, (2023) 15 SCC 472 it was held:
“ 15. The limited and extremely circumscribed
jurisdiction of the court under Section 34 of the Act,
permits the court to interfere with an award, sans the
grounds of patent illegality i.e. that “ illegality must go to
the root of the matter and cannot be of a trivial nature ”;
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 6 of 7
and that the Tribunal “ must decide in accordance with
the terms of the contract, but if an arbitrator construes a
term of the contract in a reasonable manner, it will not
mean that the award can be set aside on this ground ” [ref
: Associate Builders [ Associate Builders v. DDA , (2015)
3 SCC 49 : (2015) 2 SCC (Civ) 204] , SCC p. 81, para
42]. The other ground would be denial of natural justice.
In appeal, Section 37 of the Act grants narrower scope to
the appellate court to review the findings in an award, if
it has been upheld, or substantially upheld under Section
34.”
( emphasis supplied )
13. The view taken is plausible, suffers from no factual or legal
error much less perversity.
14. The appeal is dismissed.
15. Pending application stands disposed of.
16. Needless to say, the respondent shall be entitled to
consequential reliefs.
AVNEESH JHINGAN, J
SHAIL JAIN, J
NOVEMBER 25, 2026
‘ha’
Reportable: Yes
Signature Not Verified
Signed By:HONEY
ARORA
Signing Date:27.11.2026
12:47:45
FAO (COMM) 152/2024 Page 7 of 7