Uttar Pradesh Power Corporation Limited & Ors vs Obra-C Badaun Transmission Limited & Ors
- Court
- Appellate Tribunal For Electricity
IN THE APPELLATE TRIBUNAL FOR ELECTRICITY
(Appellate Jurisdiction)
Court-2
APPEAL No. 452 of 2022
th
Dated : 29 September, 2026
Present : Hon’ble Mr. Virender Bhat, Judicial Member
Hon’ble Mr. Ajay Talegaonkar, Technical Member
In the matter of :
1. Uttar Pradesh Power Corporation Limited
Through its Chief Engineer (Planning)
th
14 Floor, Shakti Bhawan Extension,
14-Ashok Marg, Lucknow, Uttar Pradesh – 226 001
Email : [email protected]
2. Paschimanchal Vidyut Vitran Nigam Limited
Through its Managing Director
Urja Bhawan, Victoria Park,
Meerut, Uttar Pradesh-250001
Email : [email protected]
3. Madhyanchal Vidyut Vitran Nigam Limited
Through its Managing Director
4-A, Gokhale Marg, Lucknow, Uttar Pradesh - 226 001
Email: [email protected]
4. Purvanchal Vidyut Vitran Nigam Limited
Through its Managing Director
DLW Bhikaripur, Varanasi, Uttar Pradesh - 221 010
Email: [email protected]
5. Dakshinanchal Vidyut Vitran Nigam Limited
Through its Managing Director
Urja Bhawan, NH-2 (Agra-Delhi bypass Road), Sikandra,
Agra, Uttar Pradesh - 282 002
Email: [email protected]
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 1 of 34
6. Kanpur Electricity Supply Company Limited
Through its Managing Director
Headquarter, Kesa House, 14/71 Civil Lines,
Kanpur, Uttar Pradesh - 208001
Email: [email protected]/[email protected]
……Appellants
VERSUS
1. Obra-C Badaun Transmission Limited
Through its Chairman,
C-105, Anand Niketan, New Delhi-110 021
Email: [email protected]
2. Uttar Pradesh Power Transmission Corporation Limited
Through its Managing Director,
7th Floor, Shakti Bhawan, 14-Ashok Marg,
Lucknow, Uttar Pradesh - 226 001
Email: [email protected]
3. Uttar Pradesh Electricity Regulatory Commission
Through its Secretary,
Vidyut Niyamak Bhawan, Vibhuti Khand,
Gomti Nagar, Lucknow - 226 010
Email: [email protected]
……Respondents
Counsel on record for the Appellant(s) : Shankh Sengupta
Sitesh Mukherjee
Abhishek Kumar
Harneet Kaur
Arjun Agarwal
Nived Veerapaneni
Karan Arora
Shubham Mudgil
for App. 1 to 6
Counsel on record for the Respondent(s) : Sourav Roy
Kaushal Sharma
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 2 of 34
Prabudh Singh
Vishal Malik
for Res. 1
Altaf Mansoor
for Res. 2
J U D G M E N T
PER HON’BLE MR. VIRENDER BHAT, JUDICIAL MEMBER
1. The Appellants have, in this appeal, assailed the order dated
rd rd
3 October, 2022 passed by the 3 Respondent – Uttar Pradesh
Electricity Regulatory Commission (hereinafter referred to as “the
st
Commission”) in Petition No. 1824 of 2022 filed by 1 Respondent.
2. The Appellant No. 1 is a deemed licensee under Section 14 of
the Electricity Act, 2003 and is functioning as distribution, retail and
bulk supply licensee under UP Electricity Reforms Act, 1999
(Reforms Act). The Appellant Nos. 2 to 6 are distribution licensees in
the State of UP in terms of Section 2(17) of Electricity Act, 2003.
However in the context of the present Appeal, the Appellant Nos. 2 to
st
6 are Long Term Transmission Customers (LTTCs) of the 1
Respondent – Obra C – Badaun Transmission Limited (in short
“OBTL”).
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 3 of 34
st
3. The 1 Respondent (also referred to as OBTL) is an intra-state
transmission licensee in the State of UP and was entrusted to
implement as well as operate “Evacuation of power from Obra-C
(2x660 MW) Thermal Power Project and Construction of 400 KV GIS
sub-station, Badaun with associated transmission lines” hereinafter
referred to as “the project” on Build, Own, Operate & Maintain basis
under TBCB mode, for which Transmission Service Agreement (TSA)
th st
dated 15 October, 2018 was entered between the 1 Respondent
and LTTCs. A supplementary TSA dated 15.10.2020 was also signed
st nd
between 1 Respondent and LTTCs along with 2 Respondent -
UPPTCL in which UPPTCL was nominated by LTTCs to act as their
nominee while indemnifying UPPTCL from any claim.
4. The Schedule Commercial Operation Date (SCOD) of the
st
project as per Schedule -3 of TSA for LOT-1 was 21 November,
st
2020, for LOT-II was 1 February, 2021.
5. It appears that the implementation of the project was delayed
st
on account of various Force Majeure events as contended by the 1
Respondent. Accordingly, various notices were addressed in this
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 4 of 34
st
regard by the 1 Respondent to the LTTCs informing them about the
Force Majeure events, the details of which are as under :-
(a) Stoppage of construction due to flooding of
construction sites (Notice dated 28.09.2019 &
15.10.2019)
(b) Delay in grant of transmission license/ in adoption of
Tariff in grant of authorisation under Section 164 of
the Act (Notice dated 18.10.2019)
(c) Cessation of force majeure event of flooding of
location and approach due to heavy monsoon
(Notice dated 11.11.2019)
(d) ROW issues due to delays in receiving authorisation
under Section 164 of the Act (Notice dated
14.11.2019)
(e) Sudden strike called by employees of UPPCL
(Notice dated 28.11.2019)
(f) Imposition of Section 144 due to protests against
Citizenship Amendment Act (Notice dated
23.12.2019 & 10.01.2020)
(g) Delay in receipt of materials due to closing
enterprises in China because of Covid-19 pandemic
(Notice dated 20.02.2020)
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 5 of 34
(h) Imposition of lockdown and restriction imposed by
Government of Uttar Pradesh due to Covid-19
pandemic (Notice dated 23.03.2020)
(i) Imposition of countrywide lockdown due to Covid-19
pandemic (Notice dated 26.03.2020)
(j) Extension of countrywide lockdown due to Covid-19
pandemic (Notice dated 15.04.2020, 04.05.2020 &
18.05.2020)
(k) Restrictions and lockdown imposed due to Covid-19
pandemic (Notice dated 06.06.2020, 04.07.2020,
20.08.2020, 14.09.2020 & 23.10.2020)
(l) Lockdown imposed due to Covid-10 Pandemic
(Notice dated 29.04.2021)
rd nd
6. Subsequently, while letters dated 23 March, 2021 and 2
st
April, 2021, the 1 Respondent intimated the LTTCs about the
th
deemed COD of Element 1 and Elements 2 to 8 of LOT-1 as 30
th st
March, 2021 and 9 April, 2021 respectively. The 1 Respondent also
claimed entitlement of transmission charges from these dates.
st
Thereafter, the 1 Respondent started raising monthly transmission
charges invoices for both Element I as well Elements 2 to 8 of LOT I
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 6 of 34
of the project from the date of said deemed COD along with
supplementary bills towards late payment surcharge.
st
7. Vide letter dated 1 December, 2021, Appellant No. 4 – PVVNL
st
informed 1 Respondent that it has considered the deemed COD of
th th
Element I and Elements 2 to 8 of LOT-I as 30 April, 2021 and 16
st
April, 2021 respectively, which was disputed by the 1 Respondent
st
vide the reply dated 1 December, 2021.
8. At the same time, Appellant No. 1 – UPPCL vide letter dated
th
7 December, 2021, raised invoices verification statement of
Rs.8,61,37,692/- as recoverable amount towards liquidated damages
for delay of 38 days and 53 days in achieving deemed COD of these
elements i.e. Element I and Elements 2 to 8 of LOT-I respectively.
th st
Vide reply dated 15 December, 2021, 1 Respondent stated that it
was entitled to extension of SCOD of LOT-I on account of Force
Majeure events as per Article 4 and 4.1 & 2 of TSA as well as on the
th th
basis of notifications dated 27 July, 2020 and 12 June, 2021 issued
by Ministry of Power, Govt. of India on account of Covid-19 Pandemic
and nationwide lockdown thereby granting extension of 5 months and
3 months respectively to the SCOD of all transmission projects.
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 7 of 34
st
9. In these circumstances, the 1 Respondent had approached
the Commission with petition No. 1824 of 2022 claiming extension of
SCOD for LOT-I elements of its project i.e. Element Nos. 1 to 8 by a
period of 8 months and a declaration that Appellant No. 1 is not
entitled to levy liquidated damages for any delay in commissioning of
these elements. Following Force Majeure events were agitated by the
st
1 Respondent in this petition:-
“A. Heavy rainfall leading to flooding of pits excavated
for laying down foundation of transmission towers.
B. Delay in grant of Transmission License by the Ld.
UPERC.
C. Delay in adoption of tariff by the Ld. UPERC.
D. COVID-19 pandemic.
E. Delay in grant of authorization under Section 164
[Exercise of powers of Telegraph Authority in certain
cases] of the Act.
F. Strike called by employees of UPPCL.
G. Public protests against the Citizenship Amendment
Bill.
10. The petition was disposed of by the Commission vide
rd
impugned order dated 3 October, 2022 thereby rejecting the claim
st
of the 1 Respondent with regards to all the Force Majeure events
except Covid-19 Pandemic. Accordingly, the Appellants are
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 8 of 34
aggrieved by the impugned order of the Commission in so far as it
has upheld the claim of Respondent No. 1 for extension of COD of
th
Element I till its deemed COD accepted by LTTCs i.e. 30 April, 2021
and that of the Elements 2 to 8 till their deemed COD accepted by
th
LTTCs i.e. 16 April, 2021 considering the Covid-19 Pandemic as the
Force Majeure events affecting the completion of the project.
11. Thus, the only issue involved in the appeal for our consideration
is :-
“Whether the Covid-19 Pandemic and subsequent
lockdown imposed by the Government of India constituted
a Force Majeure event in terms of the provisions of the
st
TSA executed between the parties entitling the 1
Respondent to extension of SCOD of the project”.
12. According to the Appellants, the impugned order warrants
interference by this Tribunal in this appeal on account of the
following:-
“A. The conclusion that OBTL has been affected by a
force majeure on account of the COVID-19
pandemic has been reached under the Impugned
Order without undertaking any analysis or setting
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 9 of 34
out any reasoning. To such extent, the Impugned
Order has been rendered indefensible &
unsustainable in light of the settled legal principles.
B. OBTL's prayer for and arbitrary blanket extension of
8 months in terms of the MOP notifications dated
27.07.2020 & 12.06.2021 has been rejected under
the Impugned Order by holding that the same do not
apply in the present case. Further, the Impugned
Order holds that the question as to whether force
majeure has occurred in particular case or not will
be decided by the Ld. UPERC on a case-to-case
basis considering scope of project, extent, duration
of impact, its effects, etc. However, the Impugned
Order fails to take such findings to their logical
sequitur as such analysis is conspicuous by its
absence under the Impugned Order.
C. In granting an extension in SCOD of 160 days qua
Element 1 & 146 days qua Elements 2 to 8 of LOT-
1 of the Project, the Impugned Order fails justify the
grant of such extension on a "day for day basis" as
mandated by Article 4.4.2 of the TSA. To such
extent, the Impugned Order rendered by Ld.
UEPRC is contrary to the TSA provisions.
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 10 of 34
D. By way of its notice dated 21.09.2020, issued in
purported compliance of Article 6.1.1 of the TSA,
OBTL intimated 21.11.2020 as the firm & fixed date
on which Elements 1 to 8 of LOT-1 of its Project
would achieve COD. In effect, OBTL admitted and
conceded that the construction of the aforesaid
elements was not affected/hindered in any manner.
Therefore, applying the principles of law settled by
the Hon'ble Supreme Court in a catena of
judgments including, Energy Watchdog v. CERC
& Ors. reported as (2017)14 SCC 80 , no force
majeure event occurred insofar as construction of
Elements 1 to 8 of OBTL's Project is concerned.
E. Instead of appreciating its true meaning, import and
effect, the Impugned Order inexplicably classifies
OBTL's notice dated 21.09.2020 as a force majeure
mitigation step covered by Article 11.6 of the TSA.
F. Having taken cognizance of the fact that the State
Transmission Utility i.e. Nominee of LTTC's had
already granted 3 months extension for
transmission projects under construction as of
25.03.2020 on account of the COVID-19 pandemic,
the Impugned Order is unjustified in granting an
extension of 160 days qua Element 1 & 146 days
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 11 of 34
qua Elements 2 to 8 without any analysis or
justification to substantiate such divergence.
G. Having inter alia held under its order dated
03.06.2022 that the presence of UPPTCL, being the
STU & nominee of lead LTTCs during the
construction period, was of utmost necessity for
adjudication of Petition No. 1824/2022, the
Impugned Order issued in complete ignorance of
UPPTCL's only effective pleading (i.e., application
for re-hearing) is unsustainable.”
13. We have heard Mr. Abhishek Kumar, Learned Counsel for the
Appellant and Mr. Sourav Roy, Learned Counsel for the 1st
Respondent. We have also perused the written submissions filed by
the Learned Counsels.
14. Learned Counsel for the Appellants strenuously argued that
th th
despite holding the notification dated 27 July, 2020 and 12 June,
2021 issued by Ministry of power, Government of India are
st
inapplicable to the intra-sate transmission project in question of 1
Respondent and that the occurrence of Force Majeure has to be
examined on case to case basis considering the scope of project,
extent, duration of impact, its effects, etc., the Commission has failed
to take its own findings to their logical sequitur by failing to do any
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 12 of 34
such analysis. It is submitted that without any detailed analysis with
regards to the scope of the project, extent and duration of the impact
of Covid-19 Pandemic upon it, the Commission has concluded in one
single paragraph that delay in achieving COD of the elements 1 to 8
was due to Covid-19 Pandemic and deserved to be condoned.
15. Learned Counsel would argue that these findings of the
Commission are contrary to the Articles 4 & 4.2 of the TSA which
provides that any extension ought to be granted on a day for day
basis. It is also argued by the Learned Counsel that the Commission
th
has failed to take notice of the order dated 24 March, 2020 issued
by Ministry of Home Affairs, Government of India exempting the
power transmission licensees from lockdown and subsequent order
th
dated 16 April, 2020 exempting erection of power transmission lines
nd
from lockdown. It is pointed out to the Learned Counsel that 2
Respondent – UPPTCL had granted an extension of three months on
account of Covid-19 Pandemic but no analysis has been done in the
impugned order as to why such three months extension was
st
insufficient for completing of the project of 1 Respondent
necessitating extension of 160 days for Element I and 146 days for
Element 2 to 8.
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 13 of 34
st
16. Learned Counsel also referred to the letter dated 21
st
September, 2020 issued by the 1 Respondent intimating that the
st
Elements 1 to 8 of the project would be ready for SCOD i.e. 21
November, 2020. It is his submission that this letter is a categorical
st
admission on the part of the 1 Respondent that its performance was
not affected by any Force Majeure event and therefore, claim for
extension of SCOD ought to have been rejected on the basis of the
said letter.
17. Per contra, it is argued on the behalf of Learned Counsel for
Respondent No. 1 that the Commission has considered all the
relevant facts and documents while recognizing Covid-19 Pandemic
as a Force Majeure event under Article 11 of the TSA, and has
lawfully extended SCOD of LOT-1 in terms of Article 4 & 4.1 of the
TSA. It is submitted that the Commission rightly found that the
Respondent No. 1 has served proper notices on the Appellants under
Article 11.5 of TSA informing them about the outbreak/spread out
Covid-19 Pandemic amounted to Force Majeure events. It is also
st st
submitted that the letter dated 21 September, 2020 issued by 1
st
Respondent merely reflected the bonafide efforts of 1 Respondent
to mitigate the impact of Covid-10 Pandemic and to endeavor to meet
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 14 of 34
the SCOD. It does not constitute waiver or abandonment of the
previously issued Force Majeure notices and must be read with the
rd
subsequent Force Majeure notice dated 23 October, 2020 issued
st
by 1 Respondent to LTTCs again citing Force Majeure as a reason
for delay in achieving SCOD.
st
18. Learned Counsel for the 1 Respondent would further argue
st
that the grant of three months extension from 21 November, 2020 to
st
21 February, 2021 by the Appellants themselves indicates that they
have accepted that the project was affected by Force Majeure events
st
post 21 September, 2020. The reliance is placed upon the
judgement of Hon’ble Supreme Court in Mumbai International Airport
(P) Ltd. Vs. Golden Chariot Airport, (2010) 10 SCC 422 canvassed
that a party to any legal proceedings cannot be permitted to raise
contradictory pleas. Learned Counsel would further argue that by not
st
objecting to any Force Majeure notice issued by 1 Respondent, the
Appellants shall be taken to have accepted all the notices and,
st
therefore, were precluded from objecting to the claim of 1
Respondent before the Commission. On these submissions, Learned
Counsel sought dismissal of the appeal .
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 15 of 34
Our Analysis
19. We find that discussion of the Commission on the issue
“outbreak of Covid-19 Pandemic as Force Majeure event” is in the
paragraph Nos. 99 to 102 of the impugned order which are extracted
hereinbelow:-
“99. The Petitioner vide notice dated 26.03.2020 issued
notice to UPPTCL and LTTCs regarding force majeure on
account of outbreak of Covid-19 in the Country. It was
informed that as a precautionary measure to restrict the
spread of Covid-19, national wide lockdown was imposed
for 21 days effective from 25.03.2020. Due to imposition
of lockdown and restriction in movement, the Petitioner
faced issues related to non-availability of goods and
material, disruption of supply and execution schedule,
administrative support from the Government,
transportation and accessibility issues, delay in
compensation payment to landowners, availability of
manpower, unworkable condition etc. Subsequently,
various notices vide dated 15.04.2020, 04.05.2020,
18.05.2020, 06.06.2020, 04.07.2020, 20.08.2020, 14.09
2020, 23.10.2020 and 29.04.2020 were sent to LTTC's to
update them regarding the current situation with respect
to Covid-19 and how the same affect the Petitioner in
completion the project. Petitioner's activities of
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 16 of 34
transmission line came to halt with effect from
25.03.2020.
100. At the outset, it would be prudent to first examine
advance notice dated 21.09.2020 regarding
charging/commissioning of elements, before getting into
the merits of relief claimed under force majeure on
account of Covid-19 pandemic, as it has been argued by
the Respondents that since Petitioner has issued notice
dated 21.09.2020 stating that LOT-1 would be ready by
Scheduled SCOD therefore, all the force majeure notices
prior to notice dated 21.09.2020, get blurred out and are
irrelevant in view of Petitioner's categorical admission
under the said letter.
On perusal of records, the Commission noted that notice
dated 21.09.2020 provides that LOT-1 having eight
elements would be ready for charging/ commissioning by
21.11.2020. It is pertinent to mention that the Petitioner
was affected by the force majeure event on account of
Covid-19 which could not be denied as then prevailing
situation was known to everyone. However, Petitioner in
terms of Article 11.6 of the TSA was duty bound to
perform and mitigate the effects of any event of force
majeure as soon as practical. Therefore, it can be agreed
that Petitioner was trying to fulfil its obligation to
commission the project on time considering its duty to
perform under the TSA to mitigate the effect of any event
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 17 of 34
of force majeure while using its reasonable efforts.
Therefore, the argument of the Respondents regarding
non acceptance of all the force majeure notices prior to
notice dated 21.09.2020 cannot be agreed as the
Petitioner has made reasonable efforts in trying to
commission the project on time, which ultimately got
delayed due to continued effects of pandemic.
101. While coming on merits, it is pertinent to mention
that National Disaster Management Authority issued
order dated 24.03.2020 directing Ministries/ Departments
of Government of India (GOI), State Governments and
State Authorities to take measures to prevent the spread
of Covid-19 in the country. In pursuant to the same,
Ministry of Home Affairs issued order dated 24.03.2020
and various subsequent guidelines from time to time for
their strict implementation. The Government of Uttar
Pradesh also issued guidelines from time to time.
102. The Commission has observed that the Petitioner
from time to time has issued various force majeure notices
to LTTCs and UPPTCL intimating about the force majeure
on account of outbreak of Covid-19 pandemic. UPPCL
vide letter dated 10.08.2020 denied force majeure notice
dated 04.07.2020 by stating that the GOI made it clear
that construction activities including laying/ erecting
power transmission line were allowed during the period of
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 18 of 34
lockdown subject to proper precaution and social
distancing measures being followed. However, GOI and
various authorities have allowed the extension of SCOD
on account of Covid-19 pandemic like MOP vide
notification dated 27.07.2020 have allowed five months
extension to all inter-state transmission projects which
were under construction as on date of lockdown i.e.
25.03.2020. Further, MOP vide notification dated
12.06.2021 gave another three months, extension to the
inter-state transmission projects which are under
construction with SCOD coming after 01.04.2021. Also,
MNRE vide Office Memorandum dated 17.04.2020 has
also treated Covid-19 as a force majeure event and
considered similar extension of time in SCOD. Further, in
view of the extraordinary circumstances which prevailed
due to Covid-19, nationwide lockdown and in compliance
of order dated 30.05.2020 of Ministry of Home Affairs,
UPPTCL gave three months time extension to its turnkey
projects/ supply contracts/ work contracts in force on
25.03.2020 with provision to consider relaxation on case-
to-case basis/ as a whole depending on the situation in
future. As stated in letter dated 07.12.2021 of UPPCL,
LTTCs in the instant case has also allowed extension of
three months in SCOD of the LOT-1.”
20. Perusal of the above quoted portion of the impugned order of
the Commission would reveal that the Commission has taken note of
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 19 of 34
the rival submission of the parties, Force Majeure notices issued by
st
the 1 Respondent to the Appellants, the applicability of notification
rd th
dated 23 July, 2020 and 12 June, 2021, issued by Ministry of
th
Power, Govt. of India and the O.M. dated 17 April, 2020 issued by
Ministry of Renewable Energy (MNRE) Govt. of India as well as the
three months time extension granted by UPPTCL itself to its turn key
th
projects, supply contracts, work contracts in force on 25 March,
2020 in view of nationwide lock down to Covid-19 Pandemic and
st
accordingly came to conclusion that the 1 Respondent is entitled to
seek extension of SCOD on account of Covid-19 Pandemic.
21. Therefore, the submissions made on behalf of the Appellants
that the Commission has concluded in just one single paragraph that
the delay in achieving COD of the Elements 1 to 8 was on account of
Covid-19 Pandemic without any detailed analysis, cannot be
countenanced and are liable to be rejected forthwith. Manifestly, the
Commission has analyzed in detail the submissions of the parties on
this aspect as well as relevant material on record before reaching the
conclusion that delay in achieving SCOD of Element 1 to 8 of LOT-1
st
of the project by the 1 Respondent was due to Covid-19 Pandemic.
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 20 of 34
22. Further, we may note that Article 4.4. of the TSA executed
between the parties provides for extension of time and is extracted
hereinbelow :-
“4.4 Extension of time:
4.4.1 In the event that the TSP is prevented from
performing its obligations under Article 4.1(a), (b)
and (e) by the stipulated date, due to any Long Term
Transmission Customers' Event of Default, the
Scheduled COD shall be extended, by a 'day for
day' basis, subject to the provisions of Article 13.
4.4.2 In the event that an Element or the Project cannot
be commissioned by its Scheduled COD on account
of any Force Majeure Event as per Article 11, the
Scheduled COD shall be extended, by a 'day for
day' basis, for a maximum period of one hundred
and eighty (180) days. In case the Force Majeure
Event continues even after the maximum period of
one hundred and eighty (180) days, the TSP or the
Majority Long Term Transmission Customers may
choose to terminate the Agreement as per the
provisions of Article 13.5.
4.4.3 If the Parties have not agreed, within thirty (30) days
after the affected Party's performance has ceased
to be affected by the relevant circumstance, on how
long the Scheduled COD should be deferred by, any
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 21 of 34
Party may raise the Dispute to be resolved in
accordance with Article 16.”
23. Article 4.4.2 is relevant for our consideration which provides
that in case an Element or the project cannot be commissioned by
the SCOD on account of Force Majeure event envisaged under
Article 11, the SCOD shall be extended for a maximum period of 180
days and in case the Force Majeure event continues even after the
said period of 180 days, the transmission service provider or the
majority of LTTCs may refuse to terminate the agreement.
24. Article 11 of the TSA specifies the Force Majeure events and
the consequences thereof. The same is reproduced hereinbelow :-
“ARTICLE : 11
11 FORCE MAJEURE
11.1 Definitions
11.1.1 The following terms shall have the meanings
given hereunder.
11.2 Affected Party
11.2.1 An Affected Party means any of the Long Term
Transmission Customers or the TSP whose
performance has been affected by an event of
Force Majeure.
11.2.2 An event of Force Majeure affecting the CTU/STU
or any agent of the Long Term Transmission
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 22 of 34
Customers, which has affected the
Interconnection Facilities, shall be deemed to be
an event of Force Majeure affecting the Long
Term Transmission Customers.
11.2.3 Any event of Force Majeure shall be deemed to
be an event of Force Majeure affecting the TSP
only if the Force Majeure event affects and results
in, late delivery of machinery and equipment for
the Project or construction, completion,
commissioning of the Project by Scheduled COD
and/or operation thereafter;
11.3 Force Majeure
A 'Force Majeure' means any event or
circumstance or combination of events and
circumstances including those stated below that
wholly or partly prevents or unavoidably delays an
Affected Party in the performance of its
obligations under this Agreement, but only if and
to the extent that such events or circumstances
are not within the reasonable control, directly or
indirectly, of the Affected Party and could not have
been avoided if the Affected Party had taken
reasonable care or complied with Prudent Utility
Practices:
(a) Natural Force Majeure Events:
act of God, including, but not limited to drought,
fire and explosion (to the extent originating from
a source external to the Site), earthquake,
volcanic eruption, landslide, flood, cyclone,
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 23 of 34
typhoon, tornado, or exceptionally adverse
weather conditions which are in excess of the
statistical measures for the last hundred (100)
years.
(b) Non-Natural Force Majeure Events:
i. Direct Non-Natural Force Majeure Events
• Nationalization or compulsory
acquisition by any Indian Governmental
Instrumentality of any material assets or
rights of the TSP; or
• the unlawful, unreasonable or
discriminatory revocation of, or refusal
to renew, any Consents, Clearances
and Permits required by the TSP to
perform their obligations under the RFP
Project Documents or any unlawful,
unreasonable or discriminatory refusal
to grant any other Consents,
Clearances and Permits required for the
development/ operation of the Project,
provided that a Competent Court of Law
declares the revocation or refusal to be
unlawful, unreasonable and
discriminatory and strikes the same
down; or
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 24 of 34
• any other unlawful, unreasonable or
discriminatory action on the part of an
Indian Governmental Instrumentality
which is directed against the Project,
provided that a Competent Court of Law
declares the action to be unlawful,
unreasonable and discriminatory and
strikes the same down.
ii. Indirect Non - Natural Force Majeure
Events
• act of war (whether declared or
undeclared), invasion, armed conflict
or act of foreign enemy, blockade,
embargo, revolution, riot,
insurrection, terrorist or military
action; or
• radioactive contamination or ionising
radiation originating from a source in
India or resulting from any other
Indirect Non Natural Force Majeure
Event mentioned above, excluding
circumstances where the source or
cause of contamination or radiation
is brought or has been brought into
or near the Site by the Affected Party
or those employed or engaged by
the Affected Party; or
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 25 of 34
• industry wide strikes and labour
disturbances, having a nationwide
impact in India/statewide impact in
Uttar Pradesh.
11.4 Force Majeure Exclusions
11.4.1 Force Majeure shall not include (i) any event or
circumstance which is within the reasonable
control of the Parties and (ii) the following
conditions, except to the extent that they are
consequences of an event of Force Majeure:
(a) Unavailability, late delivery, or changes in cost of
the machinery, equipment, materials, spare parts
etc. for the Project;
(b) Delay in the performance of any Contractors or
their agents;
(c) Non-performance resulting from normal wear and
tear typically experienced in transmission
materials and equipment;
(d) Strikes or labour disturbance at the facilities of the
Affected Party;
(e) Insufficiency of finances or funds or the
Agreement becoming onerous to perform; and
(f) Non-performance caused by, or connected with,
the Affected Party's:
i. negligent or intentional acts, errors or
omissions;
ii. failure to comply with an Indian Law; or
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 26 of 34
iii. breach of, or default under this Agreement
or any Project Documents.”
25. Undisputedly, there is no specific reference to a pandemic as
a Force Majeure event under Article 11.3. Understandably so,
since the last pandemic of comparable magnitude, the Spanish
Flu of 1918–1920, had occurred nearly a century earlier. Given
the remarkable advances in medical science since then, no one
could have anticipated that a pandemic of such magnitude could
once again strike the world, with devastating consequences,
bringing normal life and economic activity across the globe to a
virtual standstill. COVID-19 was a catastrophe of immense
magnitude, spreading across the globe and disrupting not only
the normal course of daily life but also adversely affecting the
mental health of people and the economies of nations. It caused
severe social and economic disruption worldwide, resulting in
over seven million confirmed deaths globally. A careful perusal
of the first paragraph of Article 11.3 makes it clear that COVID-
19 satisfies the attributes prescribed therein for an event to
qualify as a Force Majeure Event. This is particularly so since
COVID-19 does not fall within any of the exclusions specified in
Article 11.4.1. However, while a pandemic like COVID-19 is
closest in nature and origin to the events described in Article
11.3(a), relating to Natural Force Majeure Events, its
consequences, particularly the disruption of work and
movement of goods and personnel pursuant to governmental
orders issued to contain the pandemic, bear a closer
resemblance to the events contemplated under Article 11.3(b),
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 27 of 34
relating to Non-Natural Force Majeure Events. A close
examination of the TSA, however, reveals that the distinction
between Natural and Non-Natural Force Majeure Events is not
material for deciding the issue in the present appeal.
26. Covid-19 Pandemic has already been recognized as Force
Majeure event by the Govt. of India, MNRE as well as UPPTCL itself
by granting extensions to the transmission project which were under
th
construction as on date of lockdown i.e. dated 25 March, 2020. It is
th th
true that the notifications dated 27 July, 2020 and 12 June, 2021
issued by Ministry of power granting 5 months extension to the
transmission projects were applicable to inter-state transmission
projects only but that cannot be taken to indicate that Covid-19
Pandemic was not a Force Majeure event in respect of intra-state
transmission projects. Even otherwise also, the Appellants have not
contested that fact that Covid-19 Pandemic was a Force Majeure
st
event. Their only contention is that the 1 Respondent was not
entitled to the extension of the SCOD of its project as its progress was
not hampered in any manner by the Covid-19 Pandemic.
st
27. The Appellants have not disputed the fact that 1 Respondent
th
has issued various Force Majeure notices dated 20 February, 2020,
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 28 of 34
rd th th th
23 March, 2020, 26 March, 2020, 15 April, 2020, 29 April, 2020,
th th th th th
4 May, 2020, 18 May, 2020, 6 June, 2020, 4 July, 2020, 20
th rd
August, 2020, 14 September, 2020 and 23 October, 2020
intimating them about the impact of Covid-19 Pandemic upon the
progress of the project and seeking extension of SCOD of the project
as per Article 4.4 of the TSA. Concededly, none of the notice has
been responded to by the Appellants. The Appellants maintained
stoic silence on these notices in which claim for extension of SCOD
st
of the project was made by the 1 Respondent specifically. Therefore,
the Appellants shall be presumed to have accepted the fact that the
st
project of the 1 Respondent got impacted by the Covid-19
Pandemic.
st
28. Relying upon the communication dated 21 September, 2020
st
issued by the 1 Respondent to Appellants, intimating that the project
st
would be ready for commissioning by the 21 November, 2020, it is
argued on behalf of the Appellants that there was a categorical
st
admission on behalf of the 1 Respondent that this project was not in
any way affected by the Force Majeure event, and, therefore, the
claim for extension of SCOD ought to have been rejected. We do not
find any force in the submission on behalf of the Appellants. Perusal
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 29 of 34
st
of the communication dated 21 September, 2020 does reveal that
st
the 1 Respondent had notified the Appellants that the project would
st
be ready for charging and commissioning by 21 November, 2020.
However, the contents of the said communication need to be read
rd
juxtaposition with subsequent Force Majeure notice dated 23
st
October, 2020 issued by the 1 Respondent, as argued by the
st
learned Counsel for the 1 Respondent. In the said subsequent
st th
notice, the 1 Respondent has referred to the order dated 30
September, 2020 issued by the Union Home Secretary, thereby
st
extending the lockdown in containment zones upto 31 October,
2020. It has further been stated in the said notice that in view of the
st
said order of the Government, the 1 Respondent is facing following
issues :-
• “Movement of gangs has been affected since transportation of
labours in groups is limited and hence causing delay in getting
required no. of labours at site in timely manner. Due to
suspension of railway services, interstate movement of gangs
has been affected.
• Administrative support from the Government are still very
limited. Also, due to identification of containment zones, few of
the Collector offices have limited staff & closed majority of
times.
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 30 of 34
• Accessibility to landowners for resolving ROW issues for
various locations is getting affected due to fear in villagers for
Covid-19 spread & so they show resistance for meeting &
thereby clearance of ROW.
• Delay in compensation payment to landowners due to limited
staff available in banks which results in prolongation for
issuance of Demand Drafts, which delays construction
activities.
• Availability of manpower to achieve the desired output of the
contract works.
• Processing of Statutory proposals like NH, Forest clearance
as these are not moving as per desired pace.
• Liasoning part for applying shutdowns (various crossings like
Power line/Railways/NHAI) affected.
Due to identification of Containment zones, few of our site
•
offices were also closed as per instructions from
administration.”
st
29. The 1 Respondent has further sated in the said notice that
despite being affected by the Force Majeure event, they are making
best efforts to mitigate the effects of Force Majeure and are making
endeavour to complete the project by the SCOD. Accordingly, the
request for grant of extension of COD was reiterated in the said
notice.
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 31 of 34
th
30. What is relevant to note is that the order dated 30 September,
2020 issued by Union Home Secretary along with the guidelines was
st st
post the notice dated 21 September, 2020 issued by 1 Respondent
st
to the Appellants and, therefore, once the 1 Respondent realized
that the progress of the project would get further impacted in view of
th
the restrictions placed by virtue of order dated 30 September, 2020
of the Union Home Secretary, it immediately intimated the Appellants
rd
about the same vide notice dated 23 October, 2020 as detailed
hereinabove. Therefore, in these circumstances, it would be totally
incorrect and unjust to accept that in view of the contents of the
st st
communication dated 21 September 2020 issued to the 1
Respondent, performance of its project was not affected by any Force
Majeure event.
th
31. Letter dated 7 December, 2021 addressed by UPPCL to
Superintendent Engineer (Electricity), Import-Export & Payment
st
Circle, Lucknow, with a copy to the 1 Respondent, is also pertinent
on this aspect and needs to be taken note of. Vide the said letter,
UPPCL has itself granted three months extension of SCOD to the
st
Elements 1 to 8 of LOT-I of the project of 1 Respondent i.e. from
st st
21 November, 2020 to 21 February, 2021. Apparently, the
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 32 of 34
extension has been granted on account of the impact of Covid-19
Pandemic on the progress of transmission projects, even though, it is
not said so specifically in the same. Nothing has been brought on
record on behalf of the Appellants to contend otherwise. Therefore,
once the UPPCL itself acknowledged the Covid-19 Pandemic as
Force Majeure event and granted extension of three months, SCOD
of the project itself, the Appellants cannot be heard to contend that
st
the Commission committed any error or illegality in holding the 1
Respondent entitled to extension of COD of its project on account of
Covid-19 Pandemic.
st
32. What comes out of the above analysis is that the 1
Respondent has regularly been apprising the Appellants about the
occurrence of Force Majeure event (i.e. Covid-19 Pandemic) right
th rd
since 20 February, 2020 (date of first Force Majeure notice) till 23
October, 2020 (last Force Majeure notice) with the request for
extension of SCOD of the project under Act 4.4. of the TSA. The
Appellants chose not to respond to any of these notices and
maintained stoic silence. Covid-19 Pandemic, as a Force Majeure
event, falls in Article 11.3(b)(ii) of the TSA. There is nothing on record
to suggest that the project of the Appellant was not delayed or in any
manner impacted by Covid-19 Pandemic. Ministry of power, Govt. of
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 33 of 34
th th
India, has vide notifications dated 25 March, 2020 and 12
February, 2021 granted 5 months extension to the inter-state
transmission projects, the benefit of which must enure to the intra-
state transmission projects too. UPPCL (i.e. Appellant No. 1) itself
st
granted three months extension of SCOD to the project of 1
Respondent vide letter dated 07.12.2021 on account of Covid-19
Pandemic. Considering all these facts and circumstances, we are
unable to fathom that the Commission has erred in passing the
impugned order.
Conclusion
33. Having regard to the above discussion, we are not able to find
any error or infirmity in the impugned order of the Commission. The
appeal is devoid of any merit and is hereby dismissed accordingly.
All pending IAs shall also stand disposed of.
th
Pronounced in the open court on this 29 day of September, 2026.
Ajay Talegaonkar
Technical Member (Electricity)
Virender Bhat
Judicial Member
✓
REPORTABLE / NON REPORTABLE
js
-------------------------------------------------------------------------------------------------------------
Appeal No. 452 of 2022 Page 34 of 34