Trilogy Infra Private Limited vs Om Vithal Co Operative Housing Society Ltd
- Court
- Bombay High Court
arbpl25010-2026 with carbpl23586-2026-J.doc
AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION (L) NO.25010 OF 2026
Om Vithal Cooperative Housing
Society Limited
… Petitioner
Vs.
Trilogy Infra Private Limited
… Respondent
WITH
COMM ARBITRATION PETITION (L) NO.23586 OF 2026
ATUL
GANESH
KULKARNI
Trilogy Infra Private Limited
… Petitioner
Digitally signed by
ATUL GANESH
KULKARNI
Date: 2026.08.20
11:24:22 +0530
Vs.
Om Vithal Cooperative Housing
Society Limited
… Respondent
Mr. Amogh Singh with Ms. Krutisha Pandey, and Mr.
Nirav Karia i/by Bhavin Bhatia for the Petitioner in
ARBPL/25010/2026 & for the Respondent in
CARBPL/23586/2026.
Mr. Mutahhar Khan i/by Mr. Khalid Kazi for the
Petitioner in CARBPL/23586/2026 & for the
Respondent in ARBPL/25010/2026.
Mr. Vikrant Parshurami, AGP for the State.
Mr. Deepak N. Jadhav, Police Inspector, Borivali Police
Station, is present in Court.
CORAM : AMIT BORKAR, J.
RESERVED ON : AUGUST 19, 2026.
PRONOUNCED ON : AUGUST 20, 2026
1
arbpl25010-2026 with carbpl23586-2026-J.doc
JUDGMENT:
1. Arbitration Petition (L) No.25010 of 2026 is filed by a Co-
operative Housing Society against the developer. The Society seeks
various reliefs. One of the main reliefs is a declaration that,
because of the termination notice issued by the Society, the
Development Agreement executed and registered with the
developer has come to an end. The Society seeks an injunction to
prevent the developer from disturbing its possession of the suit
property. The Society further seeks to restrain the developer from
interfering with its right to redevelop the property in the manner it
may choose. On the other hand, the developer has filed
Commercial Arbitration Petition (L) No.23586 of 2026. The
developer seeks a stay to the termination notice issued by the
Petitioner Society. It seeks to restrain the Society from acting upon
or giving effect to the termination notice and from dispossessing
the developer from the subject property.
2. The facts and circumstances which led to filing of the present
petitions, as stated by the Co-operative Housing Society, are as
follows. The Petitioner is a Co-operative Housing Society registered
under the Maharashtra Co-operative Societies Act, 1960. The
Society claims to be in possession of and entitled to the land
bearing Final Plot No.275, Sub Plot No.30 of Town Planning
Scheme No.III, along with the building known as “Vithal
Apartments”, situated at Kasturi Park, Shimpoli Road, Borivali
(West), Mumbai 400092. This property is referred to as the
“Subject Property”. The Respondent is a company carrying on the
business of redevelopment and construction.
2
arbpl25010-2026 with carbpl23586-2026-J.doc
3. On 31 January 2015, the Petitioner Society had initially
appointed M/s. JKD Enterprises as the developer for
redevelopment of the Subject Property. A Development Agreement
and Power of Attorney were executed in favour of the said
developer. According to the Society, the earlier developer later
abandoned the project and committed repeated defaults.
Therefore, the Society terminated the earlier development
arrangement on 23 January 2023. Thereafter, Consent Terms were
executed before this Court. However, according to the Society, the
earlier developer again committed defaults. As a result, possession
of the Subject Property was taken through the Court Receiver and
thereafter restored to the Petitioner Society. Thereafter, between
13 June 2023 and 11 December 2023, the Petitioner Society
started a fresh process for appointment of another developer. After
following the tender process and considering different offers, the
Society appointed the present Respondent as the developer and
accepted its revised proposal for redevelopment of the Subject
Property. The parties thereafter executed a Development
Agreement dated 25 November 2023 and a Power of Attorney
dated 11 December 2023. Under these documents, redevelopment
rights were given to the Respondent. The Respondent had
represented that it had sufficient financial capacity, technical
knowledge and readiness to complete the redevelopment project
within the time agreed between the parties.
4. Under the Development Agreement, the Respondent was
required, amongst other things, to obtain all necessary approvals
and revised sanctioned plans within the agreed time. The
3
arbpl25010-2026 with carbpl23586-2026-J.doc
Respondent was required to execute Permanent Alternate
Accommodation Agreements, maintain transparency regarding the
progress of the project, regularly pay rent to the members and
complete the redevelopment work within the contractual period.
According to the Society, in spite of repeated assurances and
opportunities, the Respondent did not perform these obligations. It
failed to obtain the necessary approvals, failed to execute the
Permanent Alternate Accommodation Agreements and failed to
show that it had the necessary financial readiness for carrying out
the redevelopment project.
5. On 15 April 2025, according to the Society, instead of
removing the defaults, the Respondent raised disputes which,
according to the Society, were not connected with the obligations
of the Respondent under the Development Agreement. The
Respondent sought substantial extension of time. It attempted to
introduce revised commercial arrangements which, according to
the Society, were not part of the original Development Agreement.
The Society further states that even the revised timelines and
schedules proposed by the Respondent were repeatedly not
followed.
6. According to the Society, from January 2026 onwards, the
Respondent continued to default in payment of monthly rent and
rehabilitation compensation payable to the members of the Society.
It is the case of the Society that no meaningful redevelopment
work was carried out at the site. In spite of repeated reminders,
meetings and communications, the redevelopment project
remained at a standstill. The Society, therefore, issued a detailed
4
arbpl25010-2026 with carbpl23586-2026-J.doc
Cure Notice calling upon the Respondent to remove and cure the
various breaches and defaults under the Development Agreement.
The Respondent was asked to provide a clear and workable plan
for completion of the redevelopment project. According to the
Society, the Respondent did not cure the defaults mentioned in the
notice. It only denied the allegations without providing details of
financial closure, proper timelines or material showing actual
performance of its obligations.
7. Between 2 May 2026 and 18 May 2026, the Respondent
purported to invoke arbitration and sought to restrain the Society
from taking further steps. However, according to the Society, the
Respondent continued to remain in breach of its contractual
obligations and did not cure the defaults. Therefore, according to
the Society, because of the continued and serious breaches, long
delay, non-payment of rent, failure to obtain approvals and
complete lack of progress in redevelopment, the Society
terminated the Development Agreement, Power of Attorney and all
other documents connected with the development arrangement by
a notice dated 18 May 2026. From 22 May 2026 and thereafter,
the Society informed the concerned authorities about the
termination. The Society issued public notices informing the public
about cancellation and termination of the development
arrangement with the Respondent. The Respondent disputed the
termination. According to the Society, even after the termination,
the Respondent continued to claim rights under the documents
which, according to the Society, had been terminated, despite the
Respondent having failed to perform its obligations under the
5
arbpl25010-2026 with carbpl23586-2026-J.doc
Development Agreement.
8. The Society apprehends that, even after termination of the
Development Agreement and Power of Attorney, the Respondent
may create third-party rights in respect of the Subject Property,
create encumbrances over it, misuse the development documents
or otherwise prevent the Society from proceeding with
redevelopment. The Society states that it intends to undertake
redevelopment either by self-development or by appointing a new
developer of its choice. According to the Society, there is,
therefore, a need to protect the Subject Property and its rights
pending resolution of the disputes between the parties. On this
basis, the Petitioner Society has filed the present Arbitration
Petition under Section 9 of the Arbitration and Conciliation Act,
1996.
9. Mr. Singh, learned Advocate appearing for the Petitioner
Society, submitted that under the Development Agreement entered
into between the Society and the developer, the developer was
required to complete the redevelopment of the Society within a
period of 18 months, with an additional grace period of 6 months.
According to him, the developer was required to obtain the
Occupation Certificate from the concerned authorities. He invited
my attention to Clause 8.3 of the Development Agreement and
submitted that the developer was required to obtain all necessary
approvals within six months from the date of the Development
Agreement. Referring to the definition of “Occupation Certificate”
in the Development Agreement, he submitted that the expression
means a full Occupation Certificate issued by the Municipal
6
arbpl25010-2026 with carbpl23586-2026-J.doc
Corporation in respect of the newly constructed buildings.
10. Mr. Singh further invited my attention to Clause 10.10 of the
Development Agreement. He submitted that the said clause
required the developer to strictly provide a construction schedule
in the form of a bar chart so that the work could be completed
successfully within the agreed period. According to him, the
developer failed to provide such construction schedule. He further
submitted that since November 2025, the developer had not paid
rent to the members of the Society as required under the
Development Agreement. He submitted that not even a single RCC
slab had been completed by the developer at the site.
11. Mr. Singh then referred to the letter dated 6 December 2025,
by which the Society granted the developer an extension of 24
months for completion of the redevelopment project. He submitted
that all the terms and conditions of the Development Agreement
dated 25 November 2023 were to remain unchanged. Under the
said letter, the developer was required to increase the monthly rent
payable to the members by 10% from January 2026 onwards. The
developer was required to ensure regular and timely payment of
rent to all the members. He submitted that, thereafter, on 13
January 2026, the developer sent a communication proposing
certain terms as part of a compromise arrangement. According to
the Petitioner, the said communication required the Society to
execute a new Supplementary Development Agreement. He
submitted that the Society, by its communication dated 16 January
2026, informed the developer that the members had jointly
decided not to grant permission for obtaining a part Occupation
7
arbpl25010-2026 with carbpl23586-2026-J.doc
Certificate. The Society informed the developer that its proposal
was not in accordance with the sanction letter and that the
developer was misleading the Society. According to Mr. Singh, the
Society stated that because of these circumstances, its members
were losing trust and confidence in the developer. It was pointed
out that the developer had failed to show progress according to the
timeline provided under the Development Agreement and had not
obtained the full Occupation Certificate for the project till that
date.
12. Mr. Singh further referred to the communication dated 30
January 2026 issued by the developer, by which three options were
placed before the Society. The first option was that the Society
should accept the terms and conditions mentioned in the
developer's earlier letter and allow the developer to complete the
project. The second option was that the Society could enter into a
legal dispute with the developer, which, according to the
developer, would result in further delay in completion of the
project. The third option was that, if the Society wanted the
developer to leave the project, the Society would be required to
pay an amount of Rs.10 crore along with interest at the rate of
18%. According to Mr. Singh, the said letter required the Society to
give its reply within seven days. It was stated that if no reply was
received within that period, it would be presumed that the Society
had accepted the terms and conditions contained in the developer's
letter dated 13 January 2026.
13. Mr. Singh submitted that the Society, therefore, issued a
notice dated 16 March 2026 terminating the Development
8
arbpl25010-2026 with carbpl23586-2026-J.doc
Agreement. According to him, thereafter, the developer, by its
communication dated 8 April 2026, stated in paragraph 12 that if
the Society was not interested in completion of the project, the
developer would be constrained to exercise its right to exit from
the project. The developer further stated that, upon such exit, the
Society would be required to pay Rs.10 crore and an additional
amount of Rs.10 crore towards damages.
14. In support of his submissions, Mr. Singh relied upon the
decisions of this Court in Bank of Baroda Employees Mayuresh
CHS Limited vs. Kamla Homes Lifestyles Private Limited, Interim
Application No.916 of 2024 in Suit No.94 of 2024, decided on 13
August 2024; Yogeeta CHS Limited vs. Kamla Homes & Lifestyles
Pvt. Ltd. & Others, Commercial Arbitration Petition (L) No.10780
of 2023, decided on 5 June 2023 and 22 June 2023; Punjab
National Bank Workers CHS Ltd. vs. Meeti Developers Pvt. Ltd.,
2021 SCC OnLine Bom 5280; Rajawadi Arunodaya CHSL vs. Value
Projects Pvt. Ltd., 2021 SCC OnLine Bom 95723; Mayurpankh
CHSL vs. Surya Landmarks Developers Pvt. Ltd., Interim
Application (L) No.15831 of 2021 in Commercial Suit No.182 of
2021, decided on 28 September 2021; Swashray CHSL & Ors. vs.
Shanti Enterprises, Commercial Arbitration Petition (L) No.10432
of 2023 with 15203 of 2023, decided on 3 November 2023; The
Jal Ratan Deep CHSL vs. Kumar Builders Mumbai Realty Pvt. Ltd.,
2015 SCC OnLine Bom 5928; Saurabhakti Good P. Ltd. vs. GS
Constro & Infra P. Ltd., Arbitration Petition (L) No.13088 of 2022
with 31470 of 2022; Goverdhangiri CHSL vs. Bharat Infrastructure
and Engineering Limited, Arbitration Petition (L) No.3237 of 2020,
9
arbpl25010-2026 with carbpl23586-2026-J.doc
decided on 2 November 2020; and Taksha Spaces Pvt. Ltd. vs.
Goverdhangiri CHSL & Another, Appeal (L) No.7685 of 2020 in
Arbitration Petition No.90 of 2021, decided on 1 July 2021.
15. On the other hand, Mr. Khan, learned Advocate appearing
for the developer, submitted that on 16 April 2025, the MahaRERA
authorities had granted a stay on the basis of a complaint made by
the earlier developer. According to him, this had affected the
progress of the redevelopment project. He further submitted that
under the Development Agreement, the existing parking area was
required to be demolished and a multi-storeyed parking building
was required to be constructed. According to him, this work
required considerable time. He submitted that, on an application
made by the developer, the Municipal Corporation granted
permission for construction on 1 February 2024. Thereafter, on 11
August 2024, the developer paid the necessary premium.
According to Mr. Khan, from September 2024 till March 2025,
construction work relating to the parking building was carried out.
16. Mr. Khan invited my attention to the communication dated
19 November 2025 issued by the developer to the Society,
requesting extension of the redevelopment timeline. He submitted
that, thereafter, by a communication dated 6 December 2025, the
Society granted an extension of 24 months for completion of the
redevelopment project. He further submitted that the developer is
ready to deposit the entire outstanding corpus amount and
additional funds in a joint Escrow Account. Alternatively, the
developer is ready to pay the arrears of rent due to the members.
However, according to him, this is subject to the Society agreeing
10
arbpl25010-2026 with carbpl23586-2026-J.doc
to allow the developer to continue with the redevelopment project.
17. Mr. Khan submitted that the stay granted by MahaRERA was
lifted in December 2025. Immediately thereafter, according to him,
the developer approached various lenders and finalised discussions
with investors for arranging funds for the project. He further
submitted that, under the revised schedule dated 26 November
2025, the Society had accepted the developer's explanation
regarding the delay in completion of the project.
18. Mr. Khan invited my attention to the reliefs sought by the
Society in its petition. He submitted that prayer clause (a), by
which a declaration is sought, is in the nature of final relief and
cannot ordinarily be granted in a petition under Section 9 of the
Arbitration and Conciliation Act, 1996. In so far as prayer clause
(b) is concerned, he submitted that the Respondent developer is in
possession of the Subject Property. According to him, the
remaining reliefs claimed by the Society are beyond the scope of
Section 9. He, therefore, submitted that the petition filed by the
Society is liable to be dismissed. According to him, the developer is
entitled to the interim reliefs sought in the petition filed by it.
REASONS AND ANALYSIS:
19. I have considered the rival submissions made by the learned
Advocates appearing for the Society and the developer. I have gone
through the Development Agreement dated 25 November 2023,
the correspondence exchanged between the parties thereafter, the
Termination Notice dated 18 May 2026 and the interim reliefs
prayed in both the petitions. At this stage, this Court is not
11
arbpl25010-2026 with carbpl23586-2026-J.doc
required to finally decide all the contractual disputes between the
parties. Those disputes are required to be decided in arbitration.
The limited question before this Court is whether, on the material
available, redevelopment project should continue with the present
developer till completion of arbitration proceedings, or whether
the Society should be permitted to take the redevelopment further,
while protecting rights and claims of the developer.
20. The basic obligations under the Development Agreement are
not disputed. According to the Society, the developer was required
to complete redevelopment within 18 months, with further grace
period of 6 months. Under Clause 8.3, the developer was required
to obtain full approvals within six months from the date of
Development Agreement. The Agreement contemplated obtaining
full Occupation Certificate. The Society has relied upon definition
of “Occupation Certificate” in the Agreement and has contended
that it means full Occupation Certificate issued by Municipal
Corporation in respect of the newly constructed building. The
Society has relied upon Clause 10.10 of the Development
Agreement. According to the Society, the developer was required
to give a proper construction schedule in form of a bar chart, so
that the project could be completed within the stipulated time. It is
the case of the Society that no proper schedule was provided. The
Society has further alleged that rent was not paid to its members
from November 2025. It is contended that there was no substantial
progress in construction work. According to the Society, even one
RCC slab was not laid by the developer.
12
arbpl25010-2026 with carbpl23586-2026-J.doc
21. On the other side, the developer has tried to explain the
delay. Mr. Khan submitted that on 16 April 2025, MahaRERA had
granted a stay because of a complaint made by the earlier
developer. It is submitted that, under the Development Agreement,
the existing parking area was required to be demolished and a
multi-storeyed parking building was required to be constructed.
According to the developer, this work required considerable time.
The developer has further pointed out that the Municipal
Corporation granted permission for construction on 1 February
2024. The necessary premium was thereafter paid on 11 August
2024. It is submitted that, from September 2024 till March 2025,
work relating to the parking building was carried out.
22. At this stage, the explanation given by the developer cannot
be ignored. A stay granted by a statutory authority can affect the
progress of a redevelopment project. Similarly, demolition work,
construction of parking structure and obtaining statutory
permissions can take some time. Therefore, merely because there
is delay in the project, it cannot mean that the whole delay is only
because of the developer. The explanation given by the developer
regarding these circumstances requires consideration. However,
the matter cannot be decided only by seeing whether there was
some reason for delay during a particular period. The overall
conduct of both parties and the actual condition of the
redevelopment project are required to be considered. The material
placed before the Court shows that the developer had sought
extension of time for completion of the redevelopment project. By
communication dated 6 December 2025, the Society granted an
13
arbpl25010-2026 with carbpl23586-2026-J.doc
extension of 24 months for completion of redevelopment.
Significantly, according to the Society, this extension was granted
while keeping all the terms and conditions of the Development
Agreement dated 25 November 2023 unchanged. The said
communication provided for 10% increase in monthly rent payable
to the members from January 2026. The developer was required to
ensure timely payment of rent to the members. The Society did
not immediately terminate the Development Agreement because of
the earlier delay. Instead, it granted further time to the developer.
Thus, prima facie, the Society gave the developer one more
opportunity to continue and complete the redevelopment project.
However, the Society contends that even after such extension was
granted, the developer did not perform its obligations. The Society
has relied upon its communication dated 16 January 2026,
wherein it expressed that the members were losing trust and
confidence in the developer. According to the Society, the
developer failed to show progress as per the agreed timeline and
failed to obtain full Occupation Certificate. The communication
dated 30 January 2026 issued by the developer requires
consideration. According to the Society, the developer gave three
options to the Society. The first option was to accept the terms
proposed by the developer and permit the developer to complete
the project. The second option was to enter into legal proceedings,
which according to the developer would result in further delay of
the project. The third option was that, if the Society wanted the
developer to leave the project, the Society would have to pay Rs.10
crore together with interest at the rate of 18%. The developer was
14
arbpl25010-2026 with carbpl23586-2026-J.doc
entitled to place its stand before the Society and to protect its
financial interest. However, from the communication as placed
before the Court, it appears that continuation of redevelopment
project was being connected with acceptance of fresh terms
proposed by the developer. The Society has contended that the
developer was requiring execution of a Supplementary
Development Agreement containing terms and arrangements
which were not part of the original Development Agreement. At
this stage, it is not necessary to finally decide whether the
proposed additional terms were justified or otherwise. That issue
can be examined in arbitration. However, one fact remains that the
Society had granted extension on 6 December 2025 and, according
to its case, the original terms and conditions of the Development
Agreement were kept unchanged. Thereafter, disputes arose
between the parties regarding fresh conditions and the manner in
which the project was to be continued.
23. The Society has alleged that rent was not paid to its
members from November 2025. The developer has submitted that
it is ready to clear the arrears of rent. It has stated that it is
prepared to deposit the outstanding corpus and additional funds in
a joint Escrow Account, provided the Society agrees to allow the
developer to continue with the redevelopment project. The offer
made by the developer shows, at least at this stage, its willingness
to address some financial issues. However, the question is whether
such an offer can remove the effect of earlier defaults and
whether only because of such offer, the Society can be required to
continue with the same developer for an indefinite period. The
15
arbpl25010-2026 with carbpl23586-2026-J.doc
answer to this question cannot be in the affirmative. Payment of
rent to members who have vacated their premises is not a small
matter in a redevelopment project. Once the members vacate their
existing flats, they depend upon the arrangements made under the
Development Agreement for alternate accommodation and other
monetary benefits. If rent is not paid in time, the members may
face serious difficulties.
24. The developer has stated that after the MahaRERA stay was
lifted in December 2025, it approached lenders and investors for
funding of the project. This submission cannot be rejected without
consideration. However, at the same time, the redevelopment
project had commenced much earlier. The developer had
undertaken responsibility of carrying out and completing
redevelopment. Therefore, the subsequent statement that lenders
and investors were being approached becomes relevant while
considering whether necessary financial arrangements for
completion of the project were available with the developer.
25. The developer has relied upon the fact that the Society
granted extension of 24 months. It has contended that the revised
schedule dated 26 November 2025 was accepted by the Society.
This submission may have relevance in arbitral proceedings while
deciding whether the Society had waived any earlier breach or
whether the original time schedule was modified by mutual
consent. However, grant of extension cannot mean that the
developer got an unrestricted right to delay the project without
any further consequence. Extension is granted to enable a party to
perform its obligations within the extended period. The developer
16
arbpl25010-2026 with carbpl23586-2026-J.doc
was still expected to show reasonable progress and comply with its
continuing obligations, particularly regarding payment of rent and
carrying out redevelopment work.
26. The Society thereafter issued the Termination Notice dated
18 May 2026. The developer has challenged the validity of
termination. The developer seeks stay of the Termination Notice
and seeks a declaration that the Development Agreement
continues to remain valid and binding between the parties.
27. The Society has sought, amongst other reliefs, a declaration
that the Development Agreement and Power of Attorney stand
terminated, cancelled and revoked. The developer has submitted
that such declaration is in the nature of final relief and should not
be granted at the interim stage. The final validity of the
termination is an issue which is required to be decided in
arbitration. While exercising powers under Section 9, this Court
cannot finally decide all disputes arising from the Termination
Notice in the same manner in which the Arbitral Tribunal would
decide merits of the entire dispute. Therefore, the prayer of the
Society seeking final declaration regarding validity of termination
cannot be granted in a manner which finally concludes the dispute
between the parties. Similarly, the developer cannot obtain a final
declaration at this stage that the termination is illegal and that the
Development Agreement continues to subsist for all purposes.
28. The interim question before this Court is different. The Court
has to make a prima facie assessment on the basis of material
available and decide what interim arrangement is necessary for
17
arbpl25010-2026 with carbpl23586-2026-J.doc
protecting the rights of the parties and for ensuring that
redevelopment project does not remain stalled for an indefinite
period.
29. The decision in Pioneer Constructions vs. Sahakarnagar Co-
operative Housing Society Ltd., 2026 SCC OnLine Bom 2711,
explains the approach required in disputes concerning
redevelopment of a housing society. In paragraph 33, after
referring to the decision of the Division Bench in Huges Real Estate
Developers LLP Commercial Appeal No. 45 of 2025 decided on 19-
8-2025 , this Court observed:
“Therefore, while considering the issue of grant of temporary
injunction to restrain a housing society from proceeding
ahead with reconstruction of its building, this vital aspect
needs to be borne in mind.”
30. The reason for adopting such approach is stated in
paragraph 33 of the said judgment, where it is observed:
“the rights of a developer to earn profits through
redevelopment contracts would always remain subservient to
the rights of the society to have its building reconstructed.”
31. The above observations show that the interest of the
developer in a redevelopment project is connected with its
investment and profits which it may earn from the project. The
Society and its members, on the other hand, enter into
redevelopment so that they can get reconstructed and habitable
homes. Therefore, while considering interim relief, the Court is
required to see what actual consequence may follow if the
redevelopment project is stopped.
18
arbpl25010-2026 with carbpl23586-2026-J.doc
32. Paragraph 33 of Pioneer Constructions further states:
“When rights of residents of dilapidated buildings to reside
in safe houses is pitted against the rights of the developer to
earn profits through redevelopment contracts, the latter
must yield to the former atleast when it comes to
consideration of grant of temporary injunction.”
33. At the same time, this principle does not mean that every
termination made by the Society has to be accepted by the Court.
The same paragraph holds the need for making a prima facie
inquiry regarding breach of the Development Agreement. It states:
“Therefore prima facie inquiry in such cases would ordinarily
revolve around the issue as to who is guilty of breach of
Development agreement so as to put the guilty party to
terms.”
34. Therefore, the Court is not expected to mechanically prefer
the Society only because the Society consists of members waiting
for redevelopment. The conduct of the Society is required to be
examined. If the Society has illegally terminated the Development
Agreement even though the developer was ready and capable of
performing its obligations, appropriate conditions may be imposed
upon the Society for protecting the developer.
35. The further observations in paragraph 33 are relevant. The
Court has stated:
“Thus, if the society members are prima facie found to have
terminated the Development agreement in an illegal manner,
the Court can put the society to terms before allowing the
redevelopment process to progress further through another
developer.”
19
arbpl25010-2026 with carbpl23586-2026-J.doc
36. Therefore, the main question in the present matter is
whether the material placed before this Court shows, at least
prima facie, that the Society terminated the Development
Agreement without sufficient reason, or whether the conduct of
the developer had reached such stage that the Society could
reasonably lose confidence and decide to proceed with some other
arrangement. On the material available, it cannot be said that the
termination is and finally proved to be valid. The explanation
given by the developer regarding MahaRERA stay, construction of
parking structure, statutory permissions and financial
arrangements cannot be treated as irrelevant. These matters may
have important bearing when the dispute is finally decided in
arbitration. At the same time, the other position is clear. The
material available does not show such substantial progress in the
redevelopment project that the Society can be compelled to
continue with the present developer until completion of arbitration
proceedings.
37. The Society has alleged non-payment of rent, failure to
achieve sufficient construction progress and failure to demonstrate
financial closure. The developer's own submissions show that, even
after the dispute arose, it was approaching lenders and trying to
finalise investors. It has offered to clear financial dues subject to
the Society agreeing to continuation of the project. Prima facie
there appears to be a serious dispute regarding readiness and
capacity of the developer to complete the project within a definite
and workable time schedule. The developer has stated that it is
ready to perform its obligations. However, the material before the
20
arbpl25010-2026 with carbpl23586-2026-J.doc
Court does not provide sufficient basis to conclude that the project
can now be completed by the present developer within a certain
and reliable period. This aspect becomes more important because
the Society had granted extension of 24 months. According to the
Society, this extension was granted to give the developer one
further opportunity to complete the project. However, the
subsequent correspondence shows that disputes continued and the
relationship between the Society and the developer deteriorated.
38. The decision in Pioneer Constructions refers to Ison Builders
LLP. Commercial Arbitration Petition (L) No. 36533 of 2025
decided on 23-1-2026 Paragraph 37 of the quoted judgment
observes:
“Petitioner's interest in the project are limited to earning
profits. Petitioner can claim damages against the Society and
members if it can prove that the termination is invalid.
However, whether the Petitioner can further stall the process
of redevelopment till adjudication of its claims in respect of
the termination? The answer to the question appears, to my
mind, to be in the negative.”
39. The principle coming from these observations is that the
remedy available to the developer in arbitration for claiming
damages or compensation must be considered while deciding
whether the redevelopment project should be stopped. The
developer may establish that the termination was wrongful. If it
succeeds, its monetary claims can be adjudicated and appropriate
relief can be granted by the Arbitral Tribunal. In contrast, if
redevelopment project is not allowed to proceed till arbitration is
finally concluded, the members may remain without any certainty
21
arbpl25010-2026 with carbpl23586-2026-J.doc
as to when redevelopment will be completed. This is not merely a
temporary commercial inconvenience. The members have vacated
their homes and may be dependent upon rent or alternate
accommodation. Delay in redevelopment therefore affects their
living arrangements.
40. The Court in Pioneer Constructions has further referred to
the decision in Swashray Co-operative Society Housing Society
Limited v. Shanti Enterprises CARBP (L) 10432 of 2023 decided on
3-11-2023 and quoted paragraph 32 thereof. The following
observations are relevant:
“The Petitioner-Society is not expected to be at the mercy of
the Respondent-Developer. The Petitioner-Society cannot be
shackled with a Development agreement in which the
Respondent-Developer indulges in repeated defaults, without
any hope of the redevelopment project actually being
completed.”
41. This principle would apply where the material shows
repeated defaults and where there is no reasonable confidence that
the project will proceed within a workable period. Whether such
circumstances are finally established is a matter for arbitration. At
the interim stage, the Court is required to examine only whether
the Society has made out a sufficient prima facie case for
protecting and taking forward the redevelopment process.
42. In the present case, the developer has relied upon the stay
granted by MahaRERA and the requirement of carrying out
parking-related work. These circumstances may explain part of the
delay. However, they do not answer the Society's allegation
22
arbpl25010-2026 with carbpl23586-2026-J.doc
regarding subsequent non-payment of rent and absence of
satisfactory progress even after grant of extension. The developer
has offered to deposit the outstanding corpus and additional funds
in an Escrow Account or to pay arrears of rent. Such offer may
protect immediate financial interest of members to some extent.
However, payment of arrears does not answer the larger question
regarding future completion of redevelopment project. The Court
cannot proceed only on the basis of an assurance that the
developer will now arrange funds and complete the project. There
should be sufficient material to show that such completion is
realistically possible within a definite period. At present, the
dispute regarding funding shows that this aspect remains
uncertain.
43. The developer has sought an injunction restraining the
Society from appointing another developer. If such relief is granted
in absolute terms, the result would be that the Society would be
prevented from taking the redevelopment forward until the
dispute regarding termination is finally decided in arbitration. This
is precisely the consequence which the judgments referred above
require the Court to consider. In paragraph 35 of Pioneer
Constructions , this Court observed:
“If the interim measures are granted in Petitioner's favour,
the same would result in redevelopment project being
delayed indefinitely.”
44. The same paragraph further states:
“On the other hand, if interim measures are refused, the
Petitioner may only lose opportunity of earning profits in the
23
arbpl25010-2026 with carbpl23586-2026-J.doc
project. In case, Petitioner succeeds in its claims, it can be
adequately compensated while passing the arbitral Award.”
45. These observations do not mean that in every redevelopment
dispute a developer can always be compensated only by damages.
Each matter will depend upon its own facts. If construction is
complete, or if the developer has invested substantial amounts and
is ready and financially capable of completing the project, different
considerations may arise. The present matter has to be decided on
the basis of its own material.
46. In the present case, the Society has placed material
regarding long disputes, request for extension, subsequent
disagreement regarding additional conditions, allegation of non-
payment of rent and lack of substantial progress. The developer
has given explanations and has stated that it is now ready to
arrange funding and clear outstanding dues. On an overall prima
facie consideration, the apprehension of the Society that
redevelopment project may continue to remain uncertain cannot
be said to be without any basis.
47. The balance of convenience is therefore required to be
considered. If the Society is prevented from proceeding further, the
entire redevelopment project may remain dependent upon the
outcome of arbitration. Arbitration, even if conducted
expeditiously, may require some time. Further proceedings may
arise thereafter. During this period, the Society and its members
cannot be expected to remain indefinitely in uncertainty. On the
other hand, if the Society is permitted to proceed with
redevelopment through another developer or by any other
24
arbpl25010-2026 with carbpl23586-2026-J.doc
permissible mode, the developer's claim that termination was
wrongful does not disappear. The Arbitral Tribunal can determine
legality of the termination and can quantify damages,
compensation or any other monetary relief, if the developer
succeeds. Therefore, the balance of convenience does not favour
granting an injunction restraining the Society from taking further
steps for redevelopment. On the present facts, prejudice likely to
be caused by keeping the redevelopment project stopped appears
to be greater than the prejudice which may be caused to the
developer by allowing the project to proceed, while preserving and
protecting its financial and legal claims.
48. At the same time, the Society's prayer seeking final
declaration that the Development Agreement stands validly
terminated cannot be granted as final adjudication under Section
9. The validity and legal consequences of the Termination Notice
dated 18 May 2026 must remain open for final decision in
arbitration. The same principle applies to the prayer made by the
developer seeking final declaration that the Termination Notice is
illegal, null and void and that the Development Agreement
continues to remain fully operative. Such final adjudication cannot
be made at this interim stage. Therefore, the proper course would
be to keep the dispute regarding validity of termination open for
the Arbitral Tribunal, while making such interim arrangement
which does not unnecessarily stop redevelopment of the Subject
Property.
49. So far as possession is concerned, the Society claims that it is
in possession of the Subject Property. The developer claims
25
arbpl25010-2026 with carbpl23586-2026-J.doc
possession and control over the site. The pleadings show that the
property belongs to the Society and the developer claims rights
under the Development Agreement and Power of Attorney for the
limited purpose of carrying out redevelopment. The developer's
right to enter upon the property and carry out construction arises
from the development arrangement between the parties. Since the
Society has issued the Termination Notice and serious disputes
have arisen, it would not be proper at this stage to allow either
party to create a situation by carrying out further construction or
creating third-party rights without appropriate safeguards.
However, once the Society is permitted to proceed with
redevelopment through another lawful arrangement, the developer
cannot be permitted to use the pending arbitration proceedings as
a reason for obstructing future redevelopment activity. At the same
time, the Society must preserve all relevant records and materials
and maintain proper accounts of further redevelopment.
50. The developer has sought a direction requiring the Society to
deposit Rs.10 crore as security towards the amount allegedly
invested by the developer. At present, there is no adjudication
regarding the actual amount invested by the developer, the
manner in which such amount was utilised, or the extent to which
the developer may be entitled to recover any amount. Therefore, a
direction requiring the Society to deposit Rs.10 crore merely on
the basis of assertion made by the developer would not be justified
at this stage. However, the claim of the developer is required to be
preserved. Before entering into a fresh redevelopment
arrangement, the Society can be required to maintain complete
26
arbpl25010-2026 with carbpl23586-2026-J.doc
accounts and records relating to the project and to disclose the
relevant terms of any fresh arrangement before the Arbitral
Tribunal, if required. Such measures can protect the claim of the
developer without bringing the redevelopment project to a
complete halt.
51. The Society has sought delivery and deposit of original
documents, including the Development Agreement, Power of
Attorney, approvals, sanctions, receipts and professional NOCs.
These documents may be required both for continuation of
redevelopment and for adjudication of disputes in arbitration. At
the same time, it is necessary that such documents are preserved
and are not withheld, destroyed or misused by either party.
Therefore, the developer cannot be permitted to create any third-
party rights on the basis of the Development Agreement dated 25
November 2023 or the Power of Attorney. The developer shall not
alienate, transfer, mortgage or otherwise encumber the Subject
Property or any part thereof. The original documents and project
records are required to be preserved and made available as may be
necessary for continuation of redevelopment and for the arbitral
proceedings.
52. The permission sought by the Society to proceed with
redevelopment is required to be understood only as an interim
arrangement. Such permission shall not amount to a final finding
that the Termination Notice is valid. Similarly, refusal of interim
relief sought by the developer shall not amount to a final finding
that the developer has committed all breaches alleged by the
Society. All such questions remain open.
27
arbpl25010-2026 with carbpl23586-2026-J.doc
53. The overall position is that some submissions made by the
developer require consideration and may have relevance while
deciding the final dispute. MahaRERA stay, parking-related work,
statutory permissions and extension granted by the Society are
relevant circumstances. However, when these circumstances are
considered together with continued disputes, allegation of non-
payment of rent, absence of sufficient progress and uncertainty
regarding future funding and completion, the balance at the
interim stage tilts in favour of allowing the Society to take
redevelopment further. The consequence of granting relief sought
by the developer is required to be considered. If the Termination
Notice is stayed and the Society is restrained from appointing
another developer, the redevelopment will remain dependent upon
the present developer despite the serious loss of confidence alleged
by the Society. This Court cannot ignore the observations in
paragraph 38 of the quoted judgment that:
“The Petitioner - Society is not expected to be at the mercy of
the Respondent – Developer.”
54. In the present case, the material, prima facie, shows that the
relationship between the Society and the developer has reached a
stage where there is serious lack of confidence regarding
completion of the project. If the parties are compelled to continue
working together in such circumstances, it may result in further
delay and disputes. For these reasons, I am of the prima facie view
that the developer is not entitled to an injunction staying the
Termination Notice dated 18 May 2026 or restraining the Society
from proceeding with redevelopment through another developer
28
arbpl25010-2026 with carbpl23586-2026-J.doc
or by any other permissible mode. At the same time, the Society is
not entitled to obtain a final declaration under Section 9 that the
termination is valid and binding upon the developer. That issue is
required to be decided by the Arbitral Tribunal.
55. The interim arrangement should therefore permit the Society
to proceed with redevelopment so that the project does not remain
stalled for an indefinite period. The claims of the developer arising
from the Development Agreement and the alleged wrongful
termination shall remain fully open for adjudication in arbitration.
The developer shall be entitled to claim damages, compensation or
such other relief as may be available to it in law and under the
contract. The Society shall ensure that while taking further steps
for redevelopment, proper accounts, records, approvals, sanctions,
payments and other documents are maintained. The Society shall
ensure that no action is taken which may make it impossible for
the Arbitral Tribunal to examine and determine the monetary
claims of the developer, if any. Both parties shall preserve all
original documents, approvals, sanctions, payment receipts and
other records relating to the redevelopment project. Neither party
shall destroy, alter or misuse any such document. Appropriate
arrangement shall be made for handing over or making available
necessary documents so that continuation of redevelopment is not
obstructed and, at the same time, the material required for
arbitration remains preserved.
56. In the result, the Society has made out a prima facie case for
protection of the redevelopment process and for taking the
redevelopment further, subject to the safeguards indicated above.
29
arbpl25010-2026 with carbpl23586-2026-J.doc
57. In view of the findings recorded hereinabove, Arbitration
Petition (L) No.25010 of 2026 filed by the Society deserves to be
partly allowed. Commercial Arbitration Petition (L) No.23586 of
2026 filed by the developer does not deserve grant of the principal
interim reliefs sought therein. The following order is therefore
passed:
(i) Arbitration Petition (L) No.25010 of 2026 is partly
allowed;
(ii) Commercial Arbitration Petition (L) No.23586 of 2026
is dismissed, subject to the observations and directions
contained in this order;
(iii) Pending the arbitral proceedings, it is declared that the
Termination Notice dated 18 May 2026 shall remain
operative and effective. Consequently, the Respondent-
developer shall not, pending the arbitral proceedings and
subject to the final award, claim any right to continue or
proceed with redevelopment of the Subject Property under
the Development Agreement dated 25 November 2023 or the
Power of Attorney executed pursuant thereto;
(iv) It is clarified that the finding regarding the validity of
the termination is only a prima facie finding for the purpose
of deciding the present petitions under Section 9 of the
Arbitration and Conciliation Act, 1996. The learned Arbitral
Tribunal shall decide all disputes without being influenced
by any observation made in this order;
30
arbpl25010-2026 with carbpl23586-2026-J.doc
(v) The Respondent-developer, its directors, officers,
servants, agents and all persons claiming through or under it
are restrained from disturbing or interfering with the
Society's peaceful possession and control of the Subject
Property;
(vi) The Society shall be entitled to proceed with the
redevelopment of the Subject Property, either by self-
development or through such other developer, contractor or
agency as may be selected by it, subject to compliance with
applicable law and obtaining such permissions and approvals
as may be required from the competent authorities;
(vii) The Respondent-developer, its directors, officers,
servants, agents and all persons claiming through or under it
are restrained from obstructing or interfering with the
redevelopment activities undertaken by the Society or by any
developer, contractor or agency lawfully appointed by the
Society;
(viii) The Respondent-developer and all persons claiming
through or under it are restrained from selling, transferring,
assigning, mortgaging, charging, encumbering, alienating or
creating any third-party right, title or interest in respect of
the Subject Property or any premises proposed to be
constructed thereon;
(ix) The Respondent-developer shall not represent before
any person, authority or third party that it continues to
possess any subsisting right to independently undertake
31
arbpl25010-2026 with carbpl23586-2026-J.doc
redevelopment of the Subject Property on the basis of the
Development Agreement dated 25 November 2023 or the
Power of Attorney;
(x) The Respondent-developer shall, within a period of two
weeks from today, hand over to the Society all original
documents relating to the Subject Property and the
redevelopment project which are in its possession, including,
insofar as available with it, the original Development
Agreement dated 25 November 2023, the Power of Attorney,
approvals, sanctions, payment receipts, NOCs, drawings and
other project documents;
(xi) Before handing over the documents, the Respondent-
developer shall be entitled to retain copies thereof. The
Society shall maintain proper copies and record of all
documents received from the Respondent-developer;
(xii) The Respondent-developer shall, within two weeks
from today, provide to the Society copies of all approvals,
permissions, sanctions, applications, correspondence, NOCs
and other documents obtained or generated in connection
with the redevelopment project, to the extent the same have
not been provided;
(xiii) The Respondent-developer shall provide particulars
and copies of communications, if any, received from the
project Architect, RCC Consultant, Structural Engineer or
any other professional engaged by it in relation to the
redevelopment project. The Respondent shall not be required
32
arbpl25010-2026 with carbpl23586-2026-J.doc
to procure any fresh NOC from such professionals only for
the purpose of these proceedings. However, it shall disclose
the names and contact particulars of such professionals and
provide all documents available with it concerning their
engagement and work;
(xiv) The Society shall be entitled to approach the concerned
statutory, municipal and registration authorities for
recording, giving effect to or acting upon the termination,
and for obtaining such permissions, transfers, modifications
or fresh approvals as may be permissible in law. The
Respondent-developer shall not obstruct such lawful steps;
(xv) In view of the above directions, it is not necessary at
this stage to appoint the Court Receiver for taking custody of
the documents. The prayer for appointment of Court
Receiver is accordingly rejected;
(xvi) The Society's prayer for a final declaration that the
Development Agreement and Power of Attorney stand
permanently cancelled and revoked is not granted as such.
The declaration and consequential directions granted under
this order are only for the limited purpose of protecting the
Subject Property and enabling the redevelopment process to
proceed pending the arbitral adjudication;
(xvii)The prayers of the developer for staying the
Termination Notice dated 18 May 2026, restraining the
Society from acting upon the termination, maintaining status
quo in favour of the developer, preventing the Society from
33
arbpl25010-2026 with carbpl23586-2026-J.doc
appointing another developer and restraining the Society
from proceeding with redevelopment are rejected;
(xviii) The prayer of the developer seeking a direction
against the Society to deposit Rs.10 crore as security for the
alleged investment of the developer is rejected at this stage.
The alleged investment and the monetary consequences
arising from termination are matters which can be examined
in the arbitral proceedings on the basis of evidence;
(xix) The prayer seeking police protection is rejected.
However, all concerned parties shall maintain peace and
shall not take law into their own hands. If any obstruction or
breach of law and order takes place, the concerned
authorities shall deal with the same in accordance with law;
(xx) The Society and the Respondent-developer shall
maintain complete accounts and preserve all records relating
to the redevelopment project, including payments made
towards construction, consultants, statutory authorities,
corpus, rent, rehabilitation compensation and other project
expenses, for the purpose of the arbitral proceedings;
(xxi) The Society shall be at liberty to appoint another
developer or proceed with self-development. However,
before creating any third-party rights in respect of the
Developer's Area or entering into transactions which may
prejudice the developer's claims in arbitration, the Society
shall ensure that proper accounts and records are maintained
and the transactions are carried out in accordance with law.
34
arbpl25010-2026 with carbpl23586-2026-J.doc
The arbitral rights and claims of the Respondent-developer, if
established, shall remain subject to the final award;
(xxii) All observations and findings recorded in this order are
prima facie and only for deciding the applications for interim
measures under Section 9 of the Arbitration and Conciliation
Act, 1996. They shall not bind the learned Arbitral Tribunal
while deciding the disputes finally on merits;
(xxiii) There shall be no order as to costs.
(xxiv) The interim applications, if any, stand disposed of
accordingly.
58. At this stage, Mr. Khan, learned Advocate appearing on
behalf of the developer seeks stay of the execution and
implementation of this order. For the reasons recorded herein
above, the request for stay stands rejected.
(AMIT BORKAR, J.)
35