Sunil vs Sub Divional Officer Revenue And Land Acquisition Officer

Court
Madhya Pradesh High Court

-1-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE
BEFORE
HON'BLE SHRI JUSTICE VINAY SARAF
CIVIL REVISION No. 997 of 2026
CNR No.: MPHC020358332026

SANJAY

Versus
THE STATE OF MADHYA PRADESH AND OTHERS

WITH

CIVIL REVISION No. 991 of 2026
CNR No.: MPHC020358272026
CHUNNILAL

Versus

THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 992 of 2026

CNR No.: MPHC020358282026
HUKMICHAND
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 993 of 2026
CNR No.: MPHC020358292026
MANJUBAI
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 994 of 2026
CNR No.: MPHC020358302026

GOPAL
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 995 of 2026
CNR No.: MPHC020358312026
BADRILAL
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-2-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026


CIVIL REVISION No. 996 of 2026
CNR No.: MPHC020358322026

DINESH
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 998 of 2026
CNR No.: MPHC020358342026
HARIRAM
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 999 of 2026
CNR No.: MPHC020358352026
FAKIRCHAND

Versus

THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1000 of 2026

CNR No.: MPHC020358362026

NARAYAN
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1002 of 2026
CNR No.: MPHC020358742026
LEELABAI
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 1004 of 2026
CNR No.: MPHC020358782026
KHUSWANT
Versus

THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1005 of 2026
CNR No.: MPHC020358792026
ROOPKISHORE
Versus
STATE OF MADHYA PRADESH AND OTHERS
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-3-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026


CIVIL REVISION No. 1006 of 2026
CNR No.: MPHC020358802026

RAMBHABAI
Versus
STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1008 of 2026
CNR No.: MPHC020358832026
VYANKAT
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 1009 of 2026
CNR No.: MPHC020358852026
KAMLABAI

Versus

THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1010 of 2026

CNR No.: MPHC020358872026

SHANTILAL
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1011 of 2026
CNR No.: MPHC020358882026
TOLARAM
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 1012 of 2026
CNR No.: MPHC020358892026
DINESH
Versus

THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1013 of 2026
CNR No.: MPHC020358902026
LAKHAN SINGH
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-4-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026


CIVIL REVISION No. 1014 of 2026
CNR No.: MPHC020358922026

MOHAN
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1015 of 2026
CNR No.: MPHC020358942026
VISHNNU
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 1016 of 2026
CNR No.: MPHC020359312026
TOLARAM

Versus
SUB DIVISONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER AND OTHERS


CIVIL REVISION No. 1017 of 2026
CNR No.: MPHC020359322026
KAUSHALYABAI

Versus
SUB DIVISONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER AND OTHERS


CIVIL REVISION No. 1018 of 2026
CNR No.: MPHC020359332026
PARMANAND
Versus
SUB DIVISIONAL OFFICER REVENUE AND LAN ACQUISITION
OFFICER AND OTHERS

CIVIL REVISION No. 1019 of 2026
CNR No.: MPHC020359342026

SANJUBAI
Versus
SUB DIVISIONAL OFFICER (REVENUE) AND LAND

ACQUISITION OFFICER AND OTHERS

CIVIL REVISION No. 1023 of 2026
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-5-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
CNR No.: MPHC020360132026

DHAPUBAI
Versus
SUB DIVISIONAL OFFICER (REVENUE) AND LAND

ACQUISITION OFFICER AND OTHERS

CIVIL REVISION No. 1024 of 2026

CNR No.: MPHC020360142026
MANOHAR AND OTHERS
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1026 of 2026
CNR No.: MPHC020360172026
HARIRAM
Versus
THE STATE OF MADHYA PRADESH AND OTHERS


CIVIL REVISION No. 1027 of 2026
CNR No.: MPHC020360182026

JAGDISH
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1029 of 2026
CNR No.: MPHC020360712026
MEHARBAN
Versus
SUB DIVIONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER AND OTHERS

CIVIL REVISION No. 1031 of 2026
CNR No.: MPHC020360742026
SURESH
Versus
SUB DIVIONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER AND OTHERS

CIVIL REVISION No. 1032 of 2026
CNR No.: MPHC020360762026
SUNIL AND OTHERS
Versus
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-6-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
SUB DIVIONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER AND OTHERS


CIVIL REVISION No. 1020 of 2026
CNR No.: MPHC020359492026
CHUNNILAL
Versus
SUB DIVISIONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER TEHSIL SARDARPUR DISTRICT DHAR M P AND
OTHERS

CIVIL REVISION No. 1025 of 2026
CNR No.: MPHC020360162026

DHAPUBAI

Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1030 of 2026
CNR No.: MPHC020360722026
KRISHNABAI
Versus
SUB DIVIONAL OFFICER REVENUE AND LAND ACQUISITION
OFFICER AND OTHERS

CIVIL REVISION No. 1007 of 2026

CNR No.: MPHC020358822026
UDDIBAI
Versus
THE STATE OF MADHYA PRADESH AND OTHERS

CIVIL REVISION No. 1003 of 2026
CNR No.: MPHC020358762026
RAMESHWAR

Versus
THE STATE OF MADHYA PRADESH AND OTHERS

Appearance in all cases:
Shri Pranav Mandhanya - Advocate for the petitioner.
Shri Anshul Rajpurohit – Govt. Advocate and Shri Arnik Jain –
Panel Lawyer for the respondent Nos. 1 & 2 / State.
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-7-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
Shri Romesh Dave – Deputy Solicitor General alongwith Shri J.B.
Mehta – Advocate for the respondent No. 3.

Reserved on : 16-17.09.2026
Delivered on : 05.10.2026

ORDER
Per : Justice Vinay Saraf

These Civil Revision Petitions are arising out of the common
notification of land acquisition and common questions of law are involved
in these revision petitions, thus, with the consent of the parties, the
arguments were heard analogously for the purpose of final disposal of
these petitions and this order will dispose of all the civil revisions. For the
sake of convenience, facts are being taken from Civil Revision No.
997/2026 .
02. Facts of the case, in nutshell, sufficient to decide these revision
petitions are that a notification was issued on 10.01.2018 for acquisition of
lands for the purpose of laying down the Indore – Dahod Railway Line at
the instance of the Western Railway. The notices were issued to the
landowners on 25.09.2018 and objections were called till 26.10.2018. After
affording opportunity of hearing the objections, on 04.06.2020, the Land
Acquisition Officer passed the award. Thereafter, reference petition was
filed by the land loser on 13.06.2025, which was referred by the Collector
to the Reference Court for adjudication under the provisions of Section 64
of the Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as "the
Act, 2013").
03. The respondent No. 3, after appearance, filed an application under
Order VII Rule 11(d) read with Section 151 of Code of Civil Procedure,
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-8-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
1908 (hereinafter referred to as "CPC") for rejection of the reference
petition, on the ground that the petition is barred by limitation. The
application preferred by respondent No. 3 was allowed by the Reference
Court vide impugned order dated 30.06.2026 and the reference petition
filed under Section 64 of the Act, 2013 has been rejected as barred by
limitation. Hence, this civil revision petition has been preferred.
04. The order passed by the District Court in reference petition has been
assailed by the land loser in the instant civil revision petition filed under
Section 115 of the Code of Civil Procedure, 1908 stating that the
intimation of passing the award was never served to the land loser and the
land loser or his representative / Lawyer was not present at the time of
making the award, therefore, the land loser was not having any knowledge
of the award and when, in the year 2025, the amount of compensation was
paid to him, he came to know about the passing of award and thereafter,
preferred the reference petition before the Collector, which was duly
referred to the District Court and made over to the Reference Court, who
committed error in rejecting the reference petition treating as time barred.
05. The revisionist assailed the order passed by the Reference Court on
various grounds inter alia, the Reference Court was not having any
authority to reject the reference case and was under obligation to decide
the reference petition on merits only. The Reference Court failed to
consider that no intimation of award was ever served to the land loser and
in the absence of knowledge, the reference petition could not be filed
earlier and thus filed within limitation from the date of knowledge,
therefore, the same could not be treated as time barred. Once the reference
petition is made by the Collector to the Reference Court, it amounts to
implied condonation of delay, if any, and the decision of the Collector
being an executive action, the Reference Court had no jurisdiction to
decide the issue of limitation and delay allegedly occurred in filing the
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-9-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
reference petition before the Collector. It is also urged on behalf of the
petitioner that in Section 64(2) of the Act, 2013, the reference of Section
21 should be read as Section 37 of the Act, 2013.
06. Counsel appearing on behalf of the respondent No. 3 opposed the
revision petition on various grounds inter alia, the civil revision petition
under Section 115 of CPC is not maintainable and the order passed by the
Reference Court rejecting the reference petition amounts to an award,
therefore, the remedy to the petitioner was available under Section 74 of
the Act, 2013 to file an appeal and consequently, the revision petition is
liable to be dismissed, as not maintainable. He further raised the issue that
as per Section 64(2) of Act, 2013, the reference petition could be filed
within six weeks from the date of passing of the award if, at the time of
passing the award, the land loser or his representative was present and
otherwise, within six weeks from the date of receipt of the notice under
Section 21(2) of the Act, 2013 and in any case, not later than six months
from the date of award. However, in the case in hand, on 04.06.2020, the
award was passed, and the reference petition has been filed on 13.06.2025,
after a delay of 1834 days and, therefore, the Reference Court has correctly
rejected the reference petition considering as time barred.
07. Mr. Pranav Mandhanya, learned counsel appearing on behalf of the
petitioner submits that the Collector has already exercised his jurisdiction
to refer the reference petition to the Reference Court, thus, the Reference
Court was under obligation to decide the same on merits and could not
have been rejected the same by reopening the question of limitation, which
was already considered by the Collector at the time of making reference
and, thus, the Reference Court has travelled beyond its jurisdiction in
rejecting the reference under Order VII Rule 11 of CPC. He further
submits that the order of rejection of reference petition cannot be treated as
award, as the award necessarily contains the details of land, the
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-10-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
determination of the market value and specifies the amount awarded under
Clause 1 of Section 28 and also the amounts (if any) respectively awarded
under each of the other clauses of the same sub-section together with the
grounds of awarding each of the said amount and, therefore, the order
passed by the Reference Court in the case in hand cannot be considered as
award as per the provisions of Section 69 & 70 of the Act.
08. Mr. Mandhanya further submits that as the impugned order is not an
award, therefore, civil revision petition is maintainable. He relied on the
order 24.06.2015 passed by Coordinate Bench of this Court in a batch of
civil revision petitions in the case of Somli W/o Tersingh v/s State of M.P.
(Civil Revision No. 42/2015 and other matters) wherein it has been
decided that civil revision petition is maintainable if, the Reference Court
has rejected the reference petition treating as time barred. He further relied
on order dated 03.09.2024 in Civil Revision No. 741/2019 (Smt. Santosh
nd
and others v/s Deputy Chief Engineer (Construction) II and others,
wherein, the Coordinate Bench has held that civil revision petition is
maintainable, if the reference petition is rejected as not maintainable. The
similar view has been taken by another Coordinate Bench in Civil Revision
No. 99/2021 (Abhay Kumar Jain v/s the State of Madhya Pradesh and
another), decided on 30.06.2022 , wherein the Coordinate Bench has held
that the civil revision is maintainable.
09. Mr. Mandhanya further relied on the judgment delivered by
Rajasthan High Court in Lakshmi Narayan v/s State of Rajasthan
reported in AIR 1966 Rajasthan 118 , wherein the Rajasthan High Court
has held that in the statute, it is clearly defined that when an order will
amounts to an award and if the reference is rejected as invalid being made
on a time barred application, the order will not be treated as award and
consequently, no appeal would lie to the High Court and the remedy of
civil revision is available to the aggrieved party.
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-11-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
10. Mr. Mandhanya submits that in view of the orders passed by the
Coordinate Benches, the issue of maintainability of civil revision has
already been decided and consequently, the civil revision petitions
preferred by the petitioners are maintainable. He submits that the limitation
for filing the reference petition has been provided in Section 64 of the Act,
2013, which is pari materia to Section 18 of the Land Acquisition Act,
1894 (hereinafter referred to as "Act, 1894"). He submits that limitation
provided in Section 64 of Act, 2013 will start from the date of award if, the
applicant was present or represented before the Collector at the time, when
the award was made and in those circumstances, the reference petition
should be filed within six weeks, otherwise, the land loser will get
limitation of six weeks from the receipt of the notice from the Collector
intimating the passing of award.
11. He further submits that in Section 18 of Act, 1894, the notice from
the Collector under Section 12(2) was referred, which issued after the
passing of the award forwarding the intimation to the land loser, but the
legislature inadvertently referred Section 21 in Section 64(2) of the Act,
2013, which should be Section 37 because Section 21 has nothing to do
with the passing of award and Section 37 of Act, 2013 is pari materia to
Section 12 of the old Act of 1894 and, therefore, the correct provision is
Section 37 and thus it should be read as Section 37 and from the date of the
receipt of the notice under Section 37, the land loser may file the reference
petition within six weeks otherwise, within six months from the date of
Collector’s award.
12. He submits that in the case in hand, notice under Section 37 of Act
2013 was never served upon the land losers. At the time of passing the
award on 04.06.2020, no land loser was present or represented, intimation
of passing of award never served, the compensation was deposited in year
2025, possession was demanded in the year 2025 and, therefore, in the
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-12-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
absence of the knowledge of passing of award, no cause of action accrued
to the land losers to file reference petition and when the land loser gathered
the knowledge of passing of award, they immediately filed the reference
petition within limitation before the Collector and Collector treating them
in limitation referred the reference petitions to the Reference Court for
deciding in accordance with the law. Meaning thereby the petitions were
filed within limitation and if any delay occurred, the same has been
impliedly condoned by the Collector by an executive order of reference
and the Reference Court had no occasion to reconsider the question of
limitation.
13. Mr. Mandhanya submits that the Supreme Court has already decided
the question of limitation in the matter of Bhagwan Das and others v/s
State of U.P. and others, 2010 (3) SCC 545 , wherein the Supreme Court
has held that the limitation will start from the date of knowledge of the
passing of an award. He further submits that the Supreme Court in the
matter of Premji Nathu v/s State of Gujarat and another, 2012 (4)
M.P.L.J. 37 interpreted the expression the date of award used in the
proviso as knowledge of award either actually or constructively. He further
submits that in the case in hand, the Land Acquisition Officer received the
compensation amount from Western Railways on 05.06.2024 and
23.10.2024, after 4 years of passing the award, and thereafter, the payment
was made to the land losers and no notice under Section 37 of Act, 2013
was ever issued or served upon the revisionist. Neither the possession has
taken over, nor the compensation was paid till 2025 and, therefore, the
Collector has not committed any error in forwarding the reference cases to
the Reference Court for adjudication.
14. He submits that the petitioner, after obtaining the certified copy of
the award, filed the reference petition under Section 64 on 13.06.2025,
which was well within limitation. He further submits that in the Act, 1894,
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-13-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
the Collector was not having any authority to condone the delay, however,
in the Act, 2013, the Collector is having authority to condone the delay up
to one year and, therefore, the decision of the Collector to forward the
reference case to the Reference Court amounts to implied condonation of
delay, if any.
15. Mr. Mandhanya further submits that constructive knowledge of
passing of award can be inferred from receipt of compensation or delivery
of possession. But in the case in hand, neither the possession was obtained
before year 2025 nor compensation was paid, therefore, it cannot be
inferred that the petitioner was having knowledge of passing of the award
prior to year 2025. He further submits that mentioning of Section 21 in
Section 64(2)(b) of Act, 2013 is a drafting error and Section 21 has no
connection with the passing of the award and in Section 21, notice is not
required to be issued after passing of the award, therefore, the limitation in
filing any reference petition cannot be started from the date of receipt of
notice of Section 21. He submits that it should be "Section 37" because in
Act, 1894, it was mentioned that the reference case may be filed within six
weeks from the date of receipt of notice under Section 12(2), which was an
intimation of passing of the award and deposition of the payment. Similar
provision is available in Section 37 of Act, 2013. Section 37 of Act, 2013
provides for issuance of notice to the landowner intimating the passing of
award and deposition of compensation by the authority, therefore, it should
be read as "Section 37(2) " of the new Act, 2013.
16. To support his argument, he relied upon the judgment delivered by
the Kerala High Court in the matter of Pushpaja M. and others v/s State of
Kerala and others, I.L.R. 2019 (1) Kerala 340 , wherein the Kerala High
Court, considering the issue of limitation, has held that the words used as
"Section 21(2)" in Section 64(2)(b) of Act, 2013 should be read and
understood as "Section 37(2)" and the limitation to file the petition for
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-14-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
reference for enhanced compensation can be submitted within six weeks of
receipt of notice under Section 37(2). He submits that the Kerala High
Court, after discussing the provisions of Act, 1894 and Act, 2013 has
finally observed and suggested the Competent Authority of Union
Government to take appropriate steps for remedial amendments in Clause
(b) of Section 64(2) of Act, 2013 to substitute the words "Section 21" as
"Section 37(2)".
17. Learned counsel also relied upon the judgment delivered by the
Supreme Court in the matter of Shailesh Dhairyawan v/s Mohan
Balkrishna Lulla, (2016) 3 SCC 619 , wherein the Supreme Court has held
that the "purposive interpretation" or "purposive construction" is based on
the understanding that the court is supposed to attach that meaning to the
provisions, which serve the "purpose" behind such a provision. He further
relied upon the judgment delivered by the Constitutional Bench of
Supreme Court in the matter of Indore Development Authority v/s
Manoharlal and others, 2020 (8) SCC 129 and submits that the Supreme
Court has considered the Act of 2013 as beneficial legislation and,
therefore, its provisions must be construed liberally in favour of the land
losers. He submits that the Supreme Court has observed that technical bars
are not to defeat the substantive rights to just and fair compensation. The
preamble and objects of the act reinforce that a hyper-technical rejection
on an incorrect computation of limitation would defeat the very purpose of
the Legislature.
18. He relied on the order passed by the Coordinate Bench at Jabalpur in
the matter of Lalbahadur Pandey and others v/s Executive Engineer Purv
Naher Sambhag No.2 and others in Misc. Petition No. 4445/2021,
decided on 07.01.2026 , wherein the Coordinate Bench has held that the
date of Collector’s award would mean the date of knowledge of the party
affected by the award and also that knowledge of award does not mean a
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-15-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
mere knowledge, but knowledge must mean essential contents of the
award and the contents must be known either actually or constructively. He
further relied on the judgment delivered by the Supreme Court in the
matter of Kolkata Municipal Corporation and another v/s Bimal Kumar
Shah and others, 2024 INSC 435 , wherein the Supreme Court has
recorded the conclusion that principles for the compulsory acquisition
should be followed in all the cases.
19. Mr. Mandhanya further relied on the judgment delivered by the
Supreme Court in the matter of Sukh Dutt Ratra and another v/s State of
Himachal Pradesh and others, 2022 INSC 394 , wherein the Supreme
Court has held that the right against deprivation of property, unless in
accordance with procedure established by law, constitutes to be a
constitutional right under Article 300A of the Constitution of India and it is
the cardinal principle of rule of law that nobody can be deprived of liberty
of property without due process or authorization of law.
20. Learned counsel for the petitioner submits that the impugned order
be set aside and the matter be remanded to the Reference Court to decide
on the merits, in accordance with the law.
21. Mr. Anshul Rajpurohit, Govt. Advocate and Mr. Arnik Jain, Panel
Lawyer appearing on behalf of the respondent Nos. 1 & 2 / State supported
the order passed by the Reference Court and submit that the Reference
Court, after considering the provisions of law, correctly rejected the
reference petition, as the same was preferred after 5 years of the passing of
award and which could not be treated within limitation on any ground.
They pray for dismissal of the petitions.
22. Mr. Romesh Dave, Deputy Solicitor General and Mr. Jitendra B.
Mehta, learned counsel appearing on behalf of the respondent No. 3
advanced two fold arguments, firstly , that the civil revision petition is not
maintainable against the order of rejection of reference petition by the
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-16-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
Reference Court under Order VII Rule 11 of CPC and the proper remedy is
to file an appeal under Section 74 of the Act, 2013 and, secondly , that the
reference petition was barred by 1834 days and, therefore, the Reference
Court has not committed any error in rejecting the reference petition.
23. Mr. Mehta submits that the award was passed on 04.06.2020 and
reference petition has been filed on 30.06.2025, therefore, there was a
delay of 5 years in filing the reference petition. When respondent No. 3
received the notice of the reference petition from the Reference Court, they
raised the question of limitation and earlier there was no occasion for
respondent 3 to raise the question of limitation before the Collector. He
submits that the Reference Court considered their objections in view of the
provisions of Section 64 of the Act, 2013, which provides that the
reference petition may be filed within six weeks from the date of
Collector’s award, if the person making it was present or represented
before the Collector at the time, when the award was made or within six
weeks of the receipt of notice from the Collector under Section 21 in other
cases or within six months from the date of the Collector’s award,
whichever period shall first expire. He further submits that the Collector
has authority to entertain an application for condonation of delay of one
year only.
24. Learned counsel heavily relied upon the latest judgment delivered by
the Apex Court on 09.02.2026 in the matter of Deputy Commissioner and
Special Land Acquisition Officer v/s M/s S.V. Global Mill Limited, 2026
SCC Online SC 171 , wherein the Supreme Court has held that the
provisions of Section 5 of the Limitation Act cannot be invoked to condone
the delay, where a special statute prescribes a maximum outer time limit
for filing a reference. The Supreme Court further held that the statute does
not provide any right of appeal, if the land owner has failed to seek a
reference within the stipulated time period and it also does not supply any
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-17-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
power to the Court to grant an extension in seeking a reference. The
Supreme Court further held that the right of a landowner to seek a
reference is extinguished under the statute on the expiry of the stipulated
time period.
25. Mr. Mehta submits that as per Proviso to Section 64(2) of Act, 2013,
even the Collector can condone the delay up to one year only, if he is
satisfied that there was sufficient cause for not filing it within the period
prescribed in the first Proviso and, therefore, the law has fixed an outer
limit for the purpose of condonation of delay and in these circumstances, a
delay of more than one year could not have been condoned by the
Collector, Mr. Mehta referred the provisions of Section 34 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as the "Act,
1996") and submits that in Section 34 of the Act, 1996, an outer limit of 30
days has been fixed for condonation of delay occurred in filing the
application for setting aside the award and it is a settle position of law that
the delay of more than 30 days cannot be condoned by the Court in any
case. He submits that even after liberal reading of the provisions of Section
64 of the Act, 2013, it can be gathered that at the most, the reference
petition may be filed within 18 months from the date of passing of the
award by the Collector and not thereafter, in any case.
26. Mr. Mehta further submits that the Coordinate Bench of this Court in
Civil Revision No. 412/2019 (Jagdish v/s Land Acquisition Officer,
Barwani and another, decided on 27.08.2019) has held that a civil
revision petition challenging the award of the Reference Court rejecting
the application for reference is not maintainable, as the award is
appealable. He submits that the Bombay High Court has also taken the
similar view in the matters of Venkat Baburao Karle v/s State of
Maharashtra and others, 2012 AIR CC 2163 (BOM) , Chandu S/o
Jagannath Ambekar and another v/s Digamber S/o Kisanrao Kulkarni,
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-18-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
2004 (4) Mh.L.J. 69 and Diwakar Prabhakar Chopade v/s Sub Divisional
Officer, 2019 SCC OnLine Bom 2930 by holding that against the order of
rejection of reference petition filed for enhancement of the compensation,
no civil revision petition under Section 115 of CPC would lie and the only
remedy would be filing of an appeal.
27. Learned counsel appearing on behalf of respondent No. 3 prays for
dismissal of the revision petition.
28. Heard arguments advanced by learned counsel for the parties, at
length. After considering the arguments advanced by the counsel for the
parties and the issues raised by them in their respective arguments, the
following legal questions emerge in this case:-
(a) Whether the reference petition can be filed within six
months from the date of knowledge of the award, in case no
notice or intimation of passing of award has been served upon
the land loser?
(b) Whether the Reference Court can reject the reference
petition referred by the Collector under Section 64 of the Act,
2013 without deciding on the merits?
(c) Whether a civil revision petition would lie impugning the
order of rejection of reference petition by Reference Court
under Order VII Rule 11 of CPC?
Consideration on Question (a):
29. For consideration of this question, it will be profitable to quote the
provisions of Section 18 of the Act, 1894 and Section 64 of the Act, 2013
in juxta position:
Section 18 of the Act, 1894 Section 64 of the Act, 2013
18. Reference to Court. - (1) Any
person interested who has not accepted
the award may, by
written application to the Collector,
64. Reference to Authority .-(1) Any
person interested who has not accepted
the award may, by written application
to the Collector, require that the matter
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-19-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
require that the matter be referred by
the Collector for the determination of
the Court, whether his objection be to
the measurement of the land, the
amount of the compensation, the
person to whom it is payable, or the
apportionment of the compensation
among the persons interested.
(2) The application shall state the
grounds on which objection to the
award is taken:
Provided that every such application
shall be made-
(a) if the person making it was present
or represented before the Collector at
the time when he made his award,
within six weeks from the date of the
Collector's award;
(b) in other cases, within six weeks of
the receipt of the notice from the
Collector under section 12, sub-section
(2), or within six months from the date
of the Collector's award, whichever
period shall first expire.
be referred by the Collector for the
determination of the Authority, as the
case may be, whether his objection be
to the measurement of the land, the
amount of the compensation, the
person to whom it is payable, the rights
of Rehabilitation and Resettlement
under Chapters V and VI or the
apportionment of the compensation
among the persons interested:
Provided that the Collector shall,
within a period of thirty days from the
date of receipt of application, make a
reference to the appropriate Authority:
Provided further that where the
Collector fails to make such reference
within the period so specified, the
applicant may apply to the Authority,
as the case may be, requesting it to
direct the Collector to make the
reference to it within a period of thirty
days.
(2) The application shall state the
grounds on which objection to the
award is taken:
Provided that every such application
shall be made-
(a) if the person making it was present
or represented before the Collector at
the time when he made his award,
within six weeks from the date of the
Collector's award;
(b) in other cases, within six weeks of
the receipt of the notice from the
Collector under section 21, or within
six months from the date of the
Collector's award, whichever period
shall first expire:
Provided further that the Collector may
entertain an application after the expiry
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-20-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
of the said period, within a further
period of one year, if he is satisfied that
there was sufficient cause for not filing
it within the period specified in the
first proviso.
30. From bare reading of the provisions of Section 18 of Act, 1894 and
Section 64 of Act, 2013, it appears that both the provisions are pari
materia except few changes and the material change is that earlier the
Collector was not having any authority to condone the delay and in the
new Act, 2013, second proviso has been added, whereby the Collector has
been extended the power to condone the delay up to one year, if he is
satisfied that there was sufficient cause for not filing it, within the period
specified in the first place.
31. In Section 18(2)(b) of Act, 1894, the words "the notice from the
Collector under Section 12 sub-section (2)" was mentioned, whereas in
Section 64(2)(b) of Act, 2013, it is mentioned as "notice from the Collector
under Section 21". The intention of the Legislature is that if a notice is
issued to the land loser intimating the information of passing of the award,

the limitation would start.
32. For understanding the intention of the Legislature to refer the notice
issued by the Collector in these provisions, it would be relevant to
reproduce the provisions of Section 12(2) of the Act, 1894 and Section
37(2) of the Act, 2013 in juxta position:
Section 12(2) of the Act, 1894 Section 37(2) of the Act, 2013
12(2). The Collector shall give
immediate notice of his award to such
of the persons interested as are not
present personally or by their
representatives when the award is
made.
37(2). The Collector shall give
immediate notice of his awards to such
of the persons interested who are not
present personally or through their
representatives when the awards are
made.
33. From bare reading of these two provisions and comparison of
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-21-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
Section 12(2) of the old Act with Section 37(2) of the new Act, it appears
that both the provisions are pari materia / identical and provides that
Collector shall give immediate notice of his award to such persons, those
are interested and not present personally or through their representatives,
when the award is made. This would be treated as intimation of award and,
therefore, the limitation would start from the intimation received by the
land loser and land loser may file the reference case within six weeks from
the receipt of the notice under Section 12(2) of the old Act or Section 37(2)
of the new Act. However, in the new Act, in place of "Section 37(2)",
"Section 21” has been mentioned. To consider the relevancy of Section 21,
it is essential to quote Section 21(1) of Act, 2013, which reads as under:
" 21. Notice to persons interested .–(1) The Collector shall publish
the public notice on his website and cause public notice to be given
at convenient places on or near the land to be taken, stating that the
Government intends to take possession of the land, and that claims
to compensations and rehabilitation and resettlement for all
interests in such land may be made to him."
34. From reading of Section 21(1) of Act, 2013, it appears that after the
publication of the public notice on the website and other convenient places
stating that the Government intends to take possession of the land and the
claims to compensation and rehabilitation and resettlement for all interest
in such land may be made to the Collector. Meaning thereby, the notice
under Section 21(1) ordinarily issued before passing the award and this
provision is pari materia to Section 9 of the old Act, 1894, which reads as
under:
" 9. Notice to persons interested . - (1) The Collector shall then
cause public notice to be given at convenient places on or near the
land to be taken, stating that the Government intends to take
possession of the land, and that claims to compensations for all
interests in such land may be made to him."
35. By no stretch of imagination, it can be accepted that the limitation
for filing a reference case would start from receipt of notice under Section
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-22-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
21 of Act, 2013, which is a notice giving intimation to the land losers that
Government is interested to acquire the land and settle the claims of the
compensation, rehabilitation, resettlement and all other interest in the land
and which is an notice to be issued before passing an award and, therefore,
has nothing to do with the limitation of filing of reference petition.
36. Considering the same, in view of this Court, in Section 64(2)(b) in
place of "Section 21" it ought to be "Section 37(2)" and, therefore, by
applying the rule of reading down the said clause, Section 64(2)(b) is read
down as under :
" 64(2)(b): in other cases, within six weeks of the receipt of the
notice from the Collector under section 37(2), or within six months
from the date of the Collector’s award, whichever period shall first
expire:
Provided further that the Collector may entertain an
application after the expiry of the said period, within a further
period of one year, if he is satisfied that there was sufficient cause
for not filing it within the period specified in the first proviso."
37. If we read this clause as mentioned hereinabove, it will give its full
meaning and will not be prejudicial to anyone either land losers or the
Land Acquisition Authority. Accordingly, this Court is of the view that the
word "Section 37(2)" should be read to calculate the limitation for filing
the reference petition under Section 64 of the Act, 2013.
38. If the provision 64(2)(b) of Act, 2013 would not be read down as
suggested hereinabove, the position would be that the Land Acquisition
Officer will pass the award in the absence of the land loser or his
representative and will not serve the notice of passing the award for a
period of more than 18 months and in that situation, in any case, the land
loser would not be entitled to file any reference petition and the award
passed by the Land Acquisition Authority would attained finality by
depriving the land losers to challenge the compensation assessed by the
Land Acquisition Officer before the Reference Court.
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-23-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
39. A holistic approach is required for interpreting the provisions and it
is a duty cast upon the Collector to issue notice of his award to the person
interested, who was not present personally or through representative when
the award is made. The purpose of issuance of notice is that the land loser,
who is having the right of property and protection under Article 300A of
the Constitution of India, in case of deprivation by acquisition, may take
appropriate action in accordance with the law.
40. In this context, the judgment delivered by the Supreme Court in the
matter of Parsottambhai Maganbhai Patel and others v/s State of Gujarat
and another, (2005) 7 SCC 431 is relevant, wherein the Supreme Court
has decided that the limitation under the latter part of the Section 18(2)(b)
of the Act, 1894 has to be computed having regard to the date, on which
the claimants got knowledge of the declaration of the award, either actual
or constructive and their application under Section 18 of the Act, 1894
within the period of limitation from the knowledge of the award, would be
maintainable. The relevant paragraph of the judgment reads as under:
" 6. Learned counsel for the appellants rightly placed reliance upon
the judgment of this Court in Raja Harish Chandra Raj Singh v. Dy.
Land Acquisition Officer and submitted that since the appellants
were not present when the award was made, and no notice was
given to them under Section 12(2) of the Act, the application for
making a reference under Section 18 of the Act must be held to be
within time if it is filed within six months of the date of knowledge
of the declaration of the award. In our view, the submission is
sound and must be accepted. This Court in Raja Harish Chandra
Raj Singh¹ was dealing with a case in which an award was declared
under the Act on 25-3-1951. No notice under Section 12(2) of the
Act was given to the claimants. It was only on 12-1-1953 that the
claimants came to know about the declaration of the award
whereafter they filed an application claiming a reference under
Section 18 of the Act on 24-2-1953. The High Court of Allahabad
held that the case fell under the latter part of clause (b) of the
proviso to Section 18 and since the application made by the
appellants before the Land Acquisition Officer for claiming a
reference under Section 18 was made beyond six months from the
date of the award in question, it was beyond time. This view of the
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-24-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
High Court was overruled by this Court and in doing so the Court
made the following pertinent observations: (SCR pp. 682-84)

"Therefore, if the award made by the Collector is in law
no more than an offer made on behalf of the Government to
the owner of the property then the making of the award as
properly understood must involve the communication of the
offer to the party concerned. That is the normal
requirement under the contract law and its applicability to
cases of award made under the Act cannot be reasonably
excluded. Thus considered the date of the award cannot be
determined solely by reference to the time when the award
is signed by the Collector or delivered by him in his office;
it must involve the consideration of the question as to when
it was known to the party concerned either actually or
constructively. If that be the true position then the literal
and mechanical construction of the words 'the date of the
award' occurring in the relevant section would not be
appropriate.

There is yet another point which leads to the same
conclusion. If the award is treated as an administrative
decision taken by the Collector in the matter of the
valuation of the property sought to be acquired it is clear
that the said decision ultimately affects the rights of the
owner of the property and in that sense, like all decisions
which affect persons, it is essentially fair and just that the
said decision should be communicated to the said party.
The knowledge of the party affected by such a decision,
either actual or constructive, is an essential element which
must be satisfied before the decision can be brought into
force. Thus considered the making of the award cannot
consist merely in the physical act of writing the award or
signing it or even filing it in the office of the Collector; it
must involve the communication of the said award to the
party concerned either actually or constructively. If the
award is pronounced in the presence of the party whose
rights are affected by it it can be said to be made when
pronounced. If the date for the pronouncement of the award
is communicated to the party and it is accordingly
pronounced on the date previously announced the award is
said to be communicated to the said party even if the said
party is not actually present on the date of its
pronouncement. Similarly if without notice of the date of its
pronouncement an award is pronounced and a party is not
present the award can be said to be made when it is
communicated to the party later. The knowledge of the
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-25-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
party affected by the award, either actual or constructive,
being an essential requirement of fair play and natural
justice the expression 'the date of the award' used in the
proviso must mean the date when the award is either
communicated to the party or is known by him either
actually or constructively. In our opinion, therefore, it
would be unreasonable to construe the words 'from the date
of the Collector's award' used in the proviso to Section 18
in a literal or mechanical way."

7. This Court, therefore, held that the limitation under the latter
part of Section 18(2)(b) of the Act has to be computed having
regard to the date on which the claimants got knowledge of the
declaration of the award either actual or constructive. This
principle, however, will apply only to cases where the applicant was
not present or represented when the award was made, or where no
notice under Section 12(2) was served upon him. It will also apply
to a case where the date for the pronouncement of the award is
communicated to the parties and it is accordingly pronounced on
the date previously announced by the Court, even if, the parties are
not actually present on the date of its pronouncement. Coming to
the facts of the instant case the High Court has not rejected the plea
of the appellants that they came to know of the award only when
compensation was being paid to them in July 1988. They had
admittedly no notice under Section 12(2) of the Act. They had
therefore filed the application under Section 18 of the Act on 22-9-
1988 well within the period of limitation. The Reference Court
recorded a finding in favour of the appellants but the High Court
has reversed that finding without applying the principle laid down
in Raja Harish Chandra.

Moreover, we find from the grounds of appeal filed before
the High Court that the assertion of the claimants that they came to
know of the declaration of the award only when compensation was
being paid to them in July 1988, has not even been challenged."
41. The Supreme Court in a celebrated case of Bhagwandas and others
(supra) , considered this issue in detail and after considering it reiterated
the law laid down by the Supreme Court in the matter of Parsottambhai
Maganbhai Patel and others (supra) , by holding that the words "within
six months from the date of Collector’s award" has to be read to mean "six
months from the date of actual or constructive knowledge of essential
contents of the award" and the expression is not to be interpreted literally,
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-26-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
because such an interpretation would lead to absurd results inasmuch as
person not having knowledge of award, would be deprived of opportunity
to seek reference to Court and the procedure would become unfair and
discriminatory and violative of Article 14 and 300A of the Constitution of
India. The Supreme Court has further held that the onus of proof would be
on the applicant to state on oath that he or his representative was not
present, when the award was made and he has not received any notice or
intimation of passing the award and not aware of contents of the award,
then the onus will shift on Collector to prove otherwise that the applicant
was having the actual or constructive knowledge of the passing of award.
The Supreme Court further held that the limitation period for making the
application for reference to the Court would be six months from the receipt
of the knowledge of the award. The relevant paragraph of the judgment
reads as under:
" 24 . When land is acquired and an award is made under Section 11
of the Act, the Collector becomes entitled to take possession of the
acquired land. The award being only an offer on behalf of the
Government, there is always a tendency on the part of the Collector
to be conservative in making the award, which results in less than
the market value being offered.

25 . Invariably, the land-loser is required to make an application
under Section 18 of the Act to get the market value as
compensation. The land-loser does not get a right to seek reference
to the civil court unless the award is made. This means that he can
make an application seeking reference only when he knows that an
award has been made.

26 . If the words six months from the "date of the Collector's award"
should be literally interpreted as referring to the date of the award
and not the date of knowledge of the award, it will lead to unjust
and absurd results. For example, the Collector may choose to make
an award but not to issue any notice under Section 12(2) of the Act,
either due to negligence or oversight or due to any ulterior reasons.
Or he may send a notice but may not bother to ensure that it is
served on the landowner as required under Section 45 of the Act. If
the words "date of the Collector's award" are literally interpreted,
the effect would be that on the expiry of six months from the date of
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-27-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
award, even though the claimant had no notice of the award, he
would lose the right to seek a reference. That will lead to arbitrary
and unreasonable discrimination between those who are notified of
the award and those who are not notified of the award.

27 . Unless the procedure under the Act is fair, reasonable and non-
discriminatory it will run the risk of being branded as being
violative of Article 14 as also sticle 300-A of the Constitution of
India. To avoid such consequences, the words "date of the
Collector's award" occurring in proviso (b) to Section 18 requires
to be read as referring to the date of knowledge of the essential
contents of the award, and not the actual date of the Collector's
award.

28 . The following position therefore emerges from the interpretation
of the proviso to Section 18 of the Act:

(i) If the award is made in the presence of the person
interested (or his authorised representative), he has to
make the application within six weeks from the date of the
Collector's award itself.
(ii) If the award is not made in the presence of the person
interested (or his authorised representative), he has to
make the application seeking reference within six weeks of
the receipt of the notice from the Collector under Section
12(2).
(iii) If the person interested (or his representative) was not
present when the award is made, and if he does not
receive the notice under Section 12(2) from the Collector,
he has to make the application within six months of the
date on which he actually or constructively came to know
about the contents of the award.
(iv) If a person interested receives a notice under Section
12(2) of the Act, after the expiry of six weeks from the date
of receipt of such notice, he cannot claim the benefit of the
provision for six months for making the application on the
ground that the date of receipt of notice under Section
12(2) of the Act was the date of knowledge of the contents
of the award.

29 . A person who fails to make an application for reference within
the time prescribed is not without remedy. It is open to him to make
an application under Section 28-A of the Act, on the basis of an
award of the court in respect of the other lands covered by the same
acquisition notification, if there is an increase. Be that as it may.

30 . When a person interested makes an application for reference
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-28-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
seeking the benefit of six months' period from the date of
knowledge, the initial onus is on him to prove that he (or his
representative) was not present when the award was made, that he
did not receive any notice under Section 12(2) of the Act, and that
he did not have the knowledge of the contents of the award during a
period of six months prior to the filing the application for reference.
This onus is discharged by asserting these facts on oath. He is not
expected to prove the negative. Once the initial onus is discharged
by the claimant/person interested, it is for the Land Acquisition
Collector to establish that the person interested was present either
in persy or through his representative when the award was made, or
that he had received a notice under Section 12(2) of the Act, or that
he had knowledge of the contents of the award.

31 . Actual or constructive knowledge of the contents of the award
can be established by the Collector by proving that the person
interested had received or drawn the compensation amount for the
acquired land, or had attested the mahazar/panchnama/
proceedings delivering possession of the acquired land in
pursuance of the acquisition, or had filed a case challenging the
award or had acknowledged the making of the award in any
document or in statement on oath or evidence. The person
interested, not being in possession of the acquired land and the
name of the State or its transferee being entered in the revenue
municipal records coupled with delay, can also lead to an inference
of constructive knowledge. In the absence of any such evidence by
the Collector, the claim of the person interested that he did not have
knowledge earlier will be accepted, unless there are compelling
circumstances not to do so."
42. The judgment delivered by the Supreme Court in the matter of
Bhagwandas and others (supra) was further relied by the Supreme Court
in the matter of Premji Nathu (supra) , wherein the Supreme Court has
held that even the knowledge of the award is not sufficient and the
limitation for filing reference application would start from receipt of the
copy of the award or the notice from the Collector under Section 12(2) of
the Act, 1894. The relevant paragraph reads as under:
" 21 . A careful reading of the averments contained in Para 2 of the
application filed by the appellant under Section 18(1) shows that
the notice issued by the Collector under Section 12(2) was served
upon him on 22-2-1985. Thereafter, his advocate obtained certified
copy of the award and filed application dated 8-4-1985 for making
a reference to the Court. This implies that the copy of the award
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-29-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
had not been sent to the appellant along with the notice and without
that he could not have effectively made an application for seeking
reference.

22 . On behalf of the State Government, no evidence was produced
before the Reference Court to show that the copy of the award was
sent to the appellant along with the notice. Unfortunately, while
deciding Issue 3, this aspect has been totally ignored by the
Reference Court which mechanically concluded that the application
filed on 8-4-1985 was beyond the time specified in Section 18(2)(b).
The learned Single Judge of the High Court also committed serious
error by approving the view taken by the Reference Court, albeit
without considering the fact that the notice issued by the Collector
under Section 12(2) was not accompanied by a copy of the award
which was essential for effective exercise of right vested in the
appellant to seek reference under Section 18(1)."
43. Though the counsel for the petitioner relied on several other
judgments of other High Courts to bolster his arguments, but in view of the
law laid down by the Supreme Court in the cases of Parsottambhai
Maganbhai Patel and others (supra) , Bhagwandas and others (supra)
and Premji Nathu (supra) , which are still holding the field, it is not
relevant to discuss the other judgments, as the position of law is clear that
as per the Supreme Court, the limitation for filing the reference case would
start from the date of knowledge of the award.
44. Consequently, the question (a) is answered by holding that the
word used "Section 21" in "Section 64(2)(b) of the Act, 2013" should
be read down as "Section 37(2)" and if the land loser or his
representative was not present at the time of passing the award and
Collector has not served any intimation or notice of passing of the
award as per Section 37(2) of the Act, 2013, the limitation for filing the
reference case will start from the date of knowledge of the award and
the land loser can file the reference petition within six months from the
date of knowledge of the award .

Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-30-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
Consideration of Question (b):
45. The Collector is authorized and empowered to take a decision upon
receipt of the reference petition from the land loser and if in the view of
the Collector, the petition is time barred, he may refuse to refer it to the
Reference Court. The act of the Collector to refer the reference petition to
the Reference Court is an executive act and if a Collector has referred the
reference petition to the Reference Court, it ought to have been decided on
merits and cannot be dismissed on the ground of maintainability and even
cannot be dismissed in default, because until and unless the Court will pass
the award in accordance with Section 69 & 70 of the Act, 2013, the
proceedings would not be terminated and passing of award is sine qua non
in the reference case.
46. An order would not be treated as an award, if it does not contain the
details of the land acquired, the market value of the land assessed by the
Land Acquisition Officer and details of all the heads and assessment of
total compensation. The award shall also include the assessment made by
the Reference Court regarding the correctness of the market value assessed
by the Land Acquisition Officer and if the compensation amount is
enhanced, all the details will be included in award. Until and unless all this
information is not available, the order will not be treated, as an award.
47. As per Section 70 of Act, 2013 (Section 26 of Act, 1894), the award
will be executable as decree of the Court. The Supreme Court, after
considering different views of High Courts, in the matter of Khazan Singh
(Dead) by Lrs. v/s Union of India, (2002) 2 SCC 242 held that the civil
Court is duty bound to pass an award in answer to the reference and even
in a case of non-participation by any party, the reference petition cannot be
dismissed for default. Meaning thereby, if a reference petition has been
referred to the Reference Court, the Reference Court cannot dismiss it on
any preliminary stage and is under an obligation to decide it on merits. The
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-31-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
relevant paragraph reads as under:
" 6 . Section 18 of the Act empowers a person interested in the land
to move by a written application to the Collector requiring that the
matter be referred for determination of the court, whether his
objection be to the measurement of the land, the amount of
compensation, the person to whom it is payable, or the
apportionment of the compensation among the persons interested.
If the application for reference is in order the Collector is bound to
make a reference of it to the court. Section 20 of the Act enjoins on
the court to "proceed to determine the objection". The court shall
after holding such inquiry as may be necessary pass an award.
Section 26 of the Act reads thus: "26. Form of Awards. (1) Every
award under this Part shall be in writing signed by the Judge, and
shall specify the amount awarded under clause first of sub-section
(1) of Section 23, and also the amounts (if any) respectively
awarded under each of the other clauses of the same sub-section,
together with the grounds of awarding each of the said amounts.
(2) Every such award shall be deemed to be a decree and the
statement of the grounds of every such award a judgment within the
meaning of Section 2 clause (2) and Section 2 clause (9),
respectively, of the Code of Civil Procedure, 1908."

7 . The provisions above subsumed Would thus make it clear that the
civil court has to pass an award in answer to the reference made by
the Collector under Section 18 of the Act. If any party to whom
notice has been served by the civil court did not participate in the
inquiry it would only be at his risk because an award would be
passed perhaps to the detriment of the party concerned. But non-
participation of any party would not confer jurisdiction on the civil
court to dismiss the reference for default.

8 . It appears that various High Courts have taken the aforesaid
view in a number of decisions: Abdul Karim v. State of M.P.,
Bhadar Munda v. Dhuchua Oraon², Shyam Shankar Sahai v. State
of Bihar, Joseph v. Govt. of Kerala and Jogi Sahu v. Collectors.

9 . In Joseph v. Govt. of Kerala Paripoornan, J. (as he then was)
speaking for a Division Bench has made reference to two earlier
decisions of Single Judges, one by the same High Court and the
other by the Karnataka High Court which held the same view."
48. The judgment delivered by the Supreme Court has been relied by the
Division Bench of Bombay High Court in the matter of Diwakar
Prabhakar Chopade (supra) , wherein the Division Bench of the Bombay
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-32-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
High Court has held that the reference petition is required to be decided on
merits and an order otherwise on merits cannot be treated as an award
under Section 26(2) of the Act, 1894.
49. In view of the above, the question (b) is answered by holding
that if a reference petition is referred by the Collector to the Reference
Court under the provisions of Section 18 of the Act, 1984 or Section 64
of the Act, 2013, the Civil Court / Reference Court is duty bound to
decide the same on merits and cannot reject the same at any
preliminary stage without deciding on the merits.
Consideration on Question (c):
50. The respondent No. 3 has raised the issue of maintainability of civil
revision and submits that Civil Revision under Section 115 of the Code of
Civil Procedure would not lie against the rejection of a reference case and
the order of rejection of reference petition, amounts to an award under
Section 70 of Act, 2013 and, therefore, the only remedy available to the
petitioner is to file an appeal under Section 74 of the Act, 2013. He relied
on the judgment delivered by the Coordinate Bench in the matter of
Jagdish (supra) and the judgments delivered by the Bombay High Court
in the mater of Venkat Baburao Karle (supra) , Chandu (supra) and
Diwakar Prabhakar Chopade (supra) and submits that the revision
petition would not be maintainable.
51. Counsel for the petitioner relied on the judgment delivered by the
Coordinate Bench in the matter of Somli (supra), which has been relied by
other Coordinate Benches also. When the judgments of the High Court of
M.P. are available, there is no occasion for this Court to look into the
judgments delivered by the Bombay High Court for the purpose of
deciding the issue, because the judgment delivered by the Coordinate
Benches are binding on this Court and as per the Doctrine of Stare Decisis ,
this Court cannot ignore the judgments passed by the Coordinate Benches.
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-33-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
The Coordinate Bench has decided the issue in Somli (supra) and held that
the civil revision petition will be maintainable. The order passed by
another Coordinate Bench in the matter of Jagdish (supra) relied by the
counsel for the respondent No. 3 is having no authoritative value in view
of the Doctrine of Stare Decisis , as at the time of passing the order in the
matter of Jagdish (supra) , the Coordinate Bench has not considered and
referred the earlier judgment passed by a Bench of similar strength in
Somli (supra) and, therefore, in view of this Court, the subsequent
judgment passed taking contrary view is per incuriam .
52. A Special Bench of this Court in the case of Jabalpur Bus
Operators Association v/s State of M.P. and others, 2003 (1) MPLJ 513
has held that in case of a conflict between decisions of Courts comprising
equal number of Judges, decision of earlier Bench is binding. Therefore,
the ratio laid down by a co-ordinate bench in the matter of Jagdish (supra)
cannot be relied on and the judgment delivered in the matter of Somli
(supra) holds the field.
53. Consequently, question (c) is answered by holding that Civil
Revision Petition under Section 115 of the CPC is maintainable,
impugning order of rejection of the reference petition under Order VII
Rule 11 of CPC by the Reference Court.
Conclusion:
54. In view of above conspectus, this Court records the following
conclusion: -
(a) The word used "Section 21" in "Section 64(2)(b) of the Act,
2013" should be read down as "Section 37(2)" and if the land
loser or his representative was not present at the time of
passing the award and Collector has not served any intimation
or notice of passing of the award as per Section 37(2) of the
Act, 2013, the limitation for filing the reference case will start
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026
10:48:56

-34-
NEUTRAL CITATION NO. 2026:MPHC-IND:27950


CR-997-2026
from the date of knowledge of the award and the land loser
can file the reference petition within six months from the date
of knowledge of the award.
(b) If a reference petition is referred by the Collector to the
Reference Court under the provisions of Section 18 of the Act,
1984 or Section 64 of the Act, 2013, the Civil Court /
Reference Court is duty bound to decide the same on merits
and cannot reject the same at any preliminary stage without
deciding on the merits.
(c) Civil Revision Petition under Section 115 of the CPC is
maintainable, impugning order of rejection of the reference
petition under Order VII Rule 11 of CPC by the Reference
Court.
(d) Impugned orders passed by the Reference Court rejecting the
reference petitions as time barred are not sustainable and are
hereby set aside and the matters are remanded to the
Reference Court to decide the reference cases on merits in
accordance with law after affording the opportunity of hearing
to the parties.
(e) All the present Civil Revision Petitions are allowed in above
terms. No order as to costs.
55. Let a copy of this order be kept in the record of all the connected
Civil Revision Petitions.

( VINAY SARAF )

JUDGE
Divyansh
Signature Not Verified
Signed by: DIVYANSH
SHUKLA
Signing time: 05-10-2026