M/S Sarvpriya Securities Pvt Ltd vs M/S Ank Hotels Pvt Ltd

Court
Delhi High Court

* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 11.05.2026
Judgment pronounced on: 18.05.2026

+ O.M.P. (COMM) 432/2023
M/S SARVPRIYA SECURITIES PVT LTD .....Petitioner
Through: Mr. Ashish Aggarwal, Mr. O.P.
Faizi, Mr. Anand Aggarwal,
Mr. Madhur Sapra, Ms. Nishtha
Verma, Ms. Lisha Arora, Mr.
Himanshu Singh, Ms. Anjali
Kashyap & Ms. Ishita, Advs.
versus
M/S ANK HOTELS PVT LTD .....Respondent
Through: Mr. Manu Bajaj & Ms. Parul,
Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. This petition is filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) seeking setting aside of
the arbitral award dated 01.07.2023 (for brevity „the award‟).
2. The relevant facts are that the petitioner is engaged in business
of developing real estate projects. In the year 2017 petitioner was
developing Signature Global Mall (for short „the Mall‟) in Ghaziabad,
Uttar Pradesh under its own brand name. The parties to the lis entered
into a Memorandum of Understanding (MoU) dated 18.05.2018
whereby the respondent agreed to operate and maintain service
rd th
apartments/hotels at 3 to 6 floor of the Mall under the name of
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 1 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

„Clark Premier‟.
2.1 In terms of clause 14 of the MoU, the petitioner had to pay a
sum of Rs.50,00,000/- plus GST after deduction of TDS towards one
time brand collaboration fee and an amount of Rs.50,00,000/- towards
technical support fee. The respondent was entitled to an additional
amount of Rs.1,70,00,000/- (rupees one-crore seventy lakhs) plus GST
towards administrative marketing of the property, operational and pre-
opening expenses to commence service apartment/hotel operation,
within a period of six to eight months from the date of signing of the
MoU. As per Clause 20 of the MoU, the prior discussions between the
parties were agreed to be merged in the MoU and no further
modification would be effected unless mutually agreed between the
parties in writing.
2.2 The respondent through emails dated 08.08.2018 and
18.11.2018 sought additional space beyond what was initially agreed
between the parties. The request was denied by the petitioner through
communications dated 10.08.2018 and 01.12.2018. Thereafter, the
respondent sent three emails in December, 2018 agreeing to the denial
for the additional space. Meeting was held between the parties on
18.12.2018 and on 08.02.2019, the petitioner sent an email attaching
undertaking for mutual termination of the MoU.
2.3 Thereafter in September, 2019 the petitioner demanded a refund
of Rs.1,18,00,000/- (rupees one-crore eighteen lakhs) paid as advance.
The respondent vide communication dated 21.09.2019, declined the
refund and instead demanded payment of the balance amount of
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 2 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

Rs.1,70,00,000/- (rupees one-crore seventy lakhs).
2.4 Dispute arose between the parties and arbitration was invoked
at the instance of the respondent by issuing notice dated 09.01.2020.
The arbitrator was appointed by this court on 30.11.2021 and the
arbitral proceedings culminated in the impugned award. The claim of
the respondent of rupees one-crore seventy lakhs was rejected and the
counter-claim of the petitioner seeking refund of rupees one-crore
eighteen lakhs was also dismissed.
3. Learned counsel for the petitioner contends that the award is
non-speaking and suffers from patent illegality. The arbitrator erred in
concluding that the advance paid by the petitioner was not subject to
incurring of expenses.
3.1 The submission is that the MoU contained no clause for
forfeiture of the advance paid and that the sums paid were not earnest
money.
3.2 Reliance is placed upon the decisions of the Supreme Court in
Kailash Nath Associates v. DDA & Anr. 2015 4 SCC 136, Union of
India v. Rampur Distillery & Chemical Co. Ltd. AIR 1973 SC 1098,
Rajesh Gupta v. Ram Avtar 2022 SCC OnLine Del 1482, Amrit Pal
Singh v. Kawaljeet Singh 2022 SCC OnLine 1619, ONGC v. Saw
Pipes Ltd . (2003) 5 SCC 705 and Patel Engineering Ltd. v. North
Eastern Electric Power Corporation Ltd. (2020) 7 SCC 167 to
contend that for awarding of damages or for forfeiture of the amounts,
breach of terms of the MoU and the actual loss suffered by the
respondent had to be proved.
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 3 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

3.3 The argument is that retention of advance was not justified as
neither the brand name of the respondent was used nor the respondent
suffered actual damage.
4. Per contra, the scope of interference under Section 34 of the
Act is limited. Reliance is placed upon the decisions of the Supreme
Court in Delhi Airport Metro Express (P) Ltd. v. DMRC 2022 (1) SCC
131 and Reliance Infrastructure Ltd. v. State of Goa 2024 (1) SCC
479. The arbitral award cannot be interfered for another possible view
and that re-appreciation of evidence is impermissible under Section 34
of the Act. The submission is that the impugned award is not vitiated
with perversity.
4.1 It is emphasized that the MoU contained no clause obligating
the respondent to refund the advance received. It is canvassed that the
respondent successfully proved usage of the brand name by the
petitioner and that the respondent provided technical support service
to the petitioner. It is further submitted that rupees fifty lakh amount
paid was towards brand collaboration fee and was not dependant on
the actual usage of the brand name.
4.2 It is argued that the MoU does not provide for refund of the
advance. Further that the present case does not pertain to awarding of
damages and the judgments relied upon by the petitioner are not
applicable.
5. Heard the learned counsel for the parties at length. No other
issues than the ones noted above were pressed during the course of
hearing.
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 4 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

6. Before proceeding further, it would be apposite to reproduce
clauses 1, 3, 14 and 16 of the MoU.
“ 1 . Project
The Developer/First Party is in process of developing
Service Apartments/Hotel consisting of 80 (Eighty)
Rooms, Restaurant having 60 Covers, Bar having 40
Covers, Gym, Spa, Swimming Pool, Banquet area approx
10000 Sqft & Open Terrace space of about 4000 to 4500
Sqft to the Second Party.
3. Brand
The Service Apartments/Hotel shall be branded as:
“ Clarks Premier ” or any other brand name as per the
discretion of the Second Party.
14. Payment to the Second Party
Rs.50,00,000/- (Rupees Fifty Lakhs Only) plus GST &
less TDS as applicable as Brand Fee's payable at the time
of Signing of This MOU paid via cheque number 000113
dated 18/05/2018 drawn on HDFC Bank, KG Marg New
Delhi
Rs.50,00,000/- (Rupees Fifty Lakhs Only) plus GST &
less TDS as applicable as Technical support and
Promotional activities charges payable at the time of
signing of this MOU paid via cheque number
_________dated drawn on________
Second Party shall be entitled to utilize an additional
amount of Rs.1,70,00,000/- (Rupees One Crore Seventy
Lakhs Only) plus GST & less TDS as applicable towards
administrative, marketing of the property, operational and
pre-opening expenses to commence the Service
Apartments/Hotel Operation. Such aforestated pre-
opening amount shall be borne by the Developer/First
Party. This aforestated amount shall be paid by the First
Party to Second Party within 6-8 months from the date of
signing this MOU.
Apart from above the First Party/Developer shall arrange
the Procurement of Vehicles & Miscellaneous equipment
to the tune of Rs 45 Lacs. The details are annexed in
Annexure-1
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 5 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

16. Hand Over Date
Developer/First Party shall handover the fully furnished
Service Apartments/Hotel on or before 2 years from the
date of execution of this MOU. Developer/First Party shall
inform to the Second Party at least three months before it
intention to the handover so that Second Party shall be
able to start Service Apartments/Hotel marketing and trial
run.”
rd th
7. As per the MoU the petitioner shall give 3 to 6 floor of the
Mall to the respondent for management and operation of the service
apartment/hotel comprising of eighty rooms, restaurants, bar, gyms,
SPA, swimming pools, banquet area and open terrace. The hotel was
to operate under the brand name of the respondent. The fully furnished
hotel was to be handed over on or before two years from the date of
execution of the MoU. The service apartment/hotel was initially for a
term of thirty years from the date of commencement of the operation
along with amenities and there was lock-in period of twenty years
after commencement of the operation.
8. The arbitrator dealt with the issue of breach of the MoU. It was
considered that the respondent caused delay by repeatedly demanding
additional space beyond the terms of the MoU. It was factored that
there was no document produced whereby the parties mutually agreed
to terminate the MoU. The petitioner sent an email dated 08.02.2019
attaching an undertaking for mutual termination and started
advertising the floor in issue in MoU as office space. The conclusion
was that none of the parties adhered to the terms and conditions as
stipulated in the MoU. It was observed that within three months of
execution of the MoU, the respondent started demanding additional
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 6 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

space which continued up to December, 2018 and thereafter neither
any work was done nor did any meeting take place between the
parties. The claim of the respondent for the payment of rupees one-
crore seventy lakhs was rejected.
9. The counter-claim of the petitioner for refund of rupees one-
crore eighteen lakhs was rejected holding that there was no clause in
the MoU that the payments made were subject to the respondent
incurring expenses.
10. Before dealing with the merits of the issue, it is of utmost
importance that Section 31(3) of the Act mandates a reasoned award.
The law is well settled that the requirement of Section 31(3) of the Act
is not a mere formality. The reasoning in an appropriate case can be
implied upon a fair reading of the award and the documents referred to
therein. Reference in this regard be made to the following decisions of
the Supreme Court :-
10.1 In Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd.
(2019) 20 SCC 1 it was held as under:
“34. The mandate under Section 31(3) of the
Arbitration Act is to have reasoning which is
intelligible and adequate and, which can in appropriate
cases be even implied by the courts from a fair reading
of the award and documents referred to thereunder, if
the need be. The aforesaid provision does not require
an elaborate judgment to be passed by the arbitrators
having regard to the speedy resolution of dispute.”
10.2 In Som Datt Builders Ltd. v. State of Kerala (2009) 10 SCC
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 7 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

259 it was held as follows:
“25. The requirement of reasons in support of the award
under Section 31(3) is not an empty formality. It
guarantees fair and legitimate consideration of the
controversy by the Arbitral Tribunal. It is true that the
Arbitral Tribunal is not expected to write a judgment
like a court nor is it expected to give elaborate and
detailed reasons in support of its finding(s) but mere
noticing the submissions of the parties or reference to
documents is no substitute for reasons which the
Arbitral Tribunal is obliged to give......”
(emphasis supplied)
11. A perusal of the impugned award reveals that after adjudicating
the issue of breach of terms of the MoU, the contentions of both the
parties were noted and the counter-claim was rejected by stating that
the submission of the respondent carried force and there existed no
clause in the MoU stipulating that the payments made were subject to
incurring of expenses. The issues requiring determination before the
arbitrator were:- (i) whether the MoU contained clause for forfeiture
of the advance amount paid; (ii) whether there is clause for refund of
the amount received and most importantly (iii) whether the respondent
was legally entitled to retain the advance amounts after the breach of
the MoU. Rejection of the counter-claim of the petitioner is bereft of
reasons. The impugned award contains no discussion or reasoning on
the aforesaid aspects and is non-speaking and unreasoned. The award
dismissing the counter-claim is liable to be set aside on this ground

alone.

12. The contention of learned counsel for the respondent that there
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 8 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

was no clause for refund of advance amount is of no avail. It is not
disputed that there was no clause for forfeiture and in such
circumstances the settled principles for invoking Section 73 of the
Indian Contract Act, 1872 (for short „the Contract Act) are to be
applied. The judgment relied upon by learned counsel for the
petitioner are for the proposition that the twin condition for award of
damages encapsulated that firstly, there has to be breach of the
contract and secondly, the party suffering actual loss or damage for
the breach of the contract has to be compensated for the actual damage
or loss suffered. The only exception being the cases where it is not
possible to proof actual loss or damages suffered. These principles
would equally apply to the advance payment received and when there
is no clause agreed between the parties for forfeiture of the payment
received.
12.1 The Supreme Court in Central Bank of India v.
Shanmugavelu , (2024) 6 SCC 641 held:
“88. The observations of Mellish, L.J., in Ex parte
Barrell [ Ex parte Barrell , (1875) LR 10 Ch App 512]
assume importance. The learned Judge observed that
even when there is no clause in the contract as to the
forfeiture of the deposit if the purchaser repudiates the
contract, he cannot have back the money if it was a
deposit, as the contract has gone off through his
default. It is characteristic of a deposit to entail
forfeiture if the depositor commits breach of his
obligation. On the contrary it is inherent in a part-
payment of price in advance that it should be returned
to the buyer if the sale does not fructify. The buyer is
not disentitled to recover, even if he is the party in
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 9 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

breach, because breach of contract on the part of the
buyer would only entitle the seller to sue for damages
but not to forfeit the advance. A specific forfeiture
clause might operate to defeat the buyer's right of
recovery of even an advance payment. But equity
might step in to relieve the buyer from forfeiture. If the
amount forfeited cannot stand the test of a genuine pre-
estimate of damages, it would be unconscionable for
the seller to retain it. The question whether the amount
is a deposit (earnest) or a part-payment cannot be
determined by the presence or absence of a forfeiture
clause. Whether the sum in question is a deposit to
ensure due performance of the contract or not is not
dependent on the phraseology adopted by the parties or
by the presence or otherwise of a forfeiture clause. The
proportion the amount bears to the total sale price, the
need to take a deposit intended to act in terrorem , the
nature of the contract and other circumstances which
cannot be exhaustively listed have to be taken into
account in ascertaining the true nature of the amount.
In essence the question is one of proper interpretation
of the terms of a contract.”

12.2 The division bench of Kerala High Court in Varkey Thomas v.

G. Vijayendra Kurup, 2017 SCC OnLine Ker 100 held:-
“12. The penalty of forfeiture of the amount paid as
advance in Ext.A1 agreement in terms of Section 74 is
subject to the reasonable compensation to be awarded
under Section 73 of the Contract Act, 1872. The
defendants are not liable to be compensated in the
absence of proof of legal injury and therefore there
cannot be a forfeiture of the amount paid as advance by
the plaintiff.
13. The court below erred in holding that the plaintiff
has to forfeit the amount paid as advance even in the
absence of proof of damages sustained by the
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 10 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

defendants. The court below has blindly acted on the
terms of Ext.A1 agreement without reference to
Sections 73 and 74 of the Contract Act, 1872.......”
(emphasis supplied)
13. It is not the case set up by the respondent that actual loss or
damage was suffered or it was not possible to prove the actual loss or
damage suffered. The defence is that there is no clause for the refund
of the money. The arbitrator committed patent illegality in not
proceeding in accordance with Section 73 of the Contract Act. The
project was a non-starter. The MoU from the initial stage faced rough
weather and from the beginning the respondent insisted for the
additional space than the one stipulated in the MoU. None of the
parties adhered to the terms of the MoU and this finding recorded by
the arbitrator is not under challenge, the natural consequence is that
breach of contract by one of the parties is not proved. There is no
finding recorded of proportionate role of each of the parties in breach
of the terms and conditions. The foundation to proceed under Section

73 of the Contract Act is missing.
14. The contention that the respondent proved the utilisation of
brand name by the petitioner and technical support provided is
factually ill-founded. There is no evidence on record that the brand
name was ever used by the petitioner. The brand name was not to be
used for the Mall but for the hotel to be maintained and made
operational by the respondent, and which never saw the light of the
day. The contention that the respondent provided technical support is
contrary to the unchallenged findings recorded by the arbitrator.
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 11 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

Arbitrator held that after denial of additional space neither any

meeting took place between the parties nor any work was done.
15. The matter needs to be considered from another angle that on
the one hand, the claim of the respondent was rejected for the reason
that the project was a non-starter and no work was done and on the
other hand the counter-claim of the petitioner for refund of advance
money was rejected in spite of the fact that neither there was technical

support granted nor the brand name was used.
16. There is no quarrel with the proposition proposed by the learned
counsel for the respondent vis-a-vis the scope of interference under
Section 34 of the Act and authorities of Delhi Airport Metro Express
(P) Ltd. (supra) and Reliance Infrastructure Ltd. (supra) are relied in

support thereof.
17. The dismissal of the counter-claim is in violation of Section 73
of the Contract Act and is against the public policy. Moreover, the
dismissal by non-reasoned award falls within the teeth of Section

31(3) of the Act and is liable to be set aside.
17.1 The Supreme Court in Gayatri Balasamy v. ISG Novasoft
Technologies Ltd ., (2025) 7 SCC 1 held that while an arbitral award
cannot be modified under Section 34 of the Act, a severable part of the

award may be set aside. The relevant paragraphs are quoted below:
“32. In the present controversy, the proviso to Section
34(2)(a)(iv) is particularly relevant. It states that if the
decisions on matters submitted to arbitration can be
separated from those not submitted, only that part of the
arbitral award which contains decisions on matters non-
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 12 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

submitted may be set aside. The proviso, therefore,
permits courts to sever the non-arbitrable portions of an
award from arbitrable ones. This serves a twofold
purpose. First, it aligns with Section 16 of the 1996 Act,
which affirms the principle of kompetenz- kompetenz ,
that is, the arbitrators' competence to determine their
own jurisdiction. Secondly, it enables the Court to sever
and preserve the “valid” part(s) of the award while
setting aside the “invalid” ones. [The “validity” and
“invalidity”, as used here, does not refer to legal validity
or merits examination, but validity in terms of the
proviso to Section 34(2)(a)(iv) of the 1996 Act.] Indeed,
before us, none of the parties have argued that the Court
is not empowered to undertake such a segregation.
33. We hold that the power conferred under the proviso
to Section 34(2)(a)(iv) is clarificatory in nature. The
authority to sever the “invalid” portion of an arbitral
award from the “valid” portion, while remaining within
the narrow confines of Section 34, is inherent in the
Court's jurisdiction when setting aside an award.
34. To this extent, the doctrine of omne majus continet
in se minus —the greater power includes the lesser—
applies squarely. The authority to set aside an arbitral
award necessarily encompasses the power to set it aside
in part, rather than in its entirety. This interpretation is
practical and pragmatic. It would be incongruous to hold
that power to set aside would only mean power to set
aside the award in its entirety and not in part. A contrary
interpretation would not only be inconsistent with the
statutory framework but may also result in valid
determinations being unnecessarily nullified.”
(emphasis supplied)
18. The dismissal of counter-claim of the petitioner by a non-
reasoned award in violation of Section 73 of the Contract Act is

severable, not dependent or intricately connected on other claims.
Signature Not Verified
O.M.P. (COMM) 432/2023 Page 13 of 14
Signed By:CHANCHAL
Signing Date:18.05.2026
13:11:08

19. The petition is allowed. The award is set aside to the extent of
dismissal of the counter-claim of the petitioner for refund of advance

amount.
AVNEESH JHINGAN, J
MAY 18, 2026
Ch