M/S Bansal Construction Co. vs Union Of India

Court
Delhi High Court

* IN THE HIGH COURT OF DELHI AT NEW DELHI

% Judgment reserved on : 04.05.2026
Judgment delivered on : 15.07.2026
Judgment uploaded on : As per Digital Signature

+ FAO (COMM) 24/2022 & CM APPL. 6369/2022

M/S BANSAL CONSTRUCTION CO. ..... APPELLANT

versus

UNION OF INDIA ..... RESPONDENT

Advocates who appeared in this case

For the Appellant : Mr. S W Haider and Ms Pooja Dua,
Advocates.
For the Respondent : Ms. Pratima N Lakra, CGSC, Mr.
Shailendra Kumar Mishra and Ms. Upanita
Soumyadarshni, Advocates.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
JUDGMENT
V. KAMESWAR RAO, J.

1. This appeal has been filed challenging the judgment dated
30.07.2021 passed by the learned District Judge/Commercial Court-03,
Patiala House Court, New Delhi in O.M.P (COMM.) 19/2019, filed under
Section 34 of Arbitration & Conciliation Act, 1996 (‘the Act’, for short)
with the following prayers: -
“i. allow the present appeal and set aside the impugned


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 1 of 34

Order dated 30.07.2021 passed by the Ld. Judge in O.M.P
(COMM.) 19 of 2019 and restore the arbitration award
dated 26.09.2018 passed by the Ld. Arbitral Tribunal.
ii. call for the complete records for the adjudication of the
present appeal.”
2. The facts as noted from the record are that the work pertaining to
“ CTR(S) of 15.75 km of non circulated yard lines in the section of DSE-
III/NDLS” was awarded to appellant vide an acceptance letter dated
04.08.2004 by a competent authority of the respondent and the date of
completion of work was 6 months i.e., by 03.02.2005.
3. The case of the appellant is that the appellant made all the
arrangements for execution of the work but work could not be completed
by 03.02.2005 due to failure on the part of the respondent. Consequently,
the time period was extended upto 30.09.2007 and admittedly all extensions
were given without penalty under Clause 17 A of General Conditions of
Contract, 1999, (GCC). However, even then, the work could not be
completed because for the reason solely attributable to the respondent as the
P-Way materials required for execution of work were not provided by the
respondent. Being severely beset with the situation, the appellant requested
for closure of contract on administrative ground and to save itself from
further loss. The respondent upon receipt of the said letter, issued a letter
dated 07.08.2009 after 5 months, asking the appellant to re-start the work.
The appellant vide its letter dated 19.09.2009, stated its incapability to
execute the work as the agreed rates then had become unworkable.
4. The respondent issued notice dated 30.09.2009, which was opposed
by the appellant. The respondent did not take any action either by


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 2 of 34

terminating the contract or by foreclosing the contract, despite the appellant
again furnishing ‘no claim’ and requesting for foreclosure vide letter dated
04.01.2012. Despite lapse of considerable time, the respondent did not pay
the dues of the appellant.
5. The appellant vide letter dated 17.03.2015 invoked the arbitration
clause under the GCC by writing a letter to Northern Railway, whereby the
claimant claimed total of six claims to the tune of ₹9,50,000/-. The said
invocation letter was also followed by reminder letter dated 22.08.2016,
however the claimant enhanced its claims for previous six claims to eight
claims for an amount of ₹32,77,600/- and again another letter dated
07.02.20l7 sent to the railways by the claimant, wherein the claimant again
claimed total of six claims amounting to ₹13,92,083/-. The respondent
appointed an arbitrator to adjudicate the disputes between the parties.
6. The Arbitral Tribunal (‘Tribunal’) passed the Arbitral Award
(‘Award’) on 26.09.2018. The learned Tribunal in the Award allowed 7 out
of 8 claims of the appellant and directed the respondent to pay the appellant
to the tune of ₹22,44,464/- within six weeks failing which interest at 18%
per annum will be applicable. The claims of the appellant before the learned
Tribunal and the amount awarded by the learned Tribunal are reproduced in
a tabular format:-
Claim
Description of claim Amount
claimed (₹)
Amount
Awarded
No.
(₹)
1 Towards since forced to seek the
arbitration because of inability of
the department to take a rationale
and a practical decision entitled for
1,00,000/- 1,00,000/-


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 3 of 34

cost
2 Towards the amount of final bill
prepared, but not paid
4,08,561/- 3,66,596/-
3 Towards EMD/SD money deducted
in running account bills, but not
paid
1,00,000/- 35,600/-
4 Towards extra expenditure incurred
on maintaining regular staff, T & P
machinery etc during the
prolongation of contract on account
of the inability of the department to
provide P-way material
10,54,454/- 7,02,000/-
5 Towards interest on payment held
up for amounting to₹2,92,000/-
held up due to not sanction ing
corrigendum / addendum and
holding of ₹ 1 , 00 ,000/- on
account of security money for
47.5 months @ 18% pa on
total amount ₹3,92,000/-
3,92,000/- 3,35,160/-
6 1,00,000/- Nil
Towards legal expenses
7
Towards execution of work
for ₹11,25,000/- only against
the contract value for
₹22,09,080/- hence this claim
10% of remaining value of left
over work, i.e., on
₹10,84,080/- not executed due
to administrative reasons
1,08,408/- 1,08,408/-
8
Claim interest @24% per
annum @12% per annum on
the amount awarded against
claim no.4
7,04,130/- 5,96,700/-
Tota amount awarded 22,44,464/-

7. Against the Award, the respondent filed a petition under Section 34
of the Act. The learned District Judge vides the impugned judgment
partially allowed the petition by setting aside the claim Nos.1, 4,5,7 & 8


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 4 of 34

and modified the post award interest from 18 % to 12 % per annum.
8. Aggrieved by the same, the appellant has filed the present appeal.
SUBMISSIONS OF THE APPELLANT
9. Mr. S W Haider, the learned counsel appearing for the appellant
submitted that the learned District Judge erred in modifying the interest
from 18% to 12%. He submitted that, it is settled law as rendered by
Supreme Court in Larsen Air Conditioning and Refrigeration Company v.
Union of India (UOI) and Ors.: MANU/SC/0876/2023 , wherein, the
Supreme Court has set aside the order passed by the High Court interfering
and modifying the rate of interest as awarded and restoring the same. He
also submitted that the Supreme Court has reiterated the scope of
interference by Court under Section 34 of the Act, holding that the court
has no power to modify an arbitral award. He has also relied on the
judgment of this Court in the case of M/s Pradeep Vinod Construction Co.
v. Union of India, 2022:DHC:3616-DB , to contend that modification is
impermissible.
10. He submitted that the learned District Judge failed to appreciate the
settled legal position in the case titled Himachal Joint Venture v.
Panilpina World Transport India P Ltd, 2008:DHC:2304-DB of this
Court, wherein, it is held that 10% profit is a reasonable basis, to be
granted, and could not have been set aside by the learned District Judge.
11. He submitted that this Court in Himachal Joint Venture v.
Panilpina World Transport (India) (supra) , has held that, in a case where


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 5 of 34

a party is successful in establishing the breach then the party who suffered
on account of the said breach must be compensated for the business loss it
suffered. He also submitted that the learned Tribunal has indeed examined
the case in detail before rendering the award and thus, the same ought not to
have been interfered by the learned District Judge.
12. According to him, the impugned judgment despite mentioning the
judgment passed by this Court in the case of the Simplex Concrete Piles
(India) Ltd. v. Union of India: MANU/DE/4538/2010 , failed to appreciate
and apply the same. In the said case, this Court held that, contractual
clauses even if restrictive cannot prevent an arbitrator from awarding
damages or losses, that a party is otherwise entitled to. He also submitted
that the scope of Section 34 of the Act is limited and that the learned
District Judge has re-appreciated the evidence and the terms of the contract
between the parties, which is beyond the scope of Section 34 of the Act.
13. According to Mr. Haider, to the best of the knowledge of the
appellant, “ Special Tender Conditions and Instructions to tenderer ” were
not part of the arbitral record. Despite this, in paragraph 20 of the impugned
judgment, the learned District Judge reproduced a clause of “ Special
Tender Conditions and Instructions to tenderer ” without indicating from
where they were taken from. The appellant objected to the filing of new
documents in a petition under Section 34 of the Act, as noted by the learned
District Judge in paragraph 11 of the impugned judgment. Hence, the
learned District Judge went beyond its authority by considering documents
that were not part of the arbitral record.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 6 of 34

14. He submitted that the learned Tribunal has correctly relied upon
Clause 36(2) of the GCC to allow Claim No.4, whereas, the learned District
Judge erred in not appreciating the effect of the said clause. He also
submitted that, despite the learned District Judge noting the fact that the
respondent had failed to provide the required P-Way materials resulting in
the delay in executing the work, attributable to the respondent, has
erroneously set aside the award on certain claims.
15. He has relied upon the following judgments in support of his
submissions: -
a) Canara Nidhi Limited v. M. Shashikala and Ors.,
MANU/SC/1304/2019,
b) Ssangyong Engineering and Construction Co. Ltd. v. National
Highways Authority of India (NHAI): MANU/SC/0705/2019,
c) National Highways Authority of India v. M. Hakeem and Ors.,
MANU/SC/0461/2021,
d) Renusagar Power Co. Ltd. v. General Electric Co.,
MANU/SC/0195/199,
e) Venture Global Engineering LLC and Ors. v. Tech Mahindra Ltd.
and Ors., MANU/SC/1373/2017

f) Union of India (Ministry of Railways) & Others v. M/s. J. Sons
Engineering Corporation Limited & Another, 2015:DHC:3350.
16. He sought prayers as made in the appeal.
SUBMISSIONS OF THE RESPONDENT
17. Ms. Pratima N Lakra, Central Government Standing Counsel would
submit that, an appeal under Section 37 of the Act has a very limited scope


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 7 of 34

and this appeal clearly falls outside the purview of Section 37 of the Act.
18. She submitted that this Court in UBV Infrastructure Ltd. v. National
Highways Authority of India, 2020:DHC:92-DB, has held that; -
“11. It has been opined by this Court that when it comes to
setting aside of an award under the public policy ground, it
would mean that the award should shock the conscience of the
Court and would not include what the Court thinks is unjust on
the facts of the case seeking to substitute its view for that of the
arbitrator to do what it considers to be justice (Associate
Builders v. DDA, (2015) 3 SCC 49)”
“An arbitrator is a chosen Judge by the parties and it is on
limited parameters can the award be interfered with”. (Sudarsan
Trading Co. v. State of Kerala, (1989) 2 SCC 38)
19. She has also relied on the judgment in the case of Indian Oil
Corporation Ltd v. Institute of Geo Informatics Pvt Ltd, FAO OS
(COMM) 189/2017 , wherein this Court has held that; -
“ Thus a scrutiny conducted under Section 37 of the Act is more
in the nature of a judicial review, only to consider as to whether
the learned Single Judge, in exercise of the powers under Section
34 of the Act has overlooked any patent error that may have
crept in the Award or has taken a glaringly preposterous and
legally unsustainable view, which would call for interference.”
20. She submitted that the Award passed by the learned Tribunal does
not fall in the above categories.
21. She submitted that the appellant has also challenged the said
judgment on the ground that the court does not have power to reduce the
interest as granted by the learned Tribunal. Whereas, the Supreme Court in


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 8 of 34

Executive Engineer (R And B) v. Gokul Chandra Kanungo (Dead), has
held that¸ it is a settled position of law that it is the discretion of the Arbitral
Tribunal to award interest at a rate that it deems reasonable, and that the
Court can exercise power under Article 142 of the Constitution of India to
reduce the rate of interest. Further, an Arbitral Tribunal is duty bound to
give cogent reasons when it determine the rate of interest as reasonable. It is
also required to apply its mind to the facts of the case and decide whether
the interest is payable on the whole or any part of the money.
22. She submitted that, similarly, in V4 Infrastructure Pvt Ltd v. Jindal
Biochem Pvt Ltd , 2020:DHC:1866-DB this Court held that, “ In our
opinion, the award of interest @ 18% p.a. is wholly unjustified and the
same shocks our conscience and prompts us to intervene for the reasons
discussed hereinafter” . Therefore, the learned District Judge had the power
to reduce the interest rate if it deemed fit and the analysis of the learned
Tribunal that the 18% interest rate is exorbitant and is untenable in eyes of
law and modified the said interest rate to 12%.

23. Ms Lakra submitted that, Clause 63 of the of GCC clearly state that
the special conditions of the contract shall be deemed as “ Excepted
Matters ” and decision of the Railway Authority shall be final. She also
submitted that ‘ Excepted Matters ’ shall stand specifically excluded from
the purview of arbitration clause. She stated that the appellant had admitted
in this appeal that the respondent had duly informed the learned Tribunal
about the claims falling in the category of ‘ Excepted Matters ’ and yet the
learned Tribunal erroneously proceeded to award those claims. Therefore,
the learned Tribunal erred in granting those claims that fell within the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 9 of 34

category of ‘ Excepted Matter ’ and learned District Judge has rightly set
aside those claims.
24. She also submitted that the learned Tribunal is bound by the terms &
conditions of the contract as well as GCC. Regrettably, the claims granted
were beyond the provisions of the GCC & STC of contract.
25. In support of her submission, she has relied upon the judgments viz
(i) DDA v. R. S. Sharma & Co. VII (2008) SLT 306, (ii) New India Civil
Erectors Pvt Ltd v. Oil & Natural Gas Corporation, (1997) 11 SCC 75 .
26. She sought the dismissal of the appeal.
ANALYSIS AND FINDINGS
27. Having heard the learned counsel for the parties and perused the
record, the short issue, which arises for consideration is whether the learned
District Judge is justified in setting aside the award passed by the learned
Tribunal in respect of Claim Nos.1,4,5,7 & 8 as well as in modifying the
rate of future interest.
28. In so far as the Claim No.1 is concerned, the same was primarily for
grant of cost of ₹1,00,000/- in favour of the appellant. The learned
Tribunal, while dealing Claim No.1 has granted cost of ₹1,00,000/- for the
following reasons:-
“Reasons of award: The claimant stated that from the very
beginning the progress of the work was effected badly due
to non availability of P-way material & site of work. There
was mis planning of work, no required material was
arranged before the execution of the work nor the work was


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 10 of 34

short closed even after Aden/ Delhi accepted that there is no
material and no scope of work left in the section and
recommended to fore-close the work. But the respondent
have 'adopted' unfair trade practice being a supra position
and never close the work. And due to intermittent
suspension/ abandonment of the work for a long period, the
claimant had faced heavy losses of salaries to the staff etc.,
They further submitted that contract agreement was signed
by both parties considering that both have equal rights but
actually while dealing with this particular contract the
respondent behaved in biased manner and took totally one-
sided biased decision to cover up their misdeeds which
seemed to be full hatred and with expressing their superior
position.
The respondent miserably failed to provide essential
P.way material & site of work and this is a breach of
contract on the part of the respondent which resulted
suspension of work for a pretty long period. The delay was
totally attributable to the respondent. So they were dragged
to the Arbitration forcefully which was not their destiny
hence reasons given above are considered and an amount of
100000/- is awarded.”
29. The learned District Judge disagreed with the said finding of the
learned Tribunal by stating in paragraph no.26, as under:-
“26.Although, the Arbitrator has awarded Rs.1,00,000/- to
the respondent holding that the respondent was forced to seek
arbitration because of inability of the petitioner to take a
rational and practical decision but the award of said sum is
against clause 17-A and 61 (3) of GCC, which clearly
provide that if the progress of work has been delayed by the
act of Railways, it will grant the extension to the contractor
and no compensation shall be payable to the contractor and
the contractor shall have no claim to any payment of
compensation or otherwise, howsoever, on account of any
profit and advantage, which he might have derived from the
execution of work. In the instant case, all the extensions were


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 11 of 34

granted under clause 17 A of GCC 1999 without any penalty
and without PVC, which were duly accepted by the
respondent / contractor. Clause 64 (6) of GCC 1999, which
forms part of the contract also provides that cost of the
arbitration shall be borne by the respective parties, which
includes the fee of the Arbitrator. So, in view of specific bar
under clause 64 (6) of GCC 1999, the respondent is not
entitled to cost / compensation of Rs.1,00,000/- as awarded
under claim no.1.”
30. The conclusion drawn by the learned Tribunal for granting
₹1,00,000/- is primarily on the ground that the appellant was forced to seek
arbitration because of the inability of the respondent to provide P-way
material, which delayed the execution of the contract. In fact, this resulted
in the suspension of work for a long period. Whereas, the reasoning given
by the learned District Judge is primarily that, in terms of Clauses 17A and
61(3) of the GCC, even if the progress of the work has been delayed by the
acts of the respondent/Railway, the Engineer will grant extension of the
contract and no other compensation shall be payable to the contractor. Also,
the contractor shall not claim any payment of compensation or otherwise.
The learned District Judge has also referred to the Clause 64(6) of the GCC,
which according to the Court, forms part of the contract and also provides
that the cost of arbitration shall be borne by the respective parties. The cost
shall include the fee of the arbitrator.
31. In substance, the conclusion drawn by the learned District Judge was
in view of the specific bar under Clause 64(6) of the GCC, the appellant
/contractor is not entitled to the cost/compensation of ₹1,00,000/- as
granted under the Claim no.1.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 12 of 34

32. We are of the view that the learned District Judge is justified in
holding so, in view of Clause 64(6) of the GCC, which is reproduced as
under:-
“Clause 64.6: The cost of arbitration shall be borne by the
respective parties. The cost shall inter alia include fee of the
arbitrator (s) as per the rates fixed by the Railway
Administration from time to time.”
33. Suffice to state when the contractual clause states that the cost of the
arbitration shall be borne by the respective parties, which inter alia, include
the fee of the learned Tribunal, the learned Tribunal could not have
awarded the same contrary to the said provision.
34. In this regard, we may refer to the recent judgment of the Supreme
Court in the case of Union of India & Ors. v. Larsen & Tubro Limited
(L&T); 2026 INSC 203 wherein though the Supreme Court was
considering an issue whether the pre-award or pendente interest could have
been granted as compensation when a contract expressly prohibits payment
of such interest, the Court has held as under:-
“45. The provisions of the Act of 1996, including provisions
contained in Section 31(7)(a) give paramount importance to
the contract entered into between the parties and
categorically restrict the power of an arbitrator to award
pre-award/pendente lite interest when the parties have
themselves agreed to the contrary. Thus, the AT cannot
award pre-award/pendente lite interest, even in the form of
compensation, in view of specific Clause 16(3) of GCC read
with Clause 64(5) of GCC.”
35. The only submission of Mr. Haider in respect of this clause is that
the interpretation of terms of contract lies within the domain of the learned


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 13 of 34

Tribunal and as such, the learned District Judge could not have interfered
with the same. This submission of Mr. Haider is not appealing to us, as it is
a settled position of law that, when it is clearly stipulated in the contract
that the parties shall bear the cost of the arbitration, granting of cost as
compensation is clearly impermissible. Hence, the challenge to Claim No.1
is rejected.
36. In so far as the conclusion drawn by the learned District Judge in
respect of Claim No.4 is concerned, the same is towards ‘ expenditure
incurred on maintaining the staff, T & P machinery etc. during the
prolongation of the contract on account of the inability of the department to
provide P-way material .’ The reasons given by the learned Tribunal can be
summed up as under: -
“Reasons of award: The work was allotted to the claimant
on 09.08.2004 but the work was suspended/abandoned for a
pretty long period due to reasons totally attributable to the
respondent. The respondent failed to provide required
P.Way material and site of work. As such, in face of
principles of equality and justice the claimant is entitled for
recoupment of the extra expenditure incurred by them for
overhead charges ie by salaries to staff and other overhead
charges during the abandoned/suspension of contract. As
explained above this is a breach of contract on the part of
the respondent, as it would have been the case had the
claimant delayed the work for such long period of time for
reasons attributable to the claimant. Therefore without
providing details of loss on account extra expenditure
incurred by salaries to staff and other overhead charges
and other resources, the claimant is entitled for
compensation. There is nothing in the excepted matters
which may come in the way of adjudication of the claim for
salary and wages of the staff & machinery as claimed by the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 14 of 34

claimant during the suspension period. The excepted
clauses 36 (1) and 61 (3) are not applicable to the instant
dispute, because the suspension of contract exceeded 14
days for which clause 36(2) & clause 36(3) of GCC are
applicable.
The contract under question remained suspended for a
long time. As such contractor under clause 36(3) of GCC
could have elected to treat the suspension as an
abandonment of the contract by the Railway.
It is not in dispute that the respondent has extended time
of completion for the reason attributable to the Railway
Department. The respondent never imposed the condition
that the claimant would not be entitled for the losses that
they may suffer on account of abandonment/suspension of
the work of the contract. It is also not disputed that during
the extended period claimant deployed staff and machinery
at site. With the strength of above averments, the claimant
deserves to be compensated for the recoupment of the
salary/wages paid to the employees deputed by the claimant
& machinery deployed and had remained unutilised during
the period of suspension /abandonment.
After hearing the arguments of both claimant &
respondent and going through the documents produced
before me, the claim is partly allowed as the respondents
failed to provide the requisite P. Way materials to the
claimant in time and there was delay on account of the
respondent in this respect. The claimant had executed the
work in time as per the availability of material and had to
incur additional expenditure due to suspension of work for a
long time. In view of this work was suspended/abandoned
for a very long period from 03.02.2005 (initial date of
completion) to 03.08.2011 (as reported by respondent vide
letter dated 03.08.2011 that 41% work since have been
completed & recommended for closure of work on
administrative grounds). in view of above, it has been
tentatively quantified as a Lamp sum amount of Rs. 9000/-
per month as recoupment for the damages of the
salary/wages paid to the employees deputed by the claimant


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 15 of 34

is considered an adequate compensation which comes to
Rs.702000/- and therefore, Rs.702,000/- is awarded against
this claim.”
37. The learned District Judge, on the above finding as held that: -
“31. In my view, the Arbitrator went beyond the terms &
conditions of the agreement and GCC 1999 and awarded
the said amount. In the instant case, the respondent vide
letter dated 10.02.2006 had requested the petitioner to
foreclose the contract and process the final addendum /
corrigendum. Again vide letter dated 23.09.2008, it had
requested for foreclosure of contract. It had even given no
objection vide letter dated 13.03.2009 stating that it has no
objection, if the contract be closed on administrative
ground. It is not the case that after the period of extension,
the respondent executed any work or deployed any labour.
Its letter dated 10.02.2006 shows that it had requested the
petitioner to foreclose the contract and process the final
addendum I corrigendum. Admittedly, the petitioner did not
foreclose the contract nor prepared the final bill but clause
33.00 of the Special Tender Conditions provides that no
claim for idle labour, idle machinery and business losses is
payable to the contractor. Clause 63 of GCC 1999 provides
that the matters for which provision has been made in
clauses B(a), 18, 22(5), 39, 43(2), 45 (a), 55, 55 A (5), 57,
57 A, 61 (1), 61 (2) and 62 (1) (b) of GCC or in any clause
of the Special Conditions of Contract shall be deemed as
'excepted matters' and decisions of the Railway Authority
thereon shall be final and binding on the contractor,
provided further that 'excepted matters' shall stand
specifically excluded from the purview of the arbitration
clause and not be referred to arbitration. In the case of
General Manager Northern Railway (GMNR) Vs. Sarvesh
Chopra, 2002 (4) SCC 45 and Harsha Construction Vs.
UOI (supra), it was held that in case a particular claim falls
in the category of 'excepted matters', the same cannot be
decided by the Tribunal. Arbitrator is a creature of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 16 of 34

agreement and has to decide the disputes as per the terms &
conditions of the contract and he cannot go beyond the
same. Thus, in case any of the claims of the respondent is
found to be in the category of 'excepted matters' under
clause 63 of GCC 1999, it will be liable to be rejected being
not maintainable / arbitrable. In the present case,
admittedly the work remained suspended for more than
three months, but the respondent is not entitled to extra cost,
if any, incurred by it during the period of suspension of
work since, the respondent failed to provide any record as
to the payment of salaries / wages by it to its employees
during the period of such suspension. Further, it is not
understood why the respondent continued to hire the
equipment / staff, when it had requested to foreclose the
contract. I am of the view that if the respondent had hired /
deployed any equipment / staff, it did it on its own peril and
it is not entitled to any compensation. Further, this claims
falls in the category of 'excepted matters', which are not
arbitrable as provided under clause 63 of GCC.
32. As regards the contention that the Special Tender
Conditions were not placed before the arbitrator and the
court at the stage of entertaining the objections under
Section 34 of the Act cannot call for the Special Tender
Conditions, perusal of the arbitral record shows that the
Special Tender Conditions and GCC 1999 were referred by
the parties during the proceedings, judicial notice of which
was taken by the arbitrator. The agreement specifically
provides that the Special Tender Conditions and the GCC
shall form part of the contract. Admittedly, Section 34
application would not ordinary require anything beyond the
record as held in the case of Canara Nidhi Limited (supra)
but if there is any matter which is relevant to determination
of the issues arising under Section 34 (2) (a) of the Act, it
may be brought to the notice of the court Clause 33.00 of
Special Tender Conditions clearly provides that no claim
for idle labour, ideal machinery and business loss is
payable to the contractor/respondent. In the instant case,
the said record was relevant for determination of the issue


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 17 of 34

arising out of this petition.
33. As regards the contention that the respondent is entitled
to damages on account of breach of contract and its right
under Section 73 and Section 55 of the Indian Contract Act
cannot be waived and that the contracted clauses which
disentitle aggrieved party to the benefits of the above
sections would be void being violative of Section 23 of the
Contract Act as held in the case of Simplex Concrete Piles
(India) Ltd (supra), in the case (supra), two judgments of
the Supreme Court were referred i.e. Ramnath International
Construction P. ltd vis Union of India, (2007) 2 SCC 453
where it was held that even if the employer/Union of India is
at fault yet Clauses 11A to 11C bar the entitlement of the
contractor to damages and Asian Tech Limited vis Union of
India and Ors, (2009) 10 SCC 354 where it was held that
the clauses 11A to 11C, prevent only the department from
granting damages but it does not prevent the arbitrator
from awarding damages which are otherwise payable by the
employer on account of its breach of contract. It was
observed in Simplex Concrete Piles (India ) Ltd (supra) as
under:
"In my opinion, if I look at the issue from both the
micro and macro positions, keeping in focus the
intendment of legislation called the Contract Act, then
the judgment in the case of Asian Techs ltd can be said
to laying down a law which would further the object
and purpose of the Contract Act. I must hasten to add
that I am still doubtful whether I am entitled to decide,
the aspect that out of the two decisions of Supreme
Court, which one is to prevail, therefore, my
observations are strictly in terms of the limited
parameters of the facts of the present case required to
decide the aspect of the entitlement or the
disentitlement to damages in view of the provisions of
Section 55 and 73 of the Contract Act. I would with all
due respect to the learned Senior counsel for the
petitioner, would not venture further and would leave it
finally for a larger Bench of this court or the Supreme


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 18 of 34

Court itself to consider whether at all there is any
conflict between the judgments of Ram Nath
International and Asian Techs Ltd and if there is a
conflict, the ratio of which of the two judgments ought
to prevail."
34. In the light of above observations in Simplex Concrete
Piles (India ) Ltd (supra) and the subsequent judgment of
the Supreme Court in the case of Harsha Constructions vis
Union of India, AIR 2015 SC 270, where it was held that if a
nonarbitrable dispute is referred to an Arbitrator and even
if an issue is framed by the Arbitrator in relation to such a
dispute, in our opinion, there cannot be a presumption or a
conclusion to the effect that the parties had agreed to refer
the issue to the Arbitrator. In the instant case, the
respondent authorities had raised an objection relating to
the arbitrability of the aforestated issue before the
Arbitrator and yet the Arbitrator had rendered his decision
on the said "excepted" dispute. In our opinion, the
Arbitrator could not have decided the said "excepted
dispute", it is dear that what is to be seen is whether a
particular claim falls in the category of excepted matter or
not. In case, it falls in that category, same cannot be
decided by the arbitrator who is a creature of the agreement
and has to decide the dispute as per the terms and
conditions of the contract.”
38. It may be stated here that the plea that the claim is ‘ Excepted
Matters ’, (under Clause 63 of the GCC) and hence, shall not be arbitrable
was also urged before the learned Tribunal. The learned Tribunal
overlooking the said objection has allowed the claim in favour of the
respondent by awarding the sum of ₹7,02,000/-. The plea of Mr.Haider is
also that the learned District Judge could not have rejected the claim, as
awarded by the learned Tribunal, for the reason stated by us, that such a
conclusion is beyond the scope of the judicial review under Section 34 of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 19 of 34

the Act.
39. We must state here that Clause 63 of the GCC had come up for
interpretation in the case of M/s. J. Sons Engineering Corporation Limited
& Another (supra) which judgment has been relied upon by Mr. Haider,
wherein one of us (V. Kameswar Rao, J) has held as under:-
“22. As noted above, the claims made by the respondent and
allowed by the Arbitrator are primarily; the rescinding of
the contract is illegal (claim No 1); expenditure on
additional deployment of resources for completion of the
work (claim No. 2); loss of profit (claim No. 3); refund of
security amount (claim No. 5); interest (claim No. 8b);
arbitration cost (claim No. 9). The clause 61 of the General
Conditions of Contract relates to the termination effected
for the reasons attributable to the Railways. Clause 62
relates to determination of contract owing to the default of
the contractor. It is an undisputed fact that in the notice
dated April 26, 2004, the reasons given for the proposed
action was that the respondent had failed to abide by the
instructions issued to commence the work/to show adequate
progress of work. The reasons are found mentioned in
clause 62(vii) of the General Conditions of Contract. The
reply to the notice was given by the respondent on May 4,
2004. Vide letter dated May 7, 2004, the petitioners issued
another notice of 48 hours under clause 62 of the G.C.C. on
expiry of which period, the contract was to stand rescinded.
The notice dated May 7, 2004, according to the respondent,
was received on May 11, 2004, after the petitioners had
rescinded the contract on May 10, 2004. The respondent
made a representation dated May 21, 2004 against the letter
dated May 10, 2004. As noted from the petition, the
petitioner No. 2 addressed a letter dated September 10,
2004 suggesting a panel of Arbitrators seeking consent of
the respondent for constitution of an Arbitral Tribunal. The
demand for arbitration and the constitution of an Arbitral
Tribunal was under clause 64 of the G.C.C. There is


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 20 of 34

nothing on record to suggest that the petitioners had
considered the respondent’s representation and notified the
decision in terms of clause 63 of the G.C.C. In the absence
of a decision under clause 63, the bar under clause 63
would not apply. In other words, all matters related to the
clauses mentioned in clause 63 would be treated as
“excepted matters” if a decision is taken by the Railways.
The necessary corollary is the claims made by the
respondent cannot be deemed as „excepted matters‟. I note,
the petitioners had taken a Ground (A) in the petition as the
claims being “excepted matters”. The petitioners have not
averred nor placed on record any notification, notifying
their decision on the respondent’s representation as
contemplated in clause 63 of the G.C.C. The decision dated
May 10, 2004 would be a decision under clause 62 and not
under clause 63 Suffice to state, after a decision under
clause 62, the petitioners had taken a decision under clause
64 without resorting to clause 63. Suffice to state, the claims
are not “excepted matters”. Insofar as the judgments relied
upon by the learned counsel for the petitioners are
concerned, in NTPC Ltd. (supra), the Division Bench has
held, if the Arbitrator allows a claim covered by an
“excepted matters”, the award would not be legal merely
because the claim was referred to by the Court to
Arbitration and the award would be liable to be set aside on
the ground of error apparent on the face of the award or as
vitiated by the legal misconduct of Arbitrator. Insofar as the
judgment in Videsh Sanchar Nigam Ld. (supra) is
concerned, therein also, this Court has held that the
adjudication of and ignorance of various crucial and
material documents by the Arbitrator in proper award on
items was barred being “excepted matters”, therefore,
made beyond jurisdiction and contrary to contractual terms.
Award, therefore, was directed to be set aside. In view of the
facts of this case and my conclusion above, the judgments
referred to by the learned counsel for the petitioners would
have no applicability.”



Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 21 of 34

40. The above clearly reveals that the plea of ‘ Excepted Matters ’ shall
be sustainable only if the decision is taken by the Railways in respect of
those matters. The necessary corollary is that, in the absence of a decision
by Railways, Clause 63 of the GCC, would not be applicable. Nothing has
been placed before us that the Railways had taken a decision in respect of
the claims, which became the subject matter of the arbitration. If the same
had been rejected by the Railways, to that extent, they having attained
finality, were not arbitrable in view of the Clause 63 of the GCC. It is not
such a position here as no decision has been taken by the Railways. In any
case, the Supreme Court in respect of ‘ Excepted Matters ’ has held that,
even if certain matters are excluded from arbitration, they could not be
excluded from judicial review as vacuum of remedy is oppose to rule of
law.
41. Having noted the aforesaid position, we now proceed to decide
whether the claim as granted by the learned Tribunal, has been rightly
rejected by the learned District Judge.

42. Suffice to state that Clause 17A and 61(3) of the GCC being relevant,
are reproduced as under: -
“17–A Extension of Time in Contracts : Subject to any
requirement in the contract as to completion of any portion
or portions of the works before completion of the whole, the
Contractor shall fully and finally complete the whole of the
works comprised in the contract (with such modifications as
may be directed under conditions of this contract) by the
date entered in the contract or extended date in terms of the
following clauses:
(i) Extension due to Modification: If any modifications have
been ordered which in the opinion of the Engineer have


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 22 of 34

materially increased the magnitude of the work, then such
extension of the contracted date of completion may be
granted as shall appear to the Engineer to be reasonable in
the circumstances, provided moreover that the Contractor
shall be responsible for requesting such extension of the
date as may be considered necessary as soon as the cause
thereof shall arise and in any case not less than one month
before the expiry of the date fixed for completion of the
works.
(ii) Extension for Delay not due to Railway or Contractor: If
in the opinion of the Engineer, the progress of work has any
time been delayed by any act or neglect of Railway's
employees or by other Contractor employed by the Railway
under Sub-Clause (4) of Clause 20 of these Conditions or in
executing the work not forming part of the contract but on
which Contractor's performance necessarily depends or by
reason of proceeding taken or threatened by or dispute with
adjoining or to neighbouring owners or public authority
arising otherwise through the Contractor's own default etc.
or by the delay authorized by the Engineer pending
arbitration or in consequences of the Contractor not having
received in due time necessary instructions from the
Railway for which he shall have specially applied in writing
to the Engineer or his authorized representative then upon
happening of any such event causing delay, the Contractor
shall immediately give notice thereof in writing to the
Engineer within 15 days of such happening, but shall
nevertheless make constantly his best endeavours to bring
down or make good the delay and shall do all that may be
reasonably required of him to the satisfaction of the
Engineer to proceed with the works. The Contractor may
also indicate the period for which the work is likely to be
delayed and shall be bound to ask for necessary extension of
time. The Engineer on receipt of such request from the
Contractor shall consider the same and shall grant such
extension of time as in his opinion is reasonable having
regard to the nature and period of delay and the type and
quantum of work affected thereby. No other compensation


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 23 of 34

shall be payable for works so carried forward to the
extended period of time; the same rates, terms and
conditions of contract being applicable as if such extended
period of time was originally provided in the original
contract itself.
(iii) Extension for Delay due to Railways: In the event of
any failure or delay by the Railway to hand over the
Contractor possession of the lands necessary for the
execution of the works or to give the necessary notice to
commence the works or to provide the necessary drawings
or instructions or any other delay caused by the Railway
due to any other cause whatsoever, then such failure or
delay shall in no way affect or vitiate the contract or alter
the character thereof or entitle the Contractor to damages
or compensation therefor, but in any such case, the Railway
may grant such extension or extensions of the completion
date as may be considered reasonable.
xxx xxx xxx xxx

Clause 61 (3): The contractor shall have no claim to any
payment of compensation or otherwise, howsoever on
account of any profit or advantage, which he might have
derived from the execution of the work in full but which he
did not derive in consequence of determination of contract.”

43. The above clearly provides that, if the progress of the work has been
delayed by the act of the Railways, the engineer will grant extension to the
contractor, and no compensation shall be payable to the contractor. The
contractor shall have no right to claim any payment of compensation or
otherwise, on account of any profit or advantage, which he might have
derived from the execution of the work. There is no dispute that, extensions
of the work were granted, but because of the Clause 17A of the GCC, the
same was without any penalty or without any price variation, which
extensions were duly accepted by the appellant.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 24 of 34

44. It may also be necessary to refer to Clause 33 of the Special Tender
Conditions of Instructions to Tenderer/s, which has a bearing on the issue,
as under:-
“Clause 33: No claim for idle labour and / or idle
machinery etc or any account will be entertained. Similarly,
no claim shall be entertained for business loss or any such
loss.”
45. A plain reading of the above clauses would clearly reveal that, even
if the progress of work was delayed by the act of the Railways, the
appellant is only entitled to extension of contract, but no compensation
shall be payable to the appellant, which also includes the claim for idle
labour and / or idle machinery or on any account. The learned Tribunal has
not considered the above Clause while allowing the said claim. To that
extent, the finding is perverse. If the above clauses, bar the grant of cost
on account of idle labour and/ or idle machinery, the learned Tribunal could
not have granted the claim contrary to the contract.
46. Hence, the challenge to the conclusion drawn by the learned District
Judge in respect of Claim No. 4 is liable to be rejected, as the learned
Tribunal in view of clear bar under the contract, could not have granted the
claim. As such, the conclusion drawn by the District Judge is covered by
the ratio of the judgment of the Supreme Court in the case of Larsen &
Tubro Limited (supra) .
47. In so far as the Claim No.5 is concerned, it is for the interest on
payment held up of ₹2,92,000/- due to not sanctioning corrigendum /
addendum and holding of ₹1,00,000/- on account of security money for


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 25 of 34

47.5 months, which has been awarded by the learned Tribunal with simple
interest @ 12% pa and quantified as ₹3,35,160/-.
48. The learned Tribunal has given the following reasoning for awarding
this sum:-
“Reasons of award: The Respondent had to make all
payments due in time as per the contract agreement le by
the time of expiry of six months from date of completion of
work which has been considered as 30.09.2017. It is prime
obligation of respondent but the respondent failed to do the
payment in time. It is a breach of contract part of
respondent. As such pre interest up to the declaration of
award is awarded of final bill after six months of completion
i.e. Rs 366596/. Therefore, interest on payments held up due
to not sanctioning of final corrigendum/addendum for
period of 10 year 5 months w.e.f. 01.04.2008 to 30.08.2018
a simple interest @12% PA is considered, which comes to
Rs.458245/- but Rs.335160/ is awarded against this claim”
49. The learned District Judge has given following reasoning in respect
of claim no.5, to set aside the award of this claim by the learned Tribunal:-
“35. Qua claim no. 5 i.e. interest on the payments held up
due to non sanctioning / issuing addendum / corrigendum
and withholding the security deposit and earnest money, it
was held by the Arbitrator that the petitioner had to make
all payments as per the agreement i.e. after the expiry of six
months from the date of completion of work (in this case, the
Arbitrator considered the date of completion as 30.09.2017)
but it failed to make the payment in time and committed the
breach. As such it is entitled to pre interest upto the
declaration of award on the final bill after six months of
completion and thus, entitled to interest for a period of 10
years and 5 months w.e.f. 01.04.2008 to 30.08.2018 @ 12%
per annum.
36. Section 31 (7) (a) of the Act provides that interest is
payable to the other party at such rate as it deems


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 26 of 34

reasonable on whole or any part of the money. If there is
prohibitory clause in the agreement barring awarding of
interest, the interest cannot be awarded on the amount
claimed. Clause 16 (3) of GCC 1999 forming part of the
contract provides that no interest will be payable on the
earnest money and security deposit and the amounts
payable to the contractor under the contract. Clause 64 (5)
of GCC 1999 provides that where the arbitral award is for
payment of money, no interest shall be payable on whole or
part of the money for any period till the date on which, the
award is made. In the case of Union of India Vs. Pradeep
Vinod Construction Co., Appeal No. 2099/2014, decided on
03.08.2017 it was held that non payment of interest
contemplated between the parties under clause 16 is
exclusively limited to the component of earnest money and
the security deposit and nothing else. On a plain reading of
clause 16 (3) of GCC, it is clear that the respondent is not
entitled to interest on the amount of earnest money and the
security deposit and the amount payable to be calculated
under the contract. In the case of Chitranjan Maity Vs. UOI
(supra), it was held that if the agreement prohibits award of
interest, the Arbitrator cannot award interest for the said
period. Similar view was expressed in the case of Sayeed
Ahmed & Co. Vs. State of UP (2009) 12 SCC 26. In the case
of Ashi Limited Vs. UIO, 124 (2005) DLT 329, it was held
that in regard to pre-award period, interest has to be
awarded as specified in the contract and in the absence
thereof, then as per the discretion of the Arbitral TribunaL
In regard to post-award period, interest is payable as per
the discretion of the Arbitral Tribunal.
37. Although the reasoning given by the Arbitrator qua
allowing the interest for the pre-award period has logic but
since in the instant case, there is not only the clause 16 (3)
of GCC 1999 but also the clause 64 (5) of GCC, which
clearly prohibit grant of interest, so in view of specific bar
as provided under the above clauses of GCC 1999 forming
part of the contract and the case laws supra, the respondent
would not be entitled to interest.”


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 27 of 34


50. While granting the amount under Claim No.5, the learned Tribunal
has also granted interest for the period from 01.04.2008 and 30.08.2018;
whereas the date of the award is 26.09.2018. In that sense, the Tribunal has
granted pre arbitration as well as pendente interest. The Clause 64(5) of the
GCC, which state, ‘ where the arbitral award is for the payment of money,
no interest shall be payable on whole or any part of the money for any
period till the date on which, the award is made ’, clearly bars the grant of
interest on whole or any part of the money for any period till the date on
which, the award is made. This Clause specifically deals with the grant of
interest by the learned Tribunal till the date of award. The payment of
interest is the discretion of the learned Tribunal, but is only payable for the
period post award.
51. The Supreme Court in the case of Garg Builders v. Bharat Heavy
Electricals Limited, 2021 INSC 606, has held as under:-
“10. We have carefully considered the submissions of the
learned counsel for both the parties made at the Bar. The
law relating to award of pendente lite interest by Arbitrator
under the 1996 Act is no longer res integra. The
provisions of the 1996 Act give paramount
importance to the contract entered into between the parties
and categorically restricts the power of an arbitrator
to award pre-reference and pendente lite interest when the
parties themselves have agreed to the contrary. Section
31(7)(a) of the 1996 Act which deals with the payment of
interest is as under :
“31(7)(a) Unless otherwise agreed by the parties, where
and insofar as an arbitral award is for the payment of
money, the arbitral tribunal may include in the sum for
which the award is made interest, at such rate as it deems


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 28 of 34

reasonable, on the whole or any part of the money, for the
whole or any part of the period between the date on which
the cause of action arose and the date on which the award is
made.”
11. It is clear from the above provision that if the
contract prohibits pre-reference and pendente lite interest,
the arbitrator cannot award interest for the said period.
In the present case, clause barring interest is very clear and
categorical. It uses the expression “any moneys due to the
contractor” by the employer which includes the amount
awarded by the arbitrator.
12. In Sayeed Ahmed and Company v. State of Uttar
Pradesh & Ors.(2009) 12 SCC 26 this Court has held that a
provision has been made under Section 31(7)(a) of the 1996
Act in relation to the power of the arbitrator to award
interest. As per this section, if the contract bars payment of
interest, the arbitrator cannot award interest from the date
of cause of action till the date of award.
13. In Sree Kamatchi Amman Constructions v.
Divisional Railway Manager (Works), Palghat &
Ors.(2010) 8 SCC 767 it was held by this Court that where
the parties had agreed that the interest shall not be payable,
the Arbitral Tribunal cannot award interest between the
date on which the cause of action arose to the date of the
award.
14. Bharat Heavy Electricals Limited v. Globe Hi-Fabs
Limited (2015) 5 SCC 718 is an identical case where this
Court has held as under :
“16. In the present case we noticed that the clause
barring interest is very widely worded. It uses the
words “any amount due to the contractor by the
employer”. In our opinion, these words cannot be
read as ejusdem generis along with the earlier words
“earnest money” or “security deposit”.”
15. In Sri Chittaranjan Maity v. Union of India (2017)
9 SCC 611 it was categorically held that if a contract
prohibits award of interest for pre-award period, the
arbitrator cannot award interest for the said period.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 29 of 34

16. Therefore, if the contract contains a specific
clause which expressly bars payment of interest, then it is
not open for the arbitrator to grant pendente lite interest.
The judgment on which reliance was placed by the learned
counsel for the appellant in Ambica Construction (supra)
has no application to the instant case because Ambica
Construction was decided under the Arbitration Act
1940 whereas the instant case falls under the 1996 Act.
This has been clarified in Sri Chittaranjan Maity (supra) as
under :
“16. Relying on a decision of this Court in Ambica
Construction v. Union of India, (2017) 14 SCC 323,
the learned Senior Counsel for the appellant
submits that mere bar to award interest on
the amounts payable under the contract would not be
sufficient to deny payment on pendente lite interest.
Therefore, the arbitrator was justified in awarding the
pendente lite interest. However, it is not clear from
Ambica Construction (supra) as to whether it was
decided under the Arbitration Act, 1940 (for short “the
1940 Act”) or under the 1996 Act. It has relied on a
judgment of Constitution Bench in State of Orissa v.
G.C. Roy, (1992) 1 SCC 508. This judgment was
with reference to the 1940 Act. In the 1940 Act, there
was no provision which prohibited the arbitrator from
awarding interest for the prereference, pendente lite
or post-award period, whereas the 1996 Act
contains a specific provision which says that if the
agreement prohibits award of interest for the
pre-award period, the arbitrator cannot award
interest for the said period. Therefore, the decision in
Ambica Construction (supra) cannot be made
applicable to the instant case.”
17. The decision in Raveechee and Company (supra) relied
on by the learned counsel for the appellant is again under
the Arbitration Act 1940 which has no application to the
facts of the present case.
18. Having regard to the above, we are of the view that the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 30 of 34

High Court was justified in rejecting the claim of the
appellant seeking pendente lite interest on the award
amount.”
(emphasis supplied)

52. Even in the recent judgment of the Supreme Court in the case of
Larsen & Tubro Limited (supra) , the Court has dealt with the same
position of law, which we have reproduced in paragraph no.34 above.
53. The Supreme Court in the case of Union of India v. Bright Power
Projects (India) (P) Limited, (2015) 9 SCC 695, has similarly held as
under:-
“11. This Court also considered Section 31(7)(a) of the
1996 Act. It is specifically observed and held that Section
31(7) of the 1996 Act, by using the words “unless otherwise
agreed by the parties” categorically specifies that the
arbitrator is bound by the terms of the contract insofar as
award of interest from the date of cause of action to date of
the award is concerned. It is further observed and held that
where the parties had agreed that no interest shall be
payable, the Arbitral Tribunal cannot award interest. Thus,
the aforesaid decision of a three-Judge Bench of this Court
is the answer to the submission made on behalf of the
respondent that despite the bar under Clause 16(2) which is
applicable to the parties, the Arbitral Tribunal is not bound
by the same. Therefore, the contention raised on behalf of
the respondent that dehors the bar under Clause 16(2), the
Arbitral Tribunal independently and on equitable ground
and/or to do justice can award interest pendente lite or
future interest has no substance and cannot be accepted.
Once the contractor agrees that he shall not be entitled to
interest on the amounts payable under the contract,
including the interest upon the earnest money and the
security deposit as mentioned in Clause 16(2) of the
agreement/contract between the parties herein, the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 31 of 34

arbitrator in the arbitration proceedings being the creature
of the contract has no power to award interest, contrary to
the terms of the agreement/contract between the parties and
contrary to Clause 16(2) of the agreement/contract in
question in this case.”
(emphasis supplied)
54. Hence, the challenge to the order of the learned District Judge on
Claim No.5, is clearly unsustainable and is rejected.
55. In so far as the order on Claim No.7 is concerned, the same is setting
aside the Claim of grant of 10% loss of profit on the remaining value of the
work left over work, i.e., on ₹10,84,080/- not executed due reasons
attributable to the Railways.
56. Suffice to state that the learned Tribunal has awarded ₹1,08,408/-.
The learned District Judge has set aside the award on the ground that it is
“ Excepted Matter ”. The reasoning by us with regard to the Claim No.4
wherein we have held that the Clause 63 of the GCC, which related to
“ Excepted Matter ” shall not be applicable as no decision was taken by the
Railways, [In M/s. J. Sons Engineering Corporation Limited & Another
(supra) ]. Even assuming for a moment that the Claim is arbitrable, Clause
61(3) of the GCC, which has already been reproduced above, clearly
stipulates that the contractor shall have no claim on any payment or
compensation or otherwise, howsoever, on account of any profit or
advantage, which he might have derived from the execution of the work in
full, but which he did not derive in consequence of the determination of the
contract, will be a bar for the learned Tribunal to grant the same. The
conclusion drawn by the learned District Judge is justified, and hence, the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 32 of 34

challenge to the order of the learned District Judge on Claim No.7, is
rejected.
57. In so far as the Claim No.8 is concerned, the same is relatable to
interest @ 24% PA and @ 12% PA on the amount awarded against Claim
No.4. The learned Tribunal has granted ₹5,96,700/- by giving the
following reasoning:-
“Reasons of award: After hearing the arguments of both
claimant and respondent and going through the documents
provided before the tribunal, the arbitrator is of the opinion
that simple interest @ 12% per annum becomes due to the
claimant from the date 03.08.2011 (when the respondent
reported that 41% work has been completed and
recommended for foreclosure of work) to 30.08.2018.
Hence, simple interest @ 12% p.a. on Rs. 702000/- ie the
amount of claim no.4, which becomes to Rs.596700/-is
genuine and considered. Hence the amount of Rs.5,96,700/-
is awarded against this claim.”
58. The learned District Judge has set aside the same, while giving
following reasoning:-
“40. It has already been held in paras 36 and 37 that if the
agreement prohibits award of interest, the Arbitrator cannot
award pendente lite interest as held in the case of
Chitranjan Maity Vs. UOI (supra), Sayeed Ahmed & Co. Vs.
State of UP (supra) and Ashi Limited Vs. UOI (supra),
which inter alia provide that in regard to pre-award period,
interest has to be awarded as specified in the contract and
in the absence thereof then as per the discretion of the
Arbitral Tribunal. In the instant case, the contract does not
provide the award of interest on pre-award period. So, the
interest pendente lite is not payable to the respondent.”

59. We agree with the said conclusion of the learned District Judge,


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 33 of 34

moreso, in view of our finding with regard to Claim No.5 above, as the
interest has been granted for the period 03.08.2011 to 30.08.2018, for the
same reason as stated by us, in paragraph 50 above, while dealing with the
Claim No.5, in as much as, the learned Tribunal could not have granted pre-
arbitration and pendente interest in view of the express bar in the contract.
60. Mr.Haider, has relied upon the decisions in the case of Larsen Air
Conditioning and Refrigeration Company (Supra) ; Himachal Joint
Venture (Supra); Simplex Concrete Piles (India) Ltd. (Supra) ; Canara
Nidhi Limited (Supra); Ssangyong Engineering and Construction Co.
Ltd. (Supra); Venture Global Engineering LLC and Ors. (Supra);
Renusagar Power Co. Ltd. (Supra) and M/s Pradeep Vinod Construction
Co. (Supra) in support of his contentions. Most of the decisions are on the
scope of the judicial review in a challenge to the arbitral award under
Section 34 of the Act. We are of the view that these decisions have no
applicability in the facts and in view of our findings above.
61. In view of aforesaid discussion, present appeal being devoid of
merits, is liable to be dismissed. It is ordered so. The pending application
is also dismissed.


V. KAMESWAR RAO, J



MANMEET PRITAM SINGH ARORA, J
JULY 15, 2026
rt


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:15.07.2026
15:02:46
FAO (COMM) 24/2022 Page 34 of 34