M/S Cds Infra Projects Limited vs National Highways Authority Of India & Ors.

Court
Delhi High Court

$~86
* IN THE HIGH COURT OF DELHI AT NEW DELHI
rd
% Date of Decision: November 23 , 2026
# CNR No. DLHC010556942026
+ W.P.(C) 17142/2026 & CM APPL. 80201/2026, CM APPL.
80202/2026
M/S CDS INFRA PROJECTS LIMITED .....Petitioner
Through: Mr. Sandeep Sethi, Ms. Priya
Kumar, Sr. Advs. with Mr.
Ishan Khanna, Mr. Mohit
Raghuwanshi, Mr. Gyanendra
Shukla & Mr. Ritik Sharma,
Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA & ORS.
.....Respondents
Through: Mr. Manu Yadav, Adv. for R-1.
Mr. Saurabh Kansal, SPC with
Ms. Nasreen Khatoon, GP &
Mr. Pratham Malik, Adv. for R-
2.
CORAM:
HON'BLE MR. JUSTICE AMIT MAHAJAN
AMIT MAHAJAN, J. (Oral)
1. With the consent of the parties, the matter was heard finally
since the documents are not disputed by the respondents.
2. By the present petition, the petitioner challenges the show cause
notice dated 02.07.2025 issued by Respondent No. 1 pursuant to
which the petitioner was suspended from participating in future
bidding for a period of 1 month or till successful demonstration that
the pavement crust was complying with the specifications. By the said
Signature Not Verified
W.P.(C) 17142/2026 Page 1 of 5
Signed By:SANJAY
KUMAR
Signing Date:24.11.2026
17:38:56

show cause notice, the petitioner was also called upon to show cause
why action for debarment up to 1 year or till completion of
rectification of the defects be not taken.
3. The petitioner also challenges the show cause notice dated
22.09.2025 issued by Respondent No.1 pursuant to which the
petitioner was called upon to furnish an explanation as to why action
for declaring the petitioner as non-performer till rectification of the
defects in Project Highway be not taken for the gross negligence and
dereliction on the part of the petitioner in complying with the
obligations stipulated in the contract agreement.
4. Succinctly stated, on 10.02.2021, a contract agreement was
executed between the petitioner and Respondent No. 1 for
Construction of 6 Lane access controlled Greenfield Highway from
Km 99.000 to Km 130.73 of Rajasthan/Gujarat Border to Santalpur
Section of NH-754K under Bharatmala Pariyojana (Phase I). It is the
petitioner’s case that the commercial use of the Highway commenced
on 01.04.2025 though no provisional completion certificate was issued
by the respondent authorities. Thereafter, following certain social
media posts alleging pavement distress, Respondent No. 1 issued the
impugned show cause notice dated 02.07.2025 proposing debarment
for a period of 1 year or till completion of the rectification of the
subject stretch was carried out. The petitioner was also immediately
suspended from participating in ongoing/future bidding for a period of
1 month or till successful demonstration that the design and
construction of pavement crust complied with the specifications in the
contract agreement was carried out.
Signature Not Verified
W.P.(C) 17142/2026 Page 2 of 5
Signed By:SANJAY
KUMAR
Signing Date:24.11.2026
17:38:56

5. Following the show cause notice, on 03.07.2025, a press release
was issued which publicised that the petitioner had been debarred
from participating in ongoing/future bids for failure of the pavement
crust.
6. The petitioner furnished its reply dated 17.07.2025 to the show
cause notice dated 02.07.2025 highlighting the remedial actions and
rectification works carried out by the petitioner. However, again on
22.09.2025, a second show cause was issued noting that the petitioner
failed to demonstrate that the pavement crust was complying with the
conditions stipulated in the contract agreement and calling upon the
petitioner to furnish explanation as to why the petitioner not be
declared a non performer till the defects were rectified. The show
cause notice further recorded that the suspension imposed on the
petitioner vide show cause notice dated 02.07.2025 shall continue. The
petitioner furnished its reply to the second show cause notice on
06.10.2025.
7. The learned Senior Counsel for the petitioner submits that
despite a lapse of more than one year, no decision has been taken by
the respondent authorities on the impugned show cause notices. He
submits that the press release issued on 03.07.2025 noted that the
petitioner stood debarred and despite a passage of more than 1 year,
the petitioner continues to be debarred though the show cause notice
itself contemplated debarment for a period of 1 year.
8. On the other hand, the learned counsel for Respondent No. 1
submits that the show cause notice dated 02.07.2025 stipulated
suspension of the petitioner from participating in ongoing/future
Signature Not Verified
W.P.(C) 17142/2026 Page 3 of 5
Signed By:SANJAY
KUMAR
Signing Date:24.11.2026
17:38:56

bidding for 01 month or till successful demonstration that the
pavement crust complied with the conditions envisaged in the contract
agreement. It has been argued that the petitioner was never debarred
and the said suspension imposed on the petitioner vide show cause
notice dated 02.07.2025 was continued considering that the defects
were not rectified.
9. The essential facts are not in dispute. Undisputedly, no action
has been taken by the respondent authorities on the impugned show
cause notices. Though Respondent No. 1 has sought to impress upon
this Court that the petitioner was never debarred, since the suspension
imposed on the petitioner vide show cause notice dated 02.07.2025
prohibited the petitioner from participating in ongoing/future bidding
and considering that the same continued for a period of more than one
year, the suspension, in the opinion of this Court, was akin to
debarment.
10. Undisputedly, without traversing into the merits of the
allegations, it is pertinent to note that the show cause notice dated
02.07.2025 sought to penalise the petitioner for a period of one year
and the said period has already passed. As noted above, no action has
been taken by the respondent authorities on the impugned show cause
notices and the petitioner continues to be suspended.
11. The respondents have failed to demonstrate that any
rectification is still pending or the Highway is non functional. Even
otherwise, if certain remedial measures are still required to be taken,
the respondent authorities can take necessary action in that regard.
However, the show cause notices, being an administrative action,
Signature Not Verified
W.P.(C) 17142/2026 Page 4 of 5
Signed By:SANJAY
KUMAR
Signing Date:24.11.2026
17:38:56

cannot be allowed to operate in perpetuity pending the rival stance
taken by the respondents that the defects continue to persist.
12. In such circumstances, in the opinion of this Court, the
petitioner has already suffered the maximum penalty of 1 year as
proposed in the impugned show cause notice dated 02.07.2025, and
the show causes notices cannot be allowed to operate indefinitely. In
the light of the aforesaid discussion, the impugned show cause notices
dated 02.07.2025 and 22.09.2025 are hereby set aside.
13. The present petition is allowed in the aforesaid terms. Pending
applications also stand disposed of.
AMIT MAHAJAN, J
NOVEMBER 23, 2026
“SK”