Skymax Infra Power Ltd vs Mbook Technology Pvt Ltd

Court
Delhi High Court

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 02 November2026
Pronounced on: 06 November 2026

# CNR No. DLHC010517842026
+ O.M.P.(I) (COMM.) 503/2026, I.A. 29807/2026
MBOOK TECHNOLOGY PVT. LTD. .....Petitioner

Through: Mr. Sandeep Sethi, Sr. Adv.,
Mr.Aditya Mukherjee, Mr.Krishna
Tangirala, Mr. Ritwik Sharma,
Ms. Shreya Sethi, Mr. Aditya
Kumar Singh and Ms. Ananya
Tangri, Advs.

Versus

SKYMAX INFRAPOWER PVT. LTD. ....Respondent

Through: Mr. Anukul Raj, Ms. Nikita Raj,
Mr. Tushar Bhalla, Mr. Naveen
and Mr. Vishal Yadav, Advs.

# CNR No. DLHC010524312026

+ O.M.P.(I) (COMM.) 512/2026

SKYMAX INFRA POWER LTD .....Petitioner

Through: Mr. Anukul Raj, Ms. Nikita Raj,
Mr. Tushar Bhalla, Mr. Naveen
and Mr. Vishal Yadav, Advs.

versus

MBOOK TECHNOLOGY PVT LTD .....Respondent

Through: Mr. Sandeep Sethi, Sr. Adv.,
Mr.Aditya Mukherjee, Mr.Krishna
Tangirala, Mr. Ritwik Sharma,
Ms. Shreya Sethi, Mr. Aditya
Kumar Singh and Ms. Ananya
Tangri, Advs.

Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 1 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

CORAM:
HON'BLE MR. JUSTICE VINOD KUMAR
JUDGMENT
% 06.11.2026

O.M.P.(I)(COMM.) 503/2026
1. The disputes between the parties arose in the context of the
execution of a solar power project under Component-C of the PM-
KUSUM Scheme, situated in District Nanded, Maharashtra. In relation
to the said project, Skymax Infra Power Limited (hereinafter referred to
as “Skymax”) and Mbook Technology Private Limited (hereinafter
referred to as “Mbook”) entered into a Sub-Contract Agreement dated
18.12.2025 (hereinafter referred to as “the Agreement”), whereby
Mbook was entrusted with the execution of a part of the said project.
2. The larger project was undertaken pursuant to a Power Purchase
Agreement dated 16.01.2025 executed between Maharashtra State
Electricity Distribution Company Limited (MSEDCL) and Skymax.
Under the aforesaid arrangement, the project envisaged development of
solar power generating stations at various locations in the State of
Maharashtra. The work entrusted to Mbook under the Sub-Contract
Agreement formed part of the larger project.
3. In terms of the Agreement dated 18.12.2025, Mbook was
entrusted with the execution of specified works forming part of the
project in District Nanded. The initial scope of work under the
Agreement related to the project locations at Degaon, Tuppa, Neela,
Manjaram and Pardi. The project locations referred to in the pleadings
also include Ardhapur, Bhokar, Himayatnagar and Wadgaon.
4. The Agreement governed the contractual relationship between the
parties and stipulated their respective obligations in relation to the
execution of the works. It also contained provisions dealing with the
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 2 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

timelines for completion, the consequences of default, termination of the
Agreement and resolution of disputes. The Agreement provided for an
arbitration mechanism under Clause 16.
5. Disputes thereafter arose between the parties in relation with the
execution and progress of the works under the Agreement. While
Skymax alleges that Mbook failed to make adequate progress and did not
fulfil its contractual obligations within the stipulated timelines, Mbook
disputes the allegations and attributes the delay in execution of the works
to various acts and omissions on the part of Skymax.
6. In the course of their contractual dealings, the parties exchanged
communications concerning the progress of the works, the pending
activities at the project sites and the obligations required to be fulfilled
under the Agreement.
7. On 22.10.2026, Skymax issued a notice terminating the
Agreement dated 18.12.2025. The said notice also called upon Mbook to
demobilise from the project sites and contained directions and demands
concerning the completion of the balance works and the amounts
claimed by Skymax. The legality and validity of the termination, as well
as the consequences flowing therefrom, have been disputed by Mbook in
this petition.
8. Mbook has filed the present petition under Section 9 of the
Arbitration and Conciliation Act, 1996 seeking interim measures of
protection on account of Skymax seeking to terminate the Agreement
dated 18.12.2025 executed between the parties. The petitioner- MBook
in its petition has prayed for the following reliefs:-
“A. Grant an ad-interim injunction, staying the operation and
effect of the Termination Notice dated 22.10.2026 issued by the
Respondent, and restrain the Respondent from giving effect to the
same or terminating the Sub-Contract Agreement dated 18.12.2025
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 3 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

in any manner pending final adjudication of the disputes through
arbitration.
B. Direct the parties to maintain status quo ante as existing
prior to 22.10.2026 with respect to the operation, management,
and functioning of the Project sites at Degaon, Tuppa, Neela,
Manjaram, Pardi, Himayatnagar, Wadegaon, Ardhapur, and
Bhokar in District Nanded, Maharashtra, and at the Petitioner's
stores, under the Sub- Contract read with the Variation of Quantity
Letters dated 03.02.2026 and 23.02.2026 including uninterrupted
access and services by the Petitioner;
C. Grant an ad-interim injunction restraining the Respondent
from interfering with, or otherwise obstructing the execution of the
Project works at the Project sites by the Petitioner, in accordance
with the terms of the Sub-Contract executed between the parties;
D. Grant a prohibitory ad-interim injunction restraining the
Respondent, its officers, agents, contractors and any person
claiming through it from, directly and/or indirectly, removing,
using, installing, dismantling, altering, transferring, disposing off
or parting with possession of the materials, equipment, machinery
and work-in-progress supplied or executed by the Petitioner, and
from carrying out any work at the said sites that alters their
existing condition;
E. Grant a prohibitory ad-interim injunction restraining the
Respondent from directly and/or indirectly, engaging, appointing
or contracting with any other contractor, affiliates, subsidiaries,
agency, or third party, for execution of the Project works awarded
to the Petitioner under the Sub-Contract Agreement dated
18.12.2025 read with the Variation of Quantity Letters dated
03.02.2026 and 23.02.2026 issued by the Respondent;
F. Pass an order directing the Respondent to deposit with this
Hon'ble Court an amount of INR 25,32,54,564/- (Rupees Twenty
Five Crore Thirty-Two Lakhs Fifty-Four Thousand Five Hundred
and Sixty Four) or in the alternative, furnish security for an amount
of INR 25,32,54,564/- by way of bank guarantee or fixed deposit
receipt or any other instrument as this Hon'ble Court may deem fit;
G. Grant a prohibitory ad-interim injunction restraining the
Respondent from creating any third-party rights or interests in
respect of the said works, the Project sites or the Petitioner's
materials;
H. Pass an order directing the Respondent to disclose on
affidavit, a list of all immovable and moveable assets of the
Respondent along with encumbrances, if any, and the audited
financial statements for the previous financial year;
I. Pass ad-interim ex-parte orders in terms of the prayers
above, if required;”

9. It is submitted by Mr. Sandeep Sethi, learned Senior Advocate for
Mbook that the Termination Notice dated 22.10.2026 has been issued
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 4 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

under Clause 9.2.2 of the Agreement, whereby Skymax has terminated
the Agreement with "immediate effect". In terms of Clause 9.2.2 of the
Agreement, Skymax was entitled to terminate the same only if Mbook
failed to fulfill its obligations after affording the Mbook an opportunity
of rectifying the breach within 30 days of receiving a written notice in
this regard.
10. Therefore, it is submitted that the termination notice is wrongful
and constitutes as breach of Agreement and the emails sent by Skymax
from March 2026 cannot be constituted as “notice” as per Clause 9.2.2
of the Agreement.
11. Learned Senior Counsel further submitted that the delay in the
execution of the project is solely attributable to Skymax and not to
Mbook. Additionally, various Variation of Quantity Letters in terms of
Clause 2.1 of the Agreement were issued by Skymax to the Mbook
through which 4 (four) new locations were awarded to Mbook for
carrying out the work. However, no revised date of competition after
award of the works at the said additional location was communicated to
the petitioner.
12. Thus, learned Senior Counsel argued that it is a fit case for grant
status quo on Termination Notice and consequences following from the
same. It is submitted that the allotted work would be completed by
Mbook within 30 days and thus, the work would be expeditiously carried
out if operation of Termination Notice is stayed.
13. Mr. Sandeep Sethi, learned Senior Counsel has again drawn my
attention to Clause 9.2.2 of the Agreement dated 18.12.2025 in which it
is stated that if either party fails to fulfill its obligation under the
Agreement and does not rectified the breach within 30 days of receiving
the notice, the aggrieved party shall be entitled to terminate the
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 5 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

Agreement. It is submitted that no 30 days written notice was given to
Mbook to cure the defects. Therefore, it is submitted that Termination
Notice is illegal in the eyes of law.
14. Mr. Sandeep Sethi, learned Senior Advocate has strongly relied
upon Mahajan Imaging (P) Ltd. v. Pushpawati Singhania Research
Institute , 2026 SCC OnLine Del 1779, in which this Court held that the
parties are bound to adhere to termination mechanism embodied in the
Agreement and that the proper course would have been to issue a notice
identifying the alleged material breach and affording the aggrieved party
a contractually mandated opportunity to cure the same within the
prescribed period. It was further held that it is only upon the failure to
rectify such breach within the stipulated time, that a right to issue a
termination notice could have arisen.
15. Learned Senior Counsel pointed out that in aforesaid case, no
„cure notice‟ was issued before terminating the Agreement and therefore,
a status quo order dated 29.10.2026 was passed by this Court with
respect to operation, implementation and performance of the agreement
as it is stood immediately prior to issuance of the said termination notice.
16. Learned Senior Counsel submits that facts of the present case are
similar to case of Mahajan Imaging (Supra) .
17. Countering the submissions of learned Senior Counsel for Mbook,
learned Counsel for respondent-Skymax has drawn my attention to the
fact that in Mahajan Imaging (Supra) , the Agreement was for providing
radiology services. It is submitted that the nature of agreement between
the parties in Mahajan Imaging (Supra) should be differentiated with
the infrastructure projects which have been categorized in Schedule to
the Specific Relief Act, 1963 (in short „Act of 1963‟). It is submitted that
the Category no. II in the Schedule is „Energy Sector‟.
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 6 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

18. Learned Counsel for Skymax has drawn my attention to the
Agreement dated 18.12.2025 which shows that the Agreement is in
respect of a solar project. Therefore, the embargo of Section 20A and
Section 41 (ha) of the Act of 1963 would come into play. It is argued
that as the project falls in the category of infrastructure projects specified
in the Schedule, no stay on termination of contract can be granted.
19. I have carefully perused the material on record and considered the
submissions advanced by learned Counsels for the parties.
20. The fact that the Agreement in question pertains to Energy Sector,
specified in the Schedule of the Act of 1963, has not been disputed.
Now, I reproduce Section 20A of the Act of 1963 as under:
“Special provisions for contract relating to infrastructure
project.
20A. ( 1 ) No injunction shall be granted by a court in a suit under
this Act involving a contract relating to an infrastructure project
specified in the Schedule where granting injunction would cause
impediment or delay in the progress or completion of such
infrastructure project.

Explanation .—For the purposes of this section, section 20B and
clause ( ha ) of section 41, the expression "infrastructure project"
means the category of projects and infrastructure Sub-Sectors
specified in the Schedule.
(2) The Central Government may, depending upon the requirement
for development of infrastructure projects, and if it considers
necessary or expedient to do so, by notification in the Official
Gazette, amend the Schedule relating to any Category of projects
or Infrastructure Sub-Sectors.
(3) Every notification issued under this Act by the Central
Government shall be laid, as soon as may be after it is issued,
before each House of Parliament, while it is in session, for a total
period of thirty days which may be comprised in one session or in
two or more successive sessions, and if, before the expiry of the
session immediately following the session or the successive
sessions aforesaid, both Houses agree in making any modification
in the notification or both Houses agree that the notification
should not be made, the notification shall thereafter have effect
only in such modified form or be of no effect, as the case may be;
so, however, that any such modification or annulment shall be
without prejudice to the validity of anything previously done under
that notification .”
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 7 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

21. Thus it is clear that Section 20A of the Act of 1963 proscribes the
Court from issuing any injunction involving a contract relating to
infrastructure project specified in the Schedule to the Act of 1963, in
case it will cause impediment in completion of the project. Further,
Section 41 (ha) of the Act of 1963 contains a general prohibition from
granting a stay in any infrastructural project, even if the same does not
fall in the Schedule of the Act of 1963. Section 41 (ha) of Specific Relief
Act is reproduced as under:
“41. Injunction when refused
An injunction cannot be granted –
(a) ……………………..
(b) …………………….
(c) …………………….
(d) ……………………..
(e) …………………….
(f) ……………………..
(g) ……………………...
(h) ………………………
(ha) if it would impede or delay the progress or completion of any
infrastructure project or interfere with the continued provision of
relevant facility related thereto or services being the subject
matter of such project;”

22. Thus, Section 20A of the Act of 1963 clearly bars the Court from
granting an injunction involving a contract relating to a infrastructure
project specified in the Schedule to the Act of 1963 if it would cause
impediment or delay in the progress or completion of such infrastructure
project.
23. Argument of learned Senior Counsel for Mbook is that, had the
Skymax given a cure notice as per Clause 9.2.2, he would have complied
with the same and this would have actually expedited the progress of the
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 8 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

project. It is argued that even if today, „cure notice‟ of 30 days is given,
the defects would be removed and thus, it would save Skymax from the
trouble and expenses of bringing a third party for completion of the
contract.
24. I disagree with the submissions of Mr. Sandeep Sethi, learned
Senior Counsel.
25. It must be kept in mind that no party would like to terminate a
contract midway unless serious disputes have arisen about the execution
of the obligations. Therefore, to say that staying of Termination Notice
would expedite the project is unacceptable. The impugned Termination
Notice has mentioned that Mbook had abandoned the works without any
justification and its persistent defaults have not only inordinately delayed
the entire project but has also caused substantial loss to Skymax. It is
also mentioned that such conduct of Mbook has also exposed Skymax to
adverse action at the hands of principal employer i.e. Maharashtra State
Electricity Distribution Company Ltd. It would be of course, a subject
matter before the learned Arbitrator as to whether the said allegations are
correct or not but, at this stage, this Court is looking at the prima facie
case only.
26. If the Skymax has wrongly terminated the contract, the only
remedy with the Mbook is to claim compensation/damages. However,
this Court cannot ignore the specific prohibition of Section 20A of the
Act of 1963 from granting an injunction in a contract like the present one
as well as general prohibition under Section 41 (ha) of the Act of 1963.
27. I have carefully perused the judgment of Mahajan Imaging
(Supra) and I agree with learned Counsel for the respondent-Skymax that
in the said judgment, the Court was not dealing with an infrastructure
project as specified in the Schedule of the Act of 1963, whereas the
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 9 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

present project falls in the Schedule, in respect of which Section 20A of
the Act of 1963 creates a prohibition.
28. Hence, this petition is dismissed. The pending application also
stands disposed of.
O.M.P (I) (COMM.) 512/2026
29. Now, I take up the petition filed under Section 9 of the Act of
1996 by Skymax Infra Power Ltd. in OMP (I) (COMM.) 512/2026, in
which it is prayed as under:
“A. Direct the Respondent to vacate the project site and restore
possession of all related assets belonging to existing works,
installations, equipment, materials, and technical records, for the
42/53.268 MW PMKUSUM Component-C Solar Project located in
Nanded District, Maharashtra to Petitioner immediately; and/or
B. Direct the Respondent to forthwith hand over and deliver to
Petitioner all project-related documents, records and deliverables
required to be provided under the Sub-Contract Agreement dated
18.12.2025, including, without limitation, all original invoices,
OEM/vendor warranty and guarantee certificates, equipment and
material warranties, quality and inspection records, test reports,
operation and maintenance manuals, pre-commissioning and
commissioning records, insurance policies and endorsements,
vendor payment clearances, No Objection Certificates (NOCs),
and all departmental, statutory, regulatory, technical and other
approvals, permissions, sanctions and clearances pertaining to the
Project and the equipment, machinery and materials procured,
supplied, installed or intended to be deployed thereunder, insofar
as the same are in the possession, custody or control of the
Respondent or are required to be procured or furnished by it under
the Agreement; and/or
C. Pass such other or further orders as this Hon’ble Court may
deem just, necessary and appropriate in the facts and
circumstances of the case.”

30. In a nutshell, Skymax is praying that Mbook may be directed to
vacate the site project and restore the possession of all the assets to
Skymax and also deliver all project related documents, records etc. to the
Skymax.
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 10 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

31. Mr. Sandeep Sethi, learned Senior Counsel for Mbook has
assailed these prayers submitting that these prayers, being mandatory
injunction, are beyond the scope of Section 9 of the Act of 1996.
32. It is further argued that if the prayer of the Skymax are accepted,
the same would amount to final adjudication of the issues. In support of
his submissions, learned Senior Counsel for Mbook has referred to
judgments of Division Benches of Delhi High Court in Deepak Balutia
vs Anu Manglani , in FAO (COMM) 235/2026 dated 30.09.2026 and
National Highways Authority of India vs. Bhubaneswar Expressway
Private Limited in FAO (OS) (COMM) 66/2020 dated 11.05.2021 .
33. It is argued that the prayers of this petition are in nature of final
relief and if allowed, same would reduce the arbitral Award to a mere
paper decree.
34. I have considered the rival submissions and have perused the
judgment in Deepak Balutia (Supra ) . In this case, the Division Bench of
this Court was dealing with an order passed by District Judge under
Section 9 of the Act of 1996, whereby learned District Judge directed the
landlord to restore electricity connection in the tenanted premises
without any corresponding direction for payment of lease rent.
Therefore, the said order was set aside. But it was nowhere held that the
District Judge had no power to issue direction for restoration of the
electricity. It was set aside because it was unreasonable as it ignored the
corresponding rights of the landlord to receive the lease rent.
35. I have also perused Bhubaneswar Expressway (Supra), which is
a judgment of Division Bench of this Court.
36. Perusal of the aforesaid judgment makes it clear that though the
Court under Section 9 of the Act of 1996 can issue interim measures but
it cannot pass an order which amounts to final adjudication of an issue.
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 11 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

In the said judgment, the Division Bench was dealing with an order of
the Commercial Division, which allowed an application under Section 9
of the Act of 1996, filed by Bhubaneswar Expressway Private Limited
while holding that National Highways Authority of India was liable to
make payment of Termination Notice equivalent to 90% of debt due.
The Division Bench held that this was practically a final decision on the
dispute between the parties and that this dispute could only be
adjudicated by Arbitral Tribunal and cannot be adjudicated in
proceedings under Section 9 of the Act of 1996.
37. However, facts before this Court are totally different. As the
agreement has been terminated by Skymax, Mbook-respondent can only
claim the damages for breach of contract through arbitration. In a claim
for damages, issue of vacation of the site would not arise. Skymax-
petitioner wants to complete the project expeditiously and for that
purpose it wants the project site to be vacated by Mbook.
38. Issuing the directions as prayed would not amount to award of
claim of Mbook, which would of course be a subject matter of the
arbitration proceedings.
39. Therefore, I am of the opinion that interim measures can be
ordered by this Court for helping Skymax in timely completion of the
project. I would like to reproduce relevant provisions of Section 9 of the
Act of 1996, as under:
“9. Interim measures, etc., by Court. - [(1)] A party may, before or
during arbitral proceedings or at any time after the making of the
arbitral award but before it is enforced in accordance with section
36, apply to a Court:
(i) ……………………;
(ii) for an interim measure of protection in respect of any of the
following matters, namely:
(a) …………………..;
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 12 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

(b) …………………..;
(c) the detention, preservation or inspection of any property or
thing which is the subject-matter of the dispute in arbitration, or as
to which any question may arise therein and authorising for any of
the aforesaid purposes any person to enter upon any land or
building in the possession of any party, or authorising any samples
to be taken or any observation to be made, or experiment to be
tried, which may be necessary or expedient for the purpose of
obtaining full information or evidence;
(d) ……………………;
(e) such other interim measure of protection as may appear to
the Court to be just and convenient,
and the Court shall have the same power for making orders as it
has for the purpose of, and in relation to, any proceedings before
it.”
40. The language used in Clause (c) and (e) of Section 9 of the Act of
1996 are wide enough, but short of passing any interim award, to pass
any direction for protection or preservation of any property.
41. Accordingly, with a view to protect and preserve the project site, I
direct Mbook-respondent to vacate the project site within three weeks
from this order. This order has been passed so that the project is not
further delayed.
42. In respect of other reliefs, the respondent-Mbook shall file reply.
43. The petition is re-notified for 16.12.2026.
CONCLUSION
44. The petition under Section 9 of the Act of 1996 filed by Mbook
bearing OMP (I) (COMM.) 503/2026 along with pending application is
dismissed.
45. The petition under Section 9 of the Act of 1996, bearing OMP (I)
(COMM.) 512/2026 is partly allowed with a direction to Mbook to
vacate the project site. In respect of remaining reliefs, the respondent-
Mbook may file reply within three weeks, rejoinder, if any be filed one
week thereafter.
Signature Not Verified

O.M.P.(I) (COMM.) 503/2026 & O.M.P.(I) (COMM.) 512/2026 Page 13 of 14

Signed By:PRAMOD
KUMAR VATS
Signing Date:17.11.2026
10:22:24

46. The petition bearing OMP (I) (COMM.) 512/2026 is re-notified
for 16.12.2026

VINOD KUMAR, J
NOVEMBER 06, 2026 / vb