Union Of India vs M/S Bijender Singh Contractor
- Court
- Madhya Pradesh High Court
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
1 AA-165-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT GWALIOR
BEFORE
HON'BLE SHRI JUSTICE ASHISH SHROTI
th
ON THE 11 OF AUGUST, 2026
ARBITRATION APPEAL No. 165 of 2026
UNION OF INDIA
Versus
M/S BIJENDER SINGH CONTRACTOR
Appearance:
Mr. Praveen Kumar Newaskar - Deputy Solicitor General for Union of
India - appellant.
Mr. Arun Dudawat - Advocate for respondent no.1.
ORDER
This appeal has been filed by the appellant/Union of India under
Section 37 of the Arbitration and Conciliation Act, 1996, challenging the
order dated 17.03.2026 passed by the 20th District Judge and Special Judge
(Commercial Court), Gwalior, in MJC AV No.2 of 2019, whereby the
application filed by it under Section 34 of the Act has been rejected.
2. The facts giving rise to the filing of this appeal are that the
respondent was awarded a contract for widening and maintenance of the link
taxi track at Air Force Station Maharajpura, Gwalior, by the appellant. The
contract agreement was executed on 19.05.2009, as per which the contract
was for an amount of Rs.1,87,99,462/- and was to be completed within an
aggregate period of 12 months in two phases. The period prescribed for
completion of the first phase was from 19.09.2009 to 18.01.2010, and for the
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
2 AA-165-2026
second phase, from 19.01.2010 to 18.09.2010.
3. The respondent commenced the work. However, the work of the
first phase could not be completed within the prescribed time. The time was,
therefore, extended by the appellant up to 18.03.2010. The period for
completion of the second phase was also extended up to 07.06.2011.
4. After completion of the work, the respondent submitted his final bill
before the appellant on 04.08.2011. It is the case of the respondent that no
objection was raised by the appellant. The final payment of the bill was made
on 22.04.2013.
5. Certain disputes arose between the parties, which are not required to
be elaborately mentioned in this order. It is sufficient to mention that when
the dispute could not be resolved, the respondent served a notice on
08.08.2014 invoking the arbitration clause of the agreement and requesting
the appellant to appoint an arbitrator. Brigadier Neeraj Parashar was
thereafter appointed as the sole arbitrator, who passed his award on
26.09.2018. A total amount of Rs.29,96,926/-, along with interest, was
awarded in favour of the respondent as against his total claim of
Rs.1,51,72,881.27.
6. The said award was challenged by the appellant by filing an
application under Section 34 of the Act before the Court. The same was
dismissed vide impugned order dated 17.03.2026, challenging which the
present appeal has been preferred.
7. The learned Deputy Solicitor General appearing for the appellant
challenged the impugned order on two grounds. Firstly, that the respondent
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
3 AA-165-2026
himself was responsible for the delay in completion of the work, and
therefore, no amount under this head could have been awarded by the
arbitrator. Secondly, it was submitted that the claim raised by the respondent
was barred by limitation, inasmuch as the final bill was submitted by the
respondent on 04.08.2011, whereas the notice invoking the arbitration clause
was served on 08.08.2014, which was beyond the period of three years
prescribed for limitation.
8. Mr. Arun Dudawat, appearing for the respondent, refuted the
submissions made by learned counsel for the appellant. As per his
submission, the site was handed over to the respondent after a considerable
delay, which resulted in non-completion of the work within the stipulated
time. Therefore, the respondent could not be penalized on account of the
delay on the part of the appellant. He further argued that the final bill was
submitted by the respondent on 04.08.2011. The amount was paid by the
appellant on 22.04.2013, and thereafter, a notice requesting appointment of
an arbitrator was served on 08.08.2014. Therefore, it could not be said that
the respondent's claim was barred by limitation.
9. Considered the arguments.
10. Before adverting to the merits of the case, it is profitable to refer to
the scope of interference by this Court under Section 37 of the Act.
11. The Apex Court in the case of MMTC Ltd. Vs. Vedanta Ltd.,
reported in (2019)4 SCC 163, wherein the Court held in paras 11 to 14 as
under :
11. As far as Section 34 is concerned, the position is well-settled
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
4 AA-165-2026
by now that the Court does not sit in appeal over the arbitral award
and may interfere on merits on the limited ground provided under
Section 34(2)(b)(ii) i.e. if the award is against the public policy of
India. As per the legal position clarified through decisions of this
Court prior to the amendments to the 1996 Act in 2015, a
violation of Indian public policy, in turn, includes a violation of
the fundamental policy of Indian law, a violation of the interest of
India, conflict with justice or morality, and the existence of patent
illegality in the arbitral award. Additionally, the concept of the
“fundamental policy of Indian law” would cover compliance with
statutes and judicial precedents, adopting a judicial approach,
compliance with the principles of natural justice, and Wednesbury
[Associated Provincial Picture Houses v. Wednesbury Corpn.,
(1948) 1 KB 223 (CA)] reasonableness. Furthermore, “patent
illegality” itself has been held to mean contravention of the
substantive law of India, contravention of the 1996 Act, and
contravention of the terms of the contract.
12. It is only if one of these conditions is met that the Court may
interfere with an arbitral award in terms of Section 34(2)(b)(ii),
but such interference does not entail a review of the merits of the
dispute, and is limited to situations where the findings of the
arbitrator are arbitrary, capricious or perverse, or when the
conscience of the Court is shocked, or when the illegality is not
trivial but goes to the root of the matter. An arbitral award may not
be interfered with if the view taken by the arbitrator is a possible
view based on facts. (See Associate Builders v. DDA [Associate
Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] .
Also see ONGC Ltd. v. Saw Pipes Ltd. [ONGC Ltd. v. Saw Pipes
Ltd., (2003) 5 SCC 705] ; Hindustan Zinc Ltd. v. Friends Coal
Carbonisation [Hindustan Zinc Ltd. v. Friends Coal
Carbonisation, (2006) 4 SCC 445] ; and McDermott International
Inc. v. Burn Standard Co. Ltd. [McDermott International Inc. v.
Burn Standard Co. Ltd., (2006) 11 SCC 181] )
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
5 AA-165-2026
13. It is relevant to note that after the 2015 Amendment to Section
34, the above position stands somewhat modified. Pursuant to the
insertion of Explanation 1 to Section 34(2), the scope of
contravention of Indian public policy has been modified to the
extent that it now means fraud or corruption in the making of the
award, violation of Section 75 or Section 81 of the Act,
contravention of the fundamental policy of Indian law, and
conflict with the most basic notions of justice or morality.
Additionally, sub-section (2-A) has been inserted in Section 34,
which provides that in case of domestic arbitrations, violation of
Indian public policy also includes patent illegality appearing on
the face of the award. The proviso to the same states that an award
shall not be set aside merely on the ground of an erroneous
application of the law or by reappreciation of evidence.
14. As far as interference with an order made under Section 34, as
per Section 37, is concerned, it cannot be disputed that such
interference under Section 37 cannot travel beyond the restrictions
laid down under Section 34. In other words, the court cannot
undertake an independent assessment of the merits of the award,
and must only ascertain that the exercise of power by the court
under Section 34 has not exceeded the scope of the provision.
Thus, it is evident that in case an arbitral award has been
confirmed by the court under Section 34 and by the court in an
appeal under Section 37, this Court must be extremely cautious
and slow to disturb such concurrent findings."
12. Recently in the case of Jan De Nul Dredging India (P) Ltd. Vs.
Tuticorin Port Trust, reported in (2026)3 SCC 186, the Apex Court held
in para 29 as under:
29. That being the position, the award of the Arbitral Tribunal was
not liable to be disturbed under Section 34 of the Act and was
rightly not disturbed. It is settled in law that the appellate powers
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
6 AA-165-2026
under Section 37 are limited to the scope of Section 34 and cannot
exceed beyond it. Certainly, therefore, if an award is not liable to
be disturbed under Section 34 of the Act, the same could not have
been interfered with in exercise of powers under Section 37 of the
Act.
13. Further, in the case of Swan Gold Mining Ltd. Vs. Hindustan
Copper Ltd, reported in (2015)5 SCC 739; and in the case of Dyna
Technologies (P) Ltd. Vs. Crompton Greaves Ltd., reported in (2019)20
SCC 1, similar position of law is reiterated. In Dyna Technologies (P)
Ltd. Court held in para 24 as under :
"24. There is no dispute that Section 34 of the Arbitration Act
limits a challenge to an award only on the grounds provided
therein or as interpreted by various courts. We need to be
cognizant of the fact that arbitral awards should not be interfered
with in a casual and cavalier manner, unless the court comes to a
conclusion that the perversity of the award goes to the root of the
matter without there being a possibility of alternative
interpretation which may sustain the arbitral award. Section 34 is
different in its approach and cannot be equated with a normal
appellate jurisdiction. The mandate under Section 34 is to respect
the finality of the arbitral award and the party autonomy to get
their dispute adjudicated by an alternative forum as provided
under the law. If the courts were to interfere with the arbitral
award in the usual course on factual aspects, then the commercial
wisdom behind opting for alternate dispute resolution would stand
frustrated."
14. Keeping in view the aforesaid legal position, the submissions
made by learned counsels needs to be considered.
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM
NEUTRAL CITATION NO. 2026:MPHC-GWL:24671
7 AA-165-2026
15. The first ground of challenge raised by the appellant is with regard
to the delay in completion of the work by the respondent. This aspect has
been considered by the Lower Court in paragraphs 23 & 24 of the impugned
order. It has been held that the appellant itself was responsible for handing
over the site to the respondent, which resulted in the delay in completion of
the work. Because of this delay, the respondent was compelled to complete
the work at higher rates for construction material and labour charges. The
appellant could not point out any illegality or perversity in the aforesaid
finding. Therefore, the first ground raised by learned counsel for the
appellant is not acceptable and is accordingly rejected.
16. After completion of the work, the final bill was submitted by the
respondent on 04.08.2011. It is gathered from the record that there was some
dispute with regard to the rates at which the bill was submitted. Ultimately,
the payment was made on 22.04.2013. The notice requesting appointment of
an arbitrator was given on 08.08.2014. Thus, it cannot be said that the claim
raised by the respondent was beyond the period of limitation.
17. Considering the aforesaid, both the grounds raised by learned
counsel for the appellant are not acceptable. Consequently, the impugned
order dated 17.03.2026 is upheld and the appeal fails and is accordingly
dismissed.
(ASHISH SHROTI)
JUDGE
bj/-
Signature Not Verified
Signed by: BARKHA
SHARMA
Signing time: 08/17/2026
10:30:32 AM