Sudarshana vs The State Of Madhya Pradesh
- Court
- Madhya Pradesh High Court
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
1 WP-45080-2025
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE
BEFORE
HON'BLE SHRI JUSTICE SANDEEP N. BHATT
st
ON THE 31 OF AUGUST, 2026
WRIT PETITION No. 45080 of 2025
KULDEEP SHARMA AND OTHERS
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Vivek Patwa - Advocate for the petitioners.
Shri Shrey Raj Saxena- Dy.A.G for the State.
Shri Prashant Singh - Advocate General along with Shri Rahul Gupta - Advocate
for the respondent / MPRDC.
WITH
WRIT PETITION No. 45084 of 2025
SUDARSHANA AND OTHERS
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Vivek Patwa - Advocate for the petitioners.
Shri Shrey Raj Saxena- Dy.A.G for the State.
Shri Prashant Singh - Advocate General along with Shri Rahul Gupta -
Advocate for the respondent / MPRDC.
Reserved on : 19/08/2026
Delivered on : 31/08/2026
----------------------------------------------------------------------------------------------
ORDER
1/ This order will govern the disposal of W.P. Nos. 45080 of 2025 and
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
2 WP-45080-2025
45084 of 2025 as it is jointly submitted by counsel for the parties that both
the writ petitions involve the same issue on the identical facts situation. For
the sake of convenience, the facts are noted from W.P. no. 45080 of 2025
2/ Present petition i.e. W.P. no. 45080 of 2025 has been filed under
Article 226 of the Constitution of India seeking following reliefs :
1. Issue a writ direction or order in the nature of MANDAMUS or other
appropriate writ calling for the records from the respondents,
2. Issue a writ, direction or order in the nature of CERTIORA or other
appropriate writ quashing the impugned Notification U/s 11 dated
17/03/2025,
3. Issue a writ, direction or order in the nature of CERTIORARI or other
appropriate writ quashing the impugned order dated U/s 15 dated
14/08/2025 rejecting the objections filed by the petitioners’,
4. Issue a writ, direction or order in the nature of CERTIORARI or other
appropriate writ quashing the impugned Notification U/s 19 dated
26/09/2025
5. Issue a writ, direction or order in the nature of MANDAMUS or other
appropriate writ directing the respondents to acquire the land equally on
both the sides of the existing road,(vi) Award the costs of the petition and
6. Grant such other relief or reliefs as it deems fit in the facts and
circumstances of the case.
3/ The facts of the case in brief are that the petitioners are residents of
Village - Sanwarakhedi,Tehsil and District Ujjain, whose lands are sought to
be acquired for the widening of Ujjain Simhasth Bypass 4 lane road with
paved shoulders and up-gradation. The respondents intend to widen/ upgrade
the existing Simhasth at Ujjain By pass road from a two lane roads to a four
lane roads by extending it on one side only thereby affecting the petitioners'
lands. Respondent no. 4, requiring body, on 28/01/2025 made a request to
the respondent no. 2 to acquire the lands of the petitioners for the alleged
Ujjain Simhasth Bypass 4 lane road {hereinafter referred to as “subject
road”} with paved shoulders, which is neither a National, nor a State
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
3 WP-45080-2025
Highway. Based on the requisition, the respondent no. 2 by its order dated
31/01/2025 constituted the Social Impact Assessment Team {SIA Team},
which was required to make the assessment of the social impact after
conducting a public hearing as per section 5 of the Right to fair
compensation and transparency in land acquisition, rehabilitation, and
resettlement Act, 2013 [ hereinafter referred to “the Act of 2013”] and
submit its report to the Expert Group. On receipt of the requisition, the
respondent no. 2 had constituted the SIA Team without taking the aforesaid
mandatory statutory undertaking. The members of the SIA Team submitted
its impugned undated report for appraisal to the Expert report U/s 7 of the
Act of 2013. The aforesaid report of SIA Team was submitted to the
respondent no. 3 on 11/02/2025. On 07/02/2015, the requiring body i.e the
respondent no. 4 itself recommended the formation of Expert Group U/s 7 of
the Act of 2013 for appraisal of the SIA report. Based on the said
recommendations, the respondent no. 3 formed the Expert Group. Based on
the aforesaid recommendations, the respondent no. 2 by its order dated
25/02/2025 constituted the Expert Group U/s 7 of the Act of 2013. The
aforesaid Expert Group made the assessment of the report submitted by the
SIA Team and recommended for the impugned acquisition without taking
into consideration the fact that the acquisition is being sought only on one
side of the existing road and a benefit has been passed over to all the land
owners on the other side to the detriment of the rights of the petitioners.
Based on the aforesaid report, on 17/03/2025, the respondent no. 2 issued the
impugned notification under section 11 (1) of the Act of 2013 requisitioning
the petitioners' land for acquisition leaving the land situated on the other side
of the existing road. After the issuance of notification U/s 11(1) of the Act of
2013, the petitioners duly filed their objections by alleging that the land
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
4 WP-45080-2025
must be acquired equally on both the sides, The petitioners, on 04/07/2025,
during the course of hearing of their objections, submitted their detailed
written arguments in support of their objections. The respondent/s ignored
the objections raised by the petitioners and by the impugned order
dated14/08/2025 has rejected the objections filed by the petitioners on
extraneous and non-existing grounds. After the rejection of the petitioners'
objection as mentioned hereinabove, the respondents, on 26/09/2025, has
issued notification U/s 19 of the Act of 2013 declaring that the petitioners'
land is sought to be acquired for public purpose. Under such circumstances,
the present petition is preferred before this Court.
4/ Learned counsel for the petitioners has submitted that the right to
property of a citizen has been protected by Article 300-A of The
Constitution of India. The property of any person cannot be acquired without
following the due process of law. In the present case, the respondents have
deliberately violated the statutory provisions of the Act of 2013 and
mandatory Rules of 2014 [ in short “The Central Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation, and Resettlement (
Social Impact Assessment and Consent ) Rules, 2014”] and the Rules of
2015 [ in short “The Madhya Pradesh Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation, and Resettlement Rules,
2015”] framed prescribing the process for formation of the SIA Team and
the process to be adopted by the SIA Team to prepare the Report. Learned
counsel further submitted that the constitution of the SIA Team itself
is contrary to the Rule 6(5) of The Rules of 2014 as no team leader
was appointed/ nominated by the respondents, thus the
recommendations made by it could not have been accepted. The
respondents failed to take the mandatory undertaking from the
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
5 WP-45080-2025
members of the SIA Team as prescribed under Rule 7 (ii) of The
Rules of 2014, the SIA Team did not consist of any officer below the
rank of Dy. Collector in violation of Rule 3(1) of The Rules of 2015,
thus in the absence that of the team itself could not have been
constituted nor could the recommendations made by such Team
accepted by the Expert Group or respondents. The SIA Team did not
conduct the public hearing in accordance with section 5 of The Act
of 2013, as no publicity was given of the hearing as per law. The
respondent/s failed to publicize the notice of public hearing in the
vicinity of 5 kms as mandated in the applicable rules for the purpose.
Learned counsel has further submitted that the respondents have admittedly
overlooked the aim and object of The Act of 2013 and Rules made
thereunder and in a discriminatory and high handed manner by violating the
statutory provisions have carried out the acquisition proceedings. Learned
counsel has further submitted that the present petition has been filed
assailing the notifications issued U/s 11, 15(1) and 19 of The Act of 2013
without following the procedure prescribed under the said act and in utter
violation of The Ruler of 2014 and 2015 framed in respect thereof.
5/ Learned counsel has also submitted that the respondents are intending
to acquire the land for up-gradation on one side of the road just to give
undue advantage to the land owners on the other side of the road, but it has
to be done equally on both sides of the existing center line of the road.
Therefore, it is clear that the area, sought to be acquired, cannot be treated as
suitable even technically appropriate. It is submitted that the respondents
have clearly violated the procedure prescribed under the Rules of 2014 and
2015 for constitution of the Social Impact Assessment Team as well as the
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
6 WP-45080-2025
Expert Group. Further, the Committee formulated for the purpose also did
not follow the prescribed procedure and submitted their report which prima
facie is illegal and void. It is also submitted that, the factual aspects and
ground reality has been ignored and overlooked to mislead the appropriate
Authority to demonstrate that no Rehabilitation and Resettlement is required,
whereas the fact is that there are number of land owners, who are losing their
entire land and/ or are left with very small piece/ portion of land, which
cannot be used for agriculture purpose and will only be used either for
residential purpose or commercial purpose to open local shops. All such land
owners shall be required to be rehabilitated and resettled, which has
completely been overlooked and concealed in the alleged report prepared in
respect of the subject.
6/ Learned counsel has further submitted that the width of the road is
proposed to 45 mts, which is detrimental to the rights of all the land owners,
whose lands are under acquisition. It is submitted that a four land road can
very well be upgraded within a width of 22 mts. which the respondents
already possess. It is submitted that the road with requisite is very well
defined in the guidelines prescribed by the Indian Road Congress.
Undisputedly, Clause 2.4 of IRC SP 84-2019 specify that the width of a
carriage way is 3.5 mts and clause 2.7 thereof states that the width of the
roadway is the sum of width of the carriageway, shoulders and the meridian.
There is no necessity for acquisition of land for a 45 mts. road is required. It
is submitted that for developing the road, it is in the interest of justice that
minimum acquisition of land should be carried out. It is further submitted
that as per clause 105.7 of IRC: 5-2015, the approach to the bridge on both
sides should be at least 15 mts on horizontal profile. This can easily be done
by appropriately acquiring the lands on the approach of the bridges, for
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
7 WP-45080-2025
which the entire road is not required to be widened to 45 mts. Therefore, the
respondent / MPRDC has tried to mislead this Hon'ble High Court to
demonstrate a dire need for Simhasth, whereas their need can be satisfied in
the existing land held by them in the acquisition done in 2013. Thus, the
justification offered for public purpose is sham and unsustainable. Learned
counsel has further submitted that the Hon'ble Supreme Court in the case of
Dinesh & others Vs State of M.P. & others (SLP no. 28410-28414 of 2023)
allowed the SLP as the respondents did not followed the prescribed
procedure under The Act of 2013 and quashed the Award passed during the
pendency of proceedings. To bolster his contentions, he has placed reliance
upon the judgments reported in (2012) 1 SCC 792 [ Raghbir Singh Sehrawat
Vs State of Haryana & others] and (2012) 9 SCC 503 [Patasi Devi Vs State
of Haryana & others].
7/ Learned counsel has also submitted that the State Government has also
framed The Madhya Pradesh Right to Fair Compensation and Transparency
in Land Acquisition, Rehabilitation and Resettlement Rules, 2015 in
consonance with The Rules of 2014 which contain the similar provisions
with respect to the procedure to be followed by the SIA Team for
preparation of the report. Thus, the act of the respondents is also violative of
the Rules of 2015 also. It is further submitted that in connected W.P.
45084/2025 filed in respect of the land sought to be acquired of village
Jeevankehdi. The SIA Team formed is also violative of Rule 6 (4) (b) of The
Rules of 2014 of M.P., which mandates that there must include at least one
female member in the Team constituted for the aforesaid, which is not done.
In view of the aforesaid, the petition deserves to be allowed and the
impugned notifications as well as the Award passed based thereon deserves
to be quashed in the interest of justice.
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
8 WP-45080-2025
8/ Per-contra, learned Advocate General for the respondent / MPRDC,
duly assisted by counsel for the State, has submitted that no officer of below
the rank of Deputy Collector was made the Team Leader. As per the
statutory position under section 22 of the MP Land Revenue Code
(MPLRC), the State Government/Collector places an Assistant Collector,
Joint Collector, or Deputy Collector in charge of a Sub-Division, who is
designated as the Sub-Divisional Officer (SDO/SDM). Therefore, an
SDM/SDO is inherently drawn from the cadre of Deputy Collectors or
higher administrative ranks (Joint/Assistant Collector). An SDM/SDO
(Revenue) is an administrative charge held by an officer who is either
equivalent to or higher in rank than a Deputy Collector. Thus,
appointment/designation of the Sub-Divisional Magistrate/Officer
(SDM/SDO) as the leader or head of the SIA process fully satisfies and
complies with Rule 3(1) of the MP Rules, 2015. Learned counsel has further
submitted that there is availability of an efficacious statutory remedy under
Section 64 of the Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013 and by virtue of the
judgment delivered in the case of Saira Bee & Ors. v. Urban Administration
& Development Dept. (Writ Appeal No. 117/2025, the Division Bench of
this Court held that once a final land acquisition award is passed, the High
Court under Article 226 will not interfere with the acquisition, and the
remedy for remaining occupants is strictly to approach the authority under
Section 64 of the Act of 2013. In the case of Anil Verma v. State of M.P.
(W.P. No. 13246/2026, MP High Court Bench at Indore has reiterated that
after passing of an compensation, and maintaining a writ petition to stall
execution of a public project is impermissible. Learned counsel has further
submitted that out of nearly 1,500 affected landowners, more than 1,300
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
9 WP-45080-2025
have accepted the Award and compensation and the land owned by the
petitioners constitutes only a negligible portion of the total acquisition for
the 19.815 km project corridor and handful of objectors cannot be permitted
to frustrate or delay a mega public infrastructure project undertaken in larger
public interest. In support of his contention, learned counsel has placed
reliance upon the judgment delivered by Hon'ble Supreme Court in the case
of A.J. George v. State of Kerala (2017 SCC OnLine Ker 23421) wherein it
has been held that a land acquisition award is indivisible, and once passed
and accepted by the majority of beneficiaries, an individual landowner
cannot break the integrity of the award or seek quashing of proceedings on
the basis of minor procedural objections. (Relevant Para 7 & 11). In the case
o f Bhimavarapu Giridhar Kumar Reddy v. Union of India (2023 SCC
OnLine AP 4484) the Andhra Pradesh High Court held that where a highway
is being constructed on either side, a small patch of land forming a negligible
portion of the corridor cannot be permitted to hold the public infrastructure
project hostage.
9/ Learned counsel has further submitted that the respondents have
substantially complied with all mandatory requirements under the Act of
2013, including Sections 4, 5, 7, 11, 15, 19 and 21, read with the applicable
Madhya Pradesh Rules, He has placed reliance upon the judgment delivered
in the case of Binding Legal Precedent: Yudhvir Singh v. Govt. of NCT of
Delhi (2024 SCC Onine Del 471), relying upon the judgment of the Hon'ble
Supreme Court in CCE v. Hari Chand Shri Gopal, (2011) I SCC 236, the
Division Bench of the Delhi High Court applied the Doctrine of Substantial
Compliance to hold that where the mandatory requirements and public
interest objectives of the 2013 Act stand fulfilled, procedural shortfalls or
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
10 WP-45080-2025
technical rule deviations do not render the acquisition void. Learned counsel
has further submitted that the road alignment, right of way and one-sided
expansion are purely technical matters bevond the scope of judicial review
[See : Girias Investment (P) Ltd. v. State of Karnataka ((2008) 7 SCC 53)
and Union of India v Dr. Kushala Shetty, (2011) 12 SCC 69]. He has further
submitted that the acquisition serves an overriding public purpose and any
interference would seriously jeopardize Simhasth Mahakumbh, 2028. The
project in question is a time-bound, mega frontier infrastructure corridor and
the MPRDC has already issued the Work Order to the
concessionaire/contractor and failure to hand over vacant Right of Way
exposes MPRDC will result heavy per-day financial penalties, causing grave
and continuing loss to the public exchequer, apart from jeopardizing
preparedness for Simhasth 2028. It is further submitted that there is no
irreparable prejudice survives; balance of convenience and public interest
decisively favours the respondents He has further submitted that the present
petition is founded upon an erroneous interpretation of the applicable
statutory rules; the Madhya Pradesh Rules, 2015 alone govern the present
acquisition proceedings. The entire challenge raised by the petitioners
proceeds on an incorrect legal premise. The acquisition proceedings in the
present case are governed by the Madhya Pradesh Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Rules, 2015, framed by the State Government in exercise of
powers conferred under Section 109 of the Act of 2013. The State Rules
constitute the applicable statutory framework regulating acquisitions within
the State of Madhya Pradesh. In view of the aforesaid, present petition
deserves to be dismissed and no relief is required to be considered.
10/ I have considered the rival submissions of the parties and also
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
11 WP-45080-2025
considered the judgments cited by respective parties and also perused the
records.
11/ Considering the submissions made by learned counsel for the parties,
more particularly, considering the case of the petitioners that the petitioners
are mainly relying upon the Article 300-A of the Constitution of India,
which gives the right to property, he has submitted that in the present case,
the procedure is laid down by the statute by way of the Act, 2013. He has
also drawn my attention to the object of the Act, 2013 which read as under
“ STATEMENT OF OBJECTS AND REASONS.
1. The Land Acquisition Act, 1894 is the general law relating to
acquisition of land for public purposes and also for companies and for
determining the amount of compensation to be made on account of such
acquisition. The provisions of the said Act have been found to be
inadequate in addressing certain issues related to the exercise of the
statutory powers of the State for involuntary acquisition of private land
and property. The Act does not address the issues of rehabilitation and
resettlement to the affected persons and their families.
2. The definition of the expression "public purpose" as given in the Act is
very wide. It has, therefore, become necessary to re-define it so as to
restrict its scope for acquisition of land for strategic purposes vital to the
State, and for infrastructure projects where the benefits accrue to the
general public.
3. The provisions of the Act are also used for acquiring private lands for
companies. This when land could be arranged by the company through
private negotiations on a "willing seller-willing buyer" basis, which could
be seen to be a more fair arrangement from the point of view of the land
owner. In order to streamline the provisions of the Act causing less
hardships to the owners of the land and other persons dependent upon such
land, it is proposed repeal the Land Acquisition Act, 1894 and to replace it
with adequate provisions for rehabilitation and resettlement for the
affected persons and their families.
4. There have been multiple amendments to the Land Acquisition Act,
1894 not only by the Central Government but by the State Governments as
well. Further, there has been heightened public concern on land
acquisition, especially multi-cropped irrigated land and there is no central
law to adequately deal with the issues of rehabilitation and resettlement of
displaced persons. As land acquisition and rehabilitation and resettlement
need to be seen as two sides of the same coin, a single integrated law to
deal with the issues of land acquisition and rehabilitation and resettlement
has become necessary. Hence the proposed legislation proposes to address
concerns of farmers and those whose livelihoods are dependent on the
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
12 WP-45080-2025
land being acquired, while at the same time facilitating land acquisition
for industrialization, infrastructure and urbanization projects in a timely
and transparent manner.
5. Earlier, the Land Acquisition (Amendment) Bill, 2007 and
Rehabilitation and Resettlement Bill, 2007 were introduced in the Lok
Sabha on 6th December, 2007 and were referred to the Parliamentary
Standing Committee on Rural Development for Examination and Report.
The Standing Committee presented its reports (the 39th and 40th Reports)
to the Lok Sabha on 21st October, 2008 and laid the same in the Rajya
Sabha on the same day. Based on the recommendations of the Standing
Committee and as a consequence thereof, official amendments to the Bills
were proposed. The Bills, alongwith the official amendments, were passed
by the Lok Sabha on 25th February, 2009, but the same lapsed with the
dissolution of the 14th Lok Sabha.
6. It is now proposed to have a unified legislation dealing with acquisition
of land, provide for just and fair compensation and make adequate
provisions for rehabilitation and resettlement mechanism for the affected
persons and their families. The Bill thus provides for repealing and
replacing the Land Acquisition Act, 1894 with broad provisions for
adequate rehabilitation and resettlement mechanism for the project
affected persons and their families.
7. Provision of public facilities or infrastructure often requires the exercise
of powers by the State for acquisition of private property leading to
displacement of people, depriving them of their land, livelihood and
shelter, restricting their access to traditional resource base and uprooting
them from their socio-cultural environment. These have traumatic,
psychological and socio-cultural consequences on the affected population
which call for protecting their rights, particularly in case of the weaker
sections of the society including members of the Scheduled Castes (SCs),
the Scheduled Tribes (STs), marginal farmers and their families.
8. There is an imperative need to recognise rehabilitation and resettlement
issues as intrinsic to the development process formulated with the active
participation of affected persons and families. Additional benefits beyond
monetary compensation have to be provided to families affected adversely
by Involuntary displacement. The plight of those who do not have rights
over the land on which they are critically dependent for their subsistence
is even worse. This calls for a broader concerted effort on the part of the
planners to include in the displacement, rehabilitation and resettlement
process framework, not only for those who directly lose their land and
other assets but also for all those who are affected by such acquisition.
The displacement process often poses problems that make it difficult for
the affected persons to continue their traditional livelihood activities after
resettlement. This requires a careful assessment of the economic
disadvantages and the social impact arising out of displacement. There
must also be holistic effort aimed at improving the all-round living
standards of the affected persons and families.
9. A National Policy on Resettlement and Rehabilitation for Project
Affected Families was formulated in 2003, which came into force with
effect from February, 2004. Experience gained in implementation of this
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
13 WP-45080-2025
policy indicates that there are many issues addressed by the policy which
need to be reviewed. There should be a clear perception, through a careful
quantification of the costs and benefits that will accrue to society at large,
of the desirability and justifiability of each project. The adverse impact on
affected families-economic, environmental, social and cultural-must be
assessed in participatory and transparent manner. A national rehabilitation
and resettlement framework thus needs to apply to all projects where
involuntary displacement takes place.
10. The National Rehabilitation and Resettlement Policy, 2007 has been
formulated on these lines to replace the National Policy on Resettlement
and Rehabilitation for Project Affected Families, 2003. The new policy
has been notified in the Official Gazette and has become operative with
effect from the 31st October, 2007. Many State Governments have their
own Rehabilitation and Resettlement Policies. Many Public Sector
Undertakings or agencies also have their own policies in this regard.
11. The law would apply when Government acquires land for its own use,
hold and control, or with the ultimate purpose to transfer it for the use of
private companies for stated public purpose or for immediate and declared
use by private companies for public purpose. Only rehabilitation and
resettlement provisions will apply when private companies buy land for a
project, more than 100 acres in rural areas, or more than 50 acres in urban
areas. The land acquisition provisions would apply to the area to be
acquired but the rehabilitation and resettlement provisions will apply to
the entire project area even when private company approaches
Government for partial acquisition for public purpose.
12. "Public purpose" has been comprehensively defined, so that
Government intervention in acquisition is limited to defence, certain
development projects only. It has also been ensured that consent of at least
80 per cent, of the project affected families is to be obtained through a
prior informed process. Acquisition under urgency clause has also been
limited for the purposes of national defence security purposes and
Rehabilitation and Resettlement needs in the event of emergencies or
natural calamities only.
13. To ensure food security, multi-crop irrigated land shall be acquired
only as a last resort measure. An equivalent area of culturable wasteland
shall be developed, if multi-crop land is acquired. In districts where net
sown area is less than 50 per cent, of total geographical area, no more than
10 per cent of the net sown area of the district will be acquired.
14. To ensure comprehensive compensation package for the land owners a
scientific method for calculation of the market value of the land has been
proposed. Market value calculated will be multiplied by a factor of two in
the rural areas. Solatium will also be increased upto 100 per cent. of the
total compensation. Where land is acquired for urbanization, 20 per cent.
of the developed land will be offered to the affected land owners.
15. Comprehensive rehabilitation and resettlement package for land
owners including subsistence allowance, jobs, house, one acre of land in
cases of irrigation projects, transportation allowance and resettlement
allowance is proposed.
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
14 WP-45080-2025
16. Comprehensive rehabilitation and resettlement package for livelihood
losers including subsistence allowance, jobs, house, transportation
allowance and resettlement allowance is proposed.
17. Special provisions for Scheduled Castes and the Scheduled Tribes
have been envisaged by providing additional benefits of 2.5 acres of land
or extent of land lost to each affected family; one time financial assistance
of Rs. 50,000; twenty-five per cent. additional rehabilitation and
resettlement benefits for the families settled outside the district; free land
for community and social gathering and continuation of reservation in the
resettlement area, etc.
18. Twenty-five infrastructural amenities are proposed to be provided in
the resettlement area including schools and play grounds, health centres,
roads and electric connections, assured sources of safe drinking water,
Panchayat Ghars, Anganwadis, places of worship, burial and cremation
grounds, village level post offices, fair price shops and seed-cum-
fertilizers storage facilities.
19. The benefits under the new law would be available in all the cases of
land acquisition under the Land Acquisition Act, 1894 where award has
not been made or possession of land has not been taken.
20. Land that is not used within ten years in accordance with the purposes,
for which it was acquired, shall be transferred to the State Government's
Land Bank. Upon every transfer of land without development, twenty per
cent. of the appreciated land value shall be shared with the original land
owners.
21. The provisions of the Bill have been made fully compliant with other
laws such as the Panchayats (Extension to the Scheduled Areas) Act,
1996; the Scheduled Tribes and Other Traditional Forest Dwellers
(Recognition of Forest Rights) Act, 2006 and Land Transfer Regulations
in Fifth Scheduled Areas.
22. Stringent and comprehensive penalties both for the companies and
Government in cases of false information, mala fide action and
contravention of the provisions of the propose legislation have been
provided.
23. Certain Central Acts dealing with the land acquisition have been
enlisted in the Bill. The provisions of the Bill are in addition to and not in
derogation of these Acts. The provisions of this Act can be applied to
these existing enactments by a notification of the Central Government.
24. The Bill also provides for the basic minimum requirements that all
projects leading to displacement must address. It contains a saving clause
to enable the State Governments, to continue to provide or put in place
greater benefit levels than those prescribed under the Bill.
25. The Bill would provide for the basic minimum that all projects leading
to displacement must address. A Social Impact Assessment (SIA) of
proposals leading to displacement of people through a participatory,
informed and transparent process involving all stake-holders, including the
affected persons will be necessary before these are acted upon. The
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
15 WP-45080-2025
rehabilitation process would augment income levels and enrich quality of
life of the displaced persons, covering rebuilding socio-cultural
relationships, capacity building and provision of public health and
community services. Adequate safeguards have been proposed for
protecting rights of vulnerable sections of the displaced persons.
26. The Bill seeks to achieve the above objects. The notes on clauses
explain the various provisions contained in the Bill.
12/ He has also contended that the petitioners are having title over the
properties. There is no dispute about the documents, which are available on
record, indicates that the petitioners are having title over the property. He has
referred to the provisions of the Rules 6(2), 6(3). 6(4), 6(6) and 6(7) as also
Rule 8(3) of The Central Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation, and Resettlement ( Social Impact
Assessment and Consent ) Rules, 2014 [in short “ the Rules, 2014]. Lastly,
he has submitted that in view of these Rules, the requirement of woman in
such Team and other requirements are also not complied with. He has further
submitted that even the procedure is taken place in the hasty manner and on
04/02/2025, the notice is served upon the petitioners and by fixing date on
05/02/2025, whereby minimum required time is not granted under the Act.
He has further submitted that the entire procedure even go bye by the
respondents/ Authority. He has further submitted that the requiring body
cannot participate in the proceeding as per the scheme of the Act, 2013 and
the Rules, 2014 whereas in the present case, the requiring body is also
participated and has taken active part in the process. He has further
submitted that the interim order is also not complied with while passing the
Award and there is no whisper about pendency of the petitions while
recording the award by the Authority. He has further submitted that in view
of Sections 8, 11 and 15 of the Act, 2013, there is total violation of the
procedure, therefore, requires to be interfered with. He has relied upon the
judgments delivered in the case of Raghbir Singh Sehrawat Vs State of
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
16 WP-45080-2025
Haryana & others (supra) and Patasi Devi Vs State of Haryana & others
(supra) and Dinesh & others Vs State of M.P. & others (supra) and has
contended that when the respondent / Authority did not follow the prescribed
procedure under The Act of 2013, Hon'ble Apex Court has quashed the
Award passed during the pendency of proceedings. He has further submitted
that other Interlocutory Applications are pending along with present petition,
which are under consideration i.e. I.A for vacating stay, I.A for taking
additional documents on record, I.A for adoption of reply filed by
respondent no. 4, I.A for bringing additional submissions and documents on
record in support of the application seeking vacation interim relief and I.A
for deleting the name of respondent no. 1 from the present petition. He has
further submitted that those I.As may also be considered accordingly. He has
also contended that one aspect sought to be raised by the respondent/
MPRDC is that the bridge is located on the road, can be widened on one side
only. He has submitted that as per clause 105.7 of IRC: 5-2015, the
approach to the bridge on both sides should be at least 15 mts on horizontal
profile and therefore, the contention raised by counsel for the respondent /
MPRDC also amounts to misleading the Court. He has further submitted that
other four roads in the vicinity are widened on both sides of the road and not
taking one side of the road as is in the present case. It is now, well settled
preposition that the roads are widening equally on both sides cemetrically,
which is not done in the present case. He has further submitted that the
respondents / Authority have clearly violated the procedure prescribed under
the Rules, 2014 and the M.P. Rules, 2015 as regarding the constitution of
Social Impact Assessment Team as well as Expert Group and therefore,
learned counsel for the petitioners prays that present petitions be allowed by
setting aside the impugned Award.
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
17 WP-45080-2025
13/ Learned Advocate General appearing for respondent no. 4 / MPRDC
has submitted that the petitioners have raised mainly five grievances.
Regarding constitution of SIA Team, he has submitted by referring to this
point by referring to paragraph no. 5.3 and other paragraphs in the petition
by submitting that there are inconsistency in the pleadings as somewhere,
the petitionerd have relied upon the Central Govt. Rules, 2014 and
somewhere, the petitioner has referred to M.P. Rules, 2015. He has further
submitted that in view of Section 109 of the Act, 2013, the powers are given
to the appropriate Government for such appointment of the SIA Team and
applicability of such Rules for the acquisition. In view of section 3(e)(i) of
the Rules, 2015, no violation of any procedure can be attributed to the
respondent / Authority and therefore, the first contention of the petitioners is
required to be rejected as submitted by counsel for the respondent no. 4.
Learned counsel for respondent no. 4 has submitted that the petitioner has
raised another point of violation of Section 8 of the Act, 2013. He has
referred to paragraph no. 5.21 of the memo of petition and submitted that
such contention of the petitioners is not required to be entertained as the
petitioners have already raised objections and therefore, such contention is
not helpful to the petitioners. He has also answered to another contention
regarding member of the Requiring Body by referring to the Rules, 2014 and
M.P Rules, 2015 in which the procedure is prescribed and the Authority
have followed the M.P. Rules, 2014 and the Rules, 2015 in the present
matter and therefore, such contention is also required to be negative. He has
further submitted regarding contention that one side of the road is acquired
and other side is not acquired. By drawing my attention towards to paragraph
no. 24 of the reply filed by the contesting respondent, he has submitted that
it is the job of the technical expert, therefore, such contention is required to
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
18 WP-45080-2025
be negative. He has further submitted by drawing attention to the relief
clause, whereby no challenge is made to the Award, which has taken place,
though it is within the knowledge of the petitioners. He has further submitted
that by exercising the powers under Article 226 of the Constitution of India,
no relief can be granted in such situation. He has further submitted that by
order dated 18/05/2025, interim relief was granted, which was modified
subsequently, which is required to be taken into consideration and he has
submitted that looking to the big-scale planning of the Sinhastha Kumbh,
2028, wherein it is expected that more than 15 Crores devotees will attend
the Sinhastha Kumbh, 2028 and necessary procedure is required to be
carried out by widening of roads and other facilities. The respondent /
Authority has already deposited Rs. 94.93 Crores with the Collector and the
same can be disbursed to the affected landowners / petitioners, therefore, on
any count, since the decision making process by the respondent / Authority
by giving fair opportunity of hearing to the petitioners and by following
statutory provisions of the Act, 2013 as well as the M.P. Rules, 2015, no
interfereence is called for. He has submitted that exclusivity of M.P. Rules,
2015 over Central Rules, 2014 is required to be considered by considering
the rule making powers under section 109 of the Act, 2013 and the State of
Madhya Pradesh framed and notified the M.P. Rules, 2015. He has further
submitted that the Central Rules, 2014 apply only where the Central
Government is the Appropriate Government or in the absence of State-
specific rules enacted under section 109 of the Act, 2013. In the present
case, the appropriate Government for acquiring is within the territory
jurisdiction of the State of Madhya Pradesh for State Infrastructure Project
such as road widening by MPRDC and the State Government is the
Appropriate Government. He has further submitted that since the acquisition
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
19 WP-45080-2025
initiated by the State of Madhya Pradesh, only the M.P. Rules, 2015 governs
the acquisition process and therefore, he has submitted that the petitioners in
these two petitions have not accepted the amount of Award, which is passed,
otherwise, out of 338 beneficiaries, 228 beneficiaries have accepted the
amount of Award passed by the SDO and therefore, he has submitted that
considering the various judgments on the issue in question, the present
petitions are required to be dismissed.
14. By considering all these contentions made by the parties and by
considering the material available on record and the judgments cited by the
respective parties, it is relevant to refer to Section 109 of the Act, 2013
which is reproduced for the sake of reference as under :
109. Power of appropriate Government to make rules.
(1) Subject to the other provisions of this Act, the appropriate Government
may, by notification, make rules for carrying out the provisions of this
Act. (2) In particular, and without prejudice to the generality of the
foregoing, such rules may provide for all or any of the following matters,
namely: -
(a) the process of obtaining the prior consent under the first proviso to
sub¬section (2) of section 2;
(b) the limits of land in rural areas or urban areas under clause (a) of sub-
section (3) of section 2;
(c) the manner and the time limit for carrying out social impact assessment
study under sub-section (1) of section 4;
(d) the manner of preparing and publishing social impact assessment study
reports under sub-section (1) of section 6;
(e) the manner and time for conducting survey and undertaking census
under sub-section (1) of section 16;
(f) the manner of preparing draft Rehabilitation and Resettlement Scheme
under sub-section (2) of section 16;
(g) the manner of conducting public hearing under sub-section (5) of
section 16; (h) the manner of depositing amount by the Requiring Body
under second proviso to sub-section (2) of section 19;
(i) the manner in which and the period within which any excess amount
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
20 WP-45080-2025
paid may be recovered under sub-section (3) of section 33;
(j) the form in which the Development Plan shall be prepared under sub-
section (4) of section 41;
(k) the powers, duties and responsibilities of Administrator under sub-
section (2) of section 43;
(l) the procedure of Rehabilitation and Resettlement Committee under sub-
section (3) of section 45;
(m) the procedure to be followed by the Rehabilitation and Resettlement
Committee and allowances to be paid to the experts under sub-section (3)
of section 48;
(n) the procedures to be followed by the State Monitoring Committee and
the allowances payable to the experts under sub-section (3) of section 50;
(o) the salaries and allowances and other conditions of service of the
Registrar and other officers and employees of an Authority under sub-
section (3) of section 55;
(p) the salary and allowances payable to and the other terms and conditions
of service (including pension, gratuity and other retirement benefits) of, the
Presiding Officer of an Authority under section 56;
(q) any other matter under clause (g) of sub-section (1) of section 60;
(r) the manner of recovery of the rehabilitation and resettlement benefits,
availed of by making false claim or through fraudulent means, under sub-
section (2) of section 84;
(s) the manner of returning the unutilised land by reversion under section
101;
(t) manner of publication wherever the provisions of this Act provide for;
(u) any other matter which is required to be or may be specified under this
Act.
It is also relevant to refer to the Rule 3(i) of the M.P. Rules, 2015
which reads as under :
Rule 3. Selection of the social impact assessment team.
(i) The Collector shall constitute the Social Impact Assessment (SIA) team
for each project from amongst Government officials/or qualified
institutions in social impact assessment resource, partners and practitioners
which may also be appointed to assist the team where he feels necessary.
The team leader shall not be below the rank of Deputy Collector but he
shall not be in charge officer of the land acquisition section of the office of
the Collector.
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
21 WP-45080-2025
15. Therefore, considering the above mentioned position of law and the
judgments cited by the petitioners, there is no quarrel regarding the fact that
the ratio is that if the respondent / Authority did not follow the the procedure
prescribed under the Act, 2013, the Court has quashed the Award / order
passed, during the pendency of the proceeding, There is no dispute about the
said ratio and the legal position, however, considering the fact that in the
present case, by considering Section 109 of the Act, 2013 read with Rule 3(i)
of the M.P. Rules, 2015, prima-facie, the applicability of the M.P. Rules
2015 is required to be considered. The contention raised by learned
Advocate General appearing for the respondent no. 4 / MPRDC is required
to be accepted, moreover, considering that now the Award is already passed
and in view of section 64 of the Act, 2013, which reads as under :
“64. (1) Any person interested who has not accepted the award may, by
written application to the Collector, require that the matter be referred by
the Collector for the determination of the Authority, as the case may be,
whether his objection be to the measurenfent ofthe land, the amount of the
compensation, the person to whom it is payable, the rights of
Rehabilitation and Resettlement under Chapters V and VI or the
apportionment of the compensation among the persons interested:
Provided that the Collector shall, within a period of thirty days from the
date of receipt of application, make a reference to the appropriate
Authority:
Provided further that where the Collector fails to make such reference
within the period so specified, the applicant may apply to the Authority, as
the case may be, requesting it to direct the Collector to make the reference
to it within a period of thirty days.
(2) The application shall state the grounds on which objection to the award
is taken: Provided that every such application shall be made-
(a) ifthe person making it was present or represented before the
Collector at the time when he made his award, within six weeks
from the date ofthe Collector's award;
(b) in other cases, within six weeks ofthe receipt of the notice from
the Collector under section 21, or within six months from the date of
the Collector's award, whichever period shall first expire:
Provided further that the Collector may entertain an application after the
expiry of the said period, within a further period of one year, if he is
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
22 WP-45080-2025
satisfied that there was sufficient cause for not filing it within the period
specified in the first proviso.”
16/ The statutory remedy is available to the petitioners, however, looking
to the prayer made in the petition/s, the petitioners have not challenged the
Award during pendency of the proceedings, therefore, on that count also,
present petitions deserve to be dismissed. Considering the judgments of
various High Courts as well as the ratio of the Supreme Court's judgments
and also considering the material available on record, I found that the public
interest is required to be given precedent on the private interest, more
particularly, in the facts of the case, though the contentions raised by the
petitioners are found very attractive, but at the same point of time, in view of
the chronology of events and also considering that the respondents /
Authority have followed all procedural aspects and there is substantial
compliance of the procedure, even considering that there are minor lapses on
the part of the respondents/ Authority will not warrant any interference
considering the larger public interest of the Society by considering the fact
that the entire project will be jeopardized, therefore, I am of the view that
present case does not warrant any interference by exercising powers under
Article 226 of the Constitution of India as more particularly, the petitioners
are having statutory alternative remedy by way of challenging the Award,
though they have not preferred to do so, for the reason best known to them,
therefore, without expressing about prospect of the petitioners for
challenging such Award before the Authority, I am of the view that present
petitions are found meritless as the action of the respondents/ Authority can
not be considered arbitrary, illegal or improper on any count. It also cannot
be said that the impugned action violates any principle of natural justice or
any rights guaranteed under the Constitution of India, therefore, I am of the
view that the present petitions lack merits, which does not warrant any
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27
NEUTRAL CITATION NO. 2026:MPHC-IND:24211
23 WP-45080-2025
interference by this Court under Article 226 of the Constitution of India to
exercise my extraordinary jurisdiction. Accordingly, present petitions
deserve to be and are dismissed .
17/ The signed order be kept in the file of W.P. Nos. 45080 of 2025 and a
copy thereof be kept in the file of connected W.P. no. 45084 of 2025
18/ Interim relief / stay, if any, shall stand vacated.
CC as per rules.
(SANDEEP N. BHATT)