VITHAL vs THE KARNATAKA POWER

Court
Karnataka High Court

- 1 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026



IN THE HIGH COURT OF KARNATAKA



KALABURAGI BENCH

ST
DATED THIS THE 21 DAY OF NOVEMBER, 2026

BEFORE

THE HON'BLE MR. JUSTICE VIJAYKUMAR A. PATIL

WRIT PETITION NO. 204199 OF 2026 (S-PRO)

C/W

WRIT PETITION NO. 204193 OF 2026 (S-PRO)

WRIT PETITION NO. 204196 OF 2026 (S-PRO)



IN WP No. 204199/2026

BETWEEN:

PANDURANG
S/O RAMAPPA UDAGATTI
AGE: 42 YEARS, OCC: AE(EI)
R/O: C/O R V BIDAPA COLONY
OPP: SIDDAROOD MATH, NEAR GUMPA
H NO 17-4-294/1 BIDAR-585401
…PETITIONER





Digitally signed
by SWETA
KULKARNI
Location: HIGH
COURT OF
KARNATAKA

(BY SRI. SANTOSH B. MALLIGAWAD., ADVOCATE)
AND:
1. THE KARNATAKA POWER
TRANSMISSION CORPORATION LIMITED,
REPRESENTED BY
THE MANAGING DIRECTOR
INDHAN BHAVAN, BENGALURU-560009

2. THE KARNATAKA
POWER TRANSMISSION CORPORATION LIMITED,
REPRESENTED BY

- 2 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


THE DIRECTOR (HUMAN RESOURCE)
THE DIRECTOR (HUMAN RESOURCE)
INDHAN BHAVAN, BENGALURU-560009
…RESPONDENTS
(BY SRI. ARUNKUMAR AMARGUNDAPPA., ADVOCATE)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA, PRAYING TO, 1)
ISSUE A WRIT IN THE NATURE OF MANDAMUS DIRECTING
RESPONDENT NO.1 GRANT PROMOTION TO THE POST OF AEE
(ELE) FROM 26-06-2024 WITH ALL CONSEQUENTIAL BENEFITS
AND ARREARS IN TERMS REPRESENTATION VIDE ANNEXURE-C
DATED 02-05-2024; 2) GRANT ANY OTHER RELIEF WHICH
THIS HONOURABLE COURT MAY DEEM FIT IN THE INTEREST
OF JUSTICE AND EQUITY.
IN WP NO. 204193/2026
BETWEEN:
VITHAL S/O PANDU NAYAK
AGE: 45 YEARS, OCC: AE (EI)
R/O RANAPUR THANDA @ POST RAMMANGUD
TQ: CHINCHOLLI, DIST: KALABURAGI-585324
...PETITIONER
(BY SRI. SANTOSH B. MALLIGAWAD., ADVOCATE)
AND:
1. THE KARNATAKA POWER
TRANSMISSION CORPORATION LIMITED,
REPRESENTED BY
THE MANAGING DIRECTOR
KAVERI BHAVAN, BENGALURU-560009

2. THE KARNATAKA
POWER TRANSMISSION CORPORATION LIMITED,
REPRESENTED BY
THE DIRECTOR (HUMAN RESOURCE)
THE DIRECTOR (HUMAN RESOURCE)

- 3 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


KAVERI BHAVAN, BENGALURU-560009
...RESPONDENTS
(BY SRI. ARUNKUMAR AMARGUNDAPPA., ADVOCATE)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA, PRAYING TO,
A) ISSUE A WRIT IN THE NATURE OF MANDAMUS
DIRECTING RESPONDENT NO.1 GRANT PROMOTION TO
THE POST OF AEE FROM 27.01.2021 WITH ALL
CONSEQUENTIAL BENEFITS AND ARREARS IN TERMS
REPRESENTATION VIDE ANNEXURE-D AND D1 DATED
02.05.2024 AND 24.06.2024; B) GRANT ANY OTHER
RELIEF WHICH THIS HONOURABLE COURT MAY DEEM FIT
IN THE INTEREST OF JUSTICE AND EQUITY.
IN WP NO. 204196/2026
BETWEEN:
HANUMANTH
S/O DEVIDHAR PHULEKAR
AGE: 40 YEARS, OCC: AE (EL)
R/O: C/O 2-911/5/2/27, RAKMA NIVAS
NAIDU LAYOUT, PRASHANT NAGAR
RAJAPUR ROAD, KALBURGI-585105.
...PETITIONER
(BY SRI. SANTOSH B. MALLIGAWAD., ADVOCATE)
AND:
1. THE KARNATAKA POWER
TRANSMISSION CORPORATION LIMITED,
REPRESENTED BY
THE MANAGING DIRECTOR
KAVERI BHAVAN, BENGALURU-560009

2. THE KARNATAKA
POWER TRANSMISSION CORPORATION LIMITED,
REPRESENTED BY

- 4 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


THE DIRECTOR (HUMAN RESOURCE)
THE DIRECTOR (HUMAN RESOURCE)
KAVERI BHAVAN, BENGALURU-560009
...RESPONDENTS
(BY SRI. ARUNKUMAR AMARGUNDAPPA., ADVOCATE)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA, PRAYING TO I)
ISSUE A WRIT IN THE NATURE OF MANDAMUS DIRECTING
THE RESPONDENT NO.1 GRANT PROMOTION TO THE POST
OF AEE (ELE) FROM 26.11.2020 WITH ALL CONSEQUENTLY
BENEFIT AND ARREARS IN TERMS REPRESENTATIVE VIDE
ANNEXURE-C AND C1 DATED 05.09.2020 AND 02.05.2024;
II) GRANT ANY OTHER RELIEF WHICH THIS HONOURABLE
COURT MAY DEEM FIT IN THE INTEREST OF JUSTICE AND
EQUITY.
THESE PETITIONS, COMING ON FOR PRELIMINARY
HEARING 'B' GROUP, THIS DAY, ORDER WAS MADE THEREIN
AS UNDER:
CORAM: HON'BLE MR. JUSTICE VIJAYKUMAR A. PATIL

ORAL ORDER
These petitions are filed seeking a writ in the nature
of mandamus to respondent No.1 to grant promotion to
the post of Assistant Executive Engineer (Electrical) and
for consequential benefits, as per the representations.

2. Heard Sri. Santosh B Malligawad, learned
counsel appearing for the petitioners, Sri. Arunkumar
Amargundappa, learned counsel appearing for the

- 5 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


respondents and meticulously perused the material
available on record.

3. The petitioners initially joined as Junior
Engineers (Electrical) with the respondent No.1 on
different dates. It is averred that the petitioners were
promoted from Junior Engineers to Assistant Engineers
and are rendering service without any blemish. It is the
case of the petitioners that the respondents initiated the
departmental inquiries against the petitioners by issuing
charge memos dated 06.09.2019, 05.09.2019 and
06.09.2019 respectively, alleging that the petitioners have
improperly prepared the estimate costs with respect to the
installation of transformers and electrical line in Bidar
Division. It is to be noticed that the petitioners were due
for promotion for the post of Assistant Executive Engineer.
However, due to the pendency of the departmental
enquiry proceedings against the petitioners, petitioners’
promotions were considered and the sealed cover
procedure was followed, as can be noticed from the

- 6 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


promotion list dated 16.12.2023 and 26.06.2024 as per
Annexures-B and B1. It is to be further noticed that the
petitioners have submitted detailed representations
seeking to consider their promotions and the said
representations were not considered by the authorities. It
is averred that on 09.04.2025, the departmental enquiries
initiated against the petitioners were concluded and the
report came to be submitted stating that out of 2 charges
each, some were proved false and some were partly
proved. The petitioners have produced the departmental
inquiry report dated 09.04.2025. The respondent No.1
instead of accepting the report, directed the inquiry officer
to conduct a fresh enquiry vide endorsement dated
04.09.2025 without recording any reasons. It is to be
noted that the department inquiry report submitted to the
respondent No.1 was neither accepted nor rejected or
acted upon. However, the respondent No.1 has ordered to
hold a fresh enquiry. Be that as it may, the petitioners are
now due for promotion as Assistant Executive Engineers

- 7 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


and their colleagues, who are equally eligible have been
promoted as per the promotion list dated 05.09.2026 at
Annexure-F. However, though the petitioners are eligible
for promotion, they have not been promoted and were
kept pending consideration in sealed cover. The petitioners
in the case on hand are seeking to consider their
representations and to effect the promotion to the post of
Assistant Executive Engineer (Electrical) with effect from
26.06.2024, 27.01.2021 and 26.11.2020 respectively.

4. The petitioners have relied upon the judgment
of the Hon'ble Supreme Court in the case of State of
1
Punjab and others v. Chaman Lal Goyal , wherein the
Hon’ble Supreme Court has held at paragraph Nos.11 and
12 as under:
“11. Now what are the factors agaist the
respondents. (1) That the respondent was never
suspended nor was he served with a memo of
charges nor even with a questionnaire in that behalf
till March, 1992 when he was questioned by the

1

(1995) 2 SCC 570

- 8 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


Secretary to the Home department and charges
served in july, 1992. He had suffered no discomfort
or inconvenience on account of delay.
(ii) The charges are very grave. The charges are not
only that he was lax in discharge of his duties but
that he acceded to every demand of theirs and that
in violation of the prison rules, had allowed a number
of terrorists to gather in one cell. He is said to be
responsible for creating of the atmosphere which led
to the said attempt. His sympathies towards them
are said to be evident from the fact that he accepted
a farewell party from them on his transfer from the
post of Superintendent of the said jail. In the
attempted escape, one prison official lost his life
besides two terrorists. The earliest report of the
incident
- the report of Inspector General of Prisons dated
January 9, 1987 does specifically find the respondent
responsible for the incident. It is prima facie
evidence against the respondent. In the interest of
administration and of justice, it is necessary to find
out the truth in the matter.
(iii)There is no allegation in the writ petition that any
of the witnesses whom the respondent wanted to
examine in his defence are since dead or have

- 9 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


become unavailable and that the said fact would
cause prejudice to his case. Indeed, death or non-
availability of terrorists who made the attempt to
escape and the repair of the jail may prejudice the
ease of the government rather than the defence of
the rethe respondent. Similarly, the mere fact that
some persons who could have been examined as
witnesses have retired or have been transferred
cannot be said to cause prejudice to the respondent.
It is not stated that they have become unavailable.
(iv) Pending the writ petition, the enquiry was
proceeded with and by the date of the impugned
judgment, the government had completed its
evidence. Only the defence evidence remained to be
adduced whereafter the enquiry officer would have
made the report.
12. The principles to be borne in mind in this behalf
have been set out by a Constitution Bench of this
Court in A.R.Antulay v. R.S.Nayak & Anr. (1992 (1)
S.C.C.225). Though the said case pertained to
criminal prosecution, the principles enunciated
therein are broadly applicable to a plea of delay in
taking the disciplinary proceedings as well. In
paragraph 86 of the judgment, this court mentioned
the propositions emerging from the several decisions
considered therein and observed that "ultimately the

- 10 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


court has to balance and weigh the several relevant
factors - balancing test or balancing process - and
determine in each case whether the right to speedy
trial has been denied in a given case". It has also
been held that, ordinarily speaking, where the court
comes to the conclusion that right to speedy trial of
the accused has been infringed, the charges, or the
conviction, as the case may be, will be quashed. At
the same time, it has been observed that that is not
the only course open to the court and that in a given
case, the nature of the offence and other cir-
cumstances may be such that quashing of the
proceedings may not be in the interest of Justice.. In
such a case, it has been observed, it is open to the
court to make such other appropriate order as it
finds just and equitable in the circumstance of the
case.”


5. The petitioners have also relied on the decision
of the Division Bench of this Court in the case of The
Karnataka Power Transmission Corporation Limited
2
(KPTCL) and another v. Dattatreya S Guddalli and
connected appeals and the decision in the case of Sri.

2

WA No.100058/2025 dt. 20.03.2025

- 11 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


Shiva Prasad M. v. The State of Karnataka and
3
another . It would be useful to refer the following
paragraphs in the case of Karnataka Power
Transmission Corporation Limited (KPTCL) referred
supra:
“8. Our answer to the above point would be in the
“affirmative” for the following reasons:
Undisputedly, the petitioners are working in the
respondent/KPTCL in various positions.
Admittedly, the criminal proceedings are pending
against the petitioners since 11.10.2012 and for
more than a decade. During the course of hearing,
it is stated that the departmental enquiry was
initiated on the same set of facts, wherein the
petitioners are exonerated. No departmental
enquiry was pending as on the date of DPC, which
considered the case of the petitioners for
promotion to the next higher cadre.
9. Mere pendency of the criminal proceedings may
not be a ground to deny the promotion to an
employee. The authorities shall have to consider
longevity of the pendency of the criminal case and

3

WP No.27483/2023 dt. 12.09.2025

- 12 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


if the criminal case is pending for very long, such
as a decade or more, the Court shall have to
balance the equity between the parties.
10. The Hon’ble Apex Court in the case of
Chaman Lal Goyal (supra), while considering the
question of delay in initiating or serving the charge
memo in a departmental enquiry, observed that
“how long a delay is too long always depends upon
the facts of the given case. Moreover, if such delay
is likely to cause prejudice to the delinquent officer
in defending himself, the enquiry has to be
interdicted. Wherever such a plea is raised, the
Court has to weigh the factors appearing for and
against the said plea and take a decision on the
totality of circumstances. In other words, the
Court has to indulge in a process of
balancing……….”
11. Normally, as held by the Apex Court in the
case of K.V. Janakiraman (supra), sealed cover
procedure shall be followed in respect of an
employee against whom departmental enquiry is
pending, at the stage of issuance of charge memo
and where charge sheet is filed in criminal
proceedings. If the departmental proceeding or
criminal proceeding is continued for very long
time, then it is for the Courts to balance the

- 13 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


situation and to direct appropriately either to
conclude the enquiry within a time bound period or
to direct the consideration of such employees’
cases for promotion.
12. In the instant case, since criminal proceeding
is pending for more than 12 years, learned Single
Judge exercising his judicious discretion has rightly
directed the consideration of cases of the
petitioners for promotion to the next higher cadre.
We do not find any error or illegality in the
direction issued by the learned Single Judge. There
is no merit in the writ appeals. Accordingly, the
above writ appeals stand dismissed.”


6. Keeping in mind the enunciation of law laid
down by the Hon'ble Supreme Court, I am of the
considered view that if departmental proceedings are kept
pending for indefinite period or period longer than
expected, under such circumstances, the Court is required
to consider various factors and is required to issue
directions to consider the petitioners’ case for promotion.
It is to be noticed that the delay in completion of the
departmental inquiry is not at the instance of the

- 14 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


petitioners. In the case on hand, admittedly, the
departmental inquiry proceedings were concluded and the
inquiry officer has submitted report on 09.04.2025.
Thereafter, the respondent No.1 has not acted on the said
report. However, the respondent No.1 has taken a further
decision to hold a fresh inquiry, which would cause great
prejudice to the petitioners. Hence, considering the
aforesaid decisions, I am of the view that the respondents
are required to consider the petitioners’ case for promotion
to the post of Assistant Executive Engineer (Electrical)
from the dates on which they become eligible. However,
the said consideration would be subject to the outcome of
departmental inquiries.

7. Hence, I proceed to pass the following:
ORDER

i. The writ petitions are allowed .

ii. A writ of mandamus is issued to the
respondents to consider the petitioners’

- 15 -
HC-KAR
NC: 2026:KHC-K:12807
WP No. 204199 of 2026
C/W WP No. 204193 of 2026
WP No. 204196 of 2026


CNR: KAHC030106002026


representations dated 02.05.2024 at
Annexure-C, 02.05.2024 and 24.06.2024 at
Annexures-D and D1 and 05.09.2020 and
02.05.2024 at Annexures-C and C1
respectively, and promote the petitioners to
the post of Assistant Executive Engineer
(Electrical) from the date they become eligible
for promotion, with all consequential benefits.

iii. The aforesaid exercise shall be completed in
four (4) weeks from the date of receipt of a
copy of the order.

iv. The promotions effected would be subject to
the outcome of the pending departmental
enquiry proceedings.
No order as to costs.



Sd/-
(VIJAYKUMAR A. PATIL)
JUDGE



NJ
List No.: 1 Sl No.: 15