Pradeep Kumar vs The State Of Madhya Pradesh
- Court
- Madhya Pradesh High Court
1 WP-10487-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE
BEFORE
HON'BLE SHRI JUSTICE SANDEEP N. BHATT
th
ON THE 18 OF NOVEMBER, 2026
WRIT PETITION No. 10477 of 2026
CNR No.: MPHC020113082026
MOHAN LAL AND OTHERS
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Govind Pal Singh Songara, Advocate for the petitioners.
Shri Sudeep Bhargava, Dy. AG for the respondent/State.
Shri Sunil Kumar Jain, Senior Advocate with Shri Nilesh Jagtap,
Advocate for respondent No.5.
WITH
WRIT PETITION No. 9860 of 2026
CNR No.: MPHC020107042026
KANTA PRASAD
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Govind Pal Singh Songara, Advocate for the petitioners.
Shri Sudeep Bhargava, Dy. AG for the respondent/State.
Shri Sunil Kumar Jain, Senior Advocate with Shri Nilesh Jagtap,
Advocate for respondent No.5.
WRIT PETITION No. 10487 of 2026
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
2 WP-10487-2026
CNR No.: MPHC020113202026
PRADEEP KUMAR
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Govind Pal Singh Songara, Advocate for the petitioners.
Shri Sudeep Bhargava, Dy. AG for the respondent/State.
Shri Sunil Kumar Jain, Senior Advocate with Shri Nilesh Jagtap,
Advocate for respondent No.5.
ORDER
This order shall govern the disposal of Writ Petition Nos.10477/2026,
9860/2026, and 10487/2026.
Regard being had to the similitude of the controversy involved in the
aforesaid writ petitions, they have been heard analogously and are being disposed
of by this common order, as all three petitions involve identical facts and raise
common questions of law.
The present batch of petitions, namely Writ Petition Nos. 10477/2026,
9860/2026, and 10487/2026, has been preferred by the petitioners under
Article 226 of the Constitution of India, praying for the following identical
reliefs:
"The petitioner prays for the following relief:
Pass any other appropriate writ, order or direction as this Hon'ble Court may
deem fit and proper in the interest of justice and quash the Annexure P/1 notice
dated 20/02/2026 and also quash the all proceeding of Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 and protect the petitioners' property rights."
2. Brief facts of the case in brief is as under :-
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
3 WP-10487-2026
Facts of W.P. No.10477 of 2026 :
That the petitioner is "Challenging the Land Acquisition Notification dated
20/02/2026 (Annexure P/1) issued by Respondent No.3 for acquisition of
petitioner's land, Survey No.1027/2, 1318, 1319, 1312 Village Raghokhedi,
Tehsil Kalapipal, District Shajapur, for commercial use by Power Grid Kurawar
Transmission Limited, on grounds of non-compliance with the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013, and violation of petitioner's fundamental rights.
The
petitioners are being aggrieved by illegal, arbitrary and malafide order dated
04.02.2026 issued by respondent No.4, without jurisdiction, without any
authority of law. That cancel all the objections of petitioner before the
respondent authority.
Facts of W.P. No.9860 of 2026 :
That the petitioner is "Challenging the Land Acquisition Notification
dated 20/02/2026 (Annexure P/1) issued by Respondent No.3 for acquisition of
petitioner's land, Survey No.1314/1S, village Raghokhedi, Tehsil Kalapipal,
District Shajapur, for commercial use by Power Grid Kurawar Transmission
Limited, on grounds of non-compliance with the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013,
and violation of petitioner's fundamental rights."
Facts of W.P. No.10487 of 2026 :
That the petitioner is "Challenging the Land Acquisition Notification
dated 20/02/2026 (Annexure P/1) issued by Respondent No.3 for acquisition of
petitioner's land, Survey No.1314/2, 1317, village Raghokhedi, Tehsil Kalapipal,
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
4 WP-10487-2026
District Shajapur, for commercial use by Power Grid Kurawar Transmission
Limited, on grounds of non-compliance with the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013,
and violation of petitioner's fundamental rights."
3. For the sake of convenience, facts are being taken from W.P.
No.10477/2026.
4. It is pointed out by the learned counsel for the petitioners that the
petitioners are farmer and resident of Village Khardon Kala, Tehsil
Kalapipal, District Shajapur(M.P.). Their ancestral land bearing Survey
No.1027/2, 1318, 1319 and 1312 alongwith other survey numbers, situated at
village Raghokhedi, Tehsil Kalapipal, District Shajapur, is sought to be
acquired under the Land Acquisition Act for commercial Power Grid
Kurawar Transmission Limited, pursuant to a notice published in
newspaper. Following the publication, the petitioners filed objections before
Respondent No. 5, to which no response was received. Subsequently, the
respondents issued a public notice as well as personal notices under the Right
to Fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 (hereinafter referred to as the "Act of 2013"),
informing the owners of the aforementioned lands (Survey Nos. 1027/2,
1318, 1319, and 1312, along with other survey numbers) of the acquisition
and inviting written objections. In response, the petitioners filed an objection
on 08.10.2025 before the respondent, refusing to accept the respondent's
proposal.
5. The respondent No. 4, in compliance with the notification, issued a
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
5 WP-10487-2026
show cause notice on 09/10/2025, which was received by the petitioner on
24/10/2025. The petitioners submitted a reply on 13.01.2026, indicating that
they had already submitted replies on 17.10.2025, 24.10.2025 and
04.11.2025. It is also pointed out that some farmers sold their land under
pressure from the respondents Nos. 3 and 4 and executed sale deed in favour
of respondent no.5 at a very low price. Thereafter, a primary notification was
issued under Section 13 of the Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013, concerning the
petitioner's land bearing Survey Nos. 1027/2, 1318, 1319, and 1312, without
considering the petitioners' objections and in an attempt to acquire the land
through an unlawful procedure. Accordingly, it is contended that pursuant to
the mandate of Section 12 of the Act, 2013, the Surveying Officer is not
authorized to conduct any survey in the absence of the landowner.
Furthermore, even if such a survey is to be conducted, it is incumbent upon
the authority to issue a prior notice of at least 60 days to the landowner,
thereby affording a reasonable opportunity for participation.
6. However, in the present case, no notice as required under Section
12 has been served upon the landowner, nor has any opportunity whatsoever
been provided and, therefore, rendering the entire action arbitrary, illegal and
in gross violation of the principles of natural justice.
7. Learned counsel for the petitioner has further submitted that there is
lacking of public purpose in acquisition as the land is acquired for
commercial use by Power Grid Kurawar Transmission Limited, which is
private entity, therefore, it violates the principle of Land Acquisition. He has
further submitted that the statutory requirement is also not complied with by
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
6 WP-10487-2026
the respondent(s), which clearly transpires that the respondent has failed to
provide adequate notice and opportunity to the petitioner(s) to object the
acquisition proceedings. He has further submitted that respondents have
failed to conduct a proper survey and enquiry before issuing notification and
failed to provide adequate compensation to the petitioners. He has further
submitted that there is gross violation of fundamental rights in acquisition,
which violates the petitioner's fundamental rights under Article 21 of the
Constitution of India, which guarantees the right to life and livelilhood. He
has further submitted that this acquisition is arbitrary and unreasonable and
is not based on any rational or objective criteria. He has further submitted
that no further consideration of alternatives are considered by considering
alternative routes or options for the transmission line, which would minimize
the impact on the petitioner's land and livelihood. He has further submitted
that there is lack of transparency in a process of acquisition as process has
been shrouded in secrecy, and the petitioner has not been provided with adequate
information about the project. He has further submitted that non-compliance of
Environmental and Social Assessment is also there as t he respondents have failed to
conduct a proper environmental and social impact assessment of the project.
He has further submitted that there is Coercion and Undue Influence by the
respondents on the petitioners and other farmers and also violation of Policy
and Guidelines of Govt. of Madhya Pradesh for land acquisition. Moreover,
there is no adequate compensation is offered by the respondent / authority
and no publication is made by way of Gazette Notification which is required
more particularly the Notification under Section 11 of the Act of
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
7 WP-10487-2026
2013. Lastly, he submitted that during the pendency of the proceedings, the
award was passed; however, since he has already challenged the validity of
the land acquisition process itself, he is not challenging the award through
separate proceedings at this time, which the petitioner reserves the right to do
at an appropriate stage.
8. Per Contra, learned counsel for the State has supported the case of
the respondent / authority, submitting that the acquisition was made entirely
in accordance with the Rules and by following the necessary procedure, and
that no interference is called for.
9. Learned counsel for the respondent No.5, who is the beneficiary of the
acquired land, submitted that Respondent No. 5 is a corporation and a holly
owned subsidiary of Power Grid Corporation of India Limited, a Public Se ctor
Undertaking of the Central Government. He has further submitted that it was
selected-through tariff based competitive bidding under Section 63 of the
Electricity Act, 2003 to execute the scheme "Transmission System for
Evacuation of Power from Rajasthan REZ Phase-IV(Part-2:5:.5 GW): Part
H1", approved by the National Committee on Transmission on 09.06.2023 at
Rs.3,674 Crore. The scheme carries 5.5 GW of solar and win power into the
national grid. The Raghokhedi sub-section is the common terminating point
of four of the five lines, and without it none of them can be energised. Its
location is fixed by the Bid Process Coordinator's survey and Clause 28(ii) of
the bid documents (within 3 km of the surveyed coordinates) and cannot be
shifted. He has further contended that for the aforesaid purpose the
respondent No.5 requried around 70 Hectare land, out of 70 Hectares land,
around 60 Hectares land is private land and 9 Hectares is Government land.
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
8 WP-10487-2026
The respondent No.5 first sought the land by consent through a public notice
dated 05.02.2025. About 80% of the private land required has been obtained
through registered sale deeds, executed by the landowners of their free will.
It is only because the petitioners did not gave their consent that acquisition
of the balance 6.66 hectares had to be resorted to, as a last step. He has
further contended that on 24.03.2025, the respondent No.5 requested the
Collector, Shajapur to acquire the balance land and sought exemption from
the Social Impact Assessment ("SIA"). He further contended that the
exemption under Sections 9 and 40 was granted on 08.08.2025. He further
submits that Section 11 notification was issued on 12.08.2025 and Section 15
show-cause notice was issued on 09.10.2025. The Petitioners filed objections
and replies on 17.10.2025 to 13.01.2026, and the objections were decided by
order dated 04.02.2026. He has further submitted that Section 19 declaration
was made on 20.02.2026, within twelve months of Section 11, and the land
was measured and marked under Section 20. He has further submitted that
under Section 21, notice dated 06.03.2026 was issued, the personal hearing
was fixed on 17.03.2026 and the Petitioners' objections were heard and
decided. He also submitted that the Award under Section 23 was passed on
31.08.2026 and approved on 07.09.2026, within twelve months of the
declaration.
10. Furthermore, learned counsel for the respondent No.5 submits
that the petitioners were given notice and an opportunity of hearing at every
stage, and their objections under Sections 15 and 21 were duly considered
and decided by reasoned orders. The objections of the Petitioners were
confined to the amount of compensation and nothing more. They did not
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
9 WP-10487-2026
question the public purpose, the survey, the SIA or any other procedure. He
has further submitted that the petition raises grounds of no public purpose,
non-compliance with the Act and SIA, no survey, no hearing, loss of
livelihood under Article 21, bias, alternative site, non-compliance with
environmental norms, coercion and non-publication in the Gazette. He has
submitted that none of these grounds was raised in the objections filed earlier
under Section 15 or Section 21, each of which was duly decided. The
petitioners challenges only the Section 19 declaration, and not the Section 11
the Award. The only real grievance, the quantum of compensation and the
petitioners have a statutory remedy by reference to the Authority under
Section 64. He has further submitted that the exemption under Sections 9
and 40 was granted under a bona fide mistake, which was cured during the
proceedings themselves. By office letter dated 30.07.2026 of the Collector,
an SIA team was constituted under Section 4, the SIA was conducted and its
report was submitted, and the report was evaluated by the Expert Group
under Section 7. The SIA showed that the project is of public importance; the
Expert Group recorded that the acquisition appears necessary in public
interest and for public good. All this was completed before the Award.
11. Learned counsel further submitted that recently the Hon'ble Apex
Court has an occasion to deal with a matter, wherein there was no Social
Impact Assessment at all. In Uttar Pradesh Avas Evam Vikas Parishad
v. Chandra Shekhar & Ors. reported in (2024) 14 SCC 309, the Hon'ble
Supreme Court permitted the SIA procedure to be dispensed with where the
acquisition had advanced, and directed that compensation be determined
under the Act. This ration is also relied on by the Division Bench of this
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
10 WP-10487-2026
Hon'ble Court in Saira Bee v. State of M.P. reported in 2025:MPHC-IND:
page 823. Here in the present case, the SIA was actually done, no prejudice
is caused to the Petitioners, and the project is at an advanced stage.
12. Learned counsel further submitted that during the pendency of
this petition, the Award dated 31.08.2026 (LA. Case No. 07/A-82/2026-27,
approved by the Collector on 07.09.2026) determined total compensation of
Rs.5,69,37,959/- for the entire 6.66 Hectare, of which the Petitioners' share
for 2.37 Hectare is Rs.1,94,57,536/- (about Rs. 82 lakh per hectare) is also
determined. The market value as on 12.08.2025 (which is the date of the
Section 11 notification) was taken at Rs.19,30,019/- per hectare, being the
higher of the sale-deed average and the guideline rate of Rs.16,96,800 per
hectare under Section 26. This was multiplied by Factor 2 (rural area), with
the value of wells and tube-wells added, equal solatium of 100%, and the
additional amount at 12% per annum under Section 30(3). The entire
awarded amount, along with administrative expenses of Rs.14,23,449/-, has
been deposited, so nothing remains payable by Respondent No.5, and
payment is being arranged directly into the landowners' bank accounts. He
has further submitted that the petitioners were well aware of the factum of
passing of Award and has chosen not to challenge the same, have thus
acquiesced the acquisition. He has further submitted that the Rehabilitation
and Resettlement benefits are meant for families displaced from their
residence or deprived of their livelihood. No Petitioner is destitute of
residence or livelihood in the present acquisition. The Petitioners reside at
Village Khardonkala and not on the acquired land, only 3.74 Hectare out of
about 5.53 Hectare is acquired and the balance remains with them, and no
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
11 WP-10487-2026
dwelling is taken. The loss of land is fully compensated in terms of
money and by relying on the judgment of Estate Officer Haryana Urban
Development Authority v. Nirmala Devi, reported in 2025 INSC 843, he has
submitted that the petition is required to be dismissed. In addition, he
submitted that in other connected matters also, the amount is deposited
though as per the land acquired of the respective petitioners and, therefore, a
similar set of arguments are required to be made for sake of avoiding
repetition of the same facts.
13. I have considered the submissions made at the Bar and I have also
perused the record.
14. Learned counsel for the petitioners, at this stage, has pointed out
the judgment of the Hon'ble High Court rendered in the case of Saira Bee &
Ors. v. Urban Administration aand Development Department & Ors., passed
in W.A. No.117 of 2025 on 11.01.2025.
15. Against the aforesaid order/judgment, counsel for the respondent
has relied on Para 10 of that judgment. Para 10 and 11 of order dated
11.01.2025, passed in W.A. No.117 of 2025 are reproduced as under :-
10. Even otherwise, by way of the writ petition, the writ petitioners sought
the quashment of the award dated 12.03.2024 and amended award
10.06.2024 and also sought direction to comply with the provision relating
to social impact assessment as well as rehabilitation and resettlement for
the affected families. The writ petitioners did not challenge the
notifications issued under Section 40 of the Act of 2013 by the
respondents invoking the urgency clause and exemption granted under
Section 9 of the Act of 2013. The appellants straightway challenged the
final award passed after the issuance of the notifications from time to time
under the Act of 2013. The Writ Court has observed that out of 250
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
12 WP-10487-2026
families, more than 230 families had accepted the compensation and
vacated the land. Now only 20 families i.e. appellants remain, who have
already accepted the amount of compensation as mentioned in the last
notice dated 09.01.2025. The Writ Court has already granted the liberty to
them to challenge the award under Section 64 of Act, 2013, therefore, we
are not inclined to interfere with the impugned order.
11. In the case of U.P. Avas Vikas Parishad V/s Chandra Shekhar reported
in 2024 INSC 210 the Apex Court has granted exemption from submission
of Social Impact Assessment in a given facts and circumstances, relevant
para is as follows:-
20. We may hasten to add that the procedure prescribed under Chapter
II of the 2013 Act, mandates to carry out the Social Impact Assessment
Study in certain situations. The adherence to such a cumbersome
procedure in the instant case will be an exercise in futility for two
reasons. Firstly, a major part of the acquired land has already been
utilized for the notified public purpose. Secondly, the study referred to
above, will delay the assessment and payment of compensation to the
true tenure holders/owners of Khasra No.673. Consequently, we direct
the appropriate Government to dispense with the procedure
contemplated under Chapter II of the 2013 Act.
16. Counsel for the respondents has also relied on the judgment in the
case of Uttar Pradesh Avas Evam Vikas Parishad(Supra). Para - 20, 21 and
22 of the said judgment are relevant which are reproduced below :-
20. We may hasten to add that the procedure prescribed under ChapterII of the
2013 Act, mandates to carry out the Social Impact Assessment Study in certain
situations. The adherence to such a cumbersome procedure in the instant case
will be an exercise in futility for two reasons. Firstly, a major part of the
acquired land has already been utilized for the notified public purpose.
Secondly, the study referred to above, will delay the assessment and payment
of compensation to the true tenure holders/owners of Khasra No.673.
21. Consequently, we direct the appropriate Government to dispense with the
procedure contemplated under Chapter II of the 2013 Act. The Prescribed
Authority is permitted to accord an opportunity to submit objections under
Section 15 of the 2013 Act and, thereafter, pass an award as per Section 24(1)
of the 2013 Act. The Prescribed Authority/Collector shall give notice to the
respondents as well as to other persons who claim interest in Khasra Nos.672
and 673, within a period of six weeks. The objections, if any, shall be filed
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
13 WP-10487-2026
within four weeks and on consideration of such objections, the Collector shall
be obligated to pass an award on or before 30.06.2024.
22. We further direct that the awarded amount shall be kept in a nationalized
bank in the FDR where it can fetch the maximum rate of interest. The FDR
shall be renewed from time to time till the title dispute between the respondents
and other claimants is resolved by a court of competent jurisdiction.
Whosoever is found entitled to, the appellant Board shall release the
compensation to them as early as possible but not later than four weeks after
the final adjudication of the title dispute.
17. Having considered the above-mentioned submissions, it is undisputed
that the respondent authority has followed all relevant procedures required under
the law. Furthermore, during the pendency of this petition, a subsequent
development has taken place whereby the Award has been passed, which has not
yet been challenged by the petitioners before the competent forum under Section
64 of the New Act. It further transpires from the foregoing discussion, and it is
particularly relevant to note that at the initial stage, more than 80% of the private
land was acquired by way of registered sale deeds, and acquisition proceedings
were initiated only for the remaining 6.66 hectares. The record also reflects that
the Social Impact Assessment (SIA) was duly conducted, and the compensation
amount was determined after considering the objections filed by the petitioners at
the relevant time.
18. In view of the above, it is evident that there is no substance in the
petitioners' claim. Moreover, a bare reading of the petition reveals that the
petitioners have not challenged the entire acquisition process; rather, they
have challenged only the Section 19 declaration and not the compensation
Award passed under Section 11. Even if the petitioners have any genuine
grievance regarding the quantum of compensation, an efficacious statutory
remedy is available to them by way of a reference to the Authority under
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
14 WP-10487-2026
Section 64 of the Act.
19. For these purpose, it is pertinent to refer to the judgment of this
Hon'ble Court in Writ Petition No.2903 of 2026(Mangal Singh Panwar Vs.
The State of Madhya Pradesh & Ors), decided on 01.10.2026. Paragraphs 11
to 16 are relevant and reads as under :-
11. Moreover, considering that now the award is already passed,
provision of Section 64 of the Act, of 2013, is required to be gone into,
which reads as under :
“64. (1) Any person interested who has not accepted the award
may, by written application to the Collector, require that the
matter be referred by the Collector for the determination of the
Authority, as the case may be, whether his objection be to the
measurement ofthe land, the amount of the compensation, the
person to whom it is payable, the rights of Rehabilitation and
Resettlement under Chapters V and VI or the apportionment of the
compensation among the persons interested:
Provided that the Collector shall, within a period of thirty days from the
date of receipt of application, make a reference to the appropriate
Authority:
Provided further that where the Collector fails to make such reference
within the period so specified, the applicant may apply to the Authority, as
the case may be, requesting it to direct the Collector to make the reference
to it within a period of thirty days.
(2) The application shall state the grounds on which objection to the award
is taken: Provided that every such application shall be made-
(a) ifthe person making it was present or represented before the Collector
at the time when he made his award, within six weeks from the date of the
Collector's award;
(b) in other cases, within six weeks of the receipt of the notice from the
Collector under section 21, or within six months from the date of the
Collector's award, whichever period shall first expire:
Provided further that the Collector may entertain an application after the
expiry of the said period, within a further period of one year, if he is
satisfied that there was sufficient cause for not filing it within the period
specified in the first proviso.”
12. After going through the reply, it cannot be said that the respondents
have not followed the provisions of the Act, 2013 as well as Rules therein
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
15 WP-10487-2026
in as much as the notification has been directed to be published and in
gram sabha the same has been addressed.The SIA report was also duly
published and gram Sabha has been organized at various affected villages
thereby following Rule 6 of M.P. Rules, 2015 and Rule 8 of Central
Rules, 2014. The respondent no.2/Collector has duly passed order dated
30.05.2025 mentioning about legitimate purpose, potential benefits, area
of land and other details relating to the project as per the provision of
Section 11 and 8 of the Act,2013. He has also contended that the
petitioners are having title over the properties. There is no dispute about
the documents, which are available on record, indicates that the petitioner
is having title over the property. He has referred to paragraph no. 5.21 of
the memo of petition and submitted that such contention of the petitioners
is not required to be entertained as the petitioners have already raised
objections and therefore, such contention is not helpful to the petitioners.
He has also answered to another contention regarding member of the
Requiring Body by referring to the Rules, 2014 and M.P Rules, 2015 in
which the procedure is prescribed and the Authority have followed the
M.P. Rules, 2014 and the Rules, 2015 in the present matter and therefore,
such contention is also required to be negated. He has further submitted
regarding contention that one side of the road is acquired and other side is
not acquired. He has further submitted by drawing attention to the relief
clause, whereby no challenge is made to the Award, which has taken
place, though it is within the knowledge of the petitioners. He has further
submitted that by exercising the powers under Article 226 of the
Constitution of India, no relief can be granted in such situation. The Land
Acquisition proceedings have been initiated for construction of Indore-
Ujjain Greenfield Corridor and necessary procedure is required to be
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
16 WP-10487-2026
carried out for the said project. Upon perusal of the SIA report and the
objections raised therein, considering the public grievance and for
accommodating additional compensation to the landowners, additional
sanction of Rs. 1564.3 Crores for construction of service road and
enhancement of compensation amount has already been done for
disbursement to the affected landowners / petitioner, therefore, on any
count, since the decision making process by the respondent / Authority by
giving fair opportunity of hearing to the petitioners and by following
statutory provisions of the Act, 2013 as well as the M.P. Rules, 2015, no
interference is called for.
13. In the case of Girias Investment Pvt. Ltd. v. State of Karnataka
reported in (2008) 7 SCC 53, it has been held that land acquisition
proceedings undertaken for a public purpose are not to be lightly quashed
and that interference is warranted only when grave illegality or real
prejudice is demonstrated. The Hon'ble Court further observed that once
the statutory safeguards are substantially complied with, minor procedural
irregularities do not vitiate the acquisition. Applying the said principle to
the present case, the challenge raised by the petitioner is unsustainable and
deserves rejection.
14. In the case of Yudhvir Singh v. Govt. of NCT of Delhi, reported in
2024 SCC OnLine Del 471 it has been held that while examining land
acquisition proceedings under the Act of 2013, has upheld the acquisition
by applying the doctrine of substantial compliance, holding that once the
statutory purpose is achieved and public interest is subserved, the
proceedings cannot be invalidated on hyper-technical or procedural
objections. The Hon'ble Court further held that where objections have
been heard, public purpose is established and no real prejudice is
demonstrated, judicial interference is unwarranted.
15. Considering the aforementioned provision of the Act, 2013 and the
judgments cited by the petitioners, there is no quarrel regarding the fact
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
17 WP-10487-2026
that the ratio is that if the respondent / Authority did not follow the the
procedure prescribed under the Act, 2013, the Court has quashed the
Award / order passed, during the pendency of the proceeding, Moreso, the
statutory remedy u/S 64 of the Act of 2013 is available to the petitioner
and since the award has been passed during the pendency of this petition
and the petitioner has not challenged the award during pendency of the
proceedings, therefore, on that count also, present petition deserve to be
dismissed.
16. Considering the judgments of various High Courts as well as the
ratio of the Supreme Court's judgments and also considering the material
available on record, I found that the public interest is required to be given
precedent on the private interest, more particularly, in the facts of the case,
though the contentions raised by the petitioners are found very attractive,
but at the same point of time, in view of the chronology of events and also
considering that the respondents / Authority have followed all procedural
aspects and there is substantial compliance of the procedure, even
considering that there are minor lapses on the part of the respondents/
Authority will not warrant any interference considering the larger public
interest of the Society by considering the fact that the entire project will be
jeopardized, therefore, I am of the view that present case does not warrant
any interference by this Court, more particularly, when the petitioner is
having statutory alternative remedy by way of challenging the Award u/S
64 of the Act, 2013, though he has not chosen to do so, for the reason best
known to him, therefore, without expressing about prospect of the
petitioner for challenging such award before the Authority, the present
petition is found meritless, as the action of the respondents/ Authority can
not be considered arbitrary, illegal or improper on any count.
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
18 WP-10487-2026
20. It is also relevant to refer to the judgment of Hon'ble Apex Court
in the case of Estate Officer, Haryana Urban Development Authority & Ors.
Vs. Nirmala Devi, passed in Civil Appeal No.7707 of 2025 decided on
14.07.2025. Para - 94 of the said judgment is relevant which reads as under
:-
" 94. However, as observed earlier, since we are inclined to grant the
benefit of the scheme of 2016, we are not non-suiting the
respondents(original plaintiffs) completely".
21. In view of the aforesaid, I find no substance in these three petitions
bearing W.P. No. 10477/2026 , W.P. No. 9860/2026 , and W.P. No.
10487/2026 . The petitioners have failed to establish any genuine ground
demonstrating that the respondent authority failed to follow the prescribed
procedure under the law. On the contrary, the record indicates that the respondent
authority complied with all requisite procedures, and an award has already been
passed. In the absence of any challenge to the award under Section 64, and
without any material on record to show procedural non-compliance by the
respondent authorities, no further fruitful relief can be granted to the petitioners.
Furthermore, an adequate opportunity of hearing was afforded to the petitioners,
and their objections were duly decided. Moreover, considering that 80% of the
acquisition was already completed at the inception through private negotiations
and the execution of sale deeds by the landowners in favour of the respondents,
and that, acquisition proceedings are underway for the remaining 6.66 hectares,
the petitions cannot succeed on this count either. Additionally, given that the
respondent corporation is affiliated with a Public Sector Undertaking (PSU) of the
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20
19 WP-10487-2026
Government of India, it cannot be said that the acquisition is for a private purpose
rather than a public purpose.
22. On all counts, these three petitions fail. No arbitrariness, illegality, or
impropriety is found in any of the procedures or actions taken by the respondent
authorities.
23. Therefore, all three writ petitions bearing W.P. No. 10477/2026 , W.P.
No.9860/2026 W.P. No. 10487/2026
, and deserve to be dismissed. Accordingly,
they are hereby dismissed .
24. L et a copy of this order be kept in W.P. No.9860/2026 and W.P. No.
10487/2026.
(SANDEEP N. BHATT)
JUDGE
pn
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 20-11-2026
18:24:20