Goyal Mg Gases Pvt Ltd vs Classic Motors Pvt Ltd
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 25.02.2026
Judgment pronounced on: 12.05.2026
Judgment uploaded on: 12.05.2026
+ FAO(OS)(COMM) 172/2020
GOYAL MG GASES PVT LTD ...Appellant
Through: Mr. Simran Mehta, Mr. Prakash
Chand and Mr. Archit
Vashistha, Advs.
versus
CLASSIC MOTORS PVT LTD ....Respondent
Through: Mr. Rahul Saxena and Ms.
Padamja Sharma, Advs.
+ FAO(OS)(COMM) 23/2021
GOYAL MG GASES PVT LTD ...Appellant
Through: Mr. Simran Mehta, Mr. Prakash
Chand and Mr. Archit
Vashistha, Advs.
versus
CLASSIC MOTORS PVT LTD ....Respondent
Through: Mr. Rahul Saxena and Ms.
Padamja Sharma, Advs.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MR. JUSTICE AMIT MAHAJAN
J U D G M E N T
ANIL KSHETARPAL, J.:
1. Through the present Appeals filed under Section 37 of the
Arbitration and Conciliation Act, 1996 [hereinafter referred to as „Act
of 1996‟], the Appellant (Respondent before the Tribunal/Licensee)
assails the correctness of the common Judgment dated 20.03.2018
[hereinafter referred to as „Impugned Judgment‟] passed by the Single
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 1 of 15
Bench (SB) of this Court, whereby the application filed by the
Respondent (Claimant before the Tribunal/Licensor) under Section 34
of the Act of 1996, challenging the Arbitral Award (AA) dated
25.09.2014 along with the corrigendum dated 22.11.2014, came to be
allowed, while dismissing the application filed by the Appellant.
2. For the sake of clarity, consistency and ease of reference, the
parties in the present Appeal shall be referred to in accordance with
their respective status before the Arbitral Tribunal [hereinafter
referred to as „AT‟].
3. Pithily put, the Respondent contends that the SB, while passing
the Impugned Judgment, has substituted its own view for that of the
AT, while re-appreciating the evidence and thereby increasing the rate
of licence fee to be paid to the Claimant for the period of the contract.
Accordingly, the question that is now put for our consideration is
whether the SB while allowing the application of the Claimant under
Section 34 of the Act of 1996, has travelled beyond the permissible
scope of interference provided within the contours of the Act of 1996.
4. Since both the Appeals arise from the same lis and are founded
on the challenges raised controverting the decision of the SB in the
Impugned Judgment; they are with the consent of learned counsel for
the respective parties, being disposed of by this consolidated
judgment. However, for the sake of convenience and with the consent
of parties, FAO(OS)(COMM) 23/2021 is being treated as the lead
case to extrapolate our decision in both the Appeals.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 2 of 15
FACTUAL MATRIX:
5. In order to comprehend the issues involved in the present case,
the relevant facts in brief are required to be noticed.
6. The contractual relationship between the parties find its genesis
in the Leave and License Agreement dated 18.09.2016 [hereinafter
referred to as „Agreement‟] executed in respect of premises
admeasuring covered area of 10,625 sq. ft. and service area of 600 sq.
ft. situated at the First Floor of property bearing no. A-38, Mohan co-
operative Industrial Estate, Main Mathura Road, New Delhi against a
Licence fee of Rs. 6,73,500/- per month for an initial period of 11
months. As per the terms of the Agreement, the Respondent, as a
licensee, was at a liberty to renew said arrangement for two successive
terms of 11 months each, without any escalation in the Licence fee for
two more terms of 11 months. Further, the Agreement also
contemplated the extension of the Agreement by way of a new
Agreement after the passage of 33 months from 25.09.2006, with an
increased rate of 25% on the licence fee last paid, w.e.f. 26.06.2009.
7. Consequently, the record reflects that the contractual
arrangement did not remain static, rather the Agreement was extended
twice at the behest of the Respondent, firstly on 16.05.2007 and
thereafter on 07.05.2008, each for a further period of 11 months.
Thereafter, on 29.05.2009, the parties entered into an Addendum to
the Agreement [hereinafter referred to as „Addendum‟], whereby the
license was continued for a limited period from 26.06.2009 to
31.12.2009, albeit with a marginal enhancement of 5% on the last paid
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 3 of 15
licence fee. It may be pertinent to highlight that during all three
extensions sought, the Respondent has raised various grievances, inter
alia , a specific demand raised vide its communication dated
21.07.2009 for a documentary proof issued by MCD highlighting the
permissible commercial use of the subject premises and eventually
proceeded to withhold payment of licence fee from July 2009
onwards.
8. Faced with such withholding, the Claimant issued a notice
dated 22.08.2009 calling upon the Respondent to clear the outstanding
dues. However, upon failure of the Respondent to release the withheld
amount of licence fee, the Claimant vide its notice dated 16.10.2009,
terminated the Agreement thereby calling upon the Respondent to
hand over the possession of the subject premises. Aggrieved by the
inaction of the Respondent, the Claimant invoked arbitration clause
contained in the Agreement, thereby referring the matter to the AT.
9. The Claimant and the Respondent before the AT, by way of
Statement of Claim and Counter-Claim, respectively, sought relief on
9 counts. However, since the controversy before us, in essence, is
narrowed down to the determination of appropriate rate of licence
fee/damages payable by the Respondent, we deem it unnecessary to
deal with all the claims, while restricting ourselves only to the Claims
and Counter-Claim, that formed the fulcrum of the observation made
in the Impugned Judgment. The Claimant, inter alia , sought the
following claims:
“Claim No. II - Arrears of Licence fee w.e.f. July 2009 till the date
of termination of Agreement, i.e., 31.10.2009.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 4 of 15
Claim No. III - Damages/charges towards illegal occupation of the
premises after the termination of License w.e.f. the midnight of
31.10.2009.
Claim No. IV- Damages/charges towards illegal occupation of the
premises after the expiry of the extension period of License w.e.f.
the midnight of 31.12.2009.”
In response thereto, the Respondent by way its Statement of Counter-
Claim, inter alia , sought the following relief:
“Counter Claim No. 2 - For Rs. 1,84,40,000/- :Damages towards
difference in the rate of rent for office purpose and industrial purpose
Sept 2006 to Jan 2010.”
10. In the interregnum, the AT, while adjudicating an application
under Section 17 of the Act of 1996, vide its Order dated 03.05.2010
directed the Respondent to pay a sum of Rs. 40,00,000/- per month
w.e.f. July 2009 till the pendency of the arbitration proceedings. The
said Order travelled through successive judicial scrutiny, culminating
in direction by the Hon‟ble Supreme Court, requiring the Respondent
to comply with the order of AT, while staying the order passed by this
Court, wherein the order of AT was set aside.
11. Upon completion of pleadings and hearing of the parties, the
AT, passed the AA dated 25.09.2014. The AT, while conjointly
adjudicating Claim Nos.II, III and IV, held that the Claimant is
entitled to monthly Licence fee/Damages for use and occupation at the
rate of Rs. 20/- per sq. ft. from the period from September 2006 to
April 2011 and at the rate of Rs. 60 per sq. ft. from May 2011 till the
date of handing over of the subject premise. The findings returned on
these claims were also adopted by the AT while adjudicating Counter
Claim No.2.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 5 of 15
12. Aggrieved by the findings of the AT, the parties challenged the
AA before the SB, who, by way of Impugned Judgment, allowed the
objections raised by the Claimant, thereby modifying the operative
directions of the AA by restoring the Licence fee to the contractual
rate for the period from 25.09.2006 to 25.06.2009, whereas for the
period from 26.06.2009 to 31.12.2009, the Licence fee was directed to
be paid in accordance with the Addendum and for the illegal usage
and occupation by the Respondent for the period from 01.01.2010 to
27.03.2016, the Fee was payable at the agreed rate of Addendum.
13. Accordingly, dissatisfied by the findings rendered by the SB in
the Impugned Judgment, the Respondent by way of this Appeal has
sought the indulgence of this Court in examining the correctness of
findings thereof.
CONTENTION OF PARTIES:
14. Learned counsel for the Respondent, while controverting the
findings of the Impugned Judgment and supporting the observations
made in the AA, has made the following submissions:
14.1 It has been argued that the SB while exercising power under
Section 34 of the Act of 1996, has substituted his own view for that of
the AT, in as much as, the AT did not re-write the contract and the
Claim Nos.II to IV and Counter Claim No.2, were adjudicate based on
evidence and a categorical finding by the AT that the contractual rate
of rent was obtained through misrepresentation on the part of the
Claimant, by wrongfully stating in Clause 8(c) of the Agreement that
the subject premises is commercially usable.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 6 of 15
14.2 Further, it has been contended that the SB erred by awarding
the contractual rate for the entire period from September 2006 to
March 2016, disregarding the AT‟s finding that the contractual rate
applied only from April 2011. On the aforesaid premise, it has been
contended that by doing so the SB effectively rewrote the AA on
merits, which runs contrary to the law laid down by the Supreme
Court in Gayatri Balawamy v M/S. ISG Novasoft Technologies
1
Limited .
14.3 It has been the case of the Respondent that AT correctly applied
the law, holding that damages for misrepresentation are measured by
the difference between contractual rate and the actual market values,
not actual user of the premises. Additionally, it has been contended
that the Claimant had misrepresented the premises since the inception
of the Agreement. Nevertheless, the SB absolved the Respondent of
the consequences of such misrepresentation, holding that, since the
conversion charges were made retrospectively from 2007, no
misrepresentation existed with effect from 01.04.2007. However, this
view is argued to be patently erroneous.
15. Per contra , learned counsel for the Claimant, while supporting
the findings rendered in the Impugned Judgment, has opposed the
present Appeal, in as much as the same does not call for any
interference.
ANALYSIS:
16. This Court has heard the submissions advanced by the parties at
1
2025 INSC 605
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 7 of 15
length and has conducted a thorough examination of the pleadings,
documents, Impugned Judgment and the AA.
17. The core issue that falls for the consideration of this Court is
whether, within the narrow confines of interference permissible under
Sections 34 and 37 of the Act of 1996, the Respondent has been able
to make out any ground to set aside the Impugned Judgment, by way
of which the findings of the AA, with respect to the rate of Licence
fee, came to be modified.
18. At the outset, it is necessary to highlight that while exercising
jurisdiction envisaged under Section 37 of the Act of 1996, we are
conscious of the fact that the appellate adjudicatory power we hold
today, is one of the narrower ambits of the Arbitration jurisprudence,
as has been consistently laid down by the Hon‟ble Supreme Court in a
catena of decisions.
2
19. This Court in NHAI v. HK Toll Road (P) Ltd. , observed as
under:
“ 57. The Appellate Court is not required to substitute its views with
the view taken by the Arbitral Tribunal which is a reasonable or a
plausible view except where the discretion is exercised arbitrarily or
where the AT has ignored the settled principles of law. In fact, the
whole purpose to bring the 1996 Act is to give supremacy to the
discretion exercised by the AT. The Appellate Court is not required to
interfere in the arbitral orders especially a decision taken is at an
interlocutory stage. The Appellate Court is only required to see the
whether the AT has adhered to the settled principles of law rather
than re-assessing the merits of the AT„s reasoning. ”
(Emphasis Supplied)
2
2025 SCC OnLine Del 2376
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 8 of 15
20. The Hon‟ble Supreme Court has also reiterated that the
jurisdiction conferred on the Court under Section 34 of the Act of
1996, alike Section 37 of the Act of 1996, is tailored. However, the
powers exercised by the Courts under Section 37 of the Act of 1996,
the jurisdiction of the Appellate Court in examining an order setting
aside or refusing to set aside an Award is even more circumscribed.
The Hon‟ble Supreme Court in Larsen Air Conditioning &
3
Refrigeration Co. v. Union of India , has observed as under:-
“ 15. The limited and extremely circumscribed jurisdiction of the court
under Section 34 of the Act, permits the court to interfere with an
award, sans the grounds of patent illegality i.e. that “illegality must
go to the root of the matter and cannot be of a trivial nature”; and
that the Tribunal “must decide in accordance with the terms of the
contract, but if an arbitrator construes a term of the contract in a
reasonable manner, it will not mean that the award can be set aside
on this ground” [ref : Associate Builders [Associate Builders v. DDA,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , SCC p. 81, para 42].
The other ground would be denial of natural justice. In appeal,
Section 37 of the Act grants narrower scope to the appellate court to
review the findings in an award, if it has been upheld, or substantially
upheld under Section 34. ”
(Emphasis Supplied)
21. Having delineated the scope of interference permissible under
Sections 34 and 37 of the Act of 1996, we shall now advert to the rival
submissions made by the parties, with respect to the enhancement of
Licence fee granted by the SB, in exercise of his jurisdiction under
Section 34 of the Act of 1996.
22. At the outset, it may be noted that under Section 28(3) of the
Act of 1996, an Arbitral Tribunal seated in India is mandatorily
3
(2023) 15 SCC 472
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 9 of 15
required to decide the dispute before it in accordance with the terms of
the contract while giving due consideration to the applicable trade
usages. This Court in Divya Ashish Jamwal v India Yamaha Motor
4
Pvt. Ltd. held that absent an express authorisation to decide the
dispute ex aequo et bono, the Tribunal cannot travel beyond or rewrite
the bargain entered between the parties by way of a contract, on the
basis of abstract notion of equity or fairness.
5
23. The Supreme Court in Associate Builders v DDA , clarified
that if an AA is contrary to the substantive provision of law of India,
in effect, it is in contravention of Section 28(1)(a) of the Act of 1996.
Similarly, violation of the terms of contract, in effect, would qualify as
a contravention of Section 28(3) of the Act of 1996. Therefore, an
award granting relief not anchored in the contract, or directly
contradicting the terms and arrangements arrived at by the parties, will
be treated as being violative of Section 28(3) of the Act of 1996,
thereby amounting to patent illegality for the purpose of Section 34 of
the Act of 1996.
24. The Supreme Court in Associate Builders (Supra) , while
providing a broader meaning to the term patent illegality highlighted
that, it shall include: (i) decision contrary to substantive law or the Act
(ii) decision contrary to terms of the contract; and (iii) perversity.
25. Having delineated the above principles, we shall now turn to the
facts and circumstances that have arisen in the present dispute. The
AT while rendering the AA has rested Claim Nos.II, III and IV and
4
2026:DHC:1645-DB
5
(2015) 3 SCC 49
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 10 of 15
Counter-Claim No.2, on a finding that Clause 8(c) of the Agreement
contained a misrepresentation by the Claimant, that the subject
premise could be used for office purposes and that such usage was
permissible under the applicable laws. Against this backdrop, the AT
refused to grant the agreed licence fee and instead held that for the
period from September 2006 to April 2011, the Claimant was entitled
to receive only Rs. 20 per sq. ft. per month (described as an industrial
rate) and Rs. 60 per sq. ft. per month thereafter once conversion
charges were paid.
26. On the contrary, the SB while evaluating Section 19 of the
Indian Contral Act, 1872 [hereinafter referred to as „Act of 1872‟],
expressly factored in the conduct of the Respondent after it had begun
to raise red flags about MCD sanction. The Respondent despite
issuing its letter dated 21.07.2009 seeking documentary proof of
permissibility of official use of the subject premise from MCD, did
not rescind the contract or surrender the possession back to the
Claimant. Instead, the Respondent, proceeded to execute the
Addendum and continued occupation in the subject premises.
27. The SB also while analysing the factual matrix as also put forth
before the AT, found that (i) the Respondent had been in continuous,
unhindered commercial occupation of the premises, running its office
throughout; (ii) the original Agreement had been renewed twice, at the
instance of the Respondent and without escalation, up to
25.06.2009; (iii) by way of the Addendum, the parties again mutually
agreed to continue the arrangement from 26.06.2009 to 31.12.2009 at
a 5% enhancement, specifically affirming that all other terms and
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 11 of 15
conditions remained unchanged; and (iv) no letter seeking MCD
permission or raising misuse was written by the Respondent before
21.07.2009, while the first MCD demand for conversion charges itself
arose only on 25.03.2011, and was met by payment in April 2011.
28. In the considered view of this Court, the AT neither identified
any contractual clause authorising the re-pricing nor properly worked
out damages linking the alleged misrepresentation to a quantified
pecuniary loss; rather, the AT merely substituted the agreed rate of
licence fee with a notional industrial benchmark drawn from an
unrelated lease.
29. Before turning to the examination of the jurisdiction exercised
by the SB, we deem it pertinent to highlight that the in terms of
Section 19 of the Act of 1872, once a contracting party, after
discovering the alleged misrepresentation, elects to continue under the
contract and even enters into a further arrangement (the Addendum)
on the same footing, its conduct is consistent with affirmance of the
contract rather than rescission. Therefore, the SB rightly held that the
Respondent could not approbate and reprobate, continuing in
possession and commercially exploiting the premises while
simultaneously seeking to rework the agreed licence fee by invoking
misrepresentation.
30. The approach adopted by the AT, in effect, permitted a legally
impermissible dichotomy, permitting the Respondent to retain the
substantive benefits of the contract, including continued commercial
user, while simultaneously re-engineering the financial substratum
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 12 of 15
thereof. Such an exercise runs afoul of the statutory scheme of Section
19 of the Act of 1872, which does not contemplate selective avoidance
or partial rescission confined to economic obligations while affirming
the remainder of the contract. The SB‟s reliance on the post-disclosure
conduct of the Respondent, particularly the execution of the
Addendum, furnishes a cogent and determinative basis to hold that the
AA‟s re-pricing mechanism was ex facie contrary to both statutory
mandate and the sanctity of the contractual bargain entered into by the
parties.
31. Applying the parameters delineated in Associate Builders
(Supra), the SB was right in characterising the impugned portion of
the AA as suffering from perversity and patent illegality because it
ignored the aforesaid vital aspects of the conduct of the Respondent.
The absence of any recorded finding as to actual loss, combined with
the grant of a substantial financial adjustment predicated on an
industrial benchmark, renders the AA vulnerable on the touchstone of
reasonableness and fidelity to evidence. This was not a mere instance
of adopting one plausible view of evidence over another; rather, the
view of the AT was one that no reasonable adjudicator could take
while remaining faithful to the contract and applying Section 19 of the
Act of 1872 as well as Section 28(3) of the Act of 1996.
32. On the aspect of relief, the SB exercised circumscribed
jurisdiction under Section 34 of the Act of 1996 by confining his
interference to the severable component of the award that
impermissibly altered the agreed licence fee for the period spanning
September 2006 to April 2011. The SB by restoring the stipulated
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 13 of 15
rates under the Agreement and the Addendum, as the governing
measure of licence fee and consequential damages, and leaving the
remainder of the award intact, adhered to the doctrine of severability
as judicially recognised in Gayatri Balasamy (Supra) . Such calibrated
intervention and added emphasis by the SB on the conduct of the
Respondent underscores that the SB‟s endeavour was not to supplant
the arbitral tribunal‟s domain, but to excise the legally untenable
portion and uphold the integrity of the parties‟ consensual bargain.
33. Pithily put, the SB correctly held that despite raising red flags,
the Respondent executed the Addendum thereby continuing the
commercial use amounting to an unequivocal affirmance of the
contract under Section 19 of the Act of 1873, thereby excluding
recission. Similarly, the AT‟s substitution of the agreed licence fee
with an industrial rate, in the absence of proof of actual loss and in
disregard of the parties‟ subsequent conduct, was ex facie contrary to
Section 19 of the Act of 1872, Section 28(3) of the Act of 1996, and
the contractual stipulations, rendering the award perverse within the
meaning of Associate Builders (Supra) .
34. Therefore, the limited interference exercised by the SB, setting
aside the severable and patently illegal component of the AA, while
restoring the Agreement/Addendum rates, was a legitimate exercise of
powers conferred under Section 34 of the Act of 1996, grounded in
the parties‟ own conduct and elections, and does not disclose any
excess of jurisdiction warranting interference of this Court under
Section 37 of the Act of 1996.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 14 of 15
CONCLUSION:
35. In view of the foregoing discussion and findings, this Court
finds no infirmity in the Impugned Judgment dated 20.03.2018 passed
by the Single Bench of this Court. The Appellant has failed to
demonstrate any ground warranting interference by this Court in
exercise of its appellate jurisdiction under Section 37 of the Act of
1996.
36. The present Appeals, being devoid of merit, are accordingly
dismissed.
ANIL KSHETARPAL, J.
AMIT MAHAJAN, J.
MAY 12, 2026
s.godara/hr
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:12.05.2026
15:20:55
FAO(OS)(COMM) 172/2020 & connected matter Page 15 of 15