State Bank Of India vs K R Anand
- Court
- Delhi High Court
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 07.09.2026
Judgment pronounced on: 15.09.2026
# CNR No. DLHC010035702024
+ O.M.P. (COMM) 69/2024 &I.A. 2596/2024
STATE BANK OF INDIA .....Petitioner
Through: Mr. Dharmesh Mishra, Sr. Adv.
with Mr. Rajiv Kapur, Ms. Riya
Sood & Mr. Akshit Kapur,
Advs.
versus
K R ANAND .....Respondent
Through: Mr. Aabhas Kshetarpal, Mr.
Dhiliban Varadarajan & Mr.
Harsh N Dudhe, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. This petition is filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (for short ‘the Act’) against the
arbitral award dated 31.08.2023 (for brevity ‘the award’).
Brief Facts
2. The brief facts are that the petitioner/State Bank of India
(hereinafter ‘SBI’) invited tenders for construction of seventy-
six flats for officers at Sector-62, Noida including civil, internal
and external water supply, complete sanitary and external
development works. M/s K.R. Anand (hereinafter ‘the
respondent’) was the successful bidder. The work was awarded
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 1 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
vide Letter of Award dated 22.12.2012. The parties entered into
an agreement dated 16.01.2013 for a value of
Rs.19,81,39,324/-. The period for completion of the work was
twenty-four months i.e. by 15.01.2015.
2.1 The work was not completed within the stipulated
period. The respondent sought three extensions. The first
extension was for eighty-five days from 15.01.2015 to
08.04.2015 with Price Variation Adjustment (for short ‘PVA’).
The second extension was for one forty-five days from
09.04.2015 to 31.08.2015 with PVA. The third post-facto
extension was for one fifty days from 01.09.2015 to 28.01.2016
without PVA. The extensions were granted vide letters dated
28.07.2015, 24.11.2015 and 23.08.2016 respectively.
2.2 The respondent completed the work on 23.01.2016 and
submitted the final bill on 23.08.2016. The Virtual Completion
Certificate was issued on 11.01.2017 and the defect liability
period ended on 23.01.2017. The final bill was cleared on
15.05.2017 and the payment was released on 12.06.2017.
2.3 Disputes arose between the parties regarding the reasons
for the delay in completion of the work. The respondent
attributed the delay to SBI in providing necessary drawings and
approvals. SBI contended that the approvals were given after
inspection and preparation of the designs by the architect,
M/s Taneja Associates (P) Ltd. (hereinafter ‘the architect’). The
claims raised by the respondent vide letter dated 11.09.2018
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 2 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
were rejected by SBI on 28.09.2018, being time-barred.
2.4 On 07.01.2019, arbitration was invoked at the instance of
the respondent under clause 38 of the General Conditions of
Contract (for short ‘GCC’) and fourteen claims were raised
aggregating to Rs.4,92,35,263/-. By the impugned award, the
arbitrator awarded a total sum of Rs.1,42,95,725/- in favour of
the respondent. The claims raised and the amounts awarded are
tabulated below:
Claim
Brief Description of
claim
Claim Amount
Award (Rs.)
No.
(Rs.)
1 Loss of overhead
expenditure
65,80,940/- 30,27,231/-
2 Interest on claim no.1 34,77,982/- 8% pendente
lite & future
interest
3 PVA 1,00,65,359/- 1,00,65,360/-
4 Interest on delayed
payment of PVA
36,31,363/- 8% pendente
lite & future
interest
5(a) Short payment towards
extra items
20,40,032/- NIL
5(b) Cost of extra works
carried out but not paid
34,87,052/- NIL
6 Interest on Claims 5(a) &
5(b)
29,21,026/- NIL
7 Loss on account of delay
in payment of RA bills
and final bill
20,81,957/- 4,21,385/-+
8% future
interest
8 Reimbursement of
Service Tax
59,88,125/- NIL
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 3 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
9 Interest on Claim No.8 31,84,010/- NIL
10 Loss of interest due to
delayed release of
retention/security deposit
and withholding from
20th and final bill
17,92,113/- 8,08,750/-+
8% future
interest
10(i)–
10(iv)
Interest on Claim No.10 4,28,917/- NIL
11 Loss due to delay in
earning profit
9,80,536/- NIL
11(a) Interest on Claim No.11 5,18,207/- NIL
12 Pendente lite interest
@15% per annum
NIL
13 Future interest @15% per
annum
NIL
17 Cost of arbitration NIL
2.5 The challenge in the present petition is confined to claim
nos.1, 3, 7 & 10 and the consequential interest awarded thereon.
Submissions of the Parties
3. Learned senior counsel for SBI submits that the award
qua claim no.1 has inherent contradictions. The arbitrator
recorded that delay of 205 days was attributable to the
respondent and 175 days to SBI yet awarded damages towards
overhead expenditure for the period of delay not attributable to
SBI. Reliance is on Union of India v. Pundarikakshudu and
Sons & Anr . (2003) 8 SCC 168 to contend that an award having
inherent contradictions is liable to be set aside. The submission
is that the arbitrator erred in awarding claim no.1 in the absence
of evidence proving the loss suffered on account of overheads
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 4 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
incurred due to prolongation of the contract. Reliance is placed
on Unibros v. All India Radio 2023 SCC OnLine SC 1366 and
Batliboi Environmental Engineers Ltd. v. HPCL & Anr.
(2024) 2 SCC 375. The contention is that on failure of the
respondent to prove the actual losses suffered, the Emden
formula could not have been relied upon for quantification of
damages. It is emphasised that the award is non-speaking and
no reasons have been recorded for accepting the calculations
based upon Emden formula and the CPWD manual.
3.1 Vis-a-vis claim no.3, the contention is that the arbitrator
erred in ignoring the vital evidence on record and the award
suffers from patent illegality. The argument is fortified by
relying upon the third extension whereby the time was extended
without PVA, in contrast to the first two extensions which were
subject to PVA. It is canvassed that the architect vide letter
dated 11.11.2015 recommended the third extension without
monetary benefit and PVA but despite this evidence adduced
the arbitrator erred in awarding the claim for PVA. Reliance is
on clause 44.3 of the GCC to contend that the price adjustment
clause was applicable only to work executed during the contract
period including an authorised extension and not thereafter. The
submission is that the third extension was accepted by the
respondent without reserving the right to claim PVA and the
claim awarded is unsustainable under Sections 55 and 73 of the
Indian Contract Act, 1872 (hereinafter ‘Contract Act’). To
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 5 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
fortify the argument, reliance is placed upon Kailash Nath and
Associates v. New Delhi Municipal Committee 99 (2002) DLT
361 (DB-DHC).
3.2 Qua claim no.7 the grant of interest for delay in payment
of the running bills and final bill is challenged contending that
the running bills were in the nature of advance payments and
not debt within the meaning of the Interest Act, 1978
(hereinafter ‘Interest Act’) and no interest is to be paid.
Reliance is on the decision of Supreme Court in State of
Manipur and Others v. Shangreihan Muivah (2002) 10 SCC
516.
3.3 With regard to claim no.10 it is argued that the arbitrator
erred in awarding interest for delay in refund of the security
deposit. The submission is that clause 6.2 of the GCC stipulates
that no interest shall be paid on the amount retained by the bank
as security deposit. The grievance is that the arbitrator relying
upon Section 31(7) of the Act could not have awarded interest
consequent to the parties having agreed otherwise i.e. no
interest shall be paid on the security deposit. Reliance is on the
decision of Jai Prakash Associates Limited (JAL) v. Tehri
Hydro Development Corporation (India) Limited (THDC)
(2019) 17 SCC 786 and Garg Builders v. Bharat Heavy
Electricals Limited (2022) 11 SCC 697 to contend that the
jurisdiction of the arbitrator to award interest under Section
31(7) of the Act is ousted by the agreement between the parties.
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 6 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
4. Per contra, the scope of interference under Section 34 of
the Act is limited and a plausible view taken by the arbitrator is
not to be interfered with. Reliance is on the decision of the
Supreme Court in OPG Power Generation Private Limited v.
Enexio Power Cooling Solutions India Private Limited and
Anr. (2025) 2 SCC 417.
4.1 The award of claim no.1 is defended stating that for loss
sustained evidence in the form of bills for expenses incurred
during the prolonged period were produced before the
arbitrator. The contention is that the arbitrator rightly awarded
the claim relying upon the Emden formula read with the CPWD
manual wherein the overhead expenses were quantified at 7.5
per cent. The decision of this court in National Highways and
Infrastructure Development Corporation Limited v.
Intercontinental Consultants and Technocrats Private Limited
2026 SCC OnLine Del 1776 is relied upon for the proposition
that determination of the quantum of evidence falls within the
exclusive domain of the arbitrator.
4.2 It is argued that the view taken by the arbitrator for
awarding claim no.3 is plausible. The submission is that the
architect in cross-examination admitted that an effort was made
to convince SBI to grant PVA for the third extension.
Moreover, a factual finding is recorded by the arbitrator that
SBI was responsible for the delay necessitating third extension.
The submission is that claim no.3 also included the shortfall of
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 7 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
Rs.56,84,292/- towards PVA for the earlier extensions and is
not challenged by SBI. The contention of SBI that the
acceptance of the third extension without reserving the right to
claim price variation debars the claim for PVA is refuted. To
lend support to the contention that the delay was not attributable
to the respondent reliance is on the letter of the architect dated
23.08.2016 and the entry at serial no.16 in the document
granting the third extension. The submission is that the third
extension was granted post-facto and there was no occasion for
SBI to raise an objection regarding PVA.
4.3 With regard to claim no.7, it is contended that clause 37
of the GCC prescribes the time for payment against certificates
issued by the architect and applies to the running bills as well as
the final bill. The submission is that there was a delay of 243
days in payment of the running bills and a further delay of 133
days in release of payment towards the final bill. The arbitrator
after considering and reconciling the charts furnished by the
parties awarded interest for the period of delay proved. It is
argued that the award based on the contractual stipulation calls
for no interference under Section 34 of the Act.
4.4 The argument is that clause 6.2 of the GCC was not
pressed before the arbitrator and the grievance that claim no.10
was awarded contrary to clause 6.2 cannot be raised for the first
time under Section 34 of the Act. Reliance is placed upon the
decision of the Supreme Court in Union of India v. Susaka
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 8 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
Private Limited and Others (2018) 2 SCC 182.
5. Heard learned counsel for the parties at length and
perused the record with their able assistance.
RELEVANT CLAUSES
6. Before proceeding further, it would be apposite to quote
the relevant clauses of the GCC:
“ Clause 6 Security Deposit
6.1 Total security deposit shall be 5% of contract
value. Out of this 2% of contract value is in the form
of initial security deposit, which includes the EMD.
Balance 3% shall be deducted from the running
account bill of the work at the rate of 10% of the
respective running account bills i.e., deduction from
each running bill account will be 10% till total 3%
of contract value is reached. 50% of the total
security shall be paid to the contractors on the basis
of achieving the virtual completion along with the
final 3rd Payment. The balance 50% would be paid
to the contractors after the defects liability period as
specified in the contract provided he has carried out
all the work attended to all the defects in accordance
with the condition of the contract and clearance, if
any, of the observations of the CTE of CVC, and
would be released after closure of CTE’s Report.
6.2 No interest shall be paid to the amount retained
by the Bank as Security Deposit.
Clause 37 Certificate of payment
The contractor shall be entitle under the certificates
to be issued by the Architect / consultant to the
contractor within 14 working days from the date of
certificate to the payment from SBI from time to
time. The SBI shall recover the statutory recoveries
towards Income tax, Work contract tax as per the
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 9 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
prevailing bye laws and other dues including the
retention amount from the certificate of payment.
Provided always that the issue of any certificate by
the Architect/consultant during the progress of
works or completion shall not have effect as
certificate of satisfaction or relieve the contractor
from his liability under clause.
Clause 44 Price Variation Adjustment
44.3 The price adjustment clause shall be applicable
only for the work executed during the contract,
period including authorised extension, if any. ln case
the work is not completed within the period
including authorised extension and the provision of
liquidated damages has to be enforced, this
adjustment clause will not be applicable for work
done during that period. It is also clarified that price
adjustment clause will not be applicable to any extra
variation items, the rates of which are based on
prevailing market rate.”
7. The dispute in the present petition only pertains to claim
nos.1, 3, 7 & 10. The undisputed facts are that the work was not
completed within the stipulated period. Three extensions were
granted by SBI, the first two with PVA and the third extension
without PVA.
ANALYSIS FOR CLAIM NO. 1
8. The respondent claimed an amount of Rs.65,80,940/- for
overhead expenditure incurred during the period of
prolongation of the contract by twelve and a half months. The
respondent attributed the entire delay to SBI and the claim was
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 10 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
computed relying upon the Emden formula and the CPWD
manual.
9. The arbitrator after considering the evidence of the
architect concluded that 205 days of delay were attributable to
the respondent and 175 days to SBI. The arbitrator thereafter
proceeded to quantify the claim for the period of delay
attributable to SBI. It was taken note of that the Emden formula
was an accepted mode for assessing overhead expenditure. The
relevant portion of the award granting claim no.1 is reproduced
below:
“99. The Claimant, in cross-examination, has not
been able to rebut the testimony of RW-3 relating to
the statements made in para 13 of the affidavit by
way of evidence and the documents mentioned
therein. In that view of the matter, this Tribunal
accepts the well-reasoned analysis of RW-3.
Accepting the evidence of RW-3, this Tribunal holds
that the Claimant responsible for205 days of delay
and the Respondent responsible for 175 days of
delay.
l00. The Claimant is entitled to Overhead
expenditure for 175 days only. Emden formula has
been accepted as mode of assessing the Overhead
expenditure. Reference be made to Mcdermott
International Inc vs. Burn Standard Co. Ltd.,
(2006) 11 SCC 181, Associate Builders vs. Delhi
Development Authority, 2015 (3) SCC 49 and
Atlanta Limited vs. Union of India (2022) 3 SCC
739 relating to the principles for computation of
Overhead expenditure.
101. Applying the aforesaid principles, this Tribunal
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 11 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
awards Rs. 30,27,231/- (Rs.5,26,475 (7.5% of prime
cost of tender i.e. Rs.16,84,71,795/- x 5.75 months)
towards the Overhead expenditure for the period of
175 days. Claim No. l is partially allowed in the
above terms.”
10. The law is well settled that for awarding damages under
Section 73 of the Contract Act, the twin conditions are required
to be fulfilled: first, breach of the contractual conditions and
second, the actual loss or damage suffered or proof that it is not
possible to prove the actual damage suffered. It is fruitful to cite
the following decisions of the Supreme Court:
10.1 In Kailash Nath Associates v. DDA, (2015) 4 SCC 136 it
was held:
“43.1. Where a sum is named in a contract as a
liquidated amount payable by way of damages, the
party complaining of a breach can receive as
reasonable compensation such liquidated amount
only if it is a genuine pre-estimate of damages
fixed by both parties and found to be such by the
court. In other cases, where a sum is named in a
contract as a liquidated amount payable by way of
damages, only reasonable compensation can be
awarded not exceeding the amount so stated.
Similarly, in cases where the amount fixed is in the
nature of penalty, only reasonable compensation
can be awarded not exceeding the penalty so stated.
In both cases, the liquidated amount or penalty is
the upper limit beyond which the court cannot
grant reasonable compensation.
43.2. Reasonable compensation will be fixed on
well-known principles that are applicable to the law
of contract, which are to be found inter alia in
Section 73 of the Contract Act.
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 12 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
43.3. Since Section 74 awards reasonable
compensation for damage or loss caused by a
breach of contract, damage or loss caused is a sine
qua non for the applicability of the section.
43.4. The section applies whether a person is a
plaintiff or a defendant in a suit.
43.5. The sum spoken of may already be paid or be
payable in future.
43.6. The expression “whether or not actual
damage or loss is proved to have been caused
thereby” means that where it is possible to prove
actual damage or loss, such proof is not dispensed
with. It is only in cases where damage or loss is
difficult or impossible to prove that the liquidated
amount named in the contract, if a genuine pre-
estimate of damage or loss, can be awarded.”
10.2 In State of Rajasthan v. Ferro Concrete Construction
(P) Ltd., (2009) 12 SCC 1 it was held:
“55.While the quantum of evidence required to
accept a claim may be a matter within the exclusive
jurisdiction of the arbitrator to decide, if there was
no evidence at all and if the arbitrator makes an
award of the amount claimed in the claim
statement, merely on the basis of the claim
statement without anything more, it has to be held
that the award on that account would be invalid.
Suffice it to say that the entire award under this
head is wholly illegal and beyond the jurisdiction
of the arbitrator, and wholly unsustainable.”
11. In the present case, the arbitrator without the respondent
discharging the onus with regard to fulfilment of the second
limb for claiming damages under Section 73 of the Contract Act
directly proceeded to quantify the claim on the basis of the
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 13 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
Emden formula. The award of claim no.1 is against the
provisions of the Contract Act, the decisions of the Supreme
Court in Kailash Nath Associates v. DDA (supra) & Ferro
Concrete Construction (P) Ltd. (supra) and suffers from patent
illegality.
12. The Supreme Court in Unibros v. All India Radio (supra)
held that reliance on a formula is not a substitute for
establishing the loss actually suffered. The relevant paragraphs
of the judgment are reproduced below:
“18. Hudson's formula, while attained
acceptability and is well understood in trade, does
not, however, apply in a vacuum. Hudson's
formula, as well as other methods used to
calculate claims for loss of off-site overheads and
profit, do not directly measure the contractor's
exact costs. Instead, they provide an estimate of
the losses the contractor may have suffered. While
these formulae are helpful when needed, they
alone cannot prove the contractor's loss of profit.
They are useful in assessing losses, but only if the
contractor has shown with evidence the loss of
profits and opportunities it suffered owing to the
prolongation.
19. The law, as it should stand thus, is that for
claims related to loss of profit, profitability or
opportunities to succeed, one would be required to
establish the following conditions: first, there was
a delay in the completion of the contract; second,
such delay is not attributable to the claimant;
third, the claimant's status as an established
contractor, handling substantial projects; and
fourth, credible evidence to substantiate the claim
of loss of profitability. On perusal of the records,
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 14 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
we are satisfied that the fourth condition, namely,
the evidence to substantiate the claim of loss of
profitability remains unfulfilled in the present
case.”
( emphasis supplied )
13. In the case in hand the damages awarded relying upon the
Emden Formula in the absence of evidence to prove the actual
loss suffered is contrary to the settled position of law.
14. Another aspect to be considered is that Section 31(3) of
the Act mandates a reasoned award and recording reasons is not
a mere formality. Reference is to the decision of the Supreme
Court in Dyna Technologies Pvt. Ltd. v. Crompton Greaves
Ltd. (2019) 20 SCC 1 wherein it was held as under:
“34. The mandate under Section 31(3) of the
Arbitration Act is to have reasoning which is
intelligible and adequate and, which can in
appropriate cases be even implied by the courts
from a fair reading of the award and documents
referred to thereunder, if the need be. The aforesaid
provision does not require an elaborate judgment to
be passed by the arbitrators having regard to the
speedy resolution of dispute.”
15. There cannot be a dispute with the proposition that an
arbitral award is not to be equated with the judicial judgement
and reasons are to be gathered from a reading of the award as a
whole and the documents referred to therein. However, even on
a fair reading of the award as a whole no reason emanates for
the arbitrator accepting the calculation based on the Emden
formula without there being evidence to prove the loss suffered
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 15 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
or that it was difficult or impossible to prove the actual loss
suffered. The award of claim no.1 falls within the teeth of
Section 31(3) of the Act.
FOR CLAIM NO.3
16. The arbitrator held that during the cross-examination the
architect admitted that an attempt was made to convince SBI to
grant the third extension with PVA. There is a contradiction
between the contents of the letter dated 11.11.2015 and the
statement of the architect in cross-examination. The
recommendation of the architect was for grant of the third
extension up to 28.01.2016 without any monetary benefit and
PVA to the respondent. The relevant portion of the letter is
reproduced below:
“An overall delay of 150 days is considered for
time extension,
The Extension be granted for upto January 28,
2016 but without any monetary benefit and
without PVA to the contractor. ”
17. In respect of the third extension, the claim was awarded
solely relying upon the alleged admission of the architect in
cross-examination. The question no. 44 and the answer thereto
are reproduced below:
“Q.44. Is it correct that the claimant had submitted
the final PVA bill for Rs. 1,95,51,176/- at page 192
but the same was never processed by you, only
because you say that the third extension given by
the bank was without PVA?
Ans. I even tried to convince the bank but I could
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 16 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
not convince them as I could not explain the bank
the delay done on part of the contractor.”
18. The answer to question no.44 cannot be construed as an
admission that the third extension was subject to payment of
PVA. Be that as it may, the PVA for the third extension could
have been granted by the arbitrator had there been a clause in
the contract providing for it or if evidence was adduced to
establish the entitlement of the respondent to claim PVA for this
period. There is no reason recorded in the award for granting
PVA for the third extension except reliance upon the admission
of the architect, which does not exist.
19. The documentary evidence in the shape of the
recommendation letter dated 11.11.2015 is relevant material on
record and cannot be ignored on the basis of an alleged
admission of the architect in cross-examination.
20. Another aspect to be considered is that while deciding
claim no.1 the total delay of 380 days was attributed to both
parties i.e. 175 days to SBI and 205 days to the respondent.
However, there is no discussion either in claim no. 1 or in claim
no.3 as to the time period for which the delay was attributable
to SBI and to the respondent respectively. In such
circumstances, the conclusion recorded in claim no. 3 that SBI
was responsible for the third extension is without any basis and
is perverse. Reliance of the learned counsel for the respondent
on the entry at serial no.16 in the document granting the third
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 17 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
extension does not enhance the case of the respondent as it
reproduces the recommendation of the architect and not the
conclusion for extending the time.
21. Under claim no.3, the arbitrator dealt with two parts,
firstly the short payment of PVA for the initial two extensions
granted with PVA and secondly the PVA for the third
extension. Though the amounts were awarded under one claim,
the two amounts were dealt with separately and different
reasons were recorded for awarding Rs.56,84,292/- and
Rs.43,81,068/- respectively. This court has no power to modify
the award. However, the Supreme Court in Gayatri Balasamy v.
ISG Novasoft Technologies Ltd ., (2025) 7 SCC 1 held that
segregation of issues which are not intricately connected is
permissible. The award of PVA up to the second extension is
not under challenge. The two awards of PVA are not
interconnected and are severable and only the award of PVA for
the third extension is liable to be set aside.
FOR CLAIM NO.7
22. It is not disputed by learned counsel for the parties that
clause 37 of the GCC dealing with certificate of payment
prescribes the procedure, time for payment against certificates
issued by the architect and applies to both running bills and the
final bill. It is not under challenge that there was delay in
making payment of the running bills and the final bill. The
arbitrator on that basis awarded Rs.4,21,385/- towards interest.
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 18 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
23. The contention of SBI that the payment of running bills is
in the nature of an advance payment and delay in clearing the
running bills shall not entitle the respondent to interest, lacks
merit. Clause 37 of the GCC stipulates the timeline of fourteen
working days from the date of certificate issued by the architect
for making payment to the contractor. The arbitrator after
considering clause 37 recorded that the payments were not
made within the stipulated period and awarded interest for the
delay in payment. The view taken by the arbitrator is a plausible
view and calls for no interference in proceedings under Section
34 of the Act. Reference is made to the decision of the Supreme
Court in Prakash Atlanta v. National Highways Authority of
India 2026 INSC 76 wherein it was held that a plausible view
taken by the arbitrator is not be interfered with unless the
conclusion arrived at is perverse.
24. Reliance of learned senior counsel for SBI on the
decision of State of Manipur and Others v. Shangreihan
Muivah (supra) is of no avail. The clause considered by the
Supreme Court in that case specifically provided that the
intermediary payments were to be treated as advances against
the final payment and not as payment for the work actually
done and completed. There is no such clause in the case in hand
and clauses in both cases are materially different.
25. The contention that the jurisdiction of the arbitrator under
Section 31(7) of the Act to grant interest stood ousted is noted
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 19 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
to be rejected. No clause is brought to the notice of the court or
the arbitrator providing that no interest shall be paid on delayed
payment of running bills or the final bill. Reliance on the
decision of the Supreme Court in Jai Prakash Associates
Limited (JAL) v. Tehri Hydro Development Corporation
(India) Limited (THDC) (supra) does not come to the rescue of
SBI as in that case there was a specific contractual bar for
awarding interest whereas no such bar is pointed out in the
present case. Moreover, it was held that the phraseology of the
agreement has to be considered while examining the power of
the arbitrator to award pendente lite interest.
FOR CLAIM NO.10
26. The security deposit of 5% of the contract value as
stipulated under clause 6 of the GCC was made by the
respondent. 50% of the total security as per clause 6.1 of the
GCC was to be refunded along with the payment of the final bill
on the basis of the certification of virtual completion. The
balance 50% was to be paid back to the respondent after the
defect liability period was over subject to the respondent
carrying out and attending to the defects in accordance with the
conditions of the contract.
27. It is not disputed that the work was completed on
23.01.2016 and the defect liability period ended on 23.01.2017.
The first 50% of the security deposit was released on
18.06.2017 after a delay of 321 days and the balance 50% on
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 20 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
21.03.2018 with a delay of 424 days. In facts and
circumstances, especially in view of clause 6 of the GCC the
arbitrator rightly awarded interest for the delayed period.
28. The contention of learned counsel for the respondent that
in the statement of defence reliance upon clause 6.2 of the GCC
against awarding of interest was not pleaded is factually correct
and deserves acceptance. The decision of the Supreme Court
relied upon by learned counsel for the respondent in Union of
India v. Susaka Private Limited and Others (supra) applies to
the facts of the case. The plea not raised before the arbitrator by
SBI cannot be permitted to be raised under Section 34 of the
Act. The relevant paragraphs of the judgement are reproduced
below:
“23. If the appellant was so keen to place reliance
on Clause 13(3) of GCC to defeat the claim of
Respondent 1 relating to the award of interest on
various claims, then it was necessary for the
appellant to have raised such plea specifically, in
their reply, before the Arbitral Tribunal. No such
plea was raised even before the Arbitral Tribunal.
24. Though we find that the appellant raised this
ground, for the first time, in Section 34 proceedings
[see Ground (cc)] before the Single Judge but again
this ground was not pressed at the time of
arguments. It is clear from the perusal of the Single
Judge’s order. Not only that, the appellant again
did not raise this plea before the Division Bench.
25. In the light of the aforementioned factual
scenario emerging from the record of the case, we
cannot grant any indulgence to the appellant
(Union of India) to raise such plea for the first time.
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 21 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
In our view, it is a clear case of waiver or/and
abandonment of a plea at the initial stage itself.
( emphasis supplied )
29. Moreover, clause 6.2 of the GCC cannot be read in
isolation. From a reading of clauses 6.1 and 6.2 it emerges that
no interest shall be paid on the security deposit retained by the
bank. Clause 6.1 stipulates the conditions for release of the
security deposit. Admittedly, the security deposit was refunded
beyond the period prescribed in clause 6.1 and clause 6.2 shall
not apply in such a situation.
30. In view of the above discussion, the award in respect of
claim nos. 1 and 3 as discussed above cannot be sustained and
is liable to be set aside. However, claim nos. 7 and 10 awarded
are upheld.
31. The Supreme Court in Gayatri Balasamy (supra) held
that while the court exercising jurisdiction under Section 34
cannot modify the arbitral award, a severable part of the award
may be set aside. The relevant paragraphs are quoted below:
“32. In the present controversy, the proviso to
Section 34(2)(a)(iv) is particularly relevant. It
states that if the decisions on matters submitted to
arbitration can be separated from those not
submitted, only that part of the arbitral award
which contains decisions on matters non-submitted
may be set aside. The proviso, therefore, permits
courts to sever the non-arbitrable portions of an
award from arbitrable ones. This serves a twofold
purpose. First, it aligns with Section 16 of the 1996
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 22 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
Act, which affirms the principle of kompetenz-
kompetenz , that is, the arbitrators' competence to
determine their own jurisdiction. Secondly, it
enables the Court to sever and preserve the “valid”
part(s) of the award while setting aside the
27
“invalid” ones. Indeed, before us, none of the
parties have argued that the Court is not
empowered to undertake such a segregation.
33. We hold that the power conferred under the
proviso to Section 34(2)(a)(iv) is clarificatory in
nature. The authority to sever the “invalid” portion
of an arbitral award from the “valid” portion, while
remaining within the narrow confines of Section
34, is inherent in the Court's jurisdiction when
setting aside an award.
34. To this extent, the doctrine of omne majus
continet in se minus —the greater power includes
the lesser— applies squarely. The authority to set
aside an arbitral award necessarily encompasses the
power to set it aside in part, rather than in its
entirety. This interpretation is practical and
pragmatic.It would be incongruous to hold that
power to set aside would only mean power to set
aside the award in its entirety and not in part. A
contrary interpretation would not only be
inconsistent with the statutory framework but may
also result in valid determinations being
unnecessarily nullified.”
( emphasis supplied )
32. The claim nos. 1 & 3 are not intricately connected with
claim nos. 7 & 10 and are severable. Consequently, the
impugned award to the extent of awarding claim no.1 and the
amount under claim no.3 towards PVA for the third extension is
Signature Not Verified
O.M.P. (COMM) 69/2024 Page 23 of 24
Signed By:CHANCHAL
Signing Date:15.09.2026
16:58:31
set aside.
33. The petition is allowed to the aforesaid extent.
34. Pending application stands disposed of.