M/S BHANU METAL INDUSTRIES AND ORS vs UNION OF INDIA AND ORS

Court
Calcutta High Court

IN THE HIGH COURT AT CALCUTTA
(Constitutional Writ Jurisdiction)
ORIGINAL SIDE

Present:
The Hon’ble Justice Krishna Rao

W.P.O. No. 252 of 2025
With
GA No. 1 of 2026
With
GA No. 2 of 2026


M/s. Bhanu Metal Industries & Ors.
Vs.
Union of India & Ors.


Mrs. Monica Jaiswal
Ms. Ankita Mitra
Mr. Subrata Mukherjee
....For the petitioners.

Ms. Sanjukta Gupta
….For the respondent no. 3.

Mr. Kamal Kr. Chattopadhyay
Ms. Rimi Chatterjee
….For the respondent no. 2.

2

Hearing Concluded On : 28.09.2026
Judgment Delivered On : 07.10.2026
Judgment Uploaded On : 07.10.2026
Krishna Rao, J.:
1. The petitioners have filed the present writ petition praying for a
Mandamus commanding the respondent nos. 2 and 3, to declare the
auction being MSTC/ ERO/PRASAR BHARTI, ADG(E)(EZ), Kolkata/2/
Behind of Eden Garden Stadium/ 23-24/ 28025 as null and void, and
illegal. The petitioners have also prayed for a direction upon the
respondent no.3 to refund the sum of Rs. 70,92,500/- along with
interest.

2. The respondent no.3 floated a e-Tender being MSTC/ERO/PRASAR
BHARTI, ADG(E)(EZ), Kolkata/2/Behind of Eden Garden Stadium/ 23-
st
24/28025 (401446) on 1 November, 2023, through the respondent
no.2 for the purpose of selling of scrap and e-waste material. Before
participating in the tender, the petitioner no.1 had inspected materials
which were the subject-matter of the e-auction and being satisfied with
the quality of materials participated in the tender process and was
declared as “successful bidder”.

th
3. On 18 December, 2023, the petitioner no. 1 has made total tender
th
amount of Rs. 70,92,750/- and on receipt of the total amount, on 19
December, 2023, the respondent no.2 has issued delivery order to the
nd
petitioner no. 1. On 22 December, 2023, the petitioner no. 1 has

3

submitted delivery Challan and requested the respondent no.3 to allow
the petitioners to lift the auctioned materials and the respondents have
issued delivery order to lift materials. Pursuant to the deliver order, the
petitioners made arrangements to lift materials and went to the godown
of the respondent no. 3, the petitioners found most of the materials
have been damaged due to fire and were missing from the lifting site.
th
The petitioners immediately on 28 December, 2023, informed to the
respondents by mentioning that since some of the materials were
missing and damaged, the petitioners are not able to lift the materials
from the site.

4. On receipt of information from the petitioners, the respondent no.2
advised the respondent no.3 to cancel the tender and to go for fresh
auction with the available materials to avoid complications. The
respondent no.3 has not taken any steps inspite of the information
received from the petitioners and as per advice of the respondent no.2.
th
The petitioner no. 1 by an e-mail dated 8 January, 2024, requested
the respondent no.3 to refund the entire amount deposited by the
petitioners in terms of the bid process for purchase of scrap materials
but the respondent no.3 failed to consider the request of the petitioners
and has not taken any steps.

5. The respondent no.3 assigned the work to the respondent no.2 to carry
th
out the auction process of materials at Cossipore godown. On 5
October, 2023, auction notice was uploaded and inspection of materials
th st
to the prospective bidders was open from 9 October, 2023 to 31

4

st
October, 2023. The bid was open on 1 November, 2023. The petitioner
no.1 firm being the highest bidder, a sale intimation was issued to the
petitioner no.1 to deposit the material value of Rs. 67,55,000/-
st
excluding GST on 1 November, 2023. Final delivery order was issued
th
by the respondent no.2 on 19 December, 2023 by fixing the last date
th
of delivery on 17 January, 2024.

th
6. On 10 November, 2023, a fire incident took place in godown no.2 at
Cossipore. In the fire incident, some auction materials got burnt and
blackened due to soot. The respondent no.3 constituted a Committee of
four officers to take note of the materials damaged. As per the report
submitted by the Committee, the cost of the burnt materials assessed
at Rs. 19,450/-.

7. The respondents requested the petitioners by way of several
correspondences to lift materials but the petitioners avoided to lift
materials. On receipt of the complaint of the petitioners and on
instructions from the Vigilance Section of the Directorate of All India
Radio, again a high-level committee consisting of three (3) Senior
th
Officers and they have submitted report on 9 August, 2024. As per
report, there was no shortage of auction materials in godown no.2
except some burnt/ damaged materials.

8. The petitioner no. 1 being the highest bidder in the auction process
conducted by the respondent no.2 on behalf of the respondent no.3 has
th
deposited the total amount of Rs, 70,92,500/- including GST on 18

5

December, 2023. The respondent no.2 has issued delivery order to the
th
petitioner no. 1 on 19 December, 2023, having last date of delivery on
th
17 January, 2024.

th
9. The respondent no.3 has relied upon two inspection reports dated 16
th
January, 2024 and 9 August, 2024. In one report, it is mentioned that
the cost of the damaged materials due to the fire incident is Rs.
19,450/- and another report says that there is no shortage of auction
materials in godown no.2 except some burnt /damaged materials.

st

10. On 1 November, 2023, bid documents of the petitioners was accepted
and was declared highest bidder and was directed to pay an amount of
th
Rs.67,55,000/- excluding GST. On 18 December, 2023, the petitioner
no. 1 has paid total amount of Rs. 70,92,500/- including GST. The
respondent no.3 had the knowledge that a fire incident was occurred on
th
10 November, 2023 that is prior to deposit of the tender amount but
the respondent no.3 has neither informed to the respondent no.2 or to
th
the petitioners herein and has accepted the total amount on 19
December, 2023.

11. Now, the respondents have taken the ground that the respondents have
constituted two committees of four members and three members each
to ascertain the damaged occurred due to the fire incident. The
committees alleged to have inspected the godown wherein the fire
incident was occurred and submitted report but neither the inspection
was carried out with the notice to the petitioners or in presence of the

6

petitioners. The reports have also not been served upon the petitioners.
The petitioners neither got an opportunity to inspect materials in
presence of the committees constituted by the respondent no.3 nor the
respondent no.3 served the copy of report to the petitioners.

12. The respondent no.3 had the knowledge that they have published
tender notice through the respondent no.2 for sale of the scrap items
available in the godowns of the respondent no.3 and the petitioner no.
1 is the highest bidder and before depositing the tender amount, the
fire incident was occurred but without informing about the fire incident
either to the petitioners or to the respondent no.2, the respondents
have accepted the tender amount which amounts to suppression of
facts on the part of the respondent no.3. The respondent no. 3 being
the authority ought to have informed the fire incident to the respondent
no.2 and the petitioners before accepting the tender amount. Before
accepting the amount inspection ought to have been carried out in
presence of the petitioners to ascertain the damage of the materials due
to the fire incident.

13. When the respondent no.2 came to know about the fire incident, the
respondent no.2 advised the respondent no.3 for cancellation of auction
and suggested for fresh re-tender with the available materials to avoid
complications but the respondent no. 3 has not acted upon the
suggestion of the respondent no.2.

7

14. There is no dispute that the petitioner no. 1 was the highest bidder and
had submitted the tender value along with applicable tax total
th
amounting to Rs. 70,92,500/- on 19 December, 2023. It is also not in
th
dispute that on 10 November, 2023, a fire incident was occurred in
the godown wherein the scrap materials were stored. The only dispute
raised by the respondents that there was no much damage of the scrap
materials as per report of the committees but the petitioners raised
dispute with regard to the said report on the ground that the
petitioners had no knowledge with regard to the constitution of
committees, no inspection was carried out in presence of the petitioners
and no report was served upon the petitioners.

15. This Court finds that no purpose would be served to allow the parties
for joint inspection of the scrap materials which was the subject-matter
of the tender as more than three and half years has been passed from
the fire incident and the said materials are the scrap materials, by this
time the remaining scrap materials might have been further damaged.

16. The respondent No. 3 ought to have informed the petitioners with
regard to the constitution of the committees and the committees ought
to have issued notice to the petitioners for inspection but such
procedure is not followed and even no report was served upon the
petitioners. The reports which the Respondents are relied upon are also
contradictory.

8

17. In the circumstances mentioned above, it would be appropriate to
direct the respondent no.3 to refund the amount of Rs. 70,92,500/-
with simple interest to the petitioners.

18. In view of the above, the respondent no.3 is directed to refund an
amount of Rs. 70,92,500/- (Rupees Seventy Lakhs Ninety Two
Thousand and Five Hundred only) to the petitioners within two months
th
along with interest at the rate of 5% per annum from 19 December,
2023.


19. WPO No. 252 of 2025 is allowed . GA No. 1 of 2026 and GA No. 2 of
2026 are accordingly disposed of .

Parties shall be entitled to act on the basis of a server copy of the
Judgment placed on the official website of the Court.

Urgent Xerox certified photocopies of this judgment, if applied for,
be given to the parties upon compliance of the requisite formalities.

(Krishna Rao, J.)