Delhi Metro Rail Corporation Ltd. vs Hcc Samsung Jv

Court
Delhi High Court

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 11 May 2026
Pronounced on: 17 August 2026

# CNR No. : DLHC010247192025

+ FAO(OS) (COMM) 74/2025, CM APPL. 25351/2025
DELHI METRO RAIL CORPORATION LTD. .....Appellant
Through: Mr. Parag P. Tripathi, Sr. Adv.
along with Mr. Tarun Johri, Mr. Vishwajeet
Tyagi and Ms. Rini Mehra Advs.

versus

HCC SAMSUNG JV .....Respondent
Through: Mr. Dayan Krishnan, Sr. Adv.
with Mr. Kartik Yadav, Mr. Parinay T
Vasandani, Mr. Siddhant Kaushik, Ms.
Shriyanshi Pathak, Ms. Yugandhara Pawar
Jha and Mr. Abhimanyu Arya, Advs.

CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT
% 17.08.2026

C. HARI SHANKAR, J.


A. The lis


1. The only issue in controversy, in this appeal, is whether the
1
petition under Section 34 of the Arbitration & Conciliation Act, 1996 ,

1
“the 1996 Act” hereinafter
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 1 of 25

preferred by the appellant, was filed within the time stipulated in sub-
2
section (3) thereof. The issue is squarely covered by the judgments
of the Supreme Court in Geojit Financial Services Ltd. v. Sandeep
3 4
Gurav and National Highways Authority of India v. T. Younis .

5
2. Section 34(3) of the Arbitration and Conciliation Act, 1996
prohibits the making of an application under Section 34(1) for setting
aside of an award after the expiry of three months from the date when
the applicant receives the arbitral award. However, if a request under
6
Section 33(1) was made by the applicant, the terminus a quo, from
which the period of limitation for filing Section 34(1) application
would be computed, would stand extended to the date when the
Section 33 application is disposed of.

3. Section 33 allows applications only for correcting clerical or
typographical errors in a judgment. The issue arising in the present
case is as to whether, if the Section 33 application is not for correcting
clerical or typographical errors but is in the nature of a wholesale
review of the award on merits, the period of limitation under Section
34(3) would nonetheless stand extended till the date of disposal of the

2
(3) An application for setting aside may not be made after three months have elapsed from the date on
which the party making that application had received the arbitral award or, if a request had been made under
Section 33, from the date on which that request had been disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from
making the application within the said period of three months it may entertain the application within a further
period of thirty days, but not thereafter.
3
2025 SCC OnLine SC 1811
4
2026 SCC OnLine SC 1060
5
“the 1996 Act”, hereinafter
6
33. Correction and interpretation of award; additional award . –
(1) Within thirty days from the receipt of the arbitral award, unless another period of time has
been agreed upon by the parties—
(a) a party, with notice to the other party, may request the arbitral tribunal to
correct any computation errors, any clerical or typographical errors or any other errors of
a similar nature occurring in the award;
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 2 of 25

Section 33 application. In other words, whether a Section 33
application which, in a sense, is not a Section 33 application at all but
an application seeking review of the award, can extend time for the
purposes of Section 34(3) of the 1996 Act.

4. This being the limited issue, any detailed allusion to facts would
be superfluous, and a brief recital would suffice.

B. Facts

5. The dispute between the appellant and the respondent pertains
to a contract agreement dated 28 February 2013, under which certain
civil works were to be executed by the respondent for the appellant.
On 30 July 2018, the respondent submitted a claim for compensation
on account of variations and delay in completion of the work. The
claim was rejected by the appellant on 23 May 2019. The respondent
invoked arbitration. A three-member Arbitral Tribunal was constituted
on 24 September 2020. The majority award, rendered by two members
of the Arbitral Tribunal, was released on 23 February 2024 and the
dissenting award of the third member was released on 28 February
2024.

6. On 22 March 2024, the appellant preferred an application under
Section 33 of the 1996 Act, purportedly for seeking correction of the
arbitral award. We deem it appropriate to reproduce the points on
which “correction” of the award was sought, in extenso , thus, as they

(b) if so agreed by the parties, a party, with notice to the other party, may request
the arbitral tribunal to give an interpretation of a specific point or part of the award.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 3 of 25

manifest how far the “corrections” sought were removed from clerical
or arithmetical errors:

“3. That in respect of Majority Award on claim no. 1 as raised
by the Claimant for payment on account of variation due to an
increase in numbers/length of Cross Passages; the following factors
are worth noting: -

a. The claimant raised a claim of Rs.43,62,64,130/- as
additional costs for construction of additional numbers of
Cross Passages and also interest @ 18% w.e.f. 18.11.2020
till the date of submission of Claims.

b. In the Majority Award, the Hon'ble Arbitral
Tribunal in para 296 has mentioned that it is Respondent's
case that NFPA-130-2003 does not provide for the distance
of first cross-passage. In this context, it is a matter of record
that the Respondent/DMRC had never admitted that
distance of first cross-passage is not mentioned in NFPA-
130-2003. Instead, it was clarified that 2003 and 2010
editions are essentially the same and spacing of first cross-
passage had been made clearer in 2010 edition of NFP A.
Para 33 of SOD is reproduced for kind perusal:

“The Contention of Claimant that BOQ prevails over ODS
in accordance to Clause 1.5 of GCC is also misrepresented.
The said Clause 1.5 of GCC is referred only in case there
are conflicting clauses. Since the Claimant was required to
refer to external notes for calculating the spacing of first
cross passage and was unable to specify the presence of
same in NFPA 2003, the Claimant's contention can, thus, be
summarised that NFPA 2010 has spacing a/first cross
passage as 244m while NFPA 2003 does not specify any
spacing for first cross passage. Even if the said contention
was to be considered valid, clause 1. 5 of GCC can't be
referred as there are no contrasting spacings given in NFPA
2003 and NFPA 2010 for the first cross passage. In the
event of such non-supersession of ODS by BOQ, the
Claimant was bound to carry out construction as per ODS.

The Claimant is thus put to strict proof thereto."

c. From mere perusal of above, it is clear that it was
the claimant who has not specified the existence of 50 3m
spacing of first cross-passage from NFPA-2003. However,
the clause of NFPA clearly specifies cross-passages to be
provided at a distance not further than 244m.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 4 of 25

d. In para 299 of the Majority Award, the Hon'ble
Arbitral Tribunal has opined that the location is marked for
only 14 cross-passages though the numbering is up-to CP-
15. In this regard, it is a matter of record that the Claimant
had mentioned Chainages of CP-2 to CP-15 in its
Attachment-I7 to Appendix-5 of Technical Submission
made by the Claimant himself. However, in his submission
of Tender Programme including Design Submission
Programme, in accordance with Clause C8 and C2.3(b) of
ITT, as a part of its Technical Submission, the claimant
submitted works programme of CP-l also. The Copy of the
same is already on record as Annexure R-47 on page 1078
Vol RD-5.

e. In para 302 of the Majority Award, the Hon'ble
Arbitral Tribunal has mentioned that in the oral arguments,
the Respondent had contended that claim for only 14 cross-
passages was approved by HOD level committee. In this
regard, it is vehemently denied that no such submission was
made by the Respondent. It is pertinent to mention here that
the HOD level committee had approved cost of re-
designing of 14 Cross-Passages which weren't constructed
at the time of instruction to lower the cross-passage floor
and reworking cost of 2 cross-passages already constructed.

f. In para 313 of the Majority Award, the Hon'ble
Arbitral Tribunal has stated that the Claimant has followed
contract provision of assessment of variation which is an
agreed method between the parties with regard to
determination of quantum of varied items.

In this context, it is worth noting that the determination of
quantum of varied item by Claimant in the present claim
had not been carried out as per provisions of the Contract
Agreement. The Claimant had utilized pro-rata basis citing
clause 14(i) of Preamble of the Bill of Quantities which is
applicable only for variation in length of tunnel to be
constructed by a particular method. The contract clearly
specifies two types of tunnels, i.e., Tunnel by Tunnel
Boring Machine (Schedule-A3) and Tunnel by Cut &
Cover Method (Schedule-A4).

Moreover, on the variation in length of tunnels by aforesaid
method, the complete schedule (A3 and A4) is to be varied.
On the other hand, Cross-Passages do not fall under the
category of any of the above type of tunnels.

Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 5 of 25

Accordingly, the actual cost of construction, in case the
variation had been paid and the Respondent/DMRC had
categorially pointed out the same in its various submissions
and during arguments.

g. In para 314 of the Majority Award, the Hon'ble
Arbitral Tribunal has stated that there is no dispute with
regard to length of cross-passages actually constructed to be
of 222.302m. In this context, it is worth mentioning that the
Respondent/DMRC had all through denied the
methodology in its submission and also during the cross-
examination of CW-2 whereby the said Claimant's witness
failed to point out any provision of the Contract Agreement
to substantiate its length based pro-rata calculation for
quantification.

Since, the length was never agreed by the Respondent, the
statement in the Majority Award at para 314 that there is no
dispute in the length of actually constructed cross-passages
is not tenable. It is submitted that the AT always had full
powers to confirm the same from Respondent side whether
the said length 222.302m is agreed or not

h. In para 316 of the Majority Award, the Hon'ble
Arbitral Tribunal has stated that from the pleadings,
evidences and arguments of the parties, the twin tunnels
inter alia trackways in the present contract is mostly
parallel.

It is submitted that the said finding is dehors the pleadings,
evidences and no such arguments were ever made by either
party during the course of Arbitral proceedings.

It may be added here that the General Alignment Drawings
(GADs) of the tunnels were part of the Tender Drawings
and the AutoCAD of the same are also available.

Accordingly, calculation of cross-passage length as per
Technical submission by the Claimant during bid
submission can be easily made from the Tender drawings
itself which is available on record. However, the Hon'ble
Arbitral Tribunal has committed an erroneous calculation
while passing the Award.

i. It is submitted that a detailed calculation sheet
giving the correct calculation is annexed herewith as
Annexure-I.

Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 6 of 25

It may be added here that Annexure-I contains the Cross-
Passage lengths as per actual construction at site. If
required, the Hon'ble Arbitral Tribunal may hold joint
verification of the site alongwith the parties to ascertain the
actual facts and figures.

j. The calculation sheet i.e. Annexure-I, clearly shows
that the total length of Cross-Passage envisaged in the
Technical submission by the Claimant (excluding CP-l
which was disregarded by the Arbitral Tribunal) comes out
to be 174.964m and the constructed length is 194.739m.
Therefore, the increase in length is 19.775m only, i.e. an
increase of 11.302% as compared to 60.39% increase,
ascertained by Hon'ble Arbitral Tribunal.

4. Accordingly, by considering the pro-rata quantification
methodology as adopted by Arbitral Tribunal, the amount against
the said claim of increase in number of cross-passages should be as
follows:

S.No. Description Length Remarks
A Total length of
cross-passage
as per technical
submission
174.964 m
B Total length of
cross-
B passage as per
actual
construction
194.739 m
C Increase in
length
19.775 m C=B-A
D Percentage
Increase in
length
11.302% D= (C x
100)/A
E Cost of cross-
passages as per
Tender BOQ
₹35,24,22,756.00
F Varied Amount
due to increase
in length
₹3,98,30,819.88 F=EXD

5. Thus, in respect of claim no.1, the calculation of the
awarded amount has been done in an erroneous manner and the
same is required to be rectified by the Hon'ble Arbitral Tribunal.

6. That in respect of Majority Award on claim no.2 as raised
by the Claimant for payment on account of additional
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 7 of 25

cost/expenses incurred consequent to the extended stay (from
18.05.2016 to 15.12.2017; the following factors are worth noting: -

a. In calculation of claim 2(i) related to additional cost
on account of ownership including fixed repair and
maintenance of plant and machinery deployed and interest
on Capital investment charges, at para no. 262 of the
Majority Award, the Hon'ble Arbitral Tribunal has
considered cost per month @ 2.31 % of Book value.

It is submitted that while calculating the depreciation cost at
the end of alleged demobilization on 15.12.2017 (i.e. 39
months of the original contract duration + 19 months of
extended stay); the Hon'ble Arbitral Tribunal has
erroneously calculated total depreciation to be 133.98% (=2
.31 % x (39+ 19) months) which is never possible.

It is further submitted that this factor has also been pleaded
in para 59 of the Statement of Defence by the Respondent
wherein it has been stated that after completion of39
months, value of machinery remains equal to 10% of total
amount, which is termed as Scrap Value in terms of the
referred Codal provision by the Claimant himself.

Accordingly, the Hon'ble Arbitral Tribunal has erred in
making miscalculations and the same need to be rectified.

Furthermore, the Hon'ble Arbitral Tribunal has also erred in
the fact that 500kVA diesel generator no. HSJVA512 was
not used after September 2016 and had instead, calculated a
total of 409 days of overstay. The said facts were also
pointed out in Q. No. 37 of cross-examination of Claimant's
witness CW-2 on 11.01.2022. The calculation of the
Awarded amount on this aspect is also erroneous.

b. The Hon'ble Arbitral Tribunal in its Majority Award
has made calculation of claim 2(ii) related to cost on
account of Employees and staff remuneration and benefits
and claim 2(iii) related to cost on account of office and site
establishment expenses (including bank guarantee,
commission charges and unrecovered premium charges of
insurance policies), in para 264 to 269 of Majority Award.

In this context, it is submitted that the Hon'ble Arbitral
Tribunal has erred in calculating the compensation amount
of Overhead charges to the tune of Rs.35,19,84,486.001- to
corroborate the said claim of the Claimant amounting to Rs.
20,74,29,677.001-.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 8 of 25

It is worth mentioning here that the Hon'ble, Arbitral
Tribunal has first considered overhead charges on the total
contract value and has then calculated the overhead charges
for the period of extended stay on pro-rata time basis.
However, the Hon'ble Arbitral Tribunal has erred in making
calculation as the work amounting to Rs.
765,89,78,991.00/- had already been certified up-to May,
2016 and thus overhead on the same was already
considered by the Claimant in its bid submission.

Therefore, considering the formula adopted by the Hon'ble
Arbitral Tribunal for the time being, the correct method
would be to calculate the ceiling limit of overhead charges
during the extended stay on the basis of the amount of work
done in extended stay only.

Thus, the balance amount of work done after May 2016 (i.e.
during the extended period) amounts to Rs.
100,08,21,009.00/-.

Thus, the ceiling limit of overhead charges comes out to be
Rs 8,93,59,018.66/- (=10% of 100,08,21,0091120%, as per
the formula considered by the Hon'ble Arbitral Tribunal to
determine the compensation in para no. 269).

Furthermore, the Hon'ble Arbitral Tribunal. has made
erroneous calculations on the basis of contentions of the
claimant whereby he had even considered retirement
benefits, payment to subcontractors, rent payment to nearby
residents whose buildings were damaged by Claimant etc.
under office expenses head.

In this context, the relevance of Q. No. 49 to 57 of cross
examination of Claimant's witness CW-2 on 11.01.2022 is
worth consideration and had the same been not ignored by
the Hon'ble Arbitral Tribunal, the erroneously calculated
Award would not have been passed. It may be added here
that the said items could have never be considered as
overhead charges and thus the cost should also be deducted
from the awarded amount.

c. The Hon'ble Arbitral Tribunal has placed
calculation of claim 2(iv) related to cost on account of hired
equipment in para 270 to 272 of Majority Award. In this
regard, Q. No. 59 and 60 of cross examination of
Claimant's witness CW-2 on 11.01.2022 and para 71 of
SOD have been ignored by the Hon'ble Arbitral Tribunal
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 9 of 25

while making the Award.

The records amply show that the deployment of machinery
was varied during the said period on account of
requirements of work and was only deployed as and when it
was necessary for work. Had the work been completed in
original contract period, the same would have been required
at that time and cost of which was already included in the
bid of the Claimant.
It may be added here that the Hon'ble Arbitral Tribunal
erred in making calculations qua the said Award by
ignoring the actual facts and moreover, the claimant had
failed to submit any proof qua the idling of the machines
and their prolonged deployment beyond requirement.

d. The Hon'ble Arbitral Tribunal has placed
calculation of claim 2(v) related to cost on account of Fuel
consumed by DG sets for illumination etc. In this context,
the Hon'ble Arbitral Tribunal has erred in making the
calculations while making the Award on this head as by no
stretch of imagination, it can be said that cost of
illumination could have been incurred, if the site wasn't
handed over to the contractor during the original contract
period.

Accordingly, the very basis of granting additional cost for
illumination in period beyond original completion date for
full period of extended stay is based upon erroneous
calculations of the Hon'ble Arbitral Tribunal.

e. The Hon'ble Arbitral Tribunal has made calculation
of claim 2(vi) related to cost on account of hired
scaffolding in para 276 to 278 of its Majority Award. In this
context, it is submitted that the said calculation is erroneous
as the deployment of scaffolding was varied during the said
period on account of requirements of work and was only
deployed as and when it was necessary for work.

Moreover, had the work been completed in original contract
period, the same would have been required at that time and
cost of which was already included in the bid of the
claimant.

The Hon'ble Arbitral Tribunal has miscalculated the
Awarded amount on this head in completely ignoring Q.
No. 59 and 60 of cross-examination of Claimant's witness
CW-2 on 11.01.2022 and para 77 of SOD which amply
show that the deployment of scaffolding was varied during
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 10 of 25

the said period on account of requirements of work and was
only deployed as and when it was necessary for work.

f. With regards to claim 2(viii): cost on account of
extra cost on quarterly audit and compliance during the
extended stay period, it is submitted that the Hon'ble
Arbitral Tribunal has made miscalculations in respect of the
calculation of costs payable to the claimant under this
claim.

In this context, it is worth mentioning here that up to the
stipulated original completion period viz. till 17.05.2016,
the Claimant had already executed works amounting to
Rs.765,89,78,991/-. It is reiterated that only works
amounting to Rs 100,08,21,009/- were executed during the
extended period.

The Hon'ble Arbitral Tribunal has erroneously directed the
respondent to pay Rs 2,40,28,011/- by considering the cost
mentioned in the Schedule Al of the BOQ as the basis and
subsequently calculating the cost for this claim on time
proportionate basis for the extended period.

The calculation of the Hon'ble Arbitral Tribunal is
erroneous as this methodology does not take into account
that the claimant has already been suitably paid for the cost
incurred for quarterly audit and compliance for the works
already executed during the stipulated original completion
period.

As per the methodology adopted by Hon'ble Arbitral
Tribunal, calculations should be made on Rs
100,08,21,009/- i.e. the quantum of works executed during
the extended period. Correspondingly, ceiling limit towards
cost for quarterly audit and compliance comes out to Rs
60,04,926/-(Rs 100,08,21,009 x 6 % (for Sch. AI) x 10 %).

The Hon'ble Arbitral Tribunal erred in making the
calculation qua this claim on the surmise of the claimant
which is arbitrarily based upon BOQ of the contract.
Moreover, the same is devoid of any supporting documents
whatsoever.

It is submitted that the kind attention of Hon'ble Arbitral
Tribunal is drawn towards para 359, wherein, it has been
observed that:- “In support of its claim, the Respondent has
merely filed its self-prepared alleged" loss calculations”.
Thus, Respondent has failed to prove their alleged loss".
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 11 of 25

Thus, on the same analogy and parity, the instant claim
should be rejected since no actual details/evidence of cost
incurred has been provided by the claimant and there is no
basis to ascertain such alleged cost.

g. With regards to claim 2(vii): cost on account of road
maintenance during the extended stay period it is submitted
that the AT has erred in its findings and calculation of costs
payable to the claimant under this claim

In this context, it is submitted that till the stipulated original
completion period viz. till 17.05.2016, the Claimant had
already executed works amounting to Rs. 765,89,78,9911-.
It is reiterated that only works amounting to Rs
100,08,21,009/- were executed during the extended period.
The Hon'ble Arbitral Tribunal has erroneously directed the
respondent to pay ₹ 72,08,4611- by considering the cost
mentioned in the bifurcated Schedule A 1 of the BOQ as
the basis and subsequently calculating the cost for this
claim on time proportionate basis for the extended period.

As per the methodology adopted by Hon'ble Arbitral
Tribunal, calculations should be made on Rs
100,08,21,009/- i.e. the quantum of works executed during
the extended period. Correspondingly, ceiling limit towards
cost for maintenance of roads comes out to Rs 18,01,477/-
(Rs 100,08,21,009 x 6 % (for Sch. AI) x 10 %x 30%
(Maintenance of roads)).

The Hon'ble Arbitral Tribunal erred in making the
calculation qua this claim on the surmise of the claimant
which is arbitrarily based upon BOQ of the contract.
Moreover, the same is devoid of any supporting documents
whatsoever.

It is submitted that the kind attention of Hon'ble Arbitral
Tribunal is drawn towards para 359, wherein, it has been
observed that:" In support of its claim, the Respondent has
merely filed its self-prepared alleged" loss calculations".
Thus, Respondent has failed to prove their alleged loss".
Thus, on the same analogy and parity, the instant claim
should be rejected since no actual details/evidence of cost
incurred has been provided by the claimant and there is no
basis to ascertain such alleged cost.

7. That in respect of Majority Award on claim no.3 as raised
by the Claimant for payment of additional cost consequent to
revision in components of minimum rates of wages as per Govt.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 12 of 25

Notification dated 19.01.2017; the following factors are worth
noting:-

a. The Hon'ble Arbitral Tribunal has made erroneous
calculation of the instant claim on the surmise that the
Respondent had admitted that such variation in labour rates
is payable to the Claimant. It is pertinent to mention here
that the entire record of the Arbitral Proceeding is devoid of
any such admission.

b. It is pertinent here that the Hon'ble Arbitral Tribunal
erred in endorsing that the formula of price variation is
notional in nature. In such circumstances, it would have
been judicious to have called upon the claimant to prove
actual cost incurred on account of such variation in
minimum wages in the instant case. Moreover, the said
proof became more required as the Respondent/DMRC had
raised his objections at different stages.

c. Thus, the onus to prove actual damages suffered due
to such increase in minimum wages got shifted towards the
Claimant and in the instant matter, the Claimant failed to
prove the same.

d. It may be added here that while dealing with the
Counter Claims of the respondent/DMRC, the Hon'ble
Arbitral Tribunal in para 359, of the Majority Award has
observed that: - “In support of its claim, the Respondent has
merely filed its self-prepared alleged "loss calculations”.
Thus, Respondent has failed to prove their alleged loss".

Thus, on the same analogy and parity, the instant claim
should have been rejected since no actual details/evidence
of cost incurred has been provided/proved by the claimant
and there is no basis to ascertain such alleged cost. The
computation of the instant claim is highly erroneous.

e. It may be added here that in para 330 of the
Majority Award, the Hon'ble Arbitral Tribunal has
observed that the Claimant had clarified by referring to the
Manpower status on record that additional claim 3 is on
account of the labours engaged by the Claimant through
Piece Rate Worker Agencies/Subcontractor.

Whereas additional cost claimed under Claim 2(ii) is on
account of the labours engaged by the Claimant on
contract/site roll. The Hon'ble Arbitral Tribunal had
considered the aforementioned clarification in para 330.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 13 of 25

However, it is worth noting that the Labour Coefficient of
0.22 adopted does not exclude any type of labour whether
directly or indirectly involved in the project work.

Accordingly, the computation of the instant claim by the
Hon'ble Arbitral Tribunal on the basis/reliance of notional
formula alone is erroneous and requires to be rectified.

8. It is submitted that the Hon'ble Arbitral Tribunal in its
Majority Award has made, computation errors as pointed
out/detailed in the forgoing paras and the same need to be
rectified.”

7. It is plain that the Section 33 application was not for correcting
any clerical or typographical errors in the award, but sought a
wholesale review of the findings of the learned Arbitral Tribunal. The
perceived “errors” which the application sought to underscore related
to the merits of the disputes between the parties and questioned the
wisdom of the majority award with respect to substantive findings
returned on merits as well as alleged computational discrepancies. We
have, therefore, no manner of doubt, in our minds, that the application
was filed merely to obtain extension of time to file the substantive
challenge under Section 34.

8. By order dated 3 June 2024, the learned Arbitral Tribunal
rejected the aforesaid application submitted by the appellant.

9. The appellant thereafter challenged the arbitral award, by means
of OMP (Comm) 381/2024, before this Court on 29 August 2024.

10. Though the Section 34 petition was filed within the statutory
period of limitation, if reckoned from the date when the application
submitted by the appellant purportedly under Section 33 of the 1996
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 14 of 25

Act was rejected, it was beyond the maximum available period of
limitation as envisaged under Section 34(3) when reckoned from
23/28 February 2024, when the award was rendered.

11. The respondent in its response, submitted that OMP (Comm)
381/2024 was barred by time, and that the delay which had taken
place in filing the petition was beyond the maximum condonable
period of delay envisaged in Section 34(3).

12. The appellant contended, per contra , that the period of
limitation for the purpose of Section 34 (3) would have to be reckoned
not from 23/28 February 2024, when the arbitral award was rendered
but from 3 June 2024, when the Arbitral Tribunal rejected the
application filed by the appellant.

C. The impugned Judgment

13. By judgment dated 20 February 2025, the learned Single Judge
of this Court has dismissed OMP (COMM) 381/2024 filed by the
appellant as barred by time. The learned Single Judge has observed
that the Section 33 application was not a Section 33 application at all,
as it sought a wholesale review of the arbitral award. The application
was, therefore, found to be mischievous and an attempt to avoid the
limitation provided in Section 34(3). Such an application, holds the
learned Single Judge, could never extend limitation. In arriving at his
decision, the learned Single Judge has relied, inter alia , on the
judgment of the Supreme Court in State of Arunachal Pradesh v.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 15 of 25

7
Damani Construction Co. , particularly on the following passages
from the said decision:

“8. Firstly, the letter had been designed not strictly under
Section 33 of the Act because under Section 33 of the Act a party
can seek certain correction in computation of errors, or clerical or
typographical errors or any other errors of a similar nature
occurring in the award with notice to the other party or if agreed
between the parties, a party may request the Arbitral Tribunal to
give an interpretation of a specific point or part of the award. This
application which was moved by the appellant does not come
within any of the criteria falling under Section 33(1) of the Act. It
was designed as if the appellant was seeking review of the award.
Since the Tribunal had no power of review on merit, therefore, the
application moved by the appellant was wholly misconceived.
Secondly, it was prayed whether the payment was to be made
directly to the respondent or through the court or that the
respondent might be asked to furnish bank guarantee from a
nationalised bank as it was an interim award, till final verdict was
awaited. Both these prayers in this case were not within the scope
of Section 33. Neither review was maintainable nor the prayer
which had been made in the application had anything to do with
Section 33 of the Act. The prayer was with regard to the mode of
payment. When this application does not come within the purview
of Section 33 of the Act, the application was totally misconceived
and accordingly the arbitrator by communication dated 10-4-2004
replied to the following effect:

“However, for your benefit I may mention here that as per
the scheme of the Act of 1996, the issues/claims that have
been adjudicated by the interim award dated 12-10-2003
are final and the same issues cannot be gone into once
again at the time of passing the final award.”

9. Therefore, the reply given by the arbitrator does not give
any fresh cause of action to the appellant so as to move an
application under Section 34(3) of the Act. In fact, when the award
dated 12-10-2003 was passed the only option with the appellant
was either to have moved an application under Section 34 within
three months as required under sub-section (3) of Section 34 or
within the extended period of another 30 days. But instead of that a
totally misconceived application was filed and there too the prayer
was for review and with regard to mode of payment. The question
of review was totally misconceived as there is no such provision in
the Act for review of the award by the arbitrator and the

7
(2007) 10 SCC 742
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 16 of 25

clarification sought for as to the mode of payment is not
contemplated under Section 33 of the Act. Therefore, in this
background, the application was totally misconceived and the reply
sent by the arbitrator does not entitle the appellant a fresh cause of
action so as to file an application under Section 34(3) of the Act,
taking it as the starting point of limitation from the date of reply
given by the arbitrator i.e. 10-4-2004.”

14. The learned Single Judge has, therefore, dismissed OMP
(Comm) 381/2024 as barred by time.

15. Aggrieved thereby, the appellant has approached this Court. We
have heard Mr. Parag P. Tripathi, learned Senior Counsel for the
appellant and Mr. Dayan Krishnan, learned Senior Counsel for the
respondent.

16. Written submissions have also been filed.

D. Submissions and analysis thereof

17. The appellant has placed reliance on the judgment of the
Supreme Court in Geojit Financial Services Ltd., Geojit, we may
note, has noticed Damani and distinguished it. Geojit has later been
followed by another two Judge Bench of the Supreme Court in T.
Younis. The relevant paragraphs from Geojit and T. Younis may be
reproduced thus:

From Geojit

“23. A conjoint reading of Section 33 and Section 34 sub-
section (3) of the 1996 Act respectively makes it abundantly clear
that the limitation period for preferring an application for setting
aside, where a request was made by either party under Section 33
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 17 of 25

of the 1996 Act, commences from the date when such request
made under Section 33 was disposed of by the arbitral tribunal.

24. In a case where the arbitral tribunal considers a request
under Section 33 of the 1996 Act, for correction of the award to be
justified, the tribunal shall make the correction. In such scenario
the aggrieved party has to pray for setting aside the corrected
award and not the original award, as the original award stands
merged with the corrected award, and it is the latter which is
binding on all parties. The original award ceases to be of any
significance, either for enforcement or for the purpose of
challenging it in appeal.

25. The natural corollary of the aforesaid is that unless and
until a decision on the request under Section 33 of the 1996 Act is
made, which may or may not have culminated into any correction
or interpretation or rendition of an additional award, there can be
no effective occasion for a party otherwise aggrieved by the said
award to apply for the setting aside of the same under Section 34
of the 1996 Act.

26. Thus, what is material for the purpose of computation of
limitation under Section 34 sub-section (3) of the 1996 Act, where
a request was made in terms of Section 33, is not whether such
request fell within the purview of the said provision or not, but
only the factum that such request was made in the manner
delineated under Section 33 i.e., it was made “ within thirty days
from the receipt of the arbitral award ” and “ with notice to the
other party” .

27. The aforesaid flows from the reason that once the arbitral
award is amended/corrected, it is, for all purposes, in the form of
an award itself under Section 31 of the 1996 Act, distinct from the
award that was originally passed, prior to the making of such
request. It would be this award alone, and not the original award
passed prior to the request under Section 33 of the 1996 Act, which
has to be challenged.

8
28. This Court in Ved Prakash (supra) specifically rejected
the contention that that the expression “disposed” mentioned in
Section 34 sub-section (3) of the 1996 Act would have to be read
in consonance with and in harmony with Section 33. It held that
the Section 34 sub-section (3) when read with Section 33 of the
1996 Act, cannot be possibly understood to mean that only in cases
where some positive step has, in fact, taken place under Section 33
whereby the award is either corrected or modified, that limitation

8
Ved Prakash Mithal & Sons v. Union of India, 2018 SCC OnLine SC 3181
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 18 of 25

would then be computed from the date of disposal of the
application or request under Section 33 of the 1996 Act. The
expression “disposed” used in Section 34 sub-section (3) of the
1996 Act does not merely refer to an award which is ultimately
corrected or modified, it refers to all scenarios where after
consideration of an application under Section 33 of the 1996 Act,
that fulfils the twin conditions of having being made “ within thirty
days from the receipt of the arbitral award ” and “ with notice to the
other party” , was disposed by the arbitral tribunal, including
scenarios where such application is merely dismissed.

29. If at all the intention of the legislature was that the date of
disposal of only those applications under Section 33 of the 1996
Act which culminated into a correction or interpretation of the
award or rendition of an additional award, would be of relevance
for the purpose of computation of limitation under Section 34 of
sub-section (3), then it would not have used the word “ disposed ”
therein, and would have employed the word “ allowed ” instead.

30. The aforesaid may be looked at from one another angle.
Even if we assume for a moment, that where an application under
Section 33 of the 1996 Act, is not entertained for want of
maintainability or for reason of falling beyond the parameters of
the provision, the same, in such scenario, would not amount to
passing of an award in terms of Section(s) 31 read with 33 of the
1996 Act, and thus there would be no distinct award in existence
from what was originally passed by the arbitral tribunal prior to the
making of the request under Section 33, even then, the
interpretation that found favour with the High Court in the
impugned order, to our minds, cannot be regarded to have laid
down the correct proposition of law.

31. We say so because, the fundamental cannons of law of
limitation demands, as a thumb rule, that any period of
commencement and end of limitation should be determinable and
ascertainable in an objective parameter. The law of limitation, at
least insofar as the computation of the prescribed period of
limitation is concerned, cannot be read in a hyper-technical or
subjective manner. The same must in most cases, if not always,
adorn a formulaic understanding that is comprehendible to the
litigants. It however, cannot be tied or made contingent to the
ultimate fate of the application under Section 33 of the 1996 Act.

32. In consonance with this principle, it must be said that the
reason for dismissal of an application filed under Section 33 of the
1996 Act cannot form a yardstick for determining when limitation
would commence. Therefore, as provided in sub-section (3) of
Section 34 of the 1996 Act, in a case where a request or an
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 19 of 25

application is made under Section 33 of the 1996 Act, the
limitation period to later seek the setting aside of the award can
only commence from the date when the application is disposed of,
for whatever reasons.

33. We are conscious of the decision of this Court in State of
Arunachal Pradesh v. Damani Construction Co . , wherein this
Court had purportedly held that where an application filed under
Section 33 of the 1996 Act does not fall within any of the criteria
stipulated therein, in other words, as stipulated in clauses (a) or (b)
of sub-section (1) or sub-section (4), as the case may be, such
application would be of no significance, for the purpose of
computation of limitation under Section 34 sub-section (3) of the
1996 Act. It held that where any application seeks any correction
or modification of an award, which is beyond the scope of what is
contemplated under the said provision, such an application would
not fall within the purview of Section 33 of the Act, 1996 and even
if the arbitral tribunal decides and disposes such an application, the
date of disposal of the same would have no bearing on the
computation of limitation under Section 34 sub-section (3) of the
1996 Act. The relevant observations read as under: -

“8. Firstly, the letter had been designed not strictly
under Section 33 of the Act because under Section 33 of the
Act a party can seek certain correction in computation of
errors, or clerical or typographical errors or any other
errors of a similar nature occurring in the award with
notice to the other party or if agreed between the parties, a
party may request the Arbitral Tribunal to give an
interpretation of a specific point or part of the award. This
application which was moved by the appellant does not
come within any of the criteria falling under Section 33(1)
of the Act. It was designed as if the appellant was seeking
review of the award. Since the Tribunal had no power of
review on merit, therefore, the application moved by the
appellant was wholly misconceived. Secondly, it was
prayed whether the payment was to be made directly to the
respondent or through the court or that the respondent
might be asked to furnish bank guarantee from a
nationalised bank as it was an interim award, till final
verdict was awaited. Both these prayers in this case were
not within the scope of Section 33. Neither review was
maintainable nor the prayer which had been made in the
application had anything to do with Section 33 of the Act.
The prayer was with regard to the mode of payment. When
this application does not come within the purview of
Section 33 of the Act, the application was totally
misconceived and accordingly the arbitrator by
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 20 of 25

communication dated 10-4-2004 replied to the following
effect:

“However, for your benefit I may mention here that
as per the scheme of the Act of 1996, the
issues/claims that have been adjudicated by the
interim award dated 12-10-2003 are final and the
same issues cannot be gone into once again at the
time of passing the final award.”

9. Therefore, the reply given by the arbitrator does not
give any fresh cause of action to the appellant so as to
move an application under Section 34(3) of the Act. In fact,
when the award dated 1210-2003 was passed the only
option with the appellant was either to have moved an
application under Section 34 within three months as
required under sub-section (3) of Section 34 or within the
extended period of another 30 days. But instead of that a
totally misconceived application was filed and there too the
prayer was for review and with regard to mode of payment.
The question of review was totally misconceived as there is
no such provision in the Act for review of the award by the
arbitrator and the clarification sought for as to the mode of
payment is not contemplated under Section 33 of the Act.
Therefore, in this background, the application was totally
misconceived and the reply sent by the arbitrator does not
entitle the appellant a fresh cause of action so as to file an
application under Section 34(3) of the Act, taking it as the
starting point of limitation from the date of reply given by
the arbitrator i.e. 10-4-2004.”
(Emphasis supplied)

34. However, we are of the considered opinion that the decision
of Damani Construction (supra) is not applicable and is
distinguishable. A close reading of the aforesaid decision would
reveal that in the said case, the appellant therein had never formally
moved an application under Section 33 of the 1996 Act, but rather
had only addressed a letter to the arbitrator, requesting it inter-alia ,
to review the award passed by it and seeking ancillary
clarifications which did not concern the contents of the award so
passed. It is in this background that this Court in Damani
Construction (supra) , in the absence of any formal application or
any prayer contemplated under Section 33 of the 1996 Act, refused
to treat the letter addressed by the appellant therein as an
application thereunder. It however, does not mean that where a
party moves an application under Section 33 of the 1996 Act
within the limitation period prescribed therein and with notice to
the other party, that the same would nevertheless not be treated as
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 21 of 25

an application under the said provision, merely because what is
sought under the guise of ‘correction’ or ‘modification’ is outside
the ambit of the Section 33. It would still continue to be an
application under Section 33 of the 1996 Act for the limited extent
of computation of the period of limitation under Section 34, as long
as it fulfils the two conditions prescribed under Section 33, as
already discussed by us.”

From T. Younis

“9. The learned senior counsel appearing for the Appellant
submitted that both the parties had filed applications under Section
33 of the Act, therefore, the Appellant could not have filed the
application under Section 34 of the Act, before disposal of the said
applications. It is contended that High Court erred in refusing to
exclude the period spent in disposal of the application under
Section 33 while computing the limitation under Section 34(3) of
the Act and erred in placing reliance on the decision in State of
Arunachal Pradesh v. Damani Construction Co. It is urged that
the application under Section 33(1)(a) merely sought correction of
clerical and typographical errors in the Arbitral Award and did not
amount to review of the Award. It is submitted that the issue
involved in the appeal is no longer res integra and has been dealt
with by this Court in Geojit Financial Services Ltd. v. Sandeep
Gurav.

10. Per contra , learned senior counsel for Respondent No. 1
submitted that the application filed by the Appellant under Section
33(1)(a) of the Act, in substance was an attempt to review the
Arbitral Award and not merely an application for correction of
clerical or typographical errors. It was contended that Appellant
had sought modification of substantive findings in the Award
which fell outside the limited scope of Section 33(1)(a). It was
urged that only an application which is maintainable under Section
33 could extend the limitation under Section 34(3) of the Act.
Relying on State of Arunachal Pradesh (supra) , it was contended
that since the Appellant's application under Section 33 of the Act
was itself not maintainable, it could not claim exclusion of time
spent in disposal of the said application for the purposes of
limitation. It was argued that Arbitral Tribunal had become functus
officio after passing of the Award and therefore the merits of the
dispute could not be reopened in the guise of an application under
Section 33 of the Act. It was further argued that Appellant's
applications under Section 34 were barred by limitation as the
same were filed beyond the statutory outer limit prescribed under
Section 34(3) of the Act, even assuming that the Appellant is
entitled to exclusion of time for the period spent in disposal of
application under Section 33 of the Act.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 22 of 25

11. Having heard the rival contentions and perusing the
material on record, the issue that arises is whether the limitation
under Section 34(3) would commence from the date of the original
award or from the date on which the application under Section 33
came to be disposed of.

*

16. The reliance placed by the Respondent on State of
Arunachal Pradesh (supra) is misplaced. That case arose in an
entirely different factual context where there was no formal
application under Section 33 invoking the jurisdiction of the
Arbitral Tribunal. The party had merely addressed a letter, in
substance seeking review of the award and certain ancillary
clarifications beyond the contours of section 33. It was in that
context, that this Court held such communication could not entitle
a fresh starting point of limitation under Section 34(3). The facts of
the present case stand on an entirely different footing. Here, formal
applications under Section 33 were admittedly filed by both parties
within the statutory period, and the same were entertained and
disposed of by the Arbitral Tribunal by a common order dated
04.07.2022.”

18. Thus, Geojit distinguished Damani by observing that, in
Damani, there was no application filed under Section 33 at all and
that a mere letter had been submitted to the arbitrator. Where an
application was filed, then, irrespective of the merits of the
application, and even if the application was a mere sham and therefore
not maintainable at all, the decisions in Geojit and T. Younis make it
clear that the period of limitation for the purposes of the Section 34(3)
would commence only from the date when the application is disposed
of. These decisions make it clear that the interpretation which the
learned Single Judge has adopted in the present case would require re-
writing of Section 34(3) to provide for extending of the period of
limitation from the date of disposal of the Section 33 application only
where the Section 33 application is actually maintainable. This,
according to the Supreme Court, is impermissible.
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 23 of 25

19. The Supreme Court has, however, in T. Younis , clearly held
that in a case where the Section 33 application is found to be a sham,
the Court can and must award punitive costs. The Section 34 petition
cannot, however, be dismissed as time barred, ignoring the time spent
in disposing of the Section 33 application, howsoever frivolous it
might have been.

20. We are bound by the declaration of the law in Geojit and T.
Younis . Accordingly, the impugned judgment of the learned Single
Judge, which follows Damani cannot sustain. It has, therefore,
necessarily to be quashed and set aside.

21. At the same time, it is clear that in fact the application under
Section 33 was completely lacking in bona fides . By no stretch of
imagination can it be said that the application was mistakenly filed,
under a bona fide assumption that it fell within the parameters of
Section 33. The application does not seek correction of any clerical or
typographical error in the arbitral award. Instead, it seeks to point out
various perceived errors in the award of understanding the contractual
provisions, computing the amounts involved and such like. In fact, it
would not be too far from the truth to hold that the application is even
beyond the normally understood parameters of review jurisdiction and
essentially seeks a re-adjudication of the entire dispute.

22. It is not possible for us to believe that an organization such as
the appellant did not know the fundamentals of Section 33 and what is
permitted thereunder. This, therefore, is a classic case of misuse of
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 24 of 25

Section 33, perhaps with a view to obtain breathing space to launch
the challenge to the substantive award.

23. We are of the opinion that this is an eminently fit case for
awarding punitive costs as suggested by the Supreme Court in T.
Younis . At the same time, we bear in mind the fact that the appellant
is a public sector undertaking and that, therefore, the ultimate impact
of the costs we may award would be on the public exchequer.

E. Conclusion

24. Accordingly, while we are constrained to set aside the
impugned judgment of the learned Single Judge in view of the
declaration of the law in Geojit and T. Younis and hold that the
Section 34 petition of the appellant could not have been rejected as
barred by time, we nonetheless burden the appellant with costs of ₹
5,00,000/- (Rupees five lakhs only) to be paid by the appellant to the
respondent within a period of twelve weeks from the date of
pronouncement of this judgment.

25. The appeal stands disposed of in the aforesaid terms.

26. Let the judgment be uploaded on the website of this Court
forthwith.

C. HARI SHANKAR, J.

OM PRAKASH SHUKLA, J.
AUGUST 17, 2026 / yg/aky
Signature Not Verified
Digitally Signed By:AJIT
KUMAR
Signing Date:17.08.2026
14:59:25
FAO(OS) (COMM) 74/2025 Page 25 of 25