M/S SHREE CEMENT LIMITED vs KARNATAKA ELECTRICITY REGULATORY COMMISSION Ors
- Court
- Appellate Tribunal For Electricity
- Case type
- APPEAL
- Decided on
- 16-03-2026
<div> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> <b> IN THE APPELLATE TRIBUNAL FOR ELECTRICITY </b><br /> <b>(Appellate Jurisdiction) </b><br /> <b> </b><br /> <b>APPEAL No. 58 OF 2020 </b><br /> <b> </b><br /> <b>th </b><br /> <b>Dated: </b> <b>16</b> <b>March, 2026 </b><br /> <b>Present: Hon`ble Ms. Seema Gupta, Officiating Chairperson </b><br /> <b> </b> <b>Hon`ble Mr. Virender Bhat, Judicial Member </b><br /> <b> </b><br /> <b>IN THE MATTER OF: </b><br /> M/S SHREE CEMENT LIMITED, <br /> ( <i>Through it’s authorized Signatory</i> ) <br /> SB 187, Bapu Nagar, <br /> Opp. Rajasthan University, JLN Marg, <br /> Jaipur – 302015 … Appellant(s) <br /> <br /> <b><i>VERSUS </i></b><br /> <br /> 1. KARNATAKA ELECTRICITY REGULATORY COMMISSION <i> </i><br /> <i>Through its Secretary</i> , <br /> No.16, C-1, Miller Tank Bed Area <br /> Vasanth Nagar, <br /> Bengaluru – 560052. <br /> <br /> 2. POWER COMPANY OF KARNATAKA LIMITED (PCKL), <br /> <i>Through Its Director </i><br /> Room No.501, 5th Floor, <br /> KPTCL Building, <br /> Bengaluru-560 009 <br /> <br /> 3. BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED, <br /> <i>Through Its General Manager (EL), </i><br /> Power Procurement, <br /> BESCOM Corporate Office, <br /> K.R. Circle, Bengaluru-560 001. <br /> <br /> 4. MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED, <br /> <i>Through Its Superintending Engineer (Commercial), </i><br /> Page <b>1</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> 4th Floor, MESCOM Bhavan, Bejai, <br /> Kavoor Cross Road, <br /> Mangaluru-570 004. <br /> <br /> 5. CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LIMITED, <br /> <i>Through Its Chief Financial Officer, </i><br /> # 39, Vijayanagar, 2nd Stage, <br /> Mysuru-570 004. <br /> <br /> 6. HUBLI ELECTRICITY SUPPLY COMPANY LIMITED, <br /> <i>Through Its General Manager (Tech), </i><br /> Corporate Office, Navanagar P.B. Road, <br /> Hubballi. 580025 <br /> <br /> 7. GULBARGA ELECTRICITY SUPPLY COMPANY LIMITED, <br /> <i>Through Its Chief Engineer (Electy), </i><br /> Corporate Planning, Corporate Office, <br /> Railway Station Main Road, <br /> Kalaburagi-585 102. …. Respondents <br /> <br /> Counsel on record for the Appellant(s) : Mr. Kumar Mihir <br /> for App. 1 <br /> <br /> Counsel on record for the Respondent(s) : Mr. Shahbaaz Husain <br /> Mr. Fahad Khan <br /> for Res. 2, 3, 5, 6 & 7 <br /> <br /> <b>JUDGEMENT </b><br /> <b> </b><br /> <b>PER HON’BLE MRS. SEEMA GUPTA, OFFICIATING CHAIRPERSON </b><br /> <i> </i><br /> 1. The present Appeal No. 58 of 2020 has been filed by M/s Shree Cement <br /> Limited <b>(hereinafter referred to as “Appellant”) </b> under Section 111 of the <br /> Electricity Act, 2003 challenging the order dated 26.11.2019 (“ <b>Impugned Order</b> ”) <br /> passed by the Karnataka Electricity Regulatory Commission in O.P. No.22 of <br /> Page <b>2</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> 2019 whereby the State Commission had dismissed the Petition filed by the <br /> Appellant herein while upholding the deduction of liquidated damages by the <br /> Respondent No.2. <br /> <b><i> </i></b><br /> 2. The Appellant, M/s Shree Cement Limited, is a company registered under <br /> the Companies Act 1956, engaged in the business of manufacturers of cement <br /> and trading of electricity. <br /> <br /> 3. The Respondent No.1, i.e. Karnataka Electricity Regulatory Commission <br /> (hereinafter referred to as <b>“KERC/State Commission”</b> ), is the Electricity <br /> Regulatory Commission for the State of Karnataka exercising jurisdiction and <br /> discharging functions in terms of the Electricity Act, 2003. <br /> <br /> 4. The Respondent No.2 i.e. Power Company of Karnataka Limited <br /> (hereinafter referred to known as <b>“PCKL”</b> ), is the holding company of the <br /> Respondent Nos.3 to 7. Respondent Nos. 3 to 7 are the distribution licensees <br /> responsible for supplying electricity in the State of Karnataka. <i> </i><br /> <b><i> </i></b><br /> <b><i>Factual matrix of the Case: </i></b> <i> </i><br /> <br /> 5. On 29.08.2017, the Respondent No. 2 floated a tender for procurement of <br /> 500 MW Round-The-Clock (RTC) power for the distribution licensees for the <br /> period from 20.09.2017 to 31.05.2018 in which Appellant was declared the <br /> successful bidder (L1), and was allocated 100 MW of power at a tariff of Rs. <br /> 4.08/kWh at the KPTCL Periphery, and a letter of Award (LOA) dated 11.11.2017 <br /> was issued in favour of the Appellant. <i> </i><br /> <i> </i><br /> 6. On 16.11.2017, Appellant filed open access applications with SRLDC for <br /> supply of power to the Respondents from 16.11.2017 to 30.11.2017, and SRLDC <br /> Page <b>3</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> granted One Day Ahead open access approval for 16.11.2017 and FCFS <br /> approval for the period from 17.11.2017 to 30.11.2017. Appellant commenced <br /> supply of 100 MW RTC power to Respondent No. 2 with effect from 16.11.2017 <br /> from its generating unit situated in the State of Rajasthan. <i> </i><br /> <i> </i><br /> 7. Meanwhile, the Supreme Court of India, by order dated 17.11.2017, banned <br /> the use of Pet-coke in the National Capital Region and in the States of Uttar <br /> Pradesh, Rajasthan and Haryana with immediate effect. As the Appellant was <br /> using Pet-coke as the primary fuel for generation of electricity at its Rajasthan-<br /> based generating unit—the source from which power was being supplied to <br /> Respondents Nos. 3 to 7, the Appellant discontinued supply from 23:30 hours on <br /> 18.11.2017. Appellant, vide its letter dated 17.11.2017, intimated the said <br /> development to Respondent, and also stated that it would make its best efforts <br /> to arrange supply of power from an alternate source, to be confirmed in due <br /> course, which was said to be communicated by letter dated 20.11.2017, email <br /> dated 21.11.2017 and 22.11.2017. <br /> <br /> 8. On 21.11.2017 in compliance with the Letter of Award dated 11.11.2017, <br /> the Appellant furnished the requisite Contract Performance Guarantee at the rate <br /> of Rs. 2 lakh/MW/month in favour of Respondent Nos. 3 to 7. <br /> <br /> 9. On 24.11.2017, the Appellant executed a Power Purchase Agreement with <br /> Respondent Nos. 3 to 7 for sale of energy in terms of the agreed conditions. <br /> <br /> 10. The Appellant is aggrieved that notwithstanding the occurrence of a Force <br /> Majeure event and the Appellant’s offer to supply power from an alternate source, <br /> Respondent No. 2 raised a claim for compensation under Article 6.2 of the PPA <br /> amounting to Rs. 60,50,077/-, which was subsequently revised to Rs. 29,72,647/- <br /> Page <b>4</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> alleging short supply of power for the month of November 2017, vide bill dated <br /> 29.12.2017. Aggrieved thereby, the Appellant filed Petition being O.P. No. 22 of <br /> 2019 on 28.01.2019 before the State Commission, seeking directions to <br /> Respondent withdraw the advice of PKCL for recovery of liquidated damages of <br /> Rs. 29,72,647/- for November 2017, and to refund the amount withheld towards <br /> compensation along with interest. <br /> <br /> 11. The State Commission, passed the impugned order dated 26.11.2019, <br /> dismissing the Petition filed by the Appellant and held that though offer of supply <br /> from alternate sources between 24.11.2017 – 30.11.2017 can be considered as <br /> valid offer but for the days 22.11.2017 & 23.11.2017 cannot be construed as valid <br /> offer and Appellant is liable to pay Liquidated damages. In addition, The Appellant <br /> is also held liable for the payment of open access charges of about Rs 12,81,0101 <br /> to the extent power is not availed by the respondents. Aggrieved thereby, the <br /> Appellant has preferred the present Appeal on 09.01.2020. <br /> <b> </b><br /> <b>DISCUSSION AND ANALYSIS</b> <br /> <br /> 12. We have heard Mr. Kumar Mihir, learned counsel on behalf of the Appellant <br /> and Mr V.M. Kanan, learned counsel for Respondents Nos 2,3,5,6 and 7 and <br /> perused written submission filed by the parties, the Impugned Order, and other <br /> related documents on record. In the Impugned Order, non-supply of power has <br /> been considered from the period 19.11.2017 to 23.11.2017 and deemed supply <br /> of power from 24.11.2017 to 30.11.2017, for working out the Liquidated damages. <br /> There is no issue with regard to non-supply of power during the period from <br /> 19.11.2017 to 21.11.2017, and the primary issue pertains to whether Appellant is <br /> liable for payment of liquidated damages for non-supply of power from alternate <br /> source for a period from 22.11.2017 to 23.11.2017, and liability affixed on <br /> Appellant for Open Access Charges. <br /> <br /> Page <b>5</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> 13. It is not in dispute that in compliance to the order passed by the Supreme <br /> Court on 17.11.2017, prohibiting the use of Pet Coke in the NCR region and in <br /> the States of Uttar Pradesh, Rajasthan and Haryana, the Appellant did not supply <br /> power to the Respondents from its plant located in Rajasthan from 23.30 hrs on <br /> 18.11.2017. <br /> <br /> 14. It is submitted by the Appellant that vide its letter dated 17.11.2017, it <br /> informed the PCKL, that in view of the order passed by the Supreme Court, it <br /> shall not be in a position to supply power, citing force majeure condition and also <br /> informed that they are trying to arrange supply from alternate sources, which shall <br /> be informed in due course of time. Subsequently, vide its letter dated 20.11.2017 <br /> addressed to the Additional Director (Projects), KPTCL, the Appellant intimated <br /> the alternate source of supply of power from Sembcorp Gayatri Power Limited, <br /> which is connected to inter-State network in southern Region and sought <br /> permission to supply power from this project from 24.11.2017 to 30.11.2017 <br /> invoking clause 5.4 (Supply from alternate source) of the power purchase tender. <br /> Vide another e-mail dated 21.11.2017, the Appellant informed PCKL that it was <br /> in a position to arrange supply from the alternate source even for 22.11.2017 and <br /> 23.11.2017 and sought the consent of the Respondent in this regard. It has been <br /> contended on behalf of the Appellant that non-supply of power in the present case <br /> constitutes a Force Majeure event within the meaning of Clause 7.1 of the Power <br /> Purchase Agreement, thereby exempting the Appellant from the performance of <br /> its obligations under the Agreement to the extent such performance was affected <br /> by the said event. <br /> <br /> 15. Per contra, it has been contended on behalf of Respondents that, on one <br /> hand, the Appellant claims that non supply of power was due to ban on the use <br /> of pet coke in State of Rajasthan, where its power plant is located, that such <br /> circumstance constitutes a Force Majeure event but simultaneously, seeks to <br /> Page <b>6</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> supply power from an alternative source under article 5.1.4 of the PPA, wherein <br /> it is expressly provided that if the Seller is unable to supply power up to the <br /> Contracted Capacity from the Delivery Point, except due to a Force Majeure <br /> event, it shall supply power from an alternative generation source with the <br /> consent of the Procurer(s); by invoking Article 5.1.4, the Appellant has itself <br /> acknowledged that the situation does not fall within the scope of the Force <br /> Majeure clause and therefore the Appellant’s plea of <i>Force Majeure</i> is untenable, <br /> unsubstantiated, and evidently raised only to evade liability towards Liquidated <br /> Damages under the terms of the Agreement. <br /> In this context, it would be apposite to reproduce the relevant clauses of PPA: <br /> <b><i>“7.1 Force Majeure : </i></b> <i>Force Majeure Events shall mean the occurrence </i><br /> <i>of any of the following events- </i><br /> <i>(i) </i> <i>Any restriction imposed by RLDC/SLDC in scheduling of power due </i><br /> <i>to breakdown of Transmission/Grid constraint shall be treated as </i><br /> <i>Force Majeure without any liability on either side. </i><br /> <i>(ii) </i> <i>Any of the events or circumstances, or combination of events and </i><br /> <i>circumstances such as act of God, exceptionally adverse weather </i><br /> <i>conditions. lightning, flood, cyclone, earthquake, volcanic eruption, </i><br /> <i>fire or landslide or acts of terrorism causing disruption of the system. </i><br /> <i>(iii) </i> <i>The contracted power will be treated as deemed reduced for the </i><br /> <i>period of transmission constraint. The non/part availability of </i><br /> <i>transmission corridor should be certified by the concerned </i><br /> <i>RLDC/SLDC. </i><br /> <i>(iv) </i> <i>The procurer would return the CPG in case of non-availability of </i><br /> <i>transmission corridor during the contract period. </i><br /> <i>The Affected Party shall give intimation to the other Party of any event of </i><br /> <i>Force, Majeure immediately but not later than 24 Hours. </i><br /> <b><i>7.2 Duty to Mitigate </i></b><br /> <i>To the extent not prevented by a Force Majeure event, the Affected Party </i><br /> <i>shall continue to perform its obligations pursuant to this Agreement. The </i><br /> <i>Affected Party shall use its reasonable efforts to mitigate the effect of any </i><br /> <i>event of Force Majeure as soon as practicable. </i><br /> <br /> Page <b>7</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> 16. In terms of clause 7.1 of the PPA, transmission constraints, restrictions <br /> imposed by RLDC as well as events including acts of God, terrorism, and other <br /> occurrences affecting the supply has been identified as <i>force majeure</i> conditions, <br /> whereas impact of judicial order has not been specifically identified as a <i>force </i><br /> <i>majeure</i> event, however as non- supply of power from the identified source of <br /> generation in view of the order passed by the Supreme Court can be considered <br /> beyond the control of Appellant and even if it construed to be a <i>Force Majeure</i> <br /> event, the effect of such an event, under the provision of <i>Force Majeure </i><br /> provisions, would be that the parties are only absolved of their responsibility to <br /> fulfill the obligation under the contract and in some extreme situations, the <br /> procurer can even return the CPG. Therefore, under the event of <i>force majeure</i> , <br /> the Appellant may not be required to supply the power. The Clause 7.2, mandates <br /> that parties shall continue to perform its obligation to the extent it is not prevented <br /> by <i>Force Majeure</i> and take action to mitigate the effect of <i>Force majeure</i> as soon <br /> as practicable. Thus, in case of some part of generation, which is not affected by <br /> <i>Force Majeure</i> , the Appellant shall continue to supply power and take measures <br /> to mitigate the impact of Force Majeure for the balance and in case of complete <br /> breakdown, shall take measures to mitigate the impact. In the present case, the <br /> Appellant did not restrict its claim/ provisions available under Force Majeure, but <br /> invoking the Clause 5.1.4 of PPA, proposed to supply power from the alternate <br /> source. Clause 5.1.4 of the PPA, is reproduced hereunder: <br /> <b><i>“5.1.4 Alternate source of power supply </i></b><br /> <i>If the Seller is unable to provide supply of power to the Procurer(s) up to </i><br /> <i>the Contracted Capacity from the Delivery Point except due to a Force </i><br /> <i>Majeure Event, the Seller shall supply power up to the Contracted Capacity </i><br /> <i>from an alternative generation source to meet its obligations under this </i><br /> <i>Agreement with the consent of Procurer(s). Such power shall be supplied </i><br /> <i>to the Procurer(s) at the same Tariff as per the terms of this Agreement. If </i><br /> <i>the power is being supplied through alternate source, additional charges </i><br /> <i>and losses if any, due to cancellation of existing corridor and booking of </i><br /> <i>new corridor etc., shall be to the account of Seller.”</i> <i> </i><br /> Page <b>8</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> 17. From the reading of <b> </b> Clause 5.1.4 and Clause 7, it is inferred that these <br /> clauses operate in distinct spheres. Clause 5.1.4 is a contractual mechanism <br /> designed to ensure continuity of supply in circumstances where performance is <br /> impeded for reasons other than Force Majeure. Clause 7, conversely, is a <br /> protective provision excusing performance when extraordinary, unforeseeable <br /> events beyond the control of the parties occur. By their very wording, the two <br /> clauses are mutually exclusive: clause 5.1.4 presupposes the absence of Force <br /> Majeure, whereas Clause 7 is attracted only upon the occurrence of such an <br /> event. Under established jurisprudence, when a party elects to invoke a <br /> contractual remedy that is inconsistent with another available remedy, it is <br /> deemed to have waived the latter. Here, the Appellant’s reliance on Clause 5.1.4 <br /> of the PPA and seeking to arrange supply of power from an alternate source, has <br /> effectively elected to proceed on the footing that the prevailing circumstances did <br /> not constitute Force Majeure. Having made such an election, the Appellant <br /> cannot subsequently resile and claim <i>Force Majeure</i> under Clause 7. In our view <br /> by invoking Clause 5.1.4, the Appellant has effectively waived its right to plead <br /> <i>Force Majeure</i> . Waiver may be either express or implied, and in this case, the <br /> conduct of invoking a clause that excludes <i>Force Majeure</i> is an implied waiver. <br /> Clause 5.1.4 ensures that supply obligations are met through alternate <br /> arrangements in ordinary disruptions, thereby protecting the commercial interests <br /> of the counterparty. Clause 7, on the other hand, suspends obligations altogether <br /> in extraordinary circumstances. Allowing a party to invoke both simultaneously <br /> would defeat the commercial balance of the contract, permitting unjust <br /> enrichment or avoidance of obligations without proper justification. Accordingly, <br /> we find no infirmity in the Impugned Order insofar as it denies the relief claimed <br /> by the Appellant under the Force Majeure provisions, and the same is hereby <br /> upheld in this regard. <br /> Page <b>9</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> 18. Learned Counsel for the Appellant has contended that Respondent No. 2, <br /> in its Reply, has expressly admitted that vide email dated 21.11.2017 the <br /> Appellant had sought approval to supply power from an alternate source for the <br /> period from 22.11.2017 and 23.11.2017, and has further acknowledged that no <br /> liquidated damages were levied for the period from 22.11.2017 to 30.11.2017, <br /> which has not been considered by State Commission; therefore, if the aforesaid <br /> period from 22.11.2017 to 30.11.2017 is excluded from consideration, the <br /> monthly availability works out to 79.40%, with a deviation of only 20.60%, which <br /> is below the threshold limit of 25% stipulated under Clause 6.2.5 of the PPA, and <br /> consequently no liability could have been fastened upon the Appellant. It is <br /> further submitted that State Commission failed to appreciate that the Appellant, <br /> vide email dated 20.11.2017, had sought consent of the respondents for supply <br /> of power from an alternate source to Respondent No. 2, to which no response <br /> was ever furnished by the Respondents and due to unavailability of the consent, <br /> the Open Access application could not be punched for 22.11.2017 & 23.11.2017. <br /> In such circumstances, any contention that the Appellant’s offer was invalid on <br /> the ground that open access approval had not been obtained for the said two <br /> days is untenable and liable to be rejected. It has also been contended on behalf <br /> of the Appellant that even for the subsequent period from 24.11.2017 to <br /> 30.11.2017, Respondent No. 2 did not grant its consent and consequently the <br /> Open Access application could not be punched; nevertheless, the State <br /> Commission has accepted deemed supply for the period from 24.11.2017 to <br /> 30.11.2017, and therefore there is no justification to deny similar treatment for the <br /> period from 22.11.2017 and 23.11.2017. <br /> 19. Per contra, it has been contended on behalf of Respondent No. 2 that <br /> under Article 5.1.4 of the PPA, Appellant can supply power from an alternative <br /> generation source, subject to the consent of the Procurer, i.e., the Distribution <br /> Page <b>10</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> Companies (DISCOMs), which was sought by appellant, vide its letter dated <br /> 20.11.2017, from Sembcorp Gayathri Power Limited (SGPL), for the period <br /> 24.11.2017 to 30.11.2017, and furnished a copy of its Open Access application <br /> made to the Southern Regional Load Despatch Centre (SRLDC), thereby <br /> demonstrating its readiness and ability to supply power for the said period. This <br /> constituted a valid and substantiated offer and, consequently, the period from <br /> 24.11.2017 to 30.11.2017 can be treated as deemed supply. <br /> 20. We take note that in its letter dated 20.11.2017, addressed to Additional <br /> Director, KPTCL, the alternate source of power has been indicated and Appellant <br /> has sought the consent to supply power from 24.11.2017 to 30.11.2017, however <br /> in email dated 21.11.2017, whereby the Appellant sought to supply power on <br /> 22.11.2017 & 23.11.2017 also, no alternate source has been identified as well as <br /> no open access application was processed to supply power on these dates. It is <br /> a fact that under Article 5.1.4, invoked by the Appellant, consent of procurer is a <br /> re-requisite, and responsibility of booking of new transmission corridor is on the <br /> Seller i.e. on the Appellant. The Open Access application attached by the <br /> Appellant, is from 24.11.2017 to 30.11.2017, which establishes Bona fide of the <br /> Appellant to arrange supply power from alternate source during this period. <br /> Without even identifying the source for Alternate Power for 22.11.2017 the <br /> communication sent by the Appellant cannot be construed as a valid or <br /> substantiated offer for supply of power for the said dates. We take note that, <br /> Respondents before giving consent for supply of power from alternate source in <br /> response to the offer made on 20.11.2017, it had asked appellant to submit <br /> performance guarantee and sign the PPA. It is interesting to note that Power <br /> Purchase Agreement, has been signed on 24.11.2017, considering scheduled <br /> delivery date as 16.11.2017, however, the Appellant has agreed to the condition <br /> for prior consent of procurer for supplying power from alternate source, inspite of <br /> Page <b>11</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> being aware that the consent for supplying power from alternate source on <br /> 22.11.2017 & 23.11.2017 is not available with them from the Respondents. <br /> 21. With regard to the contention that Respondents, in their reply, has admitted <br /> for non-levy of LD for the period from 22.11.2017 to 30.11.2017, we take note <br /> that Respondents, in their reply to the petition filed by the Appellant, at para (k) & <br /> (m) has submitted that Liquidated damages are payable only for the period <br /> 19.11.2017 to 21.11.2017, and that no LD is being levied from 22.11.2017 <br /> onwards, as the Appellant has offered supply from alternate source. In para (n) <br /> & (o) it has contested the contention of Appellant with regard to supply of <br /> contracted energy from 22.11.2017 to 30.11.2017. The respondents have <br /> excluded the entire period from 22.11.2017 to 30.11.2017, from the availability <br /> calculation, whereas Appellant in its calculation has considered deemed <br /> availability of generation for the entire period from 22.11.2017 to 30.11.2017, <br /> which is not in line with submissions of Respondents in the Reply. In these <br /> circumstances, the reliance placed by the Appellant on the statements made in <br /> the Reply of the Respondents is misplaced and of no assistance to the case of <br /> the Appellant. <br /> 22. The State Commission, in the Impugned Order, considering grant of Open <br /> Access application submitted by the Appellant before SRLDC for supply of 100 <br /> MW power from alternate source, which established valid offer of supply of power <br /> from alternate source, has allowed deemed availability for the period 24.11.2017 <br /> to 30.11.2017, the Appellant has, however, contended that the same principle <br /> ought to have been applied for two days 22.11.2017 & 23.11.2017 as for the <br /> entire period from 22.11.2017 to 30.11.2017, explicit consent of Respondents <br /> was not available. In view of the fact, that Respondents have not objected to the <br /> offer of supply of power from alternate source, from 24.11.2017 to 30.11.2017, <br /> conveyed by Appellant vide letter dated 20.11.2017, as valid offer, it can be <br /> Page <b>12</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> construed as their acceptance and state Commission has considered it as a valid <br /> offer of supply. For two days, i.e 22.11.2017 & 23.11.2017, neither the alternate <br /> source was indicated, nor the Open Access application processed, leave alone <br /> availability of corridor to supply power from alternate source, we therefore do not <br /> feel it necessary to interfere with the Impugned Order on this account and upheld <br /> the Liquidated damages worked out for the month of November considering non <br /> supply of energy from 19.11.2017 to 23.11.2017 and deemed supply of energy <br /> for the period from 24.11.2017 till 30.11.2017, which in the Impugned Order has <br /> been calculated as Rs 2489412 . <br /> 23. With regard to the issue of liability of open access Charges on the <br /> Appellant, we take note that in the petition filed by Appellant (OP No 22 of 2019), <br /> before State Commission, in which Impugned Order has been passed, Appellant <br /> has prayed for withdrawal of liquidated damages of Rs. 29,72,647 levied by the <br /> Respondents. The State Commission, besides adjudicating the issue of <br /> liquidated damages, in the impugned order has worked out a liability of Rs <br /> 12,81,0101 upon Appellant, for the open access charges, to the extent energy <br /> not made available in terms of Article 6.2.5 of the PPA. In the Impugned Order, it <br /> has been held that, since the total amount of compensation payable by the <br /> Appellant, considering the liquidated damages of Rs 24,89,412 and open access <br /> charges of Rs. 12,81,0101, would exceed the deduction made of Rs. 2972647, <br /> the Appellant is non-entitled to the relief sought in the petition and accordingly, <br /> dismissed the same. <br /> 24. Learned counsel on behalf of the Appellant has contended that in terms of <br /> Regulation 5(4) of the Central Electricity Regulatory Commission (Sharing of <br /> Inter-State Transmission Charges and Losses) Regulations, 2010, as amended <br /> from time to time, the PoC charges for Short-Term Open Access transactions are <br /> specified in paisa per unit and are applicable strictly for the duration of Short-<br /> Page <b>13</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> Term Open Access as approved by the RLDC/NLDC. The short-term Open <br /> Access charges are leviable only on schedules duly approved and implemented <br /> and therefore levy of additional Open Access charges by State Commission is <br /> improper and unacceptable. <br /> 25. From the operative portion of the Impugned Order, it is evident that there is <br /> no specific or categorical direction issued to the Appellant to pay the Open <br /> Access charges so calculated. The denial of relief to the Appellant was premised <br /> only on the reasoning that the aggregate liability, when liquidated damages and <br /> open access charges are considered together, exceeded the deductions already <br /> effected by the Respondents. It is further noted that the Respondents had not <br /> raised any claim towards Open Access charges for the relevant period either prior <br /> to the passing of the Impugned Order or subsequent thereto. Neither <br /> Respondents nor the Appellant has drawn our attention towards pending claim <br /> for levy of open access charges for the period under consideration. Thus, it is <br /> evident that no independent demand or assertion of liability on account of Open <br /> Access charges was ever made by the Respondents against the Appellant. The <br /> Appellant has, in fact, confined its prayer to seeking withdrawal of the finding in <br /> the Impugned order relating to the levy of Open Access charges. <br /> 26. In view of the foregoing, and particularly in the absence of any operative <br /> direction fastening liability upon the Appellant, coupled with the Respondents’ <br /> own conduct in not raising any claim for Open Access charges during the period <br /> under consideration, we hold that the levy of Open Access charges cannot be <br /> sustained. The Appellant cannot be burdened with a liability which has neither <br /> been claimed by the Respondents nor specifically directed in the operative part <br /> of the Order. Accordingly, the prayer of the Appellant seeking withdrawal of the <br /> direction of levy of Open Access charges merits acceptance. <br /> Page <b>14</b> of <b>15</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 58 of 2020 </i><br /> <br /> <b>Conclusion </b><br /> 27. In view of the above deliberation, the calculation of liquidated damages as <br /> determined in the Impugned Order is hereby upheld. However, the Impugned <br /> Order stands modified to the extent of the liability worked out upon the Appellant <br /> towards Open Access Charges, which is set aside. <br /> 28. It is further directed that any extra amount withheld by Respondent No. 2 <br /> on account of liquidated damages, over and above the amount so upheld herein, <br /> shall be refunded to the Appellant together with simple interest at the prevailing <br /> SBI Prime Lending Rate (PLR) calculated up to the date of actual payment. For <br /> this aforesaid purpose, the Appellant shall raise an invoice within a period of four <br /> weeks from the receipt of this Order, and Respondent No. 2 shall make payment <br /> within four weeks thereafter. <br /> 29. The appeal is partly allowed in the above terms. All pending IAs, if any, <br /> stands disposed of in above terms of this order. <br /> <b>TH</b><br /> <b>PRONOUNCED IN THE OPEN COURT ON THIS 16</b> <b> OF MARCH, 2026. </b><br /> <b> </b><br /> <b> </b><br /> <b>(Virender Bhat) </b><br /> <b>Judicial Member </b><br /> <b>(Seema Gupta) </b><br /> <b>Officiating Chairperson </b><br /> <b> </b><br /> <b>REPORTABLE / NON-REPORTABLE </b><br /> <br /> <i>pr/dk/ag </i><br /> <br /> Page <b>15</b> of <b>15</b> <br /> </div>