IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION APPEAL NO. 14 OF 2025
IN
ARBITRATION PETITION NO.187 OF 2023
WITH
INTERIM APPLICATION (L) NO. 11667 OF 2024
Hindustan Petroleum Corporation Ltd.
A Government Company,
registered under the Companies Act, 1956
having its registered office at Petroleum
House, 17, Jamshedji Tata Road,
Mumbai – 400 020.
Through its Authorized Signatory …..Appellant
(Orig. Petitioner)
Vs.
Arcon Powerinfra India Pvt. Ltd.
Formerly, M/s. SKP Buildcon Pvt. Ltd.
Through Its Director, Shri. Kapil Sharma,
A Company deemed to have been
Incorporated under the Companies Act,
2013, Having its Registered Office at :
Shop No.3, Vinayak Complex,
Nr. Sola Railway Crossing, Ghatodiya,
Ahmedabad-360051
And having its Corporate Office at
409, Shapath-V, S.G. Highway,
Ahmedabad-380015. …..Respondent
(Orig. Claimant)
1/6
Uploaded on - 22/09/2026 Downloaded on - 22/09/2026 11:31:04
ssm 12-arapp14.2025.doc
____________________________________
Adv. Javeed Hussein a/w Adv. Mubashir Hussein, Adv. Munzir Hussein, Adv.
Munibah Iram, Adv. Zubi Ansari and Adv. Jay Patel i/by Hussein & Co.,
for the Appellant.
Mr. Kalpesh Joshi a/w Ms. Nisha Shah i/by Kalpesh Joshi Associates for the
Respondent.
____________________________________
CORAM : A. S. GADKARI AND
KAMAL KHATA, JJ.
th
DATE : 8 SEPTEMBER, 2026.
JUDGMENT (Per : A.S. Gadkari, J.):-
1) By this Appeal under Section 37 of the Arbitration and
Conciliation Act, 1996, (for short, “the Arbitration Act” ) the Appellant, a
public sector company of Government of India, has impugned the Order
st
dated 1 March, 2024, passed by the learned Single Judge in Arbitration
Petition No.187 of 2023, filed under Section 34 of the Arbitration Act,
th
dismissing the said Petition and upholding the Award dated 26 July, 2022,
passed by the sole Arbitrator.
2) Heard Mr. Hussein, learned counsel appearing for the
Appellant, and Mr. Joshi, learned counsel for the Respondent. Perused
entire record.
3) The argument of the Appellant that the Respondent company
did not disclose the fact that it was on the holiday list of, or banned by,
National Hydro Power Company Ltd. (NHPC), a Government of India
enterprise, while bidding for the said contract and that the Respondent did
2/6
Uploaded on - 22/09/2026 Downloaded on - 22/09/2026 11:31:04
ssm 12-arapp14.2025.doc
not carry out necessary work as per the contract, does not appeal us.
3.1) Paragraph Nos.62 and 63 of the Award reads as under:-
“62. I will now proceed to address Claim No.1 of the
Claimant. This is for work that is stated to have been
done on the site prior to the termination. The
Claimant had submitted its first RA Bill for an amount
of Rs.25,73,262/-. This RA Bill was sent to the
th
Respondent on 27 June, 2017. The Claimant
contends that there was never any dispute raised
regarding this bill or any mistake or discrepancy
pointed out. In defence, the Respondent drew my
attention to Clause 7 of the General Terms and
Condition of the subject contract and the fact that the
RA Bill in question did not contain measurements
jointly taken by the parties, nor was it certified by the
Engineer-in-Charge/ Site-in-Charge. I do not agree
with the Respondent that Clause 7 aids it. On the
contrary, Clause 7.1 requires certification to take place
by the Respondent and payment to be made within 15
days from the date of receipt of the bill. Furthermore,
Clause 7.a.2 states as follows:
“For the purpose of taking joint measurement,
the Contractor/representative shall be bound
to be present whenever required by the
Engineer-in-Charge / Site-in-Charge.”
63. It is the Claimant’s case that RA Bill was sent with the
measurements and that it would have been present in
3/6
Uploaded on - 22/09/2026 Downloaded on - 22/09/2026 11:31:04
ssm 12-arapp14.2025.doc
the event that the Respondent had asked it to under
Clause 7.a.2. Even in cross-examination, CW-1 says
that the Claimant had done its measurements and
submitted them to the Respondent for checking and
counter-signing. The Respondent failed to do so
because of its “negative attitude”, a phrase that CW-1,
with some variation, has repeatedly used for the
Respondent and its officers. To my mind, the
contractual clause is clear – it did require joint
measurements to be taken and obliged the Claimant’s
officers to remain present when called upon to do so
by the Respondent. Admittedly, the Respondent did
not call upon the Claimant to do so. There is thus no
question of the Claimant failing to remain present.”
4) The learned Single Judge has dealt with the contention of
blacklisting and affirmed the finding of the Arbitrator. In our view, the
contention is entirely baseless. The Supreme Court in Shri Kishan vs.
Kurukshetra University, Kurukshetra, reported in (1976) 1 SCC 311, has
held that, where a person on whom a fraud is committed is in a position to
discover the truth by due diligence, fraud is not proved. The Appellant has
not acted diligently. It ought to have found out lacunae or
misrepresentations, if any, prior to permitting the commencement of work
though contract was awarded. Such a defence could not have been raised
after the work was completed and it was time to pay for it. This attitude is
rank dishonesty on the part of the Appellant and cannot be countenanced.
4/6
Uploaded on - 22/09/2026 Downloaded on - 22/09/2026 11:31:04
ssm 12-arapp14.2025.doc
5) It is the settled position of law that, in an Appeal under Section
37 of the Arbitration Act, this Court cannot reassess the evidence to arrive
at an independent conclusion. According to us, the Arbitral Award is also
not in conflict with the public policy.
5.1) The contract between the Appellant and the Respondent was
purely a civil transaction and/or a contract executed under the Indian
Contract Act and nothing more than that. Appellant cannot be permitted,
after completion of the work by the Respondent, to raise a specious plea
that, it is against the public policy. We do not appreciate such a stand taken
by the Appellant who is a Government of India undertaking.
5.2) We note that repeatedly raising the contention of bias and
misconduct raised against a Counsel who acts as an Arbitrator in the matter
is extremely disturbing to say the least. Such a stand ought not to be taken
casually as a standard defence by any Appellant. The Appellant has alleged
that the Arbitrator appeared in an unrelated matter against the Petitioner.
This contention was addressed by the learned Single Judge correctly and
ruled that the contention was based on a clear misreading of Sections 12(1)
and 12(2) of the Arbitration Act. He further held that there was no
th
violation of Section 12(5) read with 7 Schedule of the Arbitration Act. We
emphatically affirm the said view.
6) Considering the rival submissions and perusal of record clearly
5/6
Uploaded on - 22/09/2026 Downloaded on - 22/09/2026 11:31:04
ssm 12-arapp14.2025.doc
indicates that the impugned Order does not suffer from the vice of any legal
perversity. The Learned Arbitrator has taken into consideration the entire
evidence available on record in its proper perspective. The Learned Single
Judge, in the Petition filed under Section 34 of the Arbitration Act, has fully
and rightly considered the case in its entirety and passed a well-reasoned
order dealing with each of the Appellant’s contentions.
7) In view of the above, we are of the considered opinion that,
there are no merits in the Appeal.
7.1) Appeal is accordingly dismissed.
8) In view of dismissal of Appeal, Interim Application (L)
No.11667 of 2024 does not survive and is also disposed off.
(KAMAL KHATA, J.) (A.S. GADKARI, J.)
Digitally signed
by SANJIV
SHARNAPPA
MASHALKAR
Date:
2026.09.22
11:05:16 +0530
SANJIV
SHARNAPPA
MASHALKAR
6/6
Uploaded on - 22/09/2026 Downloaded on - 22/09/2026 11:31:04