M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv) vs Chief Engineer (Const)-I, North Western Railway, Jaipur

Court
Delhi High Court

$~41
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 26.05.2026
+ O.M.P.(I) (COMM.) 220/2026, I.A. 14558/2026 (EX. From
filing original/typed copies of the documents), I.A. 14559/2026
(Seeking permission to file lengthy synopsis and list of dates) &
I.A. 14560/2026 (Ex. From filing translated copies of the
documents)

M/S VISHAL INFRASTRUCTURE LTD. AND M/S OJSC
EURO - ASIAN CONSTRUCTION CORPORATION
EVRASCON (JV) .....Petitioner
Through: Mr. Sonal Kumar Singh, Mr.
Ratik Sharma, Ms. Muskan
Agarwal, Mr. Parth Sindhwani
and Mr. Yashvadhan Singh
Gohil, Advocates
versus

CHIEF ENGINEER (CONST)-I, NORTH WESTERN
RAILWAY, JAIPUR .....Respondent
Through: Mr. Siddhartha Shankar Ray,
CGSC, Mr. Manish Rawat, GP,
Ms. Sonali Modi, Ms. Shrishti
Singh, Ms. Vatsala Shukla and
Mr. Mohit Bokoliya, Advocates

CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR

% JUDGEMENT (ORAL)
1. The present Petition, under Section 9 of the Arbitration and
Conciliation Act, 1996, seeks the following reliefs:
“a. Pass an ex-parte ad-interim stay/restraining the Respondent
from acting pursuant to, or taking any coercive steps in furtherance
of the Notice intimating intent to terminate the EPC Agreement
awarded to the Petitioner for “Major Upgradation of Jodhpur
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:29.05.2026
13:20:41
O.M.P.(I) (COMM.) 220/2026 Page 1 of 4

Railway Station of North Western Railway on Engineering,
Procurement and Construction (EPC) Mode” vide Agreement dated
14.07.2023 bearing Agreement No. NWR/S&C/CA/115(EPC)
pending constitution of the arbitral tribunal and adjudication of
disputes between the Parties thereunder; and
b. Pass an ex-parte ad-interim stay/restraining the Respondent from
taking any coercive action against the Petitioner pursuant to the
notice of imposition of liquidated damages vide the letter dated
13.05.2026 issued by the Respondent/PMC under the terms of the
EPC Agreement, pending constitution of the arbitral tribunal and
adjudication of disputes between the Parties thereunder;
c. Pass any such further order(s) as this Hon’ble Court may deem
fit and proper in the interest of justice, equity and good
conscience.”

2. Learned counsel appearing on behalf of the Petitioner submits
that the present reliefs have been necessitated in view of the
Respondent having issued a Notice dated 13.05.2026, bearing no.
NWR/HQ/S&C/e-444115150 [ “Termination Notice” ] intimating its
intention to terminate the EPC Agreement No.
NWR/S&C/CA/115(EPC) dated 14.07.2023 [ “Agreement” ]. It is
contended that the consequences flowing from the said Termination
Notice would include invocation of various bank guarantees and other
coercive measures, which, according to the Petitioner, may have the
effect of causing severe financial prejudice and irreparable
commercial consequences.
3. Learned counsel for the Petitioner further submits that by
Communication No. JU/Const.-/74-W-20/2025-26/PMS/JU/Pt-VII
dated 12.05.2026 and Communication No.
LECPL/MUJSNWR/JU/2025-26/1845 dated 13.05.2026, the
Respondent has also sought to impose liquidated damages amounting
to Rs. 47.75 Crores, being the maximum permissible amount
equivalent to 10% of the Contract value. It is submitted that there
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:29.05.2026
13:20:41
O.M.P.(I) (COMM.) 220/2026 Page 2 of 4

exists an urgent necessity to interdict the operation of the aforesaid
communications.
4. Per Contra , learned counsel appearing on behalf of the
Respondent opposes the grant of the reliefs sought in the present
Petition. He submits that the Petitioner has remained remiss in the
performance of its contractual obligations and that repeated extensions
of time had already been granted to the Petitioner. It is further
submitted that the Petitioner itself has acknowledged its inability to
perform the Contract within the stipulated timelines.
5. Learned counsel appearing on behalf of the Respondent further
places reliance upon Article 34 of the Agreement dealing with the
Dispute Resolution Mechanism. He submits that the present Petition is
premature inasmuch as the contractual framework first contemplates
recourse to conciliation proceedings, followed thereafter by reference
to the Disputes Adjudication Board [ “DAB” ], which is required to
render its decision within a period of ninety (90) days.
6. It is accordingly contended that, without exhausting the
contractual dispute resolution mechanism, invocation of arbitral
proceedings would itself be premature and consequently the present
Petition is not maintainable at this stage.
7. At this stage, after making submissions for some time, learned
counsel appearing on behalf of the parties submit that they are ad idem
that the Dispute Resolution Process contemplated under the
Agreement, commencing from the stage of the DAB, may continue in
accordance with the contractual mechanism and that the parties shall
remain at liberty to take recourse to such further remedies as may be
available to them under the Agreement.
8. The parties further agree that, till such time as the DAB renders
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:29.05.2026
13:20:41
O.M.P.(I) (COMM.) 220/2026 Page 3 of 4

its decision with respect to the disputes between the parties,
Communication No. JU/Const.-/74-W-20/2025-26/PMS/JU/Pt-VII
dated 12.05.2026 and Communication No.
LECPL/MUJSNWR/JU/2025-26/1845 dated 13.05.2026, insofar as
they pertain to imposition of liquidated damages amounting to Rs.
47.75 Crores, shall not be acted upon.
9. Accordingly, the present Petition, along with pending
Application(s), if any, stands disposed of in the aforesaid terms.


HARISH VAIDYANATHAN SHANKAR, J.
MAY 26, 2026/rk/DJ