PADMAVATI TRADELINK LTD. vs STANDARD CHARTERED BANK AND ORS
- Court
- Calcutta High Court
Form J(2)
Sl.No. 01
In The High Court at Calcutta
Ordinary Original Civil Jurisdiction
[Commercial Division]
Original Side
Present:
The Hon’ble Justice Aniruddha Roy
IA No. GA-COM/9/2025
[Old No. CS/159/2021]
In CS-COM/297/2024
PADMAVATI TRADELINK LTD.
VS
STANDARD CHARTERED BANK AND ORS
AND
IA No. GA-COM/11/2026
[Old No. CS/159/2021]
In CS-COM/297/2024
PADMAVATI TRADELINK LTD.
VS
STANDARD CHARTERED BANK AND ORS
For plaintiff:
Mr. Tilak Kumar Bose, Sr. Adv.
Ms. Suchismita Ghosh, Adv.
Mr. Pradip Kumar Sarawagi, Adv.
For defendant no.1/
Standard Chartered Bank Ms. Arti Bhattacharyya, Adv.
For defendant no.2 Ms. Ajeyaa Choudhury, Adv.
Mr. Anirban Ghosh, Adv.
For defendant nos.3 Mr. Rohit Banerjee, Adv.
2
Mr. S.S. Bhutoria, Adv.
For defendant no.4 Mr. Altamash Alim, Adv.
Mr. S.S. Bhutoria, Adv.
For defendant no.8 Mr. S. Pal Choudhuri, Adv.
Ms. Sanchita Dey Pal Choudhuri, Adv.
For defendant no.9 Mr. Uttam Kumar Mandal, Adv.
Mrs. Maitree Roy, Adv.
Ms. Udita Mandal, Adv.
Reserved on : 01.09.2026
Judgment on : 09.10.2026
ANIRUDDHA ROY, J.:
Facts:
CS-COM/297/2024 [OLD No. CS/159/2021]
1. (hereinafter, the instant
suit ) had been filed by the owner of the property. IA No. GA-
COM/9/2025 (hereinafter, the first application ) has been filed by
defendant no.4 . IA No. GA-COM/11/2026 (hereinafter, the second
application ) has been filed by defendant no.3 .
2. Both the said applications filed by the two applicants have been filed
under Section 10 of the Code of Civil Procedure (hereinafter, the
Code ) praying for stay of the instant suit.
3. Since both the applications arose out of the same suit with an identical
prayer relating to the self-same property and involving common
questions of law, by consent of parties, both the applications have been
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
3
taken up for consideration together and through the present composite
judgment, the said two applications are finally decided.
4. The inescapable facts are only stated.
5. The plaint case, in brief, is narrated hereinafter :
5.1. Defendant no.1 (Standard Chartered Bank) (herein, the
bank ) was the original owner of premises no.19, Netaji Subhas
Road, P.S. Hare Street, Kolkata – 700001 (herein, the property )
having a land area of about 51.638 Cottahs more or less and
building standing thereupon, comprising of basement, ground,
mezzanine, first, second and third floor and a roof, having a total
built up area of about 11,891.57 sq. mtr., equivalent to
1,28,000.59 sq. ft. The entirety of the said property was in
occupation of the bank save and except the second floor which
was in occupation of various tenants against whom several
eviction proceedings were and still are pending. The bank at all
material times was in exclusive possession and occupation of
entirety of basement, ground and mezzanine, first floor and third
floor including roof and all common areas at the property.
5.2. Third floor of the premises has covered area or built up area
of about 16389 sq. ft.. The rest of the third floor measuring about
14,166 sq. ft. comprised of terrace is open to sky (hereinafter, the
open area ). The said open area comprised of a terrace and an
open cut out area at the centre and iron stairs leading to the roof
whereat the water tanks of the bank were and still are located.
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
4
The area of the roof is equivalent to built-up area of the third floor
which is 16389 sq. ft. Towards the south of the third floor, three
dish antennas which are used by the bank are located. Towards
north-east corner of the third floor, there is a chiller plant
guarded by net wire fencing all round and an iron gate entrance
to the plant. The chiller plant is being used by the bank for
running its air conditioning system. The water tanks, disc
antennas, chiller plant and control room at all material times are
being used by the bank for its exclusive use. The staircase leading
to the roof is situated opposite to the chiller plant and servers the
only access to the roof. The control room for the chiller plant is
located at one end of the built in structure in the third floor and
opposite to the chiller plant.
5.3. Bank has been carrying on banking business from the
property since about 1958.
5.4. By a registered deed of conveyance dated June 8, 2017 the
plaintiff purchased from the bank, inter alia, all that comprising
basement (4517 sq. ft.) ground floor (29387 sq. ft.), mezzanine
floor (18934 sq. ft.), first floor (29387 sq. ft.), second floor
(29386 sq. ft.) and partly third floor (16389 sq. ft.) having an
aggregate area of 128000.859 sq. ft. together with portion of open
terrace along with all piece and parcel of land on which the
property is built up comprising of an area of land about 51.638
cottahs.
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
5
5.5. Under a registered deed of lease dated June 8, 2017
executed and entered into by and between the plaintiff and the
bank, the plaintiff permitted the bank to continue to use, occupy
and enjoy the basement having super built-up area of 4517 sq. ft.,
ground floor having a super built-up area of 29387 sq. ft.,
mezzanine floor having a super built-up area of 18934 sq. ft. and
the first floor having a super built-up area of 29387 sq. ft.,
aggregating to 82,225 sq. ft. super built-up area together with
four car parking spaces as described in the said lease deed at a
rental mentioned therein.
5.6. Defendant nos.5 and 6 are subsidiaries of the
bank/defendant no.1. By virtue of three registered lease deeds
dated January 5, 2021, December 7, 2020 and August 13, 2021,
the defendant nos.1, 5 and 6 as lessees of the plaintiff were made
liable to pay various payments concerning the properties as
aggregating thereunder.
5.7. The plaintiff is in use and occupation of portions of the third
floor, roof above the terrace and also common areas including lift
and staircase of the property. Plaintiff remains the registered
owner of and in respect of the entire second floor of the property,
though the same is occupied by several unauthorized tenants of
the bank.
5.8. On February 6, 2018 and March 09, 2018 portions of third
floor of the property comprising a built-up area for about 16389
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
6
sq. ft. was sold and conveyed by the plaintiff in favour of
defendant no.2 in LOT-A and LOT-B under two separate deeds of
conveyance marked as Annexures F and G to the plaint. The
defendant no.2 was put in possession in respect of both the said
LOT-A and LOT-B at the third floor of the property.
5.9. Defendant no.2 thereafter started creating obstruction
towards the plaintiff to have its access to the various portions of
the property which were not conveyed to the defendant no.2 and
the plaintiff still is the owner thereof.
5.10. By reasons of the said obstruction caused by the defendant
no.2, the plaintiff had filed a civil suit on or about October 13,
2020 (hereinafter, Previous Suit ) being CS-COM 206 of 202 4
(previously CS No.121 of 2020 )} against the defendant nos.1
and 2 after obtaining leave under Order II Rule 2 of the Code and
prayed for following reliefs :
“a) Declaration that the Plaintiff is the absolute owner
of the open terrace in the third floor measuring about
14166 square feet and the roof above the built up
area of the third floor measuring 16389 square feet
and all structures lying there at in respect of premises
19, Netaji Subhas Road, Kolkata 700 001 as shown
in the layout plan being Annexure 'A' hereto and
schedule being Annexure "Z-4" hereto.
b) Declaration that the Plaintiff, its servants,
representatives, assigns and lessees have right of
free ingress and egress to and use, operation and
maintenance of the control room for the chiller plant
located at the third floor of premises 19, Netaji
Subhas Road, Kolkata 700 001 as shown in the
layout plan being Annexure 'A' hereto and schedule
being Annexure "Z-4" hereto;
c) Declaration that the plaintiff, its servants,
representatives, assigns and lessees have right of
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
7
ingress and egress to all installations at the terrace in
the third floor including the Chiller Plant, satellite dish
antenna and water storage tanks located in the roof
above the built up structures in Third floor of
premises No 19, Netaji Subhas Road, Kolkata 700
001 and are entitled to use, utilise and enjoy the
same as shown in the layout plan being Annexure 'A'
hereto and schedule being Annexure "Z-4" hereto;
d) Declaration that the ownership of the defendant
no.1 in the third floor is restricted to Lot "A"
measuring only divided and demarcated built up
portion of the third floor containing an area of 12,292
sq. ft. as mentioned in the deed of conveyance dated
6th February, 2018 and Lot "B" built up area of 4097
square feet as mentioned in the deed of conveyance
dated 9th March, 2018;
e) Declaration that the plaintiff, its servants,
representatives, assigns and lessees have
easementary right over the control room for chiller
plant /AC plant located in the third floor and/or right
to use the same as common area as shown in the
layout plan being Annexure 'A' hereto and schedule
being Annexure "Z-4" hereto;
f) Declaration that the phrase "land appertaining" to
Lot "A" and "B" stated in the deeds of conveyance
dated 6th February, 2018 and 9th March, 2018 is
incapable of conveying or transferring any absolute
right, title or interest therein in favour of the
defendant no.1 in any manner whatsoever in respect
of open terrace measuring 14166 square feet at the
third floor and 16389 square feet of roof area above
the built up area in the third floor as shown in the
layout plan being Annexure 'A' hereto and schedule
being Annexure "Z-4" hereto and/or otherwise;
g) Declaration that the phrase "land appertaining" to
Lot "A" and "B" as purportedly mentioned in the
deeds or which may be allegedly shown in the maps
appended in the deed of conveyance dated 6th
February, 2018 and 9th March, 2018 in orange and
yellow colours respectively is vague, uncertain,
devoid of particulars and void and the same be
directed to be delivered up and cancelled;
h) If necessary, the entire conveyance deeds dated
6th February 2018 and 9th March 2018 be declared
null and void and the same be delivered up and
cancelled;
i) A decree of perpetual injunction restraining the
defendant no.1, its men, agents, servants, assigns
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
8
and/or anyone claiming on their behalf from
preventing and/or obstructing the plaintiff its
servants, representatives, assigns and lessees free
ingress and egress to the open terrace and all
installations and equipment there at including the
Chiller Plant Room and satellite antenna situated on
Third floor of the said building and the common
areas, facilities, amenities open spaces and allied
easementary rights on the third floor and use and
maintenance of the same as shown in the layout plan
being Annexure 'A' hereto and schedule being
Annexure "Z-4" hereto;
j) A decree of perpetual injunction in relation to
restraining the defendant no.1, its men, agents,
servants, assigns and/or anyone claiming on their
behalf from interfering with or obstructing the
plaintiff, its servants, representatives, assigns and
lessees free access, using and utilisation of the roof
above the built up area of the third floor and all
installations threat and in particular the water
storage tanks and all other common areas, facilities,
amenities open spaces and allied easementary rights
of the said building in any manner whatsoever as
shown in the layout plan being Annexure 'A' hereto
and schedule being Annexure "Z-4" hereto;
k) A decree of perpetual injunction in relation to
restraining the defendant no.1, its men, agents,
servants, assigns and/or anyone claiming on their
behalf from interfering with the rights of the plaintiff
and/or the lessees and/or tenants under the plaintiff
from accessing, visiting and maintaining the Chiller
Plant, C(Band) satellite dish antenna and the water
storage tank situated in the roof of the said building
and/or common portions thereof in any manner
whatsoever as shown in the layout plan being
Annexure 'A' hereto and schedule being Annexure "Z-
4" hereto;
l) A decree of perpetual injunction in relation to
restraining the defendant no.1, its men, agents,
servants, assigns and/or anyone claiming on their
behalf from obstructing and denying the Plaintiff, its
servants, representatives, assigns and lessees the
right of access, use, maintenance of the control room
to the chiller plant /AC plant at the third floor of the
premises as shown in the layout plan being Annexure
'A' hereto and schedule being Annexure "Z-4" hereto;
m) Decree of perpetual injunction restraining the
defendant no.1 from putting any padlock in the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
9
collapsible gate at the entrance of the control room of
the Chiller Plant/AC plant in the third floor of the
premises;
n) If, necessary decree of mandatory injunction
directing the defendant No.l to remove and dismantle
the collapsible gate at the entrance door to the control
room for the chiller plant/AC plant.
o) An enquiry into the loss and damage already
suffered by the plaintiffs for the wrongful and illegal
acts committed by the defendant no. 1 and a decree
for such sums be paid to the plaintiff upon such
enquiry being made;
p) Injunction;
q) Receiver;
r) Attachment;
s) Costs;
t) Further or other relief;”
5.11. Defendant no.1/bank herein was impleaded as the pro-
forma defendant no.2 therein in the previous suit. The defendant
no.2 herein was impleaded as the defendant no.1 in the previous
suit. The said previous suit is still pending. The defendant no.2
herein had entered appearance and filed written statement in the
said previous suit.
5.12. The defendant no.2 herein, however, in breach of its
obligation owed to the plaintiff and in violation of the covenant
contained in the said two deeds of conveyance under which
defendant no.2 had obtained right in the property, had purported
to sale, alienate and transfer portions of the property covered
under the said two deeds of conveyance executed by the plaintiff
in favour of the defendant no.2 herein to the defendant nos. 3
and 4 . Challenging the said purported transfer, inter alia, in
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
10
favour of defendant nos.3 and 4, the plaintiff had filed the instant
second suit (hereinafter, second suit ) with the following reliefs :
“(a) Delivery up and cancellation of the two Deeds of
Conveyances dated 21st May, 2018 and 15th
October, 2018 being Annexure 'J' and 'K' hereto
executed by defendant no. 2 in favour of defendant
nos. 3 and 4, and the same be adjudged as null and
void and inoperative;
(b) the area covered by the aforesaid Deeds of
Conveyance dated 21st May, 2018, and 15th,
October, 2018, from the Defendant No's. 3 and 4 to
the Recovery of possession of Plaintiff;
(c) A further decree of perpetual injunction restraining
the defendant nos. 3 and 4, and their officers,
managers, men, servants and agents, and/or anyone
claiming from and/or on their behalf from making any
transfer and/or further transfer of the portions
mentioned in Schedule being Annexure 'H' and I'
hereof in any manner whatsoever.
(d) A further decree restraining the defendant
permanently from No.2 selling, alienating and
transferring and/or otherwise dealing with any part
or portion of the areas covered by the Deeds of
Conveyance dated 6th February, 2018 and 9th
March, 2018 till such time amount of
Rs.2,47,50,000/- is paid by the defendant No.2 to
plaintiff.
(e) Decree for Rs.1,87,717/- as claimed in paragraph
48 above as against defendant No.2;
(f) Decree of mandatory injunction directing the
Defendant No.2, to pay further and future
proportionate maintenance and insurance charges for
the common area and portions of the third floor of the
said premises;
(g) Decree of mandatory injunction directing the
Defendant No. 2 to make payment of its proportionate
share of municipal taxes for portions of the third floor
of the premises on the basis of actual assessment;
(g) (i) Mandatory injunction directing defendant
Nos. 1, 5 and 6 to pay proportionate
maintenance charges on and from the effective
dates mentioned in their respective registered
Deed of Lease.
(h) Alternatively, a fit and proper person/agency
appointed for the purpose of maintenance of the
common areas of the building including its
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
11
installation and costs and expenses of such
maintenance agency be borne by the plaintiff No.1
and the defendant No.2 in equal share;
(i) Decree of perpetual injunction, restraining the
Defendant No. 1, and its officers, managers, men,
servants and agents, and/or anyone claiming from
and/or on behalf of the Defendant No.1 from
deducting or withholding any amount from the
monthly lease rentals, due and payable from the
Defendant No.1 to the Plaintiff, on account of non-
payment of electricity charges by Defendant No. 2 to
Defendant No. 1 or electricity dues and consumption
of defendant Nos. 2 to 4 or defendant Nos. 8 to 11.
(j) Decree of perpetual injunction restraining the
Defendant No. 1 and its officers, managers, men,
servants and agents, and/or anyone claiming from
and/or on behalf of the Defendant No. 1 from acting
contrary to and in breach of the registered Lease
Deed entered into between the Plaintiff and the
Defendant No. 1, dated 5th January, 2021, in any
manner whatsoever;
(k) Perpetual injunction restraining the defendant
No.1, its and agents servants, assigns from deducting
any sum on account of electricity bill or consumption
by the defendant Nos.2, 3 and 4 from payable by rent
defendant No.1 to the plaintiff;
(1) If necessary, the defendant No.7 be directed
to install separate meter in the name of the
plaintiff for use of the common areas and
portions of the building in the possession and
occupation of the plaintiff;
(m) Decree of Rs.27,15,842/-as pleaded in paragraph
41 as against defendant No.1;
(n) Interest at the rate of 18% per annum on
Rs.27,15,842/-;
(o) Delivery up and cancellation of the two Deeds of
Conveyance dated 6th February, 2018 and 9th
March, 2018 and the same be adjudged as null and
void and inoperative; (p) Decree for recovery of
vacant, peaceful and khas possession of the entirety
of the portion of the third floor and terrace of the said
premises as mentioned in LOT A and LOT B Deeds of
the two Conveyance, dated of 6th February, 2018
and 9th March, 2018, from the Defendant No.2, to the
Plaintiff;
(q) In the alternative,
i) Decree of Rs.2,47,50,000/-as pleaded in
paragraph 24, as against Defendant No. 2; the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
12
ii) Interest at the rate of 18% per annum on the
outstanding principal sum of Rs.2,47,50,000/-
on and from 1st May, 2018;
(r) Receiver;
(s) Injunction;
(t) Costs of legal proceedings;
(u) Further or other relief;”
6. In the above facts and circumstances the defendant no.4 has filed the
said First Application praying for stay of the second suit in view of the
pendency of the said previous suit along with other consequential
reliefs.
7. Similarly, the defendant no.3 has also filed the said Second
Application with an identical prayer for stay of the second suit .
8. Parties have filed and exchanged their respective affidavits. Parties have
also filed their written notes.
Submissions :
9. Mr. Altamash Alim learned Advocate appearing for the defendant
no.4/applicant at the outset has placed both the plaints and the reliefs
claimed thereunder extensively. He submits that the matter in issue in
the second suit, which is the subsequent suit, is directly and
substantially in issue in the said previous suit. He submits that the
defendant no.4 claims litigating under the same title which is pending
adjudication in the previous suit.
10. Mr. Altamash Alim learned Advocate appearing for the defendant
no.4/applicant submits that the defendant no.2 had purchased portion
of the Third Floor, inter alia , LOT-A and the property appertaining
thereto from the plaintiff on February 6, 2018 and March 9, 2018. The
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
13
defendant no.4 had purchased a portion of LOT-A from the defendant
no.2 on October 15, 2018 by way of registered conveyance upon
making payment of the consideration mentioned therein. The agreement
dated February 06, 2018 is the deed based on which defendant no.4 has
purchased a portion from the defendant no.2 which is recorded in the
deed dated October 15, 2018. If the deed dated February 06, 2018
executed by the plaintiff in favour of the defendant no.2, does not exist
then consequentially the deed of conveyance dated October 15, 2018
executed by the defendant no.2 in favour of the defendant no.4 shall not
exist and the defendant no.4 in effect would loose its valuable right, title
and interest over the property.
11. Referring to the said three deeds of conveyance, two being executed in
favour of the defendant no.2 by the plaintiff and the one being executed
in favour of the defendant no.4 by the defendant no.2, Mr. Altamash
Alim submits that the defendant no.4 has assumed and acquired a valid
right and title from defendant no.2 which in turn assumed the title from
the plaintiff flowed in favour of defendant no.4. He further submits that
there are several disputes and differences about LOT-A on account of
the interpretation of conveyance dated February 6, 2018 and the alleged
claim on account of unpaid money, which resulted the plaintiff to file
the previous suit against the defendant no.2 and the defendant no.1
herein.
12. With specific reference to the reliefs claimed by the plaintiff in the
previous suit, learned Advocate for the defendant no.4 submits that the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
14
plaintiff had claimed delivery up and cancellation of the deeds of
conveyance dated February 6, 2018 and March 9, 2018 executed by the
plaintiff in favour of the defendant no.2. He specifically refers to prayer
(h) from the previous plaint.
13. Mr. Altamash Alim, learned Advocate then submits that if the said
prayer (h) in the previous suit is allowed, automatically the conveyance
executed by the defendant no.2 in favour of the defendant no.4 would
be of no effect or further effect and would be rendered void. The plaintiff
ought to have filed a comprehensive suit, if at all and not the two
separate suits in their present from where the issue in the second suit
is identically same and/or substantially same with that of the previous
suit.
14. Learned Advocate for the defendant no.4 then refers to prayers from the
second suit where the plaintiff has made a monetary claim coupled with
cancellation of the conveyance dated October 21, 2018 and February
06, 2018 along with other prayers. Learned Advocate then refers to
prayers (a), (b), (o) and (p) from the second suit.
15. Learned Advocate for the defendant no.4 has then referred to Section
10 of the Code and submits that the provisions laid down thereunder
is not restricted only between/amongst the same parties in two suits,
rather it is extended to any and every person who claims litigating
under the same title. He submits that the expression “ same party ” is not
at all a consideration while dealing with a Section 10 application as
plaintiff may choose to add several parties to mislead the Court and
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
15
imply clever drafting to avoid rigour of Section 10 of the Code. In
support, he has placed reliance on a decision In the matter of : AIR
2006 Cal 2972 .
16. Learned Advocate for the defendant no.4 submits that his client has
obtained the property from the defendant no.2 under a registered
conveyance dated October 15, 2018 who in turn had obtained title from
the plaintiff under the registered conveyance dated February 6, 2018
and the title has successfully passed upon the defendant no.4.
Defendant no.4 purchased well within the caveat prescribed under
Section 10 of the Code and as such there is no such impediment upon
the defendant no.4 in maintaining the Section 10 application.
17. Mr. Altamash Alim, learned Advocate appearing for defendant no.4
further submits that the issue of a non-party to the previous suit can
maintain an application under Section 10 of the Code is no more res
integra . Reliance has been placed on the following decisions :-
(a) In the matter of: Challapalli Sugar Ltd. vs. Swadeshi
Sugar Supply Pvt. Ltd. reported at AIR 1983 Cal 199;
(b) In the matter of: The Laxmi Bank Ltd. Aloka and Others
vs. Harikisan and Ors. reported at AIR 1948 Nag 297;
(c) In the matter of: Shorab Merwanji and Anr. vs. Mansata
Film Distributors and Anr., reported at AIR 1957 Cal 727.
18. On the expression “ same parties ” learned Advocate Mr. Altamash Alim
submits that it would mean the parties between whom the matter
substantially in issue has arisen and has been decided. The complete
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
16
identity either of the subject-matter or the parties are not required. The
purport and intent behind the two suits are to be looked into. For the
purpose of Section 10 application there may not be a complete identity
of party or complete identity of the subject-matter. Such a situation
would promote an unscrupulous or dishonest litigant like the plaintiff
herein to avoid the provisions under Section 10 of the Code and to
permit to file consecutive suits which may be with identical issues.
Thus, there is no bar in law for non-party to maintain a Section 10
application and pray for stay of the subsequent suit.
19. The expression “ same title ” used in Section 10 of the Code would mean
that the liability for one to file an application is when the dispute of the
entire area and not a portion of it. The defendant no.2 had purchased
LOT-A on the Third Floor from the plaintiff. Defendant no.4 had
purchased a portion from the defendant no.2, however, that does not
make any difference because common areas are part of the ownership of
defendant no.2 which is also a subject-matter in the second suit.
Defendant no.4 assumes and derives title from the chain of title flowing
down from the plaintiff to the defendant no.4. The phase used
same title
in Section 10 of the Code does not make a distinction which the plaintiff
had asserted. It is settled that even a portion of land would construe
and/or come within the phase same title . Reliance has been placed in a
decision In the matter of: Abdul Gani and Anr. vs. Nabendra
Kishore Roy & Ors., reported at 33 CWN Cal 876.
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
17
20. Learned Advocate further submits that in a case where whole title is in
issue in a previous suit, the same cannot be agitated in a subsequent
suit. Applying the same principle, the phase same title cannot be
allowed to be given a restrictive interpretation rather the same should
be considered in the light of the entire section. As such, even a portion
of the title would construct same title, entitling the defendant no.4, in
the facts of this case, to maintain the Section 10 application.
21. Mr. Altamash Alim further submits that the plaintiff before filing the
instant suit had duly cancelled the conveyance dated February 06, 2018
by way of a letter. The plaintiff had also asked for possession of the
premises from the defendant no.2 since the relevant conveyance stand
cancelled by the defendant no.2. As per the plaintiff, the previous suit
has been primarily filed seeking declaration that the area of the
defendant no.2, which in turn includes the area of the defendant no.4 is
restricted to LOT-A and does not include the open space including
chiller plant and others are not the common subject-matter in both the
suits. The plaintiff has sought for correction in the conveyance and
prayed for prayer (h), as quoted above, in the previous suit, which has
already been obtained by the plaintiff would it had cancelled the
conveyance dated February 6, 2018. The natural outcome of the prayer
is recovery of possession by the plaintiff which would include the
possession of the defendant no.4. The plaintiff had not necessitated to
make the prayer in the previous suit had it its prayers been restricted to
declaration of area as has been submitted by the plaintiff before this
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
18
Court. Till date, the plaintiff has not given up prayer (h) in the previous
suit. In the second suit being the instant suit, the plaintiff has also
asked for delivery up and cancellation of the same deeds as sought for
in the previous suit. In case, the trial of the instant suit is allowed to be
proceeded then there will be an anomalous situation which would lead
to absurdity and multiplicity of judicial pronouncement.
22. Mr. Altamash Alim submits that in case the previous suit is allowed to
be proceeded with and prayer (h) is granted, then prayers in the second
suit will automatically be granted and it would have an effect of res
judicata in the second suit. In the event prayer (h) in the previous suit is
allowed, prayers (o) and (p) are not allowed in the second suit then the
situation will be so absurd that it will give birth to a complicated
situation. The plaintiff would claim res judicata in view of grant of
prayer (h) in the previous suit so far as the second suit is concerned.
23. Referring to prayer (h) from the previous suit, learned Advocate for the
defendant no.4 submits that if the said prayer is allowed it would
operate as res judicata in the instant second suit and therefore, the
issue in the instant second suit would be directly and substantially be
same with that of the previous suit. Prayer h in the previous suit if is
allowed, would automatically non-suit the defendant no.4 in the instant
suit. In the light of the above, defendant no.4 submits that the instant
Section 10 application should be allowed.
24. Mr. Rohit Banerjee, learned Advocate appearing for the defendant no.3
being the applicant in the second application has submitted that the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
19
defendant no.3 is identically situated and similarly placed with the
defendant no.4. Mr. Banerjee has adopted the entire submissions made
on behalf of the defendant no.4.
25. He has also prayed for identical relief in his application and prays for
stay of the instant suit.
26. Mr. Tilak Kumar Bose, learned Senior Advocate appearing for the
plaintiff, at the outset, has referred to both the plaints, the averments
and reliefs made therein. He submits that in the previous suit
admittedly, defendant no.4 is not a party. It is a suit filed by the plaintiff
against the defendant nos. 1 and 2 herein. Subject-matter of the
previous suit relates to built up area measuring 16389 sq. ft. on the
Third Floor of the property which was sold and conveyed in two lots –
LOT-A and LOT-B under two separate deeds of conveyance dated
February 6, 2018 and March 9, 2018. Under the said conveyance dated
February 6, 2018 LOT-A comprised an area of 12292 sq. ft. more less
super built-up which forms the covered area of a portion of Third Floor
of the property. Under the deed of conveyance dated March 9, 2018,
LOT-B comprising an area of 4097 sq. ft. more or less super built-up
which forms the covered area of a portion of Third Floor of the property.
27. Learned Senior Advocate, Mr. Tilak Kumar Bose submits the specific
case of the plaintiff in the previous suit against the defendant no.2 is
that the open terrace and roof on the Third Floor of the property, were
never conveyed to defendant no.2. The plaintiff has only sold and
transferred built-up area on the Third Floor of the property to
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
20
defendant no.2 concluding the open area , where Air Conditioning
chiller plant, satellite disc-antenna and other equipment are installed.
In this fact situation, the previous suit had been filed with the leave
under Order II Rule 2 of Code. The reliefs are restricted to the open
terrace and roof on the Third Floor of the property. He submits that
prayer (h) in the previous suit is an incidental relief which is depends on
other reliefs. The issues framed in the previous suit by an order dated
June 19, 2023 by the Coordinate Bench, would clearly show that the
issues in the second suit are not identical or same with that of the
previous suit.
28. Mr. Tilak Kumar Bose, learned Senior Advocate appearing for the
plaintiff then submits, on a comparative reading of the issues in the two
suits would show that by nature and character they are totally different.
Defendant no.2 is a party in both the suits and has filed its written
statement. Defendant no.2 has not filed any application for stay of the
trial in the second suit. He submits that defendant nos.3 and 4 who are
not the parties in the previous suit but the parties in the second suit
had chosen to file their respective application under Section 10 of the
Code without filing their written statements. Both the defendant nos.3
and 4 seek to claim right under the defendant no.2, have consciously
chosen not to file written statement but to file Section 10 applications.
29. Mr. Tilak Kumar Bose, learned Senior Advocate appearing for the
plaintiff then has referred to the third conveyance, as referred to above
and submits that prima facie it is evident that the defendant nos.3 and
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
21
4 must have noticed the parent deed of conveyance dated February 6,
2018 under which, LOT-A –Third Floor covered built up area measuring
about 12292 sq. ft. was sold and conveyed by the plaintiff to the
defendant no.2, at the time of execution of the conveyance with the
defendant no.2 dated October 15, 2018. He has referred, inter alia,
clauses 18, 19 and 20 from the conveyance deed dated October 15,
2018 at pages 354 to 355 of the plaint – volume III . Thus, defendant
no.4 is bound by the covenant mentioned in the deed under which it is
claiming title.
30. Mr. Tilak Kumar Bose, further submits that defendant no.4 has
allegedly purchased 425.18 sq. ft. super built up area on the Third Floor
of the property, which is a miniscule portion of the covered constructed
area under LOT-A as would be evident from the schedule at page 367 of
the plaint being part of the conveyance dated October 15, 2018. He
further submits that the defendant no.4 is not connected or claiming to
have any interest with regard to the open area covering the roof and
terrace on the Third Floor which is the issue involved in the previous
suit.
31. Referring to Section 10 of the Code, Mr. Tilak Kumar Bose learned
Senior Advocate submits that four tests are required to be satisfied to
apply the said provision, which are, inter alia :-
(i) Identical issues involved in previous suit as well as
in the second suit;
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
22
(ii) No relief or cause of action but the issues involving
in both the suits are to be looked into while deciding
an application filed under Section 10;
(iii) Both the suits must be between the same parties for
principle akin to res judicata to apply and ;
(iv) The issues in two suits must be identical or atleast
substantially similar.
32. Mr. Tilak Kumar Bose, learned Senior Advocate for the plaintiff then
submits the foundation of Section 10 is that no person should be vexed
towards for the same issue which is akin to the principle of res judicata .
The defendant no.4 or 3 has no locus to maintain the said first
application since, they are not parties in the previous suit and also such
application is not maintainable under Section 10 when the same party ,
namely, defendant no.2 is impleaded in the second suit and has filed its
written statement and consciously chosen not to file an application
praying for stay of the second suit. In support, Mr. Bose has cited few
decisions which are reproduced herein with their respective proposition
:-
(i) Issues must be identical :
(a) In the matter of: Bepin Behary Mozumdar and
others vs. Jogendra Chandra Ghosh and Another
reported at AIR 1917 Cal 248;
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
23
(b) In the matter of: Aspi Jal and Another vs.
Khushroo Rustom Dadyburjor reported at (2013)
4 SCC 333;
(c) In the matter of: Shaw Wallace & Co. Ltd., vs.
Bholanath Mandanlal Sherawala and Others
reported at 1975 Cal 411.
(ii) Does not relate to relief or cause of action but issues :
(a) In the matter of: Adhish Chandra Sinha vs.
Hindusthan Gas & Industries Ltd. and Another
reported at AIR 1985 Cal 154.
(iii) Between the same parties :
(a) In the matter of: Sivaprasad Ram vs. Tricomdas
Coverji Bhoja reported at (1915) ILR (XLII) 926;
(b) In the matter of: Mahadevappa vs. Dharmappa
Sanna and Another reported at (1942) ILR Bom
798.
(iv) Akin to Res Judicata :
(a) In the matter of: Shaw Wallace & Co. Ltd., vs.
Bholanath Mandanlal Sherawala and Others
reported at AIR 1975 Cal 411.
33. While dealing with the judgments relied upon by the defendant no.4, In
the matter of: Shorab Merwanji and Anr., (Supra) Mr. Tilak Kumar
Bose, learned Senior Advocate for the plaintiff submits that the said suit
was between the same parties and issues were same. Existence of
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
24
additional parties did not make any difference, as additional party did
not apply under Section 10 of the Code.
34. While dealing with the judgment In the matter of: Challapalli Sugar
Ltd., (Supra) Mr. Tilak Kumar Bose submits that parties in the Andhra
Suit and Calcutta Suit were common. The same goods were involved. No
additional party was involved. Hence, the suit was stayed. It was held
that subject-matter of controversy was the same which arose from the
same contract and same transaction. The issue involved whether
property had passed or not was the common issue in both the suits.
35. While dealing with the judgment In the matter of: Abdul Gani and
Anr. (Supra) Mr. Tilak Kumar Bose, learned Senior Advocate submits
that it was a case on the principle of res judicata under Section 11 of
the Code. The expression “ litigating under same title” will come into
operation only when a third party who was not a party in the first suit is
a party in the second suit and the original party is not impleaded in the
second suit.
36. While concluding his submission, Mr. Tilak Kumar Bose, learned Senior
Advocate submits that the issue pertaining to conditional conveyances,
charge, under Section 55 (4)(b) of Transfer of Property Act, 1882 has
been created in favour of the plaintiff, since the defendant no.2 has not
paid the consideration in full as agreed. Hence, the plaintiff is entitled to
delivery up and cancellation of the conditional conveyances executed by
it in favour of the defendant no.2.
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
25
37. In reply , Mr. Altamash Alim learned Advocate appearing for the
defendant no.4/applicant has specifically submitted that even though
defendant no.4 or 3 were not parties in the previous suit, since
defendant no.4 and 3 have received their right and title from defendant
no.2 who is a party in the first suit, the defendant no.4 has been after
being impleaded in the second suit is litigating under the same title.
Therefore, if the right, title and interest of the defendant no.2 in the first
suit, is declared to be void, it will automatically and in effect would
affect the right, title and interest of the defendant no.4.
Decision :
38. After considering the rival contentions of the parties and on perusal of
the materials on record, it appears to this Court that, admittedly, the
defendant no.4/applicant or the defendant no.3/applicant are not
impleaded in the previous suit. The previous suit had been instituted by
the plaintiff against the defendant nos.1 and 2 herein only.
39. To ascertain the scope and construction of the relevant provisions for
staying the subsequent suit, Section 10 of the Code is quoted below: -
“ 10. Stay of suit - No Court shall proceed with the
trial of any suit in which the matter in issue is also
directly and substantially in issue in a previously
instituted suit between the same parties, or between
parties under whom they or any of them claim
litigating under the same title where such suit is
pending in the same or any other Court in [India]
having jurisdiction to grant the relief claimed, or in
any Court beyond the limits of [India] established or
continued by the [ Central Government] and having
like jurisdiction, or before [the Supreme Court].”
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
26
40. On a meaningful and harmonious reading of the provisions laid down
under Section 10 of the Code, this Court finds that the essential tests
for stay of the subsequent suit are :
(i) The matter in issue in the second suit is directly and
substantially in issue in the previous suit;
(ii) Both the previous suit and the subsequent suit shall
have to be between the same parties;
(iii) In the event and in the alternative, if the parties to
the subsequent suit are not same with that of the
previous suit, then a party who claims for stay of
trial of the subsequent suit must be one who claims
to be litigating under the same title with that of the
previous suit.
41. The object underlying Section 10 of the Code is to avoid two parallel
trials on the same issue of two Courts of concurrent jurisdiction or in
two distinct separate suits even before the same Court and to avoid
recording of conflicting findings on the issues which are directly or
substantially in issue in a previously instituted suit. Mere filing of an
application under Section 10 does not in any manner cause an
impediment or put an embargo on the power of the Court to examine
the merits of the matter. For application of the provisions under Section
10 of the Code, it is essential that the Court in which previous suit is
pending is competent to grant relief claimed. The use of the negative
expression at the inception of Section 10 that no Court shall proceed
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
27
with the trial of any suit makes the provision mandatory and the Court
in which the subsequent suit has been filed is prohibited from
proceeding with the trial of that subsequent suit, if the conditions laid
down under Section 10 of the Code are satisfied. The key expression in
Section 10, the matter in issue is directly and substantially in issue in the
previously instituted suit is to be seen in the light of the tests for
applicability of Section 10 of the Code is whether on a final decision
being reached in the previously instituted suit, such decision would
operate as res judicata in the subsequent suit.
42. The second important test is whether parties to both the suits are same
and even if not same whether a party in the second suit is litigating
under the same title in the first suit, parties are litigating. This is to pin
down the plaintiff to one litigation so as to avoid the possibility of
conflict of judicial pronouncement by two Courts in respect of the same
or substantially same issue and to protect the defendant from
multiplicity of judicial proceeding.
43. On a close scrutiny of both the plaints and the reliefs claimed therein,
in the facts of this case, it appears to this Court that the subject-matter
of the previous suit is the built-up area measuring about 16389 sq. ft.
on the Third Floor of the property which was sold and conveyed in two
Lots – LOT-A and LOT-B under two separate deeds of conveyance dated
February 06, 2018 and March 09, 2018 by the plaintiff in favour of
the defendant no.2.
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
28
44. The subsequent plaint case in the previous suit filed by the plaintiff
against the defendant no.2 is that the open terrace and roof on the
Third Floor of the said property, which were never conveyed to
defendant no.2 The plaintiff had only sold, transferred and conveyed the
built-up area of Third Floor of the property to defendant no.2 excluding
the open area. The plaintiff has further contended that the defendant
no.2 has not paid the entire purchase price to the plaintiff, hence, by
operation of Section 55(4) (b) of the Transfer of Property Act, 1882, the
absolute right, title and interest had not been passed in favour of the
defendant no.2.
45. The specific case of the defendant no.4 in the application that it has
allegedly purchased 425.018 sq. ft. super built-up area from the
defendant no.2 on the Third Floor under an alleged conveyance dated
October 15, 2018. The defendant no.4 further has contended that the
defendant no.2 had conveyed the title in favour of the defendant no.4 on
the strength of the conveyance dated February 06, 2018 executed by the
plaintiff in favour of the defendant no.2.
46. On a plain, meaningful and comparative reading of both the plaints, this
Court finds that in the previous suit the plaintiff has, inter alia , sought
for correction of some portion of the conveyance with a declaration that
no right, title or interest was conveyed by the plaintiff in favour of the
defendant no.2 insofar open area is concerned. Plaintiff has further
contended that the transfer of title by the plaintiff in favour of the
defendant no.2 is not complete as the defendant no.2 has not paid the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
29
full consideration amount, hence, in the second suit the plaintiff has
claimed consequential reliefs against the defendant no.2 along with the
defendant nos.3 and 4, who claimed to be alleged purchasers under the
defendant no.2. Therefore, on a parallel reading of the two plaints and
the reliefs claimed thereunder, this Court is of the considered view that
the issues relating to defendant no.4 or 3 in the second suit is not an
issue or not substantially in issue with that of the previous suit. In any
event, if the previous suit is decreed, the decree cannot operate as res
judicata against the defendant nos.3 or 4, as they are not parties to the
previous suit. Therefore, an independent trial in the second suit is
required against the defendant nos.3 and 4.
47. Inasmuch as, admittedly, the defendant nos.3 and 4 claimed their
alleged right, title and interest in the property through the defendant
no.2. The defendant no.2 is party in both the suits. Since the defendant
no.2 is impleaded and present in the second suit, it cannot be
construed or held that the defendant nos.3 and 4 are litigating under
the same title with the alleged same title that of defendant no.2.
Defendant no.2 has filed its written statement and has been contesting
the suit with its own defense. Defendant nos.3 and 4 have not filed their
written statement in the second suit. On an overall assessment of the
facts and circumstances, this Court finds that neither the defendant
nos.3 and 4 can be construed to be litigating under the same title of the
defendant no.2 and moreover defendant nos.3 and 4 not being parties to
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
30
the previous suit are disqualified to maintain their respective
applications filed under Section 10 of the Code.
48. Inasmuch as the plea taken by the plaintiff that since the entire
payment has not been made by the defendant no. 2 in favour of the
plaintiff under the conditional conveyance, the portion of the property
sought to be conveyed in favour of the defendant no. 2 has not been
conveyed in favour of the defendant no. 2 by operation of Section
55(4)(b) of the Transferred of Property Act, as the title had not past, is
also required to be gone into during the trial of the first suit and on the
outcome of which the alleged right, title and interest of the defendant
nos. 4 and 3 would depend. If such plea of the plaintiff is decided in the
affirmative, then in absence of any title on the property in favour of the
defendant no. 2, claims of the defendant nos. 4 and 3 would be
rendered without any title on the property. Thus, until the title of the
defendant no. 2 is clearly adjudicated upon, it cannot be said that the
defendant nos. 4 or 3 are litigating on the same title of the defendant
no. 2. This Court is therefore of the considered view that when the
defendant no. 2 is a party in both the suits, the defendant nos. 4 or 3
would have no right to claim stay of the trial of the second suit. Moreso,
when they are not parties in the previous suit.
49. In the matter of: ASPI JAL (Supra) , the Hon’ble Supreme Court had
observed as under:-
“10. The view which we have taken finds support
from a decision of this Court in National Institute of
Mental Health & Neuro Sciences v. C. .Parameshwara,
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
31
in which it has been held as follows: (SCC pp. 259-6-,
para 8)
“ 8. The object underlying Section 10 is to prevent
courts of concurrent jurisdiction from simultaneously
trying two parallel suits in respect of the same matter
in issue. The object underlying Section 10 is to avoid
two parallel trials on the same issue by two courts
and to avoid recording of conflicting findings on
issues which are directly and substantially in issue in
previously instituted suit. The language of Section 10
suggests that it is referable to a suit instituted in the
civil court and it cannot apply to proceedings of other
nature instituted under any other statute. The object
of Section 10 is to prevent courts of concurrent
jurisdiction from simultaneously trying two parallel
suits between the same parties in respect of the same
matter in issue. The fundamental test to attract
Section 10 is, whether on final decision being reached
in the previous suit, such decision would operate as
res-judicata in the subsequent suit. Section 10 applies
only in cases where the whole of the subject-matter in
both the suits is identical. The key words in Section
10 are “the matter in issue is directly and
substantially in issue” in the previous instituted suit.
The words “directly and substantially in issue” are
used in contradistinction to the words “incidentally
or collaterally in issue”. Therefore, Section 10 would
apply only if there is identity of the matter in issue in
both the suits, meaning thereby, that the whole of the
subject- matter in both the proceedings is identical.”
11. In the present case, the parties in all the three
suits are one and the same and the court in which the
first two suits have been instituted is competent to
grant the relief claimed in the third suit. The only
question which invites our adjudication is as to
whether “the matter in issue is also directly and
substantially in issue in previously instituted suits”.
The key words in Section 10 are “the matter in issue
is directly and substantially in issue in the previously
instituted suit”. The test for applicability of Section
10 of the Code is whether on a final decision being
reached in the previously instituted suit, such
decision would operate as res-judicata in the
subsequent suit. To put it differently one may ask,
can the plaintiff get the same relief in the subsequent
suit, if the earlier suit has been dismissed? In our
opinion, if the answer is in affirmative, the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
32
subsequent suit is not fit to be stayed. However, we
hasten to add then when the matter in controversy is
the same, it is immaterial what further relief is
claimed in the subsequent suit.
12. As observed earlier, for application of Section 10
of the Code, the matter in issue in both the suits have
to be directly and substantially in issue in the
previous suit but the question is what “the matter in
issue” exactly means? As in the present case, many of
the matters in issue are common, including the issue
as to whether the plaintiffs are entitled to recovery of
possession of the suit premises, but for application of
Section 10 of the Code, the entire subject-matter of
the two suits must be the same. This provision will
not apply where few of the matters in issue are
common and will apply only when the entire subject
matter in controversy is same. In other words, the
matter in issue is not equivalent to any of the
questions in issue. As stated earlier, the eviction in
the third suit has been sought on the ground of non-
user for six months prior to the institution of that
suit. It has also been sought in the earlier two suits
on the same ground of non-user but for a different
period. Though the ground of eviction in the two suits
was similar, the same were based on different causes.
The plaintiffs may or may not be able to establish the
ground of non-user in the earlier two suits, but if they
establish the ground of non-user for a period of six
months prior to the institution of the third suit that
may entitle them the decree for eviction. Therefore, in
our opinion, the provisions of Section 10 of the Code
is not attracted in the facts and circumstances of the
case.”
50. In the matter of: Bepin Behari Majumdar and others (supra) , the
Hon’ble Division Bench of this Court had observed as under: -
“4. It is plain that if Section 10 is otherwise
applicable, its operation is not excluded by the fact
that the previously instituted suit has reached the
stage of an appeal. This is clear from the use of the
expression. “Before His Majesty in Council," and this
view was expressly adopted in the case of
Chinnakaruppan Chetty, A.L.M.S.S. v. M.V.M. Meyappa
Chetty where it was pointed out that proceedings on
appeal are for many purposes deemed only a
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
33
continuation of the suit instituted in the first Court,
Pichuvayyangar v. Seshayyngari and Kristnama
Chariar v. Mangammal Consequently, the mere fact
that the decree in the previously instituted suit is
under appeal in this Court, does not enable the
plaintiffs to invite us to hold that Section 10 is
inapplicable. The question, accordingly, reduces to
this; is the matter in issue in the subsequently
instituted suit for rent also directly and substantially
in issue in the previously instituted suit? The suits
are between the same parties litigating under the
same title and that requirement of the Code is
fulfilled. What, then, is the meaning of the expression
"the matter in issue." The defendants invite us to hold
that the expression is equivalent to "any of the
questions in issue." The obvious answer is that if that
had been the intention of the framers of the section,
appropriate words might have been used to bring out
such sense. We ore of opinion that the expression “the
matter in issue" has reference to the entire subject in
controversy between the parties.”
51. In the matter of: Adhish Chandra Sinha (supra) , the Hon’ble
Division Bench of this Court had observed as under: -
“5. But in our considered opinion, Section 10 of the
Code on its terms does not apply to the present case
in view of the subject-matter involved in the two suits.
The learned Subordinate Judge in directing stay
under Section 10 of the Code has taken the view that,
since one of the issues, which would arise for
consideration in both the suits, namely, whether the
notice dated January 16, 1978, to quit given by the
defendant is legal, valid and binding on the
defendant or not, the subsequent Alipore suit should
be stayed. We, therefore, find that the learned
Subordinate Judge made a grievous error in assuming
jurisdiction under Section 10 of the Code which he
had none to make such an order on a clear
misreading of the said provision of the Code. In order
to attract Section 10 of the Code the subject-matter in
issue in the subsequent suit must be directly and
substantially in issue in the previous suit. In that
way the subject-matter of two suits must be identical.
Merely because one of the questions in issue in the
same as in the other suit, would not make the subject-
matter identical. It was Sir Ashutosh Mookerjee who
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
34
pointed out in Bepin Behari V. Jogendra Chandra, AIR
1917 Cal 248, that ‘the matter in issue’ is not
equivalent to ‘any of the questions in issue’, it means
the entire subject-matter in controversy. This view has
been consistently followed by this Court vide
Narendra v. Rungta & Sons, 70 Cal WN 375: (AIR
1966 Cal 382), and Shaw Wallace v. Bholanath. AIR
1975 Cal 411 (The observation of Chakravarti, C.J. in
Shorab M. Modi v. Mansata Film Distributors, AIR
1957 Cal 727, being otherwise explanable as not
laying down any contrary view).”
52. In the matter of: Mahadevappa (supra) , the Co-ordinate Bench of this
Court had observed as under :-
“Mr. Coyajee on behalf of the appellant has not
disputed the proposition that the decree in a former
suit based on a compromise has to all intents and
purposes the same effect, so far as the rule of res
judicata is concerned, as a decree passed per invtium
(Bhaishankar Nanabhai v. Morarji Keshavji & Co.
(1911) I.L.R. 36 Bom. 283, S.C. 13 Bom. L.R. 950) The
question that arises under Section 11 of the Civil
Procedure Code is whether any matter directly and
substantially in issue of suit No. 50 of 1928 between
the parties litigating under the same title as in the
present suit, which was heard and finally decided in
that suit, is now again directly and substantially in
issue in the present suit. According to the learned
trial Judge such a matter is the question whether
defendant No. 2 had the power to adopt. In suit No.
50 of 1923 the plaintiff was the present defendant
No. 1, and defendants Nos. 1 and 2 in that suit are,
respectively, the plaintiff and defendant No. 2 in the
present suit. There is no doubt, therefore, that the
two suits were between the same parties. One
question that arises is whether these parties are
litigating under the same title. In suit No. 50 of 1928
Mahadevappa, i.e. defendant No. 1, claimed to have
been adopted as Somappa's son in 1927. In the
present suit he claims to have been adopted as
Somappa's son in 1935. It seems to me difficult to
say, therefore, that he is litigating under the same
title. The title that he has sought to make out in the
two suits has, according to him, been derived from
different transactions. Prima facie, therefore, his title
in each suit, though of the same nature in both, is
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
35
different. In Shidlingappa Maharudrappa v.
Ramappa, which I decided sitting singly, the facts
were somewhat similar to those in the present suit,
and I held that the parties there could not be said to
be litigating under the same title in the two
successive suits.”
53. In the matter of: Siba Prasad Jash (supra) , the Coordinate Bench of
this Court had observed as under :-
10. Question now is whether the matter in issue in
both the suits is directly and substantially the same
so as to satisfy one of the most essential
requirements of Section 10 of the Code. It is true that
the learned Chief Justice has said that the "fact that
one is a suit under the agreements entered into by the
parties and the other is a suit de hors the agreements
does not make a substantial identity of the subject-
matter per se impossible" in the case of Shorab
Merwanji Modi v. Mansata Film Distributors, (AIR
1957 Cal 727) (supra), at page 734 of the report, but
his Lordship has qualified his own statement by
using the expression "per se impossible." The question
as to whether the entire field of controversy in both
the suits is the same must be determined on the
construction of the pleadings in both the suits and,
therefore, no new principle has been laid down in
that case by the learned Chief Justice.
*
*
12. In our opinion, the expression "principal matter in
issue" used by the learn-ed Chief Justice and followed
by Mitra, J., should be read, understood and
construed in consonance with and subject to the
following statement of Sir Ashutosh Mookerjee in the
case of Bepin Behari v. Jogendra Chandra, reported
in 24 Cal LJ 514 at p. 515 = (AIR 1917 Cal 248 at p.
249) of the report:
"What then is the meaning of the expression 'the
matter in issue.' The defendants invite us to hold
that the expression is equivalent to 'any of the
questions in issue.' The obvious answer is that if
that had been the intention of the framers of the
section, appropriate words might have been used
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
36
to bring out such sense. We are of opinion that the
expression 'the matter in issue' has reference to the
entire subject in controversy between the parties.
The object of the section is to prevent courts of
concurrent jurisdiction from simultaneously trying
two parallel suits in respect of the same matters in
issue.”
13. One of the most essential conditions of Section 10
is that the matter in issue in the later suit which is
sought to be stayed must be directly and substantially
in issue in the earlier suit which is pending in the
same or in any other court of concurrent jurisdiction.
A mere identity of some of the issues in both the suits
is not sufficient to attract this section in view of the
law laid down by Sir Ashutosh Mookerjee. Unless the
decision of the suit operates as res judicata in the
other suit it cannot be said that the matter in issue is
"directly and substantially" the same in both the
suits. In other words, the decision in one suit must
non-suit the other suit before it can be said that the
matter in issue in both the suits is directly and
substantially the same.
*
*
15. It is well-settled that unless an issue is framed
and decided by the Court it cannot operate as res
judicata in a subsequent suit between the same
parties or their privies. It is true that the written
statement in the Ferrukhabad suit has raised some of
the questions which are also present in the plaint of
the Calcutta suit, but unless in both the suits the
entire subject-matter in controversy between the
parties are substantially and directly the same it
cannot be said that the matter in issue in both the
suits is the same. There being no issue in the
Ferrukhabad suit as to the terms and conditions of
the dealership agreement nor as to its breach, in my
opinion, it cannot be said that the matter in issue in
both the suits is substantially and directly the same.
Hence, the judgment under appeal cannot be
supported.”
54. In the matter of: Challapalli Sugar Ltd.(Supra), parties were
common and same subject-matter was involved in both the suits. In the
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
37
said judgment all the other judgment namely, AIR 1917 Cal 248, AIR
157 Cal and AIR 75 Cal 411 were considered. It was held that, the
subject-matter in controversy was the same which arose from the same
contract and same transaction, the ratio of the said judgment would not
apply in the facts of this case.
55. In the matter of: Abdul Gani and Anr. (supra), the case was based on
Section 11 of the Code i.e. res judicata in that case the plaintiffs in the
second suit where the defendants in the first suit. Therefore, parties
were common in both the suits, thus, the ratio of the judgment would
not apply in the facts of the instant case.
56. In view of the forgoing reasons and discussions, this Court is of the firm
and considered view that the defendant nos.4 or 3 are not qualified to
maintain an application under Section 10 of the Code. The
applicants/defendants firstly are not parties in the previous suit and
secondly, they cannot claim to be litigating under the same title of the
defendant no.2, who is a party in the previous suit. Both the
applications are, therefore, devoid of any merit and are not
maintainable.
57. The applicants/defendants have not filed their written statement. The
applications filed by them are not only devoid of any merit but also
frivolous, harassive and vexatious in nature and have been filed in
abuse of the process of law and this Court.
58. The pendency of these two applications have delayed the trial of the
suit.
IA No. GA-COM/9/2025 &
IA No. GA-COM/11/2026
IN CS-COM/297/2024
A.R.,J.
38
59. Considering the nature of the suits, it is directed that both the previous
and second suit henceforth shall be heard and considered in an
analogous trial.
60. Accordingly, both the applications being IA No. GA-COM/9/2025 and IA
No. GA-COM/11/2026 stand dismissed with cost assessed at
Rs.25,000/- each to be paid by the defendant nos.4 and 3 respectively
in favour of Calcutta High Legal Services Committee through a
banker's instrument within a period of six weeks from date.
61. Defendant nos.4 and 3 shall provide copies of the money receipt
showing payment of cost to the learned Advocate on record for the
plaintiff.
(Aniruddha Roy, J.)