Delhi Development Authority vs M/S Simplex Infrastructure Ltd
- Court
- Delhi High Court
$~11
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC011557572017
+ O.M.P. (COMM) 168/2017
DELHI DEVELOPMENT AUTHORITY .....Petitioner
Through: Mr. Vaibhav Agnihotri, ASC
with Mr. Vidit Pratap Singh, Mr.
Ankit Singh and Mrs. Suruchi
Khandelwal, Advocates.
versus
M/S SIMPLEX INFRASTRUCTURE LTD .....Respondent
Through: Mr. Rajesh Markanda,
Advocate.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT(ORAL)
% 14.08.2026
1. The present petition has been filed by the Petitioner under
1
Section 34 of the Arbitration and Conciliation Act, 1996 challenging
the arbitral award dated 14.10.2008 passed by the learned Sole
Arbitrator, Mr. N.L. Singh.
2. The dispute arises out of a contract for the design and
construction of a Road Over Bridge (ROB) at the level crossing on the
Delhi–Rewari railway line, including a half-trumpet interchange at the
intersection of Pankha Road and Station Road. The letter of award was
issued on 15.05.2002 with the stipulated date of completion 24.11.2003,
whereas the actual date of completion was 24.11.2005.
3. The dispute arose because the project, which was required to be
completed by 24.11.2003, was actually completed on 24.11.2005,
1
“Act” hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 1 of 16
resulting in a delay of about two years.
4. The present matter is a classic case of disputes relating to delayed
projects. The Respondent contends that the delay was caused largely by
hindrances attributable to petitioner and as a consequence, because of
the prolonged execution period, the respondent claimed additional
amounts whereas Petitioner disputes its liability for these amounts,
which ultimately led to the claims being referred to arbitration.
5. Claim No. 1, which was related to additional and extra works, the
arbitrator awarded Rs.26,83,385/- against a total claim of
Rs.97,37,791/-. The amounts awarded included compensation for
reconstruction of the labour colony, execution of additional pile lengths,
increase in the size of pile caps, protection of a Jal Board manhole and
expenditure arising from non-utilisation of certain tested materials.
6. Under Claim No. 2, the Respondent claimed Rs.2,53,42,734/-
towards expenditure incurred on maintaining manpower, machinery
and other resources during the extended period of the contract. The
Arbitrator concluded that the two-year delay in completion of the work
was not attributable to the respondent but mainly to the petitioner,
because delays arose from late approval of drawings, and non-
availability and delayed handing over of sites, shifting of utilities, and
other hindrances that were substantially admitted in the petitioner’ own
Hindrance Register and EOT records.
7. Using the Hudson Formula, the learned Sole Arbitrator awarded
Rs.1,79,01,487/- under claim no.2.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 2 of 16
8. Consequent upon the finding regarding prolongation, the
arbitrator awarded the full amounts claimed under Claim No. 3, which
is Rs.8,08,192/- towards additional expenditure incurred in renewing
bank guarantees and insurance policies during the extended period, and
under Claim No. 4, which amounted to Rs.12,45,370/- towards land rent
recovered during the extended stay at the site.
9. Under Claim No. 10, relating to increase in the price of steel
during the extended period, the contractor claimed approximately Rs.
2.05 crore. After considering the material concerning the increase in
steel prices and the purchase documents placed on record, the arbitrator
awarded Rs.1,44,93,703/-.
10. Under Claim No. 13, relating to escalation in the prices of other
construction materials such as cement, POL, sand, admixtures,
aggregates and allied materials during the extended period, the
Respondent claimed Rs.63,75,521.70/-. The arbitrator applied an
escalation assessment and awarded Rs.39,90,015/-.
11. Under Additional Claim No. 16.3, the Respondent sought
reimbursement of Rs.17,77,264/- deducted towards labour cess. The
Respondent contended that the cess liability was imposed after
submission of its tender and had therefore not been factored into the
bid. The arbitrator accepted the claim and awarded the entire amount of
Rs.17,77,264/-.
12. The learned Sole Arbitrator also awarded interest at 12% per
annum. In respect of most claims, interest was awarded from a date
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 3 of 16
corresponding to six months after completion of the work, whereas
interest on Claim No. 2 was awarded from the date of the award.
13. Briefly put, the award proceeded on the findings that several
items executed by the Respondent were compensable as additional
works, and that material portions of the contractual delay were
attributable to circumstances for which the petitioner was responsible.
The learned sole arbitrator, however, did not allow all claims in full and
reduced the amounts claimed under several heads.
14. The Petitioner has challenged the Award and the interpretation
of the contracts by learned sole arbitrator, wherein the delay was made
attributable to petitioner and the claims of the Respondents were
allowed to some extent.
15. Needless to state, the scope of judicial review under Section 34
of the Act is narrow and well settled. The Court does not sit as an
Appellate Court over an arbitral record and cannot reappreciate
evidence merely because other view may be possible.
16. In various decisions, the Supreme Court has reiterated that an
arbitral award is not liable to be interfered with merely because the
Court may prefer a different interpretation of the contract or a different
appreciation of the evidence.
17. Where the view taken by the Arbitrator is a plausible and
reasonably possible view based on the material before the Tribunal, it
is well settled that the Court must ordinarily defer to such view.
Interference is warranted only where the award falls under the limited
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 4 of 16
grounds prescribed under Section 34 of the Act, including patent
illegality, perversity or conflict with the public policy of India as
applicable to the present proceedings.
18. The claims raised in the present petition must therefore be
examined within these limited parameters.
19. The Petitioner has challenged a set of sub-claims forming part of
Claim No.1 as well as Claim Nos.2, 3, 4, 10, 13, 14 and additional
Claim No.16.3.
20. As far as this Claim No.1, sub-claim No.1. (reconstruction of
labour colony) is concerned, the Petitioner submits that under Clause
4.18 and 7.36.3 of the contract, the responsibility for providing land for
labour accommodation rested exclusively with the respondent.
21. It is contended that the labour huts were constructed on MCD
green belt line without prior approval of MCD and the Petitioner cannot
be held responsible for subsequent demolition carried out by the MCD.
22. The Respondent on the other hand submits that the huts were
constructed on land identified by the officers of the petitioner and that
the construction was permitted or at least accepted by the concerned
officer. It is also submitted that petitioner subsequently secured
permission in respect of the said land.
23. The Arbitrator held that the Petitioner were responsible for the
loss caused by demolition of the labour huts. Although the petitioner
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 5 of 16
argued that the contractor had constructed the huts without their
permission, the Arbitrator rejected this defence as an afterthought,
because the Respondent had informed the respondents in advance about
the construction, the respondents’ officers were present at the site, and
no objection was raised until after the huts were demolished by MCD.
24. The learned sole Arbitrator therefore found the claim for
reconstruction expenses justified. As per the learned arbitrator, since
the respondents had also not disputed the expenditure details when
originally submitted, those expenses were accepted, subject to
deduction of the salvage value of materials recovered from the
demolished huts. Thus, after adjusting the salvage value, the learned
Arbitrator awarded Rs.1,45,000/- to the respondent.
25. According to this court, the finding is essentially factual and is
based on the material considered by the Arbitrator. The Arbitrator relied
on the Respondent’s letter dated 20.06.2002 informing the Petitioner
about construction of the labour huts, and thus in the absence of any
contemporaneous objection, coupled with the presence of the
Petitioner’s officers at site, and the later permission to reconstruct the
huts at the same place, the arbitrator awarded the claim to Respondent.
26. The inference of tacit approval was at least a possible factual
view. The Petitioner has been unable demonstrate that the finding is
perverse, unsupported by evidence or otherwise vitiated by patent
illegality. Accordingly, no ground for interference under Section 34 of
the Act is made out.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 6 of 16
27. As far as sub-claims No.5 and 6, which are about additional pile
length and increase in pile cap size, the learned counsel for the
Petitioner relied upon Clause 7.36.1 and 7.8 and contends that the
contract was a lump sum design and construct contract. According to
the Petitioner, the GAD drawings were indicative and the contractor
was required to absorb any valuation in pile length or pile cap
dimension without additional financial implications.
28. On the contrary, the Respondent submits that additional piling
and modification of the design became necessary on the ground of
underground utilities which were not reflected in the available
drawings. The revised drawings were thereafter approved by the
Petitioner’s consultant. It is further submitted that the calculations
supporting the additional work remained unremitted before the
Arbitrator.
29. The learned Sole Arbitrator, being a technical expert, examined
the manner in which the work was executed and found that the
additional work had been carried out in accordance with the approved
revised drawings.
30. The question whether additional work was necessitated by
enforcing site condition and whether such work fell within or outside
the original contractual scope, involved an appreciation of the technical
material and contractual provisions. The Arbitrator’s assessment on
these matters cannot be displaced merely because the Petitioner seeks
to advance another interpretation of the contract.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 7 of 16
31. The view taken by the Arbitrator is a plausible view on the
material before him. No perversity or patent illegality has been
demonstrated. These awards therefore warrant no interference.
32. As far as Claim 1.11 regarding protection of manhole on Jal
Board’s sit is concerned, the Petitioner contends that under Clause 6.4
and 7.36.1, the Respondent was required to inspect the site and modify
its design and planning wherever necessary, to protect existing services
without claiming additional payments.
33. For this the Respondent submits that the manhole was located
within the alignment of the RE wall and had not been disclosed in the
tender drawings. The protection work was therefore additional work
necessitated during execution.
34. The learned Arbitrator considered the technical necessity of the
work and allowed the claim on the basis of an independent rate analysis.
35. The finding is based on technical evidence and material before
the Tribunal. The Petitioner has not shown that the finding is perverse
or that the arbitral award is beyond the contractual framework. The
learned arbitrator actually considered the relevant contractual
provisions and expressly held that they did not cover an undisclosed
manhole requiring special protection. The tribunal held that the
Respondent had notified the Petitioner and submitted drawings for such
protection, which work was in fact carried out and not denied.
36. Even if another interpretation of the clauses relied upon are taken,
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 8 of 16
the award would ordinarily not warrant interference as learned counsel
for the Petitioner has not pointed out that the Tribunal completely
ignored an express contractual prohibition covering even such
undisclosed manhole protection work. Needless to state, the view of
arbitrator is possible and therefore cannot be interfered with.
37. Claim 1.20 is about testing charges for material tested and found
suitable, the Petitioner relied upon Clause 7.30.3 and contends that cost
of all sampling and testing was to be borne by the Respondent
38. The Respondent submits that M-40 design mix was tested in
terms of the contractual requirements but the Petitioner subsequently
did not permit its use. The learned Arbitrator awarded reimbursement
on the basis that the testing expenditure had been incurred as required
but the benefit of the test was lost because the material was not
permitted to be used pursuant to Petitioner’s direction. Therefore, it
cannot be said that the learned arbitrator ignored any contractual
provision. The finding is made in the circumstances, that M-40 design
mix was not required at the site only.
39. Therefore, the finding is basically a factual determination based
on the circumstances that testing was undertaken. Accordingly, no
perversity or patent illegality has been established. The award under
this head is also therefore upheld.
40. Now coming to Claim No.2, which is about expenditure on
maintaining resources during the period of over-stay, the Petitioner
contends that the delay was attributable to the Respondent in efficient
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 9 of 16
planning, in adequate deployment of labour and use of old machinery.
It relied upon Clause 7.36.2 and 6.4.1(iii) and Annexure 4 of the
statement of defence to submit that no monetary compensation was
payable for delay arising from shifting of services or obtaining third-
party permissions and that the contractual remedies in such
circumstances were limited to extension of time.
41. The Petitioner further submits that Petitioner has levied
compensation of Rs.44,754/- under Clause 2 which was accepted by the
contractor.
42. Learned Counsel for the Respondent however relied upon
Petitioner’s own hindrance register and the recommendation
concerning EOT II, according to the Respondent these
contemporaneous records establish that the delay was caused inter alia
by non-availability of permissions from difference authority, delayed
approval of GAD drawings by Petitioner, delayed execution of railway
spans and belated sifting of utility lines.
43. The Respondent also relies upon audited vouchers and charted
accountant certificates to establish the expenditure actually incurred
during the extended period and submits that the lost was accessed on
principals underlying the Hudson Formulae.
44. The learned Arbitrator considered the contemporaneous records
including the hindrance register and the extension of time approvals and
concluded that DDA had failed to provide clear and unhindered site
access within the stipulated period resulting in prolongation of contract.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 10 of 16
45. The principal that an employer responsible for prolongation of a
contract may be liable for the resulting loss is well recognised in
2
Associate Builders v. Delhi Development Authority . The hon’ble
Supreme Court recognised that contractual provisions restricting
monetary claims for delay does not necessarily bar a claim for damages
arising from the employers’ own approach.
46. In the present case, the Arbitrator conclusion was based upon
contemporaneous records and the evidence before the Tribunal.
47. The assessment of the loan awarded involved a technical and
factual evaluation. The Petitioner could not establish that the conclusion
is perverse and based on merits.
48. The award in the Claim No. 2, therefore, does not warrant and
service under Section 34 of the Act.
Now, Claim No. 3, 4, 10, 13 and 14 renewal of Bank Guarantees /
insurance and land
49. The Petitioner submits that under Clause 7.4.3, 7.4.4 and 7.31.1,
the Respondent was required to maintain the Bank Guarantees and
insurance policies throughout the extended period at its own cost.
50. It is also submitted that the land rent for labour camps during the
period of road stay was recoverable under Clause 4.18.
2
(2015) 3 SCC 49
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 11 of 16
51. The submission of the Respondent against this was that the two
years prolongation was attributable to Petitioner’s breaches
52. These claims are consequential upon the findings recorded under
Claim No. 2, as once the learned Arbitrator concluded that the
prolongation was attributable to Petitioner, the additional expenditure
necessarily incurred in maintaining contractual securities, insurance,
labour and arrangements during the extended period was not capable of
being awarded as consequential loss.
53. The findings of the learned Arbitrator are neither perverse nor
contrary to the contractual claim, no ground for interference is therefore
made out.
Claim No. 10 & 13 (about increase in steel and construction
material prices)
54. The Petitioner submits that Clause 10 CC which provide for
escalation was expressly deleted by Corrigendum No. 3. It is, therefore,
contended that in the absence of an escalation Clause the Arbitrator
could not have awarded compensation for the increase in the market
price of steal and other construction materials.
55. The Respondent submits that there was an unprecedent increase
in the price of steal stated to be as high as 70%, as well as substantial
increase in the costs of basic construction material during the two years
period of prolongation.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 12 of 16
3
56. Reliance is placed upon P.M Paul v. Union of India to contend
that additional cost incurred during a period of prolongation attributable
to the employer may be recoverable as damages even in the absence of
an escalation Clause.
57. The learned Arbitration confined in the award that the price
increase is attributable to the extended period of the contract. The mere
deletion of the escalation Clause does not by itself exclude liability from
damages resulting from an employer’s breach where such breach causes
prolongation of the contract and demonstrable additional expenditure.
58. The learned Arbitrator conclusion based upon the material before
him and confined to the period of prolongation constitute a plausible
view, the Petitioner could not establish patent illegality or perversity
while entering interference under Section 34.
Additional Claim No. 16.3 (reduction on account of labour cess)
59. The Petitioner contends that labour cess became recoverable
w.e.f. 10.01.2002, pursuant to the NCT, Delhi notification dated
16.08.2005 and the Clause 38 of the Contract provides that the quoted
rates were inclusive of all taxes.
60. The Respondent submits that its bid was submitted on
26.11.2001, before the relevant notification and the operationalisation
of the labour.
3
AIR 1989 SC 1034
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 13 of 16
61. It is therefore, contended that the subsequently introduced
statutory levy could not have been factored into the tendered rates.
62. The learned Arbitrator accepted the Respondents’ contention and
held that a statutory levy introduced after submission of the bid, could
not reasonably have been incorporated into the rates quoted by the
Respondent
63. The fact that the bid was submitted on 26.11.2001 prior to the
relevant statutory change, support the learned Arbitrator’s conclusion.
At the very least, the view adopted by the learned Arbitrator is a
plausible view based on the contractual and statutory provisions.
64. The Petitioner could not establish that the finding is perverse or
suffers from patent illegality.
65. Thud, the award under this claim also warrants no interference.
Claim No. 14 (for interest)
66. The Petitioner submits that the contract contains no provision for
payment of interest @ 12% per annum awarded by the learned
Arbitrator is unacceptable.
67. For this, the submission of the Respondent was that the Arbitral
Tribunal poses statutory authority under Section 31(7) of the Act to
award interest subject to the terms of the contract.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 14 of 16
68. Clearly, Section 31.7 confers upon the Arbitral Tribunal, the
power to award interest in accordance with the statutory framework,
unless the agreement between the parties specially excludes or restricts
such power.
69. In the present case, the Arbitrator awarded interest @ 12% per
annum commencing six months after actual completion.
70. The award of interest in the present circumstances considered by
the Arbitrator cannot be said to be so unreasonable or excessive as to
warrant interference under Section 34.
71. The award of interest is accordingly upheld.
72. The Court has considered the grounds placed by the Petitioner
against each of the impugned heads of the award.
73. The principal challenge is in substance and invitation to this
Court to reappreciate the contractual provisions, the contemporaneous
records and the evidence considered by the learned Arbitrator.
74. Such re-appreciation is outside the limited scope of jurisdiction
under Section 34 of the Act. The Arbitrator has considered the
contractual clauses, correspondence hindrance registers, extension of
time records and other material placed before him.
75. The conclusions reached are supported by the material available
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:00:17
O.M.P. (COMM) 168/2017 Page 15 of 16
on record and represent views that are reasonably possible on the facts
and contractual framework.
76. Merely because another interpretation of the contract or another
assessment of the evidence specially does not permit a ground for
setting aside the award.
77. The learned Sole Arbitrator was a technical officer who has
rendered a reasoned award after considering technical provisions
contemporaneous correspondence, hindrance register and the evidence
placed before the Tribunal.
78. The Petitioner could not establish that the impugned award
suffers from patent illegality, perversity, violation of public policy or
another other ground recognised under Section 34.
79. No jurisdiction error or fundamental infirmity has been
demonstrated.
80. Consequently, no ground for interference to the arbitral award
dated 14.10.2008 is made.
81. The Petition under Section 34 is accordingly dismissed along
with all pending application.
OM PRAKASH SHUKLA, J