MRS. SAVITHRI ALIAS SAVITHRI G RAO vs THE SPECIAL LAND ACQUISITION OFFICER
- Court
- Karnataka High Court
- 1 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
ST
DATED THIS THE 21 DAY OF NOVEMBER, 2026
PRESENT
THE HON'BLE MRS. JUSTICE ANU SIVARAMAN
AND
THE HON'BLE MR. JUSTICE T.P.VIVEKANANDA
MISCELLANEOUS FIRST APPEAL NO. 4416 OF 2025 C/W
MISCELLANEOUS FIRST APPEAL NO. 7426 OF 2025(AA)
IN MFA NO. 4416/2025
BETWEEN:
NATIONAL HIGHWAY AUTHORITY OF INDIA
PROJECT IMPLEMENTATION UNIT
MANGALORE, DOOR NO.3-29
"BETHEL", THARETHOTA
NEAR PUMPWELL (NH-66)
MANGALORE-575 005
REP. BY ITS THE PROJECT DIRECTOR
...APPELLANT
(BY SRI: PRAKASHA ANGADI B V, ADVOCATE)
AND:
1. SMT. SAVITHRI
ALIAS SAVITHRI G. RAO
W/O M.R. GOPALAKRISHNA RAO
2. SRI. M.G. RAMACHANDRA
S/O M.R. GOPALAKRISHNA RAO
3. SMT. PRASEEDA R BHAT
D/O M.R. GOPALAKRISHNA RAO
RESPONDENT NOS.1 TO 3
ARE R/AT "ABHINANDANA"
SRI LAXMINARAYANA KRIPA COMPOUND
MUKKA, SURATHKAL
MANGALURU TALUK
Digitally signed
by PAVITHRA B
Location: HIGH
COURT OF
KARNATAKA
- 2 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
4.
THE ARBITRATOR AND
DEPUTY COMMISSIONER
D.K.DISTRICT
MANGALURU-575 001
5. THE SPECIAL LAND ACQUISITION OFFICER
AND COMPETENT AUTHORITY
NHAI, N.G.O.S BUILDING
MINI VIDHANA SOUDHA COMPOUND
MANGALURU-575 001
...RESPONDENTS
(BY SRI: SACHIN B S, ADVOCATE FOR R1 TO R3;
SRI: BYREGOWDA N, AGA FOR R4 & R5)
THIS MFA IS FILED U/S.37(1)(c) OF THE ARBITRATION
AND CONCILIATION ACT, 1996, AGAINST THE JUDGMENT
DT. 22.03.2025 PASSED IN A.P.NO. 35/2023 ON THE FILE
OF THE I ADDITIONAL DISTRICT AND SESSION JUDGE,
MANGALURU, DISMISSING THE ARBITRATION PETITION
FILED U/S 34 OF THE ARBITRATION AND CONCILIATION
ACT.
IN MFA NO. 7426/2025
BETWEEN:
1. SMT. SAVITHRI
ALIAS SAVITHRI G. RAO
W/O M.R. GOPALAKRISHNA RAO
AGED ABOUT 76 YEARS
2. MR. M.G. RAMACHANDRA
S/O LATE M.R. GOPALAKRISHNA RAO
AGED ABOUT 59 YEARS
APPELLANT NOS.1 AND 2 BOTH ARE
R/AT "ABHINANDANA"
SRI LAXMINARAYANA KRIPA COMPOUND
MUKKA, SURATHKAL
MANGALURU TALUK-574 144
3. MRS. PRASEEDA R BHAT ALIAS PRASEEDA RAO
W/O MR. H. RAGHAVENDRA RAO
- 3 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
AND D/O LATE M.R. GOPALAKRISHNA RAO
AGED ABOUT 57 YEARS
TH TH
R/AT 09, 9 CROSS, 8 C MAIN
SRI CHAKRA NAGAR
ANDRAHALLI, NEAR SRI PRASANNA
CHANDRASHEKARA ASHARAMA
BANGALORE NORTH-560 091
APPELLANTS NOS.(1) AND (3) ARE
REPRESENTED BY THEIR GPA HOLDER
APPELLANT NO.2
MR. M.G.RAMACHANDRA
...APPELLANTS
(BY SRI: SACHIN B S, ADVOCATE)
AND:
1. THE SPECIAL LAND ACQUISITION OFFICER
OFFICER AND COMPETENT AUTHORITY
NATIONAL HIGHWAYS
KUNDAPUR-SURATHKAL SECTION
NEAR MINI VIDHANA SOUDHA
OPP. TOWN HALL, HAMPANKATTA
MANGALORE-575 001
2. NATIONAL HIGHWAYS AUTHORITY OF INDIA
PROJECT IMPLEMENTATION UNIT
THARETHOTA, MANGALORE-575 002
REPRESENTED BY ITS PROJECT DIRECTOR
3. THE ARBITRATOR AND
DEPUTY COMMISSIONER
DAKSHINA KANNADA DISTRICT
NEAR HAMILTON CIRCLE
MANGALORE- 575 001
...RESPONDENTS
(BY SRI: BYREGOWDA N, AGA FOR R1 & R3;
SRI: PRAKASHA ANGADI, ADVOCATE FOR R2)
THIS MFA IS FILED U/S.37(1)(c) OF THE
ARBITRATION AND CONCILIATION ACT, 1996, AGAINST
THE ORDER DT. 22.03.2025 PASSED IN A.P.NO.20/2023
- 4 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
ON THE FILE OF THE I ADDITIONAL DISTRICT AND
SESSIONS JUDGE, MANGALURU, DISMISSING THE
ARBITRATION PETITION FILED U/S.34 OF THE
ARBITRATION AND CONCILIATION ACT.
THESE APPEALS, HAVING BEEN HEARD AND RESERVED
FOR JUDGMENT ON 24.09.2026 AND COMING ON FOR
PRONOUNCEMENT OF JUDGMENT THIS DAY,
T.P.VIVEKANANDA J., PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MRS. JUSTICE ANU SIVARAMAN
and
HON'BLE MR. JUSTICE T.P.VIVEKANANDA
CAV JUDGMENT
(PER: HON'BLE MR. JUSTICE T.P.VIVEKANANDA)
MFA.No.4416/2025 is filed by the National
Highway Authority of India challenging the award
dated 20.12.2022 passed by the Arbitrator and the Deputy
Commissioner, Dakshina Kannada District, in proceedings
No.C.DIS.ARB(2)NH.LAQ.CR-200/2019-20, so also the
judgment dated 22.03.2025 in AP.No.35/2023 passed by I
Additional District Judge and Commercial Court, Dakshina
Kannada, Mangaluru.
2. MFA.No.7426/2025 is filed by the land owners
challenging the judgment dated 22.03.2025 in AP
No.20/2023 and seeking for allowing of the said petition in
- 5 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
its entirety by enhancing the market value of the land in
question.
3. The brief facts leading to filing of the present
appeals are as follows. The parties are referred to as the
NHAI and land owners .
4. The lands measuring 20 square meters (0.49
cents) in Survey No.27/4B1 (garden land), 323.3 square
meters (7.99 cents) in Survey No.27/4B3 (garden land),
36.46 square meters (0.90 cents) in Survey No.27/9B2
(converted residential land) and 226.54 square meters
(5.60 cents) in Survey No.27/9B2 (wet land) of Surathkal
Village, Mangaluru Taluk, were notified for acquisition
through Preliminary Notification dated 08.09.2012 under
Section 3A(1) of the National Highways Act, 1956
(hereinafter referred to as “the Act” for short), which was
followed by the Final Notification dated 29.08.2013 issued
under Section 3D(1) of the Act.
5. It is stated that the respondent-landowners had
filed W.P.No.672/2014 along with other landowners
- 6 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
challenging the acquisition notifications on several
grounds. During the pendency of the said writ petition, the
Special Land Acquisition Officer, NHAI, passed an award
under Section 3G of the Act determining the market value
of the acquired garden land at Rs.43,262/- per cent in
respect of Survey Nos.27/4B1 and 27/4B3, converted
residential land at Rs.1,71,593/- per cent in respect of
Survey No.27/9B2 and wet land at Rs.19,426/- per cent in
respect of Survey No.27/9B2. Simultaneous with the
challenge to the acquisition proceedings, the respondents-
landowners had filed a petition under Section 3G(5) of the
Act before respondent No.3 seeking redetermination of
compensation for the acquired land. The said petition
having been allowed by order dated 20.12.2022 by
redetermination of the compensation at Rs.3,24,800/-in
respect of garden lands Rs.2,86,000/- per cent for
converted land and Rs.3,19,200/- for wet land.
6. To arrive at the aforesaid value, respondent
No.3 - Deputy Commissioner/Arbitrator has relied upon an
award dated 22.09.2011 concerning the land situated at
- 7 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
Surathkal Village. The other prayer of the landowners for
determination of market value at Rs.21,000/- per square
meter has been rejected by the learned Arbitrator holding
that in support of the said claim, no documentary evidence
has been placed on record. It was the observation of the
learned Arbitrator that for determination of the market
value of the land prevailing as on the date of issuance of
Section 3A(1)Notification and according to the learned
Arbitrator, the award passed on 22.09.2011 in respect of
an another extent of land in Surathkal Village could be the
guiding factor.
7. Before the learned Arbitrator, the landowners
have produced a copy of the sale deed dated 03.12.2012,
which was registered after three months from the date of
issuance of the Notification under Section 3A of the Act.
The learned Arbitrator had refused to consider the said
sale deed on the ground that the said sale deed was
executed and registered after the issuance of the
Preliminary Notification. Therefore, the same cannot be
- 8 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
considered for the purpose of determination of the market
value.
8. Aggrieved by the determination of market value
at Rs.3,24,800/- per cent for garden land in
Sy.Nos.27/4B1 and 27/4B3, Rs.2,86,000/- per cent for
converted residential land in Sy.No.27/9B2 and
Rs.3,19,200/- per cent for wet land in Sy.No.27/9B2,
NHAI had filed A.P.No.35/2023 before the I Additional
District Judge and Commercial Court, Dakshina Kannada,
Mangaluru. Similarly, being dissatisfied with the
determination of market value by the learned Arbitrator,
the landowners had filed A.P.No.20/2023 before the very
same Court.A.P.No.20/2023 filed by the landowners and
A.P.No.35/2023 filed by NHAI were dismissed on
22.03.2025, thereby confirming the award dated
20.12.2022 passed by the learned Arbitrator.
9. While dismissing the Arbitration Petitions filed
by the landowners, so also the NHAI, the District
Court/Commercial Court has held that the petitioners in
both the petitions have failed to make out a ground for
- 9 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
setting aside the award of the learned Arbitrator within the
parameters and the grounds enumerated in Section 34(2)
of the Arbitration and Conciliation Act, 1996. It is the
specific finding of the District Court that the petitioners in
both the petitions have failed to make out a ground for
setting aside the arbitral award.
10. There is a finding by the District Court in the
petition filed by the land owners that, since the subject
land was abutting the National Highway and the portion of
the land belongs to the petitioners have been acquired for
the purpose of expansion of National Highway, though two
items of the lands are agricultural lands, the potentiality
of the agricultural land for use of the same for non-
agricultural purposes cannot be ruled out. It is also the
observation of the District Court that the learned Arbitrator
was persuaded to re-determine the market value, since
the subject land is a garden land.
11. As stated supra, the NHAI as well as the
landowners are before this Court through the aforesaid
two separate appeals. The grounds urged in the appeal
- 10 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
filed by the NHAI are that the landowners are entitled for
the market value, which was prevailing on the date of
issuance of the Preliminary Notification. However, the
learned Arbitrator has not considered the market value of
the land as on the date of Preliminary Notification.
Therefore, the award suffers from the patent illegality. The
claim of the landowners for redetermination of
compensation could not have been considered by the
learned Arbitrator. It is his further submission that in view
of the pendency of W.P.No.672/2014, the possession of
the notified land was never handed over/surrendered by
the landowners to the National Highway Authority.
Therefore, even if this Court were to confirm the award of
the learned Arbitrator, so also the judgment of the District
Court, the landowners cannot be made entitled for
payment of interest on the market value in terms of
Section 3H(5) of the NHAI Act. The appeal filed by the
landowners is with the delay 74 days.
12. Learned counsel for the NHAI has brought to
our notice that the landowners have filed
- 11 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
W.P.No.672/2014, whereby the acquisition proceedings
itself were challenged. When that being the position, the
reasons assigned for delay of 74 days do not constitute
sufficient reason. Therefore, the application for
condonation of delay is liable to be rejected.
13. Learned counsel for the landowners has relied
upon the judgment of the Hon’ble Supreme Court in the
case of Suresh Kumar Vs. State of Haryana and
1
Others to persuade this Court to condone the delay on
the ground that in the cases relating to acquisition of land
and grant of compensation liberal approach to be adopted
while considering the application for condonation of delay.
The said judgment was rendered in the context of
acquisition of land under the Land Acquisition Act, 1894
and therefore, the same cannot be made applicable to the
facts of the present case.
14. Learned counsel has further relied upon the
judgment of the High Court of Kerala in the case of
National Highways Authority of India Vs.
1
2025 Supreme (SC) 695
- 12 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
2
P.V.George and contend that the National Highways Act
does not prescribe a limitation period for arbitration and
therefore, the Limitation Act does not apply. The said
judgment is rendered in the context of filing a petition
before the learned Arbitrator and not while considering an
appeal under Section 37 of the Arbitration and Conciliation
Act, 1996. The facts involved in the judgment relied upon
by the learned counsel for the landowners is not applicable
to the facts of the present case.
15. The learned counsel for the appellant in
MFA.No.7426/2025, that is, the appeal filed by the
landowners, has advanced the contention that a sale
exemplar subsequent to the issuance of the preliminary
notification could also be considered if the date of sale is
within close proximity to the date of issuance of the
preliminary notification. In support of the said contention,
reliance is placed on the judgment of the Hon'ble Apex
Court in the case of Chimanlal Hargovinddas v. Special
2
2024 Supreme (Ker) 733
- 13 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
3
Land Acquisition Officer, Poona , reported in, and also
on other judgments laying down the very same
proposition. It is the submission of the learned counsel
that the sale deed dated 03.12.2012, which was registered
within three months of issuance of the preliminary
notification, discloses a sale consideration of Rs.14,964/-
per square metre and that the said value ought to have
been considered by the learned Arbitrator.
16. The aforesaid contention deserves to be
rejected for the reason that the purchaser of the property
under the sale deed referred to supra is one Sri
Sadananda A.V., and the land purchased by him under the
said sale deed was also notified for acquisition in the very
same preliminary notification. The said purchaser has also
approached the learned Arbitrator for redetermination of
compensation. The learned Arbitrator had rejected the
claim of Sri Sadananda A.V. for redetermination of
compensation, taking note of the sale consideration shown
in the sale deed dated 03.12.2012. From the above, it is
3
(1988) 3 SCC 751
- 14 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
discernible that, knowing fully well that the land was
notified under the preliminary notification, Sri Sadananda
A.V. had purchased the land at a higher value, probably
with a view to claim compensation at the same rate as the
sale consideration reflected in the registered instrument
multiplied by applicable factor under 2013 Act. This
transaction of sale under the sale deed dated 03.12.2012,
entered into by a person whose land was itself notified for
acquisition, cannot be considered a bona fide transaction
so as to place reliance on the registered sale deed for the
purpose of redetermination of market value in respect of
all the lands covered under the preliminary notification in
question.
17. It is not in dispute that the present proceedings
rose out of the proceedings under Section 37 of the
Arbitration and Conciliation Act, 1996, challenging the
judgment passed by the Commercial Court in the
proceedings under Section 34 of the Arbitration and
Conciliation Act, 1996. Though, the appeal filed by the
NHAI and landowners are classified as miscellaneous first
- 15 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
appeals, however, in effect the appeals are not only under
Section 37(1)(c) of the Arbitration and Conciliation Act,
1996, it is also under Section 13(1A) of the Commercial
Courts Act, 2015. Therefore, law of limitation in respect of
the appeals filed under the provisions of the Commercial
Courts Act is equally applicable in respect of the present
appeals. The Hon'ble Supreme Court in the cases of
Government of Maharashtra (Water Resources
Department) Vs. Borse Brothers Engineers and
4
Contractors Private Limited has clearly held that
sufficient cause for condonation of delay must be assessed
in the context of the statutory object of speedy resolution
of disputes. The Hon'ble Supreme Court held the
following:-
"58. Given the object sought to be achieved
under both the Arbitration Act and the Commercial
Courts Act, that is, the speedy resolution of
disputes, the expression “sufficient cause” is not
elastic enough to cover long delays beyond the
period provided by the appeal provision itself.
Besides, the expression “sufficient cause” is not
itself a loose panacea for the ill of pressing
negligent and stale claims. This Court, in Basawaraj
v. LAO , has held : (SCC pp. 85-88, paras 9-15)
4
(2021) 6 SCC 460
- 16 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
“9. Sufficient cause is the cause for which the
defendant could not be blamed for his absence. The
meaning of the word “sufficient” is “adequate” or
“enough”, inasmuch as may be necessary to
answer the purpose intended. Therefore, the word
“sufficient” embraces no more than that which
provides a platitude, which when the act done
suffices to accomplish the purpose intended in the
facts and circumstances existing in a case, duly
examined from the viewpoint of a reasonable
standard of a cautious man. In this context,
“sufficient cause” means that the party should not
have acted in a negligent manner or there was a
want of bona fide on its part in view of the facts
and circumstances of a case or it cannot be alleged
that the party has “not acted diligently” or
“remained inactive”. However, the facts and
circumstances of each case must afford sufficient
ground to enable the court concerned to exercise
discretion for the reason that whenever the court
exercises discretion, it has to be exercised
judiciously. The applicant must satisfy the court
that he was prevented by any “sufficient cause”
from prosecuting his case, and unless a satisfactory
explanation is furnished, the court should not allow
the application for condonation of delay. The court
has to examine whether the mistake is bona fide or
was merely a device to cover an ulterior purpose.
10. In Arjun Singh v. Mohindra Kumar this
Court explained the difference between a “good
cause” and a “sufficient cause” and observed that
every “sufficient cause” is a good cause and vice
versa. However, if any difference exists it can only
be that the requirement of good cause is complied
with on a lesser degree of proof than that of
“sufficient cause”.
11. The expression “sufficient cause” should
be given a liberal interpretation to ensure that
substantial justice is done, but only so long as
negligence, inaction or lack of bona fides cannot be
imputed to the party concerned, whether or not
sufficient cause has been furnished, can be decided
- 17 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
on the facts of a particular case and no straitjacket
formula is possible.
12. It is a settled legal proposition that law of
limitation may harshly affect a particular party but
it has to be applied with all its rigour when the
statute so prescribes. The court has no power to
extend the period of limitation on equitable
grounds. ‘A result flowing from a statutory provision
is never an evil. A court has no power to ignore that
provision to relieve what it considers a distress
resulting from its operation.’ The statutory
provision may cause hardship or inconvenience to a
particular party but the court has no choice but to
enforce it giving full effect to the same. The legal
maxim dura lex sed lex which means “the law is
hard but it is the law”, stands attracted in such a
situation. It has consistently been held that,
“inconvenience is not” a decisive factor to be
considered while interpreting a statute.
13. The statute of limitation is founded on
public policy, its aim being to secure peace in the
community, to suppress fraud and perjury, to
quicken diligence and to prevent oppression. It
seeks to bury all acts of the past which have not
been agitated unexplainably and have from lapse of
time become stale. According to Halsbury's Laws of
England, Vol. 28, Para 605 p. 266:
‘605. Policy of the Limitation Acts.—The
courts have expressed at least three differing
reasonssupporting the existence of statutes of
limitation, namely, (1) that long dormant claims
have more of cruelty than justice in them, (2) that
a defendant might have lost the evidence to
disprove a stale claim, and (3) that persons with
good causes of actions should pursue them with
reasonable diligence.’
An unlimited limitation would lead to a sense
of insecurity and uncertainty, and therefore,
limitation prevents disturbance or deprivation of
what may have been acquired in equity and justice
- 18 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
by long enjoyment or what may have been lost by a
party's own inaction, negligence or laches.
14. In P. Ramachandra Rao v. State of
Karnataka this Court held that judicially engrafting
principles of limitation amounts to legislating and
would fly in the face of law laid down by the
Constitution Bench in Abdul Rehman Antulay v. R.S.
Nayak .
15. The law on the issue can be summarised
to the effect that where a case has been presented
in the court beyond limitation, the applicant has to
explain the court as to what was the “sufficient
cause” which means an adequate and enough
reason which prevented him to approach the court
within limitation. In case a party is found to be
negligent, or for want of bona fide on his part in the
facts and circumstances of the case, or found to
have not acted diligently or remained inactive,
there cannot be a justified ground to condone the
delay. No court could be justified in condoning such
an inordinate delay by imposing any condition
whatsoever. The application is to be decided only
within the parameters laid down by this Court in
regard to the condonation of delay. In case there
was no sufficient cause to prevent a litigant to
approach the court on time condoning the delay
without any justification, putting any condition
whatsoever, amounts to passing an order in
violation of the statutory provisions and it
tantamounts to showing utter disregard to the
legislature.”
xxxxx
63. Given the aforesaid and the object of
speedy disposal sought to be achieved both under
the Arbitration Act and the Commercial Courts Act,
for appeals filed under Section 37 of the Arbitration
Act that are governed by Articles 116 and 117 of
the Limitation Act or Section 13(1-A) of the
Commercial Courts Act, a delay beyond 90 days, 30
days or 60 days, respectively, is to be condoned by
- 19 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
way of exception and not by way of rule. In a fit
case in which a party has otherwise acted bona fide
and not in a negligent manner, a short delay
beyond such period can, in the discretion of the
court, be condoned, always bearing in mind that
the other side of the picture is that the opposite
party may have acquired both in equity and justice,
what may now be lost by the first party's inaction,
negligence or laches."
18. In the case of State of Uttar Pradesh Vs.
5
Satish Chand Shivhare and Brothers , the Hon'ble
Supreme Court declined to interfere with the dismissal of
an appeal under Section 37 where sufficient cause had not
been shown. It was held that the right of appeal is subject
to limitation and that a liberal approach requires a
plausible explanation for the delay.
19. In the light of the aforesaid enunciation of law
by the Hon'ble Supreme Court, we do not find it
appropriate to condone the long delay of 74 days in filing
the appeal by the landowners.
20. Insofar as the appeal filed by the NHAI is
concerned, the District Court has come to a categorical
conclusion that the NHAI has not made out any ground for
5
2022 SCC ONLINE SC 2151
- 20 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
setting aside the arbitral award within the parameters of
Section 34(2) of the Arbitration and Conciliation Act, 1996.
If the District Court while exercising the power under
Section 34(2)of the Arbitration and Conciliation Act, 1996,
has held that no grounds are made out for setting aside
the arbitral award, this Court while considering an appeal
under Section 37 of the Arbitration and Conciliation Act,
1996, is not in a position to take a different view than that
of the view taken by the District Court under Section 34 of
the Arbitration and Conciliation Act, 1996. The grounds
urged by the NHAI in the memorandum appeal, so also the
arguments advanced would not in any way make out a
ground for interference of the arbitral award as confirmed
by the District Court.
21. The scope of interference of this Court in an
appeal under Section 37 of the Arbitration Act has been
categorically laid down by the Apex Court MMTC Ltd. v.
Vedanta Ltd. reported in (2019) 4 SCC 163. The Apex
Court held as follows:-
- 21 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
"11. As far as Section 34 is concerned, the
position is well-settled by now that the Court does
not sit in appeal over the arbitral award and may
interfere on merits on the limited ground provided
under Section 34(2)(b)(ii) i.e. if the award is
against the public policy of India. As per the legal
position clarified through decisions of this Court
prior to the amendments to the 1996 Act in 2015, a
violation of Indian public policy, in turn, includes a
violation of the fundamental policy of Indian law, a
violation of the interest of India, conflict with justice
or morality, and the existence of patent illegality in
the arbitral award. Additionally, the concept of the
“fundamental policy of Indian law” would cover
compliance with statutes and judicial precedents,
adopting a judicial approach, compliance with the
principles of natural justice, and Wednesbury
reasonableness. Furthermore, “patent illegality”
itself has been held to mean contravention of the
substantive law of India, contravention of the 1996
Act, and contravention of the terms of the contract.
12. It is only if one of these conditions is
met that the Court may interfere with an arbitral
award in terms of Section 34(2)(b)(ii), but such
interference does not entail a review of the merits
of the dispute, and is limited to situations where
the findings of the arbitrator are arbitrary,
capricious or perverse, or when the conscience of
the Court is shocked, or when the illegality is not
trivial but goes to the root of the matter. An arbitral
award may not be interfered with if the view taken
by the arbitrator is a possible view based on facts.
14. As far as interference with an order
made under Section 34, as per Section 37, is
concerned, it cannot be disputed that such
interference under Section 37 cannot travel beyond
the restrictions laid down under Section 34. In
other words, the court cannot undertake an
independent assessment of the merits of the award,
and must only ascertain that the exercise of power
by the court under Section 34 has not exceeded the
scope of the provision. Thus, it is evident that in
case an arbitral award has been confirmed by the
- 22 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
court under Section 34 and by the court in an
appeal under Section 37, this Court must be
extremely cautious and slow to disturb such
concurrent findings."
22. These principles were reaffirmed in Konkan
6
Railway Corpn. Ltd. v. Chenab Bridge Project
reported in, wherein the Apex Court held that the
jurisdiction of the court under Section 37 of the Arbitration
Act is akin to its jurisdiction under Section 34 of the
Arbitration Act, and that the scope of interference in an
appeal under Section 37 of the Arbitration Act, while
examining an order setting aside or refusing to set aside
an award, is restricted to and subject to the same grounds
as a challenge under Section 34 the Arbitration Act. It was
also held that the jurisdiction under Sections 34 and 37
the Arbitration Act is not in the nature of normal appellate
jurisdiction.
23. The narrow jurisdiction under Section 37 of the
Arbitration Act was also laid down in UHL Power
7
Company Ltd. v. State of Himachal Pradesh reported
6
(2023) 9 SCC 85
7
(2022) 4 SCC 116
- 23 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
in. This line of reasoning was further affirmed in Larsen
Air Conditioning & Refrigeration Co. v. Union of
8
India , wherein the Apex Court held that the jurisdiction
of the court under Section 34 of the Arbitration Act is
limited and extremely circumscribed, permitting
interference only on the ground of patent illegality which
goes to the root of the matter and is not of a trivial nature.
24. The Apex Court in Punjab State Civil
Suppliers Corporation Limited and Another v. M/s
9
Sanman Rice Mills and Others , held that an Arbitral
Award is not liable to be interfered with only on the ground
that the award is illegal or is erroneous in law, that too
upon reappraisal of the evidence adduced before the
arbitral trial. Even an award which may not be reasonable
or is non-speaking to some extent cannot ordinarily be
interfered with by the Courts. It is also well settled that
even if two views are possible, there is no scope for the
Court to reappraise the evidence and to take the different
view other than what has been taken by the arbitrator.
8
(2023) 15 SCC 472
9
2024 INSC 742
- 24 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
25. Further, in Somdatt Builders-NCC-NEC(JV)
10
v. National Highways Authority of India and Ors . ,
the Apex Court after considering the case law on the point,
held as under: -
"42. As already discussed above, the Arbitral
Tribunal had interpreted Clause 51 in a reasonable
manner based on the evidence on record. This
interpretation was affirmed by the learned Single
Judge exercising jurisdiction under Section 34 of
the 1996 Act. Therefore, Division Bench of the High
Court was not at all justified in setting aside the
arbitral award exercising extremely limited
jurisdiction under Section 37 of the 1996 Act by
merely using expressions like ‘opposed to the public
policy of India’, ‘patent illegality’ and ‘shocking the
conscience of the court’. As reiterated by this Court
in Reliance Infrastructure Ltd. (supra), it is
necessary to remind the courts that a great deal of
restraint is required to be shown while examining
the validity of an arbitral award when such an
award has been upheld, wholly or substantially,
under Section 34 of the 1996 Act. Frequent
interference with arbitral awards would defeat the
very purpose of the 1996 Act."
26. It is also a fact that the subject land is abutting
and facing the National Highway. Therefore, the
determination of the market value by the learned
Arbitrator based on an award passed in the year 2011 in
respect of another extent of land in the very same village
cannot be found fault with. It is now well established that
10
2025 INSC 113
- 25 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
there cannot be different yardstick for determination of the
market value in respect of the lands situated in the very
same village.
27. In addition to the above, before the learned
Arbitrator except for the oral statement and the statement
made in the petition that the subject lands are situated
very near to the National Highway and within the limits of
Mangaluru City Corporation and are located within the
vicinity of several Engineering Colleges and Hospitals, no
other material evidence was placed before the learned
Arbitrator.
28. In the result:
(i) MFA.No.4416/2025 filed by the NHAI and
MFA.No.7426/2025 filed by the landowners are
dismissed .
(ii) It is clarified that the entitlement of interest at
9% per annum on the compensation
redetermined by the learned Arbitrator/Deputy
Commissioner would be only from the date on
- 26 -
MFA No.4416 of 2025
C/W MFA No.7426 of 2025
which the landowners surrenders/handover the
acquired land in favour of the NHAI in terms of
Section 3H(5) of the National Highways Act,
1956.
(iii) The aforesaid observation is made in view of
the contention urged by the learned counsel for
NHAI that in view of pendency of
W.P.No.672/2014, which was disposed of on
08.06.2026, the landowners have not either
surrendered or handed over possession to the
NHAI and NHAI could not carry out any
developmental work in the subject lands.
Sd/-
(ANU SIVARAMAN)
JUDGE
Sd/-
(T.P.VIVEKANANDA)
JUDGE
PB