KULDEEP THAKUR AND OTHERS vs THE STATE OF HP AND OTHERS

Court
High Court of Himachal Pradesh

High Court of H.P.
2026:HHC:41820
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
CWP No. 7206 of 2026
Reserved on : 08.09.2026
Decided on: 29.09 .2026
Uploaded on: 29.09.2026
Kuldeep Thakur and others …….Petitioners
Versus
State of Himachal Pradesh and others … Respondents
Coram
Hon’ble Mr. Justice Ajay Mohan Goel, Judge
Hon’ble Mr. Justice Yogesh Jaswal, Judge
1
Whether approved for reporting? Yes
_____________________________________________________
For the petitioners : Mr. Dinesh Kumar Thakur, Advocate.
For the respondents : Mr. Ramakant Sharma, Additional
Advocate General for respondents No.
1 to 4.
: Mr. Narender Singh Thakur, Advocate
for respondent No. 5.
Ajay Mohan Goel, Judge
By way of this writ petition, the petitioners have inter
alia prayed for the following reliefs:-
“i) That a writ of mandamus may kindly be issued by
quashing and setting aside Annexure P-1, P-3, P-4 and P-5
as the same has been deemed to be rescinded by section 19
(7) of the act as the Notification has been issued without
assigning written reasons.
1
Whether reporters of the local papers may be allowed to see the judgment?


::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
2
ii) That the respondents may be directed to prepare and
enact the resettlement and rehabilitation plan as per the
mandate of the act qua the petitioners.
iii) That the respondent may be directed to pay damages to
the petitioners as they have restrained from developing the
land.
iv) In the alternative, issue a writ of mandamus directing the
respondents to complete the acquisition proceedings within a
time-bound period in accordance with law, including
issuance of declaration and payment of compensation;
v) In the event the respondents fail to complete the
acquisition within the time stipulated by this Hon'ble Court,
the land of the petitioners be released from acquisition and
the petitioners be permitted to use and enjoy the same
without any restriction.”
2. The issue raised in the present petition is in a very
narrow compass. The petitioners are the residents of villages Upperli
Bhater, Barmana and Khater, Post Office Barmana, Tehsil Sadar,
District Bilaspur. In terms of the averments made in the writ
petition, they claim to be agrarian by profession and their livelihood
is dependent upon agriculture. According to the petitioners, the
agricultural land of the petitioners along with the land of co-
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
3
villagers, on which their houses are also situated, is being acquired
for the construction of Bhanupali-Bilaspur-Beri Broad-Gauge
Railway Line. Their grievance is that their legal rights are being
infringed without following the mandate of Section 19(7) of the
provisions of the Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013
(hereinafter to be referred as ‘the 2013 Act’). They contend that as
per the provisions of Section 19 of the 2013 Act, when the
appropriate Government is satisfied, after considering the report, if
any, made under sub-section (2) of Section 15 of the Act, that any
particular land is needed for a public purpose, a declaration has to
be made to that effect, along with a declaration of an area identified
as “resettlement area” for the purposes of rehabilitation and
resettlement of the affected families, under the hand and seal of a
Secretary to such Government or of any other officer duly authorised
to certify its orders and different declarations may be made from
time to time in respect of different parcels of any land covered by the
same preliminary notification, irrespective of whether one report or
different reports has or have been made wherever required. They
submit that, further as per Section 19, the Collector has to publish a
summary of the Rehabilitation and Resettlement Scheme along with
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
4
declaration referred to sub-section (1). They state that as per sub-
section (7) of Section 19, where no declaration is made under sub-
section (1) within 12 months from the date of preliminary
notification, such notification shall be deemed to have been
rescinded, provided that in computing the period referred to in sub-
section (7), any period or periods during which the proceedings for
the acquisition of any land were held up on account of any stay or
injunction by the order of any Court shall be excluded. Further, as
per the petitioners, as per the second proviso to sub-section (7), the
appropriate Government shall have the power to extend the period of
12 months, if in its opinion, circumstances exist justifying the same
and as per the third proviso to said section, any such decision to
extend the period shall be recorded in writing and the same shall be
notified and be uploaded on the website of the authority concerned.
3. Learned Counsel for the petitioners argued that in the
present case, the preliminary notification was issued under the
provisions of Section 11 of the 2013 Act for acquisition of 538-13-05
bighas (40.54 hectares) of land in terms of Annexure P-1 dated
29.03.2023. However, no declaration, as is required to be made
under sub-section (1) of Section 19 of the Act, was made within a
period of 12 months. Learned Counsel referred to Annexure P-3,
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
5
Notification dated 16.03.2024, Annexure P-4, Notification dated
24.03.2025, and Annexure P-5, which is a copy of notification dated
25.03.2026. By referring to these three notifications, learned
Counsel argued that, in terms thereof, the respondents extended the
period for issuing notification or declaration in terms of sub-section
(1) of Section 19 by invoking the provisions of sub-section (7) of
Section 19 of the 2013 Act on three occasions. Yet till date, no
declaration has been made as per Section 19(1) of the 2013 Act.
Learned Counsel further argued that even the extension in terms of
Annexure P-3 to P-5 are no extensions in the eyes of law because the
provisos to sub-section (7) of Section 19 of the 2013 Act clearly lay
down that what is required in law is that, where the necessary
declaration under sub-section (1) of Section 19 could not be made
within 12 months by the Authority concerned, the decision to extend
the period has to be recorded in writing and notified and the same
has to be uploaded on the website of the Authority concerned. He
argued that Annexure P-3 to P-5 are non-speaking notifications, as
they do not spell out reasons recorded in writing as to why the
extension beyond the period of 12 months was being required for the
issuance of declaration, which was a condition precedent while
exercising the right of extending the period to make a declaration.
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
6
Accordingly, he argued that as no declaration was made by the
Authority concerned after the issuance of Annexure P-1 within 12
months and as the extensions made by the Authority concerned
were not in consonance with the provisions of sub-rule (7) of Section
19 of the 2013 Act and provisos thereto, the present writ petition be
allowed by quashing Annexures P1 and P-3 to P-5.
4. On the other hand, learned Additional Advocate General
and learned Counsel for respondent No. 5 submitted that the factum
of no declaration having been made within 12 months from the date
of issuance of Notification, as is the requirement of sub-section (1) of
Section 19 of the 2013 Act, after the issuance of notification
Annexure P-1, is a matter of record. However, they argued that as
the Government exercised its power of extending the period and the
reason why the period was being extended is clearly mentioned in
Annexure P-3 to P-5, the present writ petition is without any merit
and is liable to be dismissed. No other point was urged on behalf of
the respondents.
5. When this case was heard on 01.09.2026, this Court
had passed the following order:-
“Compliance affidavit in terms of the previous order stands filed.
The main issue, which this Court has to decide in the present case
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
7
is whether the decision to extend the 12 months period within
which a declaration has to be made as from the date of the
issuance of preliminary notification can be extended by the
appropriate Government without adhering to the 3rd Proviso to
Section 19(7) of the Right to Fair Compensation Transparency in
Land Acquisition Rehabilitation and Resettlement Act, 2013 in letter
and spirit, that is to say whether the appropriate Government can
extend the period without recording in writing the actual reasons in
some reasonable detail as to why the declaration could not be made
within 12 months or an extension made by the appropriate
Government by simply stating in the notification that declaration
could not be made due to “certain unavoidable administrative
circumstances, suffices the purpose.
Heard for some time. List for continuation on 08.09.2026, as
prayed for.”
6. When the matter was heard thereafter on the request of
this Court, learned Additional Advocate General made available for
the perusal of the Court the record of the case, in terms whereof, the
notifications extending the period of making declaration were issued
and a perusal of the same demonstrated that no reasons indeed
were recorded in the official records also as to why the declarations
were not made within a period of 12 months, as is the requirement
of the third proviso to Section 19(7) of the 2013 Act. This fact was
candidly admitted on behalf of the respondents.
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
8
. Section 19 of the 2013 Act reads as under:
“ 19. Publication of declaration and summary of
Rehabilitation and Resettlement .–(1) When the appropriate
Government is satisfied, after considering the report, if any, made
under sub-section (2) of section 15, that any particular land is
needed for a public purpose, a declaration shall be made to that
effect, along with a declaration of an area identified as the
“resettlement area” for the purposes of rehabilitation and
resettlement of the affected families, under the hand and seal of a
Secretary to such Government or of any other officer duly authorised
to certify its orders and different declarations may be made from
time to time in respect of different parcels of any land covered by the
same preliminary notification irrespective of whether one report or
different reports has or have been made (wherever required).
(2) The Collector shall publish a summary of the Rehabilitation
and Resettlement Scheme along with declaration referred to in sub-
section (1):
Provided that no declaration under this sub-section shall be
made unless the summary of the Rehabilitation and Resettlement
Scheme is published along with such declaration:
Provided further that no declaration under this sub-section
shall be made unless the Requiring Body deposits an amount, in full
or part, as may be prescribed by the appropriate Government
toward the cost of acquisition of the land:
Provided also that the Requiring Body shall deposit the
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
9
amount promptly so as to enable the appropriate Government to
publish the declaration within a period of twelve months from the
date of the publication of preliminary notification under section 11.
(3) In projects where land is acquired in stages, the application for
acquisition itself can specify different stages for the rehabilitation
and resettlement, and all declarations shall be made according to
the stages so specified.
(4) Every declaration referred to in sub-section (1) shall be
published in the following manner, namely:—
(a) in the Official Gazette;
(b) in two daily newspapers being circulated in the locality, of
such area of which one shall be in the regional language;
(c) in the local language in the Panchayat, Municipality or
Municipal Corporation, as the case may be, and in the offices of
the District Collector, the Sub-Divisional Magistrate and the
Tehsil;
(d) uploaded on the website of the appropriate Government;
(e) in the affected areas, in such manner as may be prescribed.
(5) Every declaration referred to in sub-section (1) shall indicate,—
(a) the district or other territorial division in which the land is
situated;
(b) the purpose for which it is needed, its approximate area; and
(c) where a plan shall have been made for the land, the place at
which such plan may be inspected without any cost.
(6) The declaration referred to in sub-section (1) shall be conclusive
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
10
evidence that the land is required for a public purpose and, after
making such declaration, the appropriate Government may acquire
the land in such manner as specified under this Act.
(7) Where no declaration is made under sub-section (1) within twelve
months from the date of preliminary notification, then such
notification shall be deemed to have been rescinded:
Provided that in computing the period referred to in this sub-section,
any period or periods during which the proceedings for the
acquisition of the land were held up on account of any stay or
injunction by the order of any Court shall be excluded:
Provided further that the appropriate Government shall have the
power to extend the period of twelve months, if in its opinion
circumstances exist justifying the same:
Provided also that any such decision to extend the period
shall be recorded in writing and the same shall be notified and be
uploaded on the website of the authority concerned.”
7. Thus, the requirement of the law is that publication of
declaration and summary of rehabilitation and settlement upon the
satisfaction of the appropriate Government after the publication of
preliminary notification in terms of Section 11 of the 2013 Act, has
to be made within a period of 12 months from the date of
preliminary notification, and if no declaration is made under Sub-
section (1) of Section 19 within 12 months from the date of
preliminary notification, then such notification shall be deemed to
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
11
have been rescinded.
8. In the present case, the preliminary notification was
issued on 29.03.2023 and till date, no declaration has been made
qua the same, as is the requirement of Sub-section (1) of Section 19
of the 2013 Act.
9. Ordinarily, in such a circumstance, such a notification is
deemed to have been rescinded, which is the mandate of Sub-section
(7) of Section 19 of the 2013 Act. and this is mandatory, as the
words used in the Statute is that ‘if no declaration is made under
Sub-section (1) of Section 19 of the Act within 12 months from the
date of preliminary notification, then, "such notification shall be
deemed to have been rescinded."
10. However, the provisos to Sub-section (7) of Section 19
provide that the appropriate Government shall have the power to
extend the period of 12 months, if in its opinion, circumstances exist
justifying the same, and if the appropriate Government exercises
said power of its, then any such decision to extend the period shall
be recorded in writing and shall be notified and uploaded on the
website of the Authority concerned.
11. Therefore, the requirement of the law is that when the
appropriate Government exercises its power of extending the period
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
12
of 12 months in which declaration has to be made as per Sub-
section (1) of Section 19 of the 2013 Act, then the decision to extend
the period "shall be recorded in writing" and "shall be notified and
uploaded on the website."
12. Therefore, it is not as if the appropriate Government can
exercise the power to extend the period of 12 months on its whims
and fancies in each and every case where a declaration has not been
made within 12 months as from the date of preliminary notification.
This power of the State Government to extend the period of 12
months is coupled with the duty to record in writing the decision as
to why the time was being extended.
13. Unfortunately, in the present case, no decision or reason
exist on record, recorded in writing, as to why, in the opinion of the
appropriate Government, circumstances were existing, justifying the
extension beyond the period of 12 months of making the declaration
as per Sub-section (1) of Section 19.
14. In the present case, three notifications have been issued
by the appropriate Government extending the time for making
declaration by 12 months. In none of the notifications which have
been issued, the reasons, which obviously have to be the foundation
of the decision and on the basis whereof a decision has to be arrived
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
13
at by the appropriate Authority (which has to be reduced in writing
by recording the same in writing), have been mentioned.
15. The notifications extending the time of making the
declaration are, bald notifications in which it is simply mentioned
that, as the plan for rehabilitation and resettlement could not be
finalized due to certain unavoidable administrative circumstances,
therefore, the declaration could not be made within prescribed
period of 12 months and therefore, the period of issuing the
notification of declaration was being extended.
16. Now, what were those unavoidable administrative
circumstances, do not find mention in any of these three
notifications nor the record. In fact, Annexures P-3, P-4, and P-5 are
all conspicuously silent of the so-called unavoidable administrative
circumstances, which, as per the third proviso to Sub-section (7) of
Section 19 of 2013 Act, are required to be reduced in writing and
also notified and uploaded on the website when the appropriate
Government exercises its power to extend the period of 12 months.
What to speak of the recording and uploading of these
circumstances by way of a decision in the notifications issued, we
find that even in the record of the department, there are no reasons
recorded while taking a decision to issue notifications for extension
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
14
of time for making the declaration. Thus, here is a situation where
what was required to be done by the appropriate Government within
12 months as from the date of the notification of the preliminary
notification, has not been done even after the passing of more than
three and a half years as from the date of the issuance of the
preliminary notification.
17. Not only this, while exercising its power to extend the
period of making the declaration, the statutory requirement of
recording down the reasons why this power was being exercised, has
not been met by the appropriate Authority and neither any reasons
are there on the record nor any reasons or decision(s) as to why the
rehabilitation and resettlement policy could not be finalised, the
period was being extended is there in the notifications, which have
been uploaded on the website by the Authority concerned. This
according to us, at the best, is an excuse as to why declaration was
not made. The reasons were required to be mentioned why the
rehabilitation and resettlement plan could not be finalized and what
were the hurdles in the finalization of the said plan. A simple
mention that the plan for rehabilitation and resettlement could not
be finalized, cannot be termed to be sufficient enough to meet the
requirement of proviso to Sub-section (7) of Section 19 of the 2013
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
15
Act.
18. Therefore, in these circumstances, as there is a blatant
non-compliance of the third proviso of Sub-section (7) of Section 19
of the 2013 Act, by the appropriate Government while exercising its
power to extend the period of 12 months for making the declaration,
the preliminary notification stood rescinded with the efflux of
operation of Sub-section (7) of Section 19 of the 2013 Act, in terms
whereof, where no declaration is made under Sub-section (1) of
Section 19 of the 2013 Act within 12 months from the date of
preliminary notification, such notification is be deemed to have
rescinded and it is held accordingly.
19. Therefore, in the light of the above observations, this
writ petition is allowed. Preliminary notification (Annexure P-1),
dated 29.03.2023, is held to be deemed to have been rescinded in
view of the provisions of sub-Section (7) of Section 19 of the 2013
Act as no declaration was made within 12 months from the date of
issuance of the notification and the extensions, which have been
granted by the appropriate Government for making declaration as
per Annexures P-3 to P-5, i.e. notifications dated 16.03.2024
(Annexure P-3), 24.03.2025 (Annexure P-4) and 25.03.2026
(Annexure P-5), are held to be bad in law, as they do not contain in
::: Downloaded on - 29/09/2026 18:31:35 :::CIS

High Court of H.P.
16
them reasons/decision to extend the period beyond 12 months for
making such declaration. Pending miscellaneous application(s), if
any, also stand disposed of accordingly.

(Ajay Mohan Goel)
Judge
(Yogesh Jaswal)
Judge
September 29, 2026