Transmission Corporation Of Andhra Pradesh Limited Represented By Its Director, vs Jaladi Sita Rama Koteswara Rao
- Court
- Supreme Court
2026 INSC 1296
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 8998-9000 OF 2026
TRANSMISSION CORPORATION OF
ANDHRA PRADESH LIMITED,
REPRESENTED BY ITS DIRECTOR …APPELLANT(S)
VERSUS
JALADI SITA RAMA KOTESWARA
RAO & ORS. …RESPONDENT(S)
J U D G M E N T
NONGMEIKAPAM KOTISWAR SINGH, J.
THE CHALLENGE
1. The present Civil Appeals have been preferred by the
Transmission Corporation of Andhra Pradesh Limited (hereinafter
referred to as “the appellant-Corporation” ), the successor-in-
interest of the erstwhile Andhra Pradesh State Electricity Board
(“the Board” , for short), against the judgment and order dated
19.04.2018 passed by a Division Bench of the then High Court of
Signature Not Verified
Digitally signed by
RAHUL KUMAR
Date: 2026.11.28
17:43:28 IST
Reason:
Judicature at Hyderabad for the State of Telangana and the State
Page 1 of 42
of Andhra Pradesh (“the High Court” ) in Writ Appeal No. 2163 of
1998, and the two consequential judgments of even date in
L.A.A.S. No. 1610 of 2005 and L.A.A.S. No. 444 of 2007.
2. By the impugned judgment, the High Court set aside the
order dated 08.09.1998 of the learned Single Judge in Writ
Petition No. 33513 of 1997, and held that the possession of the
lands of the private respondents (“the respondent-
landowners” ), taken by the Board with their consent before the
publication of any notification under Section 4(1) of the Land
Acquisition Act, 1894 ( “the Act” ), was dehors the said Act; that
the acquisition proceedings stood lapsed under Section 11-A of
the Act; and that Award Nos. 11 and 12 of 1999, both dated
15.09.1999, were non est . A mandamus was issued to initiate
fresh acquisition proceedings and to determine and pay
compensation as per the law of land acquisition in force on the
date of such initiation, within three months. The two L.A.A.S.,
arising out of the rejection of the respondent-landowners’ claims
for enhancement by the Reference Courts, were consequently
disposed of as infructuous.
Page 2 of 42
FACTUAL MATRIX
3. The facts essential for the adjudication of these appeals lie
in a narrow compass. The respondent-landowners or their
predecessors-in-interest held about Ac. 4.00 of land in T.S. Nos.
209, 210/4, 211 and 214, Ward No. I, Block No. 9 of Tenali Town,
Guntur District ( “the subject land” ). Pursuant to a decision
taken on 07.01.1990 to establish a 132 KV/33 KV sub-station
and staff quarters at Tenali, the Divisional Engineer, Operation,
Tenali of the Board, by letter dated 25.09.1990, informed the
landowners that land acquisition proposals had been sent to the
Revenue authorities and, as the construction was to be taken up
“ immediately ” and “ in view of delay in finalisation of land
acquisition by Revenue Authorities ”, requested them to consent to
hand over the sites pending such finalisation, assuring that the
amount fixed by the Revenue authorities would be deposited with
the Revenue Divisional Officer, Tenali ( “the RDO” ). The
landowners, by identically worded letters dated 05.10.1990,
consented, subject inter alia to the following conditions:
“a) compensation solatium, interest etc. are
acceptable to me, when they are finally fixed by the
highest court or as per my choice
Page 3 of 42
b) I retain with my self the right to receive the
compensation under protest, and prefer reference to
court, appeal etc. to the higher courts.
c) whether Gazette publication etc. and other
procedures are gone through or not, as per the land
acquisition Act, you abide by the said Act, for
payment of the compensation, solatium, interest etc.
xxx xxx xxx
e) Whether the acquisition is treated as under the act
or not, the provision of the act with regards to
payment of compensation, solatium, interest etc. are
to be made as per the provisions of the Act.”
4. Acting on the said consent, the Board took over the land in
two phases, about Ac. 2.95 on 22.01.1991 and about Ac. 1.12 on
08.07.1991, recording in each case that the land was taken over
“ subject to final handing over by Revenue Authorities ”. The sub-
station and staff quarters were constructed thereon, and the sub-
station has, according to the appellant-Corporation, been
continuously operational since 1993.
5. The statutory process followed thereafter was in two stages.
For Stage-I , a notification under Section 4(1) of the Act vide
G.O.Rt. No. 613, Energy, Forest, Environment, Science and
Technology (P.R.II) Department, was published in the Andhra
1
Pradesh Gazette on 30.09.1991 for about Ac. 2.40946 , and the
1
The extents in the notifications, declarations and awards are expressed in acres and square
feet, and not in decimal acres. Thus, ‘Ac. 3.00156’ denotes 3 acres and 156 sq. ft. (14,537.31
sq. yards), and the total extent covered by the two awards (Ac. 4.00591) corresponds to about
4.0136 acres in decimal terms.
Page 4 of 42
declaration under Section 6 of the Act was published on
15.10.1992. For Stage-II , a notification under Section 4(1) of the
Act vide G.O.Rt. No. 568 dated 31.07.1992 was published on
15.10.1992 for Ac. 1.05227; on 09.11.1993, an extent of 5,227
sq. ft. was withdrawn from acquisition under Section 48(1) of the
Act, and the declaration under Section 6 of the Act for the
remaining extent was published on 12.11.1993. Neither
notification invoked the urgency provisions under Section 17 of
the Act; on the contrary, both appointed an officer to perform the
functions of the Collector under Section 5-A of the Act. The Board
deposited a sum of Rs. 1,75,000/- with the RDO towards Stage-II
on 06.04.1992, but no deposit was made towards Stage-I.
6. Pursuant to notices under Sections 9(3) and 10 of the Act, the
landowners appeared at the award enquiry held on 27.12.1993
and 03.01.1994, and claimed Rs. 600/- to Rs. 800/- per sq. yard.
However, no award followed. The parties then negotiated, the
State having permitted the Board by G.O.Rt. No. 1728 dated
12.11.1993 to acquire up to Ac. 5.00 by direct negotiation, but
without success; at the meeting held on 12.07.1996, the Board’s
committee proposed Rs. 34,94,700/- and Rs. 33,46,200/- per
Page 5 of 42
acre for the two stages, while the landowners insisted upon Rs.
50,62,500/- per acre.
7. In the meantime, the period stipulated under Section 11-A of
the Act expired. According to the report of the Anti-Corruption
Bureau, the Executive Engineer of the Board had, on 31.01.1995,
requested the RDO to republish the proposals in acres and cents,
as otherwise the land cost might increase. By letter dated
09.01.1996, the Executive Engineer of the Board himself informed
the RDO that the proceedings for Stage-I had lapsed in November
1994 and the declaration for Stage-II had lapsed for want of an
award before 11.11.1995, and sought fresh proposals. By letter
dated 19.02.1996, the RDO informed the Board that the
proceedings in both stages had lapsed as sufficient funds had not
been provided, and called upon the Board to deposit Rs.
5,11,09,900/- (computed at a basic value of Rs. 1,000/- per sq.
yard) for fresh proceedings. The Board did not make the deposit,
regarding the amount as excessive, and no fresh notification was
issued. An enquiry by the Anti-Corruption Bureau into the
proposed payment of compensation followed in 1997.
8. The landowners thereupon filed Writ Petition No. 33513 of
1997 on 15.12.1997, seeking a mandamus for the determination
Page 6 of 42
and payment of compensation under the Act, contending that the
notifications had lapsed and that the State, having retained the
land, was obliged to issue fresh notifications. In their counter
affidavits, the RDO and the Board did not dispute the facts and
admitted that the notifications had lapsed; the RDO attributed
the failure to pass the awards to the prolonged correspondence of
the Board seeking revision of the extents from “acres and square
feet” to “acres and cents”. In its additional counter affidavit, the
Board offered to shift the sub-station and return the land with
compensation for its use and occupation, which the landowners
declined.
9. The learned Single Judge, by order dated 08.09.1998, held
that though the urgency clause had not been invoked, possession
taken with consent prior to the notifications was to be treated as
possession under Section 17(1), whereupon the land vested in the
State; that Section 11-A, therefore, had no application; and that
the admissions of lapse were made under a misconception of law.
The respondents were directed to pass the awards with reference
to the market value on the dates of the notifications, along with
solatium and interest. The landowners preferred Writ Appeal No.
Page 7 of 42
2163 of 1998 on 06.11.1998, in which no interim order was
passed.
10. In compliance with the order of the learned Single Judge,
the RDO-cum-Land Acquisition Officer passed Award No. 11 of
1999 (Stage-I, Ac. 3.00156) and Award No. 12 of 1999 (Stage-II,
2
Ac. 1.00435) on 15.09.1999, fixing the market value at Rs. 60/-
per sq. yard (Rs. 2,90,400/- per acre), and awarding solatium at
30%, additional market value at 12% and interest from the
respective dates of taking possession, i.e., 22.01.1991 and
08.07.1991. The compensation under the two awards was
determined at Rs. 30,36,119/- and Rs. 9,63,976/-, respectively,
aggregating to Rs. 40,00,095/-. Four of the landowners received
their share under protest on 12.10.1999; the demand drafts dated
12.10.1999 for the share of the others were deposited in the Court
of the District Judge, Guntur on the same day, which was
intimated to the Office of the Accountant General on 20.03.2002.
11. The writ appeal was dismissed for non-prosecution on
19.07.2002, and was restored on 10.08.2004 in W.A.M.P. No.
2093 of 2004. The references under Section 18 were rejected by
2
The extents were revised upon a re-survey of the lands actually taken over by the Board, and
the amended extents were adopted in the awards.
Page 8 of 42
the Reference Courts on 30.04.2005 (L.A.O.P. No. 83 of 2000),
09.02.2007 (L.A.O.P. No. 87 of 2000) and 03.10.2007 (L.A.O.P.
Nos. 88 and 89 of 2000), the Reference Court in L.A.O.P. No. 83
of 2000 finding the sale exemplars relied upon by the claimants
to be unreliable. Against the judgments in L.A.O.P. Nos. 83 and
87 of 2000, L.A.A.S. No. 1610 of 2005 and L.A.A.S. No. 444 of
2007 were preferred.
12. By the impugned judgment, the Division Bench, relying
3
upon R.L. Jain (D) by LRs. v. DDA , held that possession taken
before any step under the Act was dehors the Act, distinguished
4
Satendra Prasad Jain v. State of U.P. as a case where the entire
procedure under Sections 4(1), 17(4), 9, 10 and 17(1) had been
followed, and issued the mandamus noticed above.
13. Before this Court, by order dated 03.07.2019, notice was
issued, and the operation of the impugned judgment was stayed.
The appellant-Corporation was directed to deposit the awarded
sum, with liberty to the respondents to withdraw it under protest,
without either the deposit or the withdrawal creating any
additional rights; on 29.07.2019, counsel for both parties stated
3
(2004) 4 SCC 79.
4
(1993) 4 SCC 369.
Page 9 of 42
that the direction stood complied with even before the said order.
At the hearing on 08.10.2026, the learned Additional Solicitor
General offered alternative land, and the appellant-Corporation,
by an affidavit dated 16.10.2026, offered agricultural parcels
aggregating Ac. 7.14 near Tenali, stating that the sub-station
serves, inter alia , the traction loads of the South Central Railway
and sixteen 33/11 KV sub-stations in Tenali town, and that fresh
acquisition would cost about Rs. 154.88 crores. By order dated
26.10.2026, this Court noted that the land offered belonged to
private individuals; recorded that the respondents were not
agreeable to alternative land and that, if the Right to Fair
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 ( “the 2013 Act” ) were
applied, the liability would exceed Rs. 154 crores; and directed
the appellant-Corporation to place a monetary offer on record. By
affidavit dated 03.11.2026, a lump sum of Rs. 47,72,32,560/-
was offered, computed at Rs. 12,000/- per sq. yard as on
01.01.2014 with solatium at 100% and additional market value
at 12% for one year on Ac. 4.0136 (Rs. 49,41,92,963/-), less a
credit of Rs. 1,69,60,403/- towards the awarded amount of Rs.
Page 10 of 42
40,00,095/- together with interest thereon at 12% per annum
from 2000 to 2026.
SUBMISSIONS ON BEHALF OF THE APPELLANT
14. Ms. Aishwarya Bhati, learned Additional Solicitor
General appearing for the appellant-Corporation, made the
following submissions, both orally and by way of a written note:
Firstly , the landowners voluntarily handed over
possession “ irrespective of the formalities, technicalities
etc. ”, retaining only the right to compensation under the
Act; the proceedings under Sections 4 and 6 were
undertaken only to determine the compensation, and the
rigour of compulsory acquisition ought not to apply.
5
Reliance was placed on Balakrishnan v. Union of India
6
and Mangalore Electric Supply Co. Ltd. v. CIT .
Secondly , the requirement of notice under Section 4
stood substantially complied with, since the landowners
had actual notice of the intended acquisition and had
consented to it, and the notifications were issued only for
the determination of compensation, reliance being placed
5
(2017) 3 SCC 634.
6
(1978) 3 SCC 248.
Page 11 of 42
7
on Urban Improvement Trust v. Vidhya Devi and Sunder
8
v. Union of India . Possession taken with consent before
the notification does not invalidate the acquisition: Lt.
9
Governor of H.P. v. Avinash Sharma .
Thirdly , the letter dated 25.09.1990 and the consent
letters show that the acquisition was, in substance, one
under Section 17 of the Act, reliance being placed on
Section 17(2), which provides for urgent acquisition for a
system pertaining to electricity; possession having been
taken after notice and with the consent of the
landowners, the requirements of Section 17(1) stood
satisfied, the land vested absolutely, and Section 11-A
had no application: Satendra Prasad Jain (supra). Even
without the deposit under Section 17(3-A), possession
does not become illegal where the land loser concedes the
10
position: Delhi Airtech Services (P) Ltd. v. State of U.P. .
The landowners, by negotiating, waived any challenge,
7
2024 SCC OnLine SC 3725.
8
(2001) 7 SCC 211.
9
(1970) 2 SCC 149.
10
(2024) 17 SCC 610.
Page 12 of 42
and the awards cured any prejudice by granting
additional market value and interest.
Fourthly , the admissions of lapse were concessions on a
point of law, not binding on the State: B.S. Bajwa v. State
11
of Punjab ; and inter-departmental communications,
such as the RDO’s letter dated 20.03.1995, cannot found
12
a right: Mahadeo v. Sovan Devi .
Fifthly , the writ petition, filed in December 1997 after
the negotiations failed, was belated, and the writ appeal
was itself dismissed for default in 2002: Banda
13
Development Authority v. Moti Lal Agarwal . Having
received compensation and sought references, the
landowners were estopped from pleading lapse.
Sixthly , the higher compensation claimed rested on
sham sales among family members, as found by the
14
Reference Courts: Trishala Jain v. State of Uttaranchal .
The acquisition, for a public purpose and on payment of
compensation, did not infringe the right to property: State
11
(1998) 2 SCC 523.
12
(2023) 10 SCC 807.
13
(2011) 5 SCC 394.
14
(2011) 6 SCC 47.
Page 13 of 42
of Bihar v. Maharajadhiraja Sir Kameshwar Singh of
15
Darbhanga and Kolkata Municipal Corporation v. Bimal
16
Kumar Shah .
Seventhly , under R.L. Jain (supra), possession taken
before the notification entitles the landowner, at best, to
rent or damages, which too stood waived under the
consent letters, and not to a fresh acquisition, which was
not even prayed for: Land Acquisition Officer & Asstt.
17
Commissioner v. Hemanagouda .
Lastly , and without prejudice, a fresh acquisition for a
critical public utility would cost the exchequer more than
Rs. 150 crores, and the relief ought to be moulded: Gauri
18
Shankar Gaur v. State of U.P. , Competent Authority v.
19 20
Barangore Jute Factory , Savitri Devi v. State of U.P. ,
Noida Industrial Development Authority v. Ravindra
21
Kumar , Special Agricultural Produce Market Committee
22
v. N. Krishnappa and Delhi Airtech (supra).
15
(1952) 1 SCC 528.
16
(2024) 10 SCC 533.
17
(2005) 12 SCC 443.
18
(1994) 1 SCC 92.
19
(2005) 13 SCC 477.
20
(2015) 7 SCC 21.
21
(2022) 13 SCC 468.
22
(2017) 13 SCC 239.
Page 14 of 42
SUBMISSIONS ON BEHALF OF THE RESPONDENTS
15. Mr. R. Basant, learned Senior Counsel appearing for the
respondent-landowners, supported the impugned judgment and
submitted as follows:
Firstly , Section 17 of the Act was never invoked. Both
notifications contemplated an enquiry under Section 5-A
of the Act, no direction of urgency was issued, nothing
was tendered under Section 17(3-A), and possession was
taken by the Board, not the Collector, before any
notification. The land never vested, and the proceedings
lapsed under Section 11-A.
Secondly , the lapse was admitted by the Board in its
letter dated 09.01.1996, by the RDO in his letter dated
19.02.1996, and by both in their counter affidavits. The
awards passed in 1999, after the lapse, were void and
incapable of binding the landowners, and were in any
case passed mechanically.
Thirdly , the handing over of possession was not a
voluntary transfer. The consent was expressly
conditioned on acquisition and payment of compensation
in accordance with the Act, and whatever amounts were
Page 15 of 42
received under the awards were received under protest.
The landowners have been deprived of their property for
over three decades on payment of a mere Rs. 60/- per sq.
yard.
Lastly , the landowners are not agreeable to alternative
land and seek compensation in accordance with law. The
direction of the High Court for a fresh acquisition, which
preserves the sub-station while securing such
compensation, ought to be affirmed.
ISSUES FOR CONSIDERATION
16. Upon hearing the parties, the following questions arise
for our consideration:
(i) Whether the High Court was justified in holding
that the acquisition proceedings lapsed under Section
11-A of the Act and that the awards dated 15.09.1999
were non est, and, if so, what is the consequence of such
lapse; and
(ii) Whether, notwithstanding such lapse, the direction
of the High Court to initiate fresh acquisition
proceedings under the law in force on the date of such
Page 16 of 42
initiation ought to be interfered with, and the relief
moulded, as prayed for by the appellant-Corporation.
ANALYSIS
A. Whether the acquisition proceedings lapsed
17. The Act provides only two modes by which the State may
take possession of land proposed to be acquired: under Section
16, after the award, or under Section 17, in cases of urgency. A
three-Judge Bench of this Court in R.L. Jain (supra) explained the
position thus:
“11. … The scheme of the Act does not contemplate
taking over of possession prior to the issuance of
notification under Section 4(1) of the Act and if
possession is taken prior to the said notification it
will be dehors the Act. It is for this reason that both
Sections 11(1) and 23(1) enjoin the determination of
the market value of the land on the date of
publication of notification under Section 4(1) of the
Act for the purpose of determining the amount of
compensation to be awarded for the land acquired
under the Act. These provisions show in
unmistakable terms that publication of notification
under Section 4(1) is the sine qua non for any
proceedings under the Act. …
xxx xxx xxx
18. In a case where the landowner is dispossessed
prior to the issuance of preliminary notification
under Section 4(1) of the Act the Government merely
takes possession of the land but the title thereof
continues to vest with the landowner. …”
Page 17 of 42
18. Section 17(1) permits possession to be taken before an
award only where two conditions are met: first, there must be a
direction that the case is one of urgency; and secondly, the
Collector may then take possession on the expiration of fifteen
days from the publication of the notice under Section 9(1). Neither
condition is made out in the present case. No direction under
Section 17(1) was ever issued, and both notifications
contemplated an enquiry under Section 5-A. Possession was
taken by the Board itself, and not by the Collector, before the
publication of any notification under Section 4(1), let alone a
notice under Section 9(1). Nor was any amount tendered under
Section 17(3-A). The foundation of Satendra Prasad Jain (supra),
on which the learned Single Judge relied, is the statutory vesting
that follows a valid exercise of the urgency power. This Court in
that case held as follows:
“15. … In the ordinary case, therefore, when
Government fails to make an award within two
years of the declaration under Section 6, the land
has still not vested in the Government and its title
remains with the owner, the acquisition proceedings
are still pending and, by virtue of the provisions of
Section 11-A, lapse. When Section 17(1) is applied
by reason of urgency, Government takes possession
of the land prior to the making of the award under
Section 11 and thereupon the owner is divested of
the title to the land which is vested in the
Government. … Clearly, Section 11-A can have no
Page 18 of 42
application to cases of acquisitions under Section 17
because the lands have already vested in the
Government …”
19. The present case falls squarely within the “ordinary case”
described above. The reliance on Section 17(2) of the Act is equally
misplaced. That provision applies where, in the provided
circumstances, the appropriate Government considers it
necessary to acquire the immediate possession of land for
maintaining, inter alia , any structure or system pertaining to
electricity. In such a case, the Collector may enter upon and take
possession of the land “ immediately after the publication of the
notice mentioned in sub-section (1) and with the previous sanction
of the appropriate Government ”. None of these conditions is
present here. The new sub-station was a planned project, decided
upon on 07.01.1990; no sanction under Section 17(2) was ever
accorded; and possession was taken by the Board itself, months
before any notification. A letter of a Divisional Engineer cannot
take the place of a statutory power that the Government never
chose to invoke.
20. Nor does Avinash Sharma (supra) assist the appellant-
Corporation. There, a notification under Section 17(1) and (4) had
in fact been issued, and this Court held, in paragraph 4, that
Page 19 of 42
“ when a notification under Section 17(1) is issued ”, the possession
previously obtained would be deemed to be the possession of the
Government on the expiration of fifteen days from the notice
under Section 9(1). The deeming operates on the strength of the
urgency notification. In its absence, as here, there is nothing on
which the previously obtained possession can be grafted. The view
of the learned Single Judge that the consensual possession
“should be held as possession taken by the Government” under
Section 17(1) would amount to reading into the notifications a
power that the Government consciously chose not to exercise.
21. The decision of the three-Judge Bench in Delhi Airtech
(supra) puts the matter beyond doubt. It holds that even where
Section 17(1) is invoked, non-compliance with Section 17(3-A)
prevents absolute vesting and attracts the lapsing provision
under Section 11-A:
“22. … Therefore, even if possession is taken, such
possession cannot be considered as legal so as to
vest the land absolutely if the prerequisite condition
for payment of 80% before taking possession is not
complied with. In such circumstance, by legal fiction
it loses its character as an acquisition under Section
17 and since the absolute vesting does not take
place, it will lapse if the further process is not
complied with and the award is not passed within
two years from the date of declaration.
23. However, even when the precondition is not
complied with, if the land-loser does not challenge
Page 20 of 42
the acquisition and/or taking of possession as
illegal, but concedes to the position, the possession
taken does not become per se illegal and the vesting
will be absolute and in such event it cannot be
considered to have lapsed until the land-loser
exercises the right. …”
22. If the lapse under Section 11-A operates where the
urgency clause is invoked without compliance with Section 17(3-
A), it must operate a fortiori where the urgency clause was never
invoked at all. The appellant-Corporation’s reliance on paragraph
23 of Delhi Airtech (supra) is misplaced. The landowners did not
concede the position. The negotiations between the parties were
confined to the quantum of compensation, and were conducted
on the footing of the consent letters dated 05.10.1990, which
expressly preserved the rights of the landowners under the Act.
Such negotiations cannot, by any stretch, be construed as an
acceptance by the landowners that the land had vested in the
State. The landowners invoked the lapse in their writ petition,
filed within about two years of the expiry of the period stipulated
for the Stage-II award, and have diligently pursued their claim
since. Nor can the awards made in 1999, years after the period
had expired, be said to have cured the absence of the deposit;
Page 21 of 42
proceedings that had lapsed by operation of law could not be
revived by a subsequent award.
23. The submission that the transaction was a voluntary
transfer outside the rigours of the Act cannot be accepted either.
The letter dated 25.09.1990 sought only interim possession
pending acquisition. The consent letters were expressly
conditioned on compensation under the Act. The Board itself
recorded that the land was taken over “subject to final handing
over by Revenue Authorities”, and no instrument of conveyance
was ever executed. Title could, therefore, pass to the State only
upon the land validly vesting in it through the statutory process.
Further, Balakrishnan (supra) does not advance the case of the
appellant-Corporation. In that case, which arose under the
Income Tax Act, 1961, the State Government had initiated
acquisition proceedings under the Act, and a notification under
Section 4, a declaration under Section 6 and an award had
followed. Thereafter, instead of seeking a reference, the landowner
negotiated the quantum of compensation with the beneficiary,
Techno Park, and executed a sale deed in its favour. This Court
nevertheless held that the acquisition remained compulsory,
because the entire procedure prescribed under the Act had been
Page 22 of 42
followed, and the settlement related only to the amount of
compensation. It was in that context that this Court observed:
“8. In our view, insofar as acquisition of the land is
concerned, the same was compulsorily acquired as
the entire procedure prescribed under the LA Act
was followed. The settlement took place only qua the
amount of the compensation which was to be
received by the appellant for the land which had
been acquired. … Merely because the compensation
amount is agreed upon would not change the
character of acquisition from that of compulsory
acquisition to the voluntary sale. …”
24. In the present case, the position is different. No
agreement on the compensation was ever arrived at between the
landowners and the Board or the State, and the statutory
procedure, though initiated, was not carried to its conclusion
within the period prescribed. The mere fact that the landowners
handed over possession of their land at the initial stage, pending
acquisition, cannot dispense with the statutory requirements for
a valid acquisition, nor can it result in the land vesting in the
State.
25. Nor does the decision in Urban Improvement Trust (supra)
assist the appellant-Corporation. That decision concerned the
adequacy of service of notice where the owners had participated
in the proceedings; it does not hold that land can vest in the State
Page 23 of 42
before, or without, any notification. The reliance placed by the
appellant-Corporation on B.S. Bajwa (supra) is also misplaced. In
that case, the Division Bench of the High Court, having found the
claim to seniority barred by laches, nevertheless granted relief on
the basis of a concession made by the Additional Advocate
General, without considering its effect or its inconsistency with its
own finding, and this Court held that the concession, being one
on a point of law, could not bind the State. The principle is not
attracted here. Our conclusion does not rest on any concession or
admission made on behalf of the State. We have held that the
acquisition proceedings lapsed because no award was made
within two years from the publication of the declarations under
Section 6, as mandated by Section 11-A, and because the land
never vested in the State under Section 17. That conclusion
follows from the statutory scheme itself, independently of what
the Board or the RDO may have stated. For the same reason,
Mahadeo (supra) is of no avail to the appellant-Corporation. That
decision holds that inter-departmental communications, being
part of the process of consideration towards a decision, cannot be
relied upon as a basis to claim a right. The right of the
respondent-landowners does not arise from the letters dated
Page 24 of 42
09.01.1996 and 19.02.1996, or from any other inter-
departmental communication. It arises from the lapse of the
acquisition proceedings by operation of Section 11-A. The
admissions in those letters and in the counter affidavits filed
before the High Court merely show that the authorities
themselves, at the relevant time, correctly understood the
consequence of Section 11-A.
26. Nor can the respondent-landowners be non-suited on
the ground of delay or estoppel. In Banda Development Authority
(supra), the landowner approached the High Court nine years
after the declaration under Section 6, seeking to quash the
acquisition after the land had been utilised for a residential
scheme and third-party rights had been created. It was in that
context that this Court held the delay to be fatal. The position
here is materially different. The respondent-landowners have
never sought to undo the acquisition or to recover the land; they
declined the land when the Board offered to return it, and sought
only compensation, the denial of which is a continuing wrong.
They approached the High Court on 15.12.1997, within about two
years of the expiry of the period stipulated for the Stage-II award
and within seventeen months of the failure of the negotiations,
Page 25 of 42
and no third-party rights have intervened in the meantime. As
regards estoppel, the amounts under the awards were received, if
at all, under protest, in terms reserved as early as 05.10.1990,
and the references under Section 18 related only to the quantum.
Such conduct cannot breathe life into proceedings that had
lapsed by operation of law, for there can be no estoppel against a
statute. The amounts so received must, however, be adjusted.
27. We, therefore, find merit in the submissions of the
respondent-landowners and hold that the High Court rightly
concluded that the acquisition proceedings had lapsed under
Section 11-A of the Act, and that the awards dated 15.09.1999
could not bind them.
28. The consequence of such lapse flows from the statute
itself. Section 11-A provides that, if no award is made within the
stipulated period, “ the entire proceedings for the acquisition of the
land shall lapse ”. Upon such lapse, there remains no proceeding
under which the land could vest in the State. The land did not
vest under Section 16, since no valid award was made and
possession was not taken thereunder; nor did it vest under
Section 17, since that provision was never invoked. Possession
having been taken before any notification under Section 4(1), the
Page 26 of 42
Board merely took possession of the land, while the title thereto
continued to vest with the respondent-landowners, as held in R.L.
Jain (supra). The respondent-landowners, therefore, continue to
be the owners of the subject land, though they have been out of
possession since 1990–91 and have not been paid for it in
accordance with law. If the State requires the land for the public
purpose for which it is being used, the only course open to it is to
acquire the land afresh in accordance with the law in force. This
23
Court, in Laxmi Devi v. State of Bihar , having held that the
acquisition proceedings had lapsed under Section 11-A, adopted
the course of directing the issue of a fresh notification.
29. Once it is held, in agreement with the High Court, that
the acquisition proceedings lapsed, the legal consequence that
follows is evident. Since the title to the subject land never vested
in the State and continues to vest in the respondent-landowners,
only two courses are open in law: either the land must be restored
to its owners, or, if the State requires it for the public purpose, it
must be acquired afresh in accordance with the law in force,
which today is the 2013 Act. In the present case, the restoration
23
(2015) 10 SCC 241.
Page 27 of 42
of the land is not a course that commends itself. The land has
been in the occupation of the appellant-Corporation for over three
decades, and the sub-station constructed thereon serves an
important public purpose, catering, inter alia, to the traction
loads of the South Central Railway and to the sub-stations
supplying Tenali town. Its dislocation, in our opinion, ought not
to be directed. Nor have the respondent-landowners ever sought
the return of the land; indeed, they declined it when the Board
offered to return it, ostensibly because the character of the land
had changed. The only course that remains, therefore, is the one
adopted by the High Court, namely, a direction to initiate fresh
acquisition proceedings. Notably, the High Court also did not
direct the restoration of the land or the removal of the sub-station.
It preserved the public utility and left only the compensation to
be determined under the law in force. The first question is
answered accordingly.
B. Whether the relief ought to be moulded
30. It is in this context that the learned Senior Counsel on
behalf of the appellant-Corporation vehemently contended that a
fresh acquisition under the 2013 Act would entail a huge outlay
Page 28 of 42
by way of compensation and would cost the public exchequer
dearly. It was submitted that the liability would exceed Rs. 150
crores, and, according to the affidavit dated 16.10.2026, would be
about Rs. 154.88 crores, which would be an exorbitant price for
land of which possession was taken as far back as 1991. The
appellant-Corporation, therefore, prays that this Court ought not
to sustain the direction for a fresh acquisition, but should mould
the relief by confining the respondent-landowners to rent or
damages, to alternative land, or to a lump sum.
31. We are unable to accept this contention. To begin with,
the direction for a fresh acquisition is the very course which was
followed in R.L. Jain (supra), where, the earlier acquisition
proceedings having been declared void, fresh proceedings were
initiated in order to save the construction, and the three-Judge
Bench held the landowner to have been adequately compensated
by the award made in those proceedings:
“20. … It is in such circumstances that in order to
save the construction the land acquisition
proceedings were initiated again by issuing a
notification under Section 4(1) of the Act on 9-9-
1992. Under the award given by the Collector on 11-
6-1994 he has been awarded Rs 16,54,175 as the
market value of the land and Rs 4,96,252 as
solatium. …”
Page 29 of 42
Similarly, in Hemanagouda (supra), possession had been
taken between 1968 and 1970, but acquisition proceedings were
initiated only on 02.02.1999, and the compensation was
determined with reference to that notification. Even in Gauri
Shankar Gaur (supra), on which the appellant-Corporation relies,
this Court recognised, in paragraph 48 of the said judgment, that
the acquiring body “ could have acquired the land by issuing fresh
notification ”.
32. The direction of the High Court also accords with Article
300-A of the Constitution. In Kolkata Municipal Corporation
(supra), on which the appellant-Corporation itself relies, this
Court identified, among the sub-rights constituting the right to
property, “ the duty of the State to restitute and rehabilitate — the
right of restitution or fair compensation ” and “ the duty of the State
to conduct the process of acquisition efficiently and within
prescribed timelines of the proceedings — the right to an efficient
and expeditious process ”. Neither was honoured here. In Urban
Improvement Trust (supra), this Court in paragraph 69 thereof
Page 30 of 42
reiterated the following observations from Ultra-Tech Cement Ltd.
24
v. Mast Ram :
“46. … This Court held in Tukaram Kana Joshi and
Ors. thr. Power of Attorney Holder v. M.I.D.C., (2013)
1 SCC 353 that in a welfare State, the statutory
authorities are legally bound to pay adequate
compensation and rehabilitate the persons whose
lands are being acquired. …
xxx xxx xxx
48. … The State cannot abdicate its constitutional
and statutory responsibility of payment of
compensation by arguing that its role was limited to
initiating acquisition proceedings … We find that the
delay in the payment of compensation to the
landowners after taking away ownership of the
subject land from them is in contravention to the
spirit of the constitutional scheme of Article 300A
and the idea of a welfare State.
49. Acquisition of land for public purpose is
undertaken under the power of eminent domain of
the government much against the wishes of the
owners of the land which gets acquired. When such
a power is exercised, it is coupled with a bounden
duty and obligation on the part of the government
body to ensure that the owners whose lands get
acquired are paid compensation/awarded amount
as declared by the statutory award at the earliest.”
33. The moulding of relief is an equitable discretion of the
Court, exercised to prevent an unjust result. It is not a right that
a party in default may claim. The question, therefore, is whether
affirming the direction of the High Court would produce an unjust
24
2024 SCC OnLine SC 2598.
Page 31 of 42
result. The decisions relied upon by the appellant-Corporation do
not support such a conclusion.
34. In Gauri Shankar Gaur (supra), the acquisition came to
an end for want of a timely declaration, but housing colonies had
been constructed and sold, and the landowners had no interim
order in their favour. In the said case, R.M. Sahai, J., observed as
follows:
“48. But this is not the end. Even though the law is
in favour of the petitioners but equity stands in their
way since in pursuance of these proceedings the
Avas Evam Vikas Parishad entered into possession
and constructed housing colonies as there was no
interim order in favour of land owners during
pendency of the writ petitions in the High Court.
Therefore the individual interest of the land owners
is faced with public interest of those large number of
middle class persons who must have invested their
life’s savings in purchasing these houses … Larger
social interest therefore requires this Court to mould
the relief in such manner that justice may not suffer.
…”
The equity there lay with the large number of purchasers
whose homes would otherwise be demolished. No such third-
party interest arises here. The land remains with the appellant-
Corporation itself, and the direction of the High Court does not
disturb it.
Page 32 of 42
35. In Barangore Jute Factory (supra), where the
notification was invalidated but a national highway had been
constructed on the land, this Court held:
“14. … No useful purpose will be served by quashing
the impugned notification at this stage. … Therefore,
the ultimate question will be about the quantum of
compensation payable to the landowners. …
Balancing the rights of the petitioners as against the
problems involved in quashing the impugned
notification, we are of the view that a better course
will be to compensate the landowners, that is, the
writ petitioners appropriately for what they have
been deprived of. …”
The Court there moulded the relief to avoid quashing the
notification and dismantling a completed highway, and, in
paragraph 15, moved the date for determining compensation
forward to the date of dispossession, noting that in similar
situations this Court had “ shifted the date of the notification so
that the landowners are adequately compensated ”. The moulding
thus enured to the benefit of the landowners. Here, the High Court
has already preserved the public utility, and nothing would be
achieved by moulding the relief except a reduction in the
compensation payable to the landowners.
36. In Savitri Devi (supra) and Noida Industrial Development
Authority (supra), the challenges were brought belatedly, after
Page 33 of 42
vast extents of land had been developed and allotted to third
parties. Even so, in Savitri Devi (supra), the landowners received
an enhancement of 64.7% and an allotment of developed land,
with the clarification, in paragraph 50, that the directions “ would
not form precedent for future cases ”. In Noida Industrial
(supra), this Court approved compensation
Development Authority
under the 2013 Act itself:
“17. In Sahara India Commercial Corpn. Ltd. v. State
of U.P., this Court found that invocation of urgency
clause under Section 17 was invalid and illegal. This
Court moulded the relief and directed payment of
compensation in terms of the 2013 Act by treating
the relevant date as the date of its judgment.
Therefore, we find no error in the approach of the
High Court when it directed payment of market
value computed as per the 2013 Act to those
landowners who have not accepted the
compensation under Karar Niyamawali by taking
the date of the judgment as a deemed date after
following the 2013 Act. …”
These decisions, relied on by the appellant-Corporation, far
from supporting their case, show that even where the relief is
moulded, landowners who have not acquiesced are not to be
deprived of compensation at current value.
37. The decision of the three-Judge Bench in Delhi Airtech
(supra) requires closer consideration. After holding that Section
11-A applied, the Court declined to direct a fresh notification,
observing:
Page 34 of 42
“33. … Further, the course as suggested in Laxmi
Devi to issue a fresh notification also would not be
appropriate, since the very scheme of acquisition
and determination of compensation under the old
regime has undergone a sea change. As such it
would be unjust not only to the State exchequer but
also the other land-losers under the same
notification if the present prevailing process is
applied in determining the compensation. …”
That decision is distinguishable on at least four grounds:
(a) In Delhi Airtech (supra), the appellant’s land was
a small extent of 2-06-1/3-0 bighas within a planned
industrial layout of 101-15-17 5/6 bighas, and the other
land-losers under the same notification had settled under
the old regime. Applying the new regime to one landowner
would have been unjust to them. Here, the respondent-
landowners are the only land-losers, and no question of
parity arises.
(b) There, the acquisition had been initiated under
the Act and the urgency clause invoked, the defect being
the failure to deposit eighty per cent of the estimated
compensation. Here, possession was taken wholly outside
the Act, before any notification, without deposit of
compensation in respect of the Stage I portion, and the
urgency clause was never invoked.
Page 35 of 42
(c) There, the award was made about six years after the
notification, and the market value was directed to be re-
determined as on the date of the award. Here, more than
three decades have passed since possession was taken.
Applying the same yardstick would confine the landowners
to the market value as it stood in 1999, some twenty-seven
years ago, which would render the compensation illusory,
the awards of that date having themselves granted only
about Rs. 60/- per sq. yard on the basis of the market
value in 1991.
(d) The principle underlying the same decision, that
the “vice” of non-compliance by the acquiring authority
“cannot be permitted to be converted into a ‘virtue’”
(paragraph 25), applies with equal force here. To fix the
compensation at an old value on account of a delay
attributable to the acquiring authority would do precisely
that.
38. Equity, in the exercise of this discretion, also requires us
to weigh the conduct of the parties. We find no mala fides or
negligence on the part of the respondent-landowners. They
handed over their land in 1990–91 at the Board’s own request,
Page 36 of 42
pending acquisition. They participated in the award enquiry and
in the negotiations, never sought any interim order against the
project, and never sought the return of the land; indeed, they
declined it when offered, insisting only on compensation in
accordance with law. No doubt, the respondent-landowners were
firm in their demand during the negotiations, and declined the
rates offered by the Board. That firmness, however, was directed
only at securing what they regarded as the true market value of
their land, and they remained willing, throughout, to have the
compensation determined through the process prescribed by law.
The allegation that they effected sales to relatives to inflate the
value, made in the Board’s counter affidavit in the writ petition,
has not been properly established. The two exemplars doubted by
the Reference Court were executed by persons other than the
respondent-landowners. The enquiry of the Anti-Corruption
Bureau was directed against public servants. The allegation that
inflated basic value certificates were issued to respondent No. 1
was held not substantiated. The only lapses on their part are
procedural: their writ appeal was dismissed for default in 2002
and restored in 2004, and the legal representatives of some
deceased landowners were not brought on record before the High
Page 37 of 42
Court, a matter dealt with by this Court on 16.03.2022. Neither
caused any prejudice to the appellant-Corporation, nor did either
lead to the creation of third-party rights.
39. The conduct of the Board stands on a different footing. It
took possession before any notification and never invoked the
urgency clause. It deposited nothing towards Stage-I. According
to the report of the Anti-Corruption Bureau, placed on record by
the appellant-Corporation itself, its Executive Engineer requested
the RDO on 31.01.1995 to republish the proposals in acres and
cents because, otherwise, “the land cost may increase”. According
to the RDO, it was the prolonged correspondence of the Board on
this aspect that prevented the awards from being passed in time.
The Board itself acknowledged the lapse on 09.01.1996, yet
deposited nothing and caused no fresh notification to be issued
for three decades. We do not find this conduct to be actuated by
mala fides, but it was a sustained default on the part of the
acquiring authority. To mould the relief so as to fix the
compensation at an earlier value would reward the party in
default at the expense of the party who was not.
40. It must also be borne in mind that the plea for moulding
the relief rests, in substance, on the ground, namely that a fresh
Page 38 of 42
acquisition under the 2013 Act would cast a burden of over Rs.
154 crores on the public exchequer. That is not a circumstance
which renders the relief granted by the High Court unjust. It is
the direct consequence of the failure of the acquiring authority to
acquire the land, or to pay for it, for over three decades. Moreover,
to mould the relief as suggested, this Court would have to
determine, in substitution of the statutory process, what amount
would represent fair compensation for the land. There is no
material on record on which such an assessment could be made.
The figure of Rs. 154 crores is itself an estimate, unsupported by
any valuation, and neither party has placed on record the
guideline values or sale statistics. Any amount fixed by this Court
would, in these circumstances, be little more than a guesstimate,
and it would be hazardous to undertake such an exercise without
proper materials on record. Nor would it be fair to the respondent-
landowners, who have consistently resisted the determination of
their compensation otherwise than in accordance with law. They
reserved their right to receive compensation under protest as early
as 05.10.1990. In 1999, only four of them received the amounts
under the awards, and that too under protest, the amounts due
to the others being deposited in court; any subsequent withdrawal
Page 39 of 42
was permitted by this Court only under protest. Before this Court,
too, the respondent-landowners have not sought to have the
compensation fixed at any particular figure; while submitting that
the liability under the 2013 Act would exceed Rs. 154 crores, they
have sought only that the compensation be determined in
accordance with law. While Rs. 154 crores can be said to be a
huge amount, it cannot be said to shock the conscience of this
Court to warrant intervention. The determination of
compensation is, therefore, best left to the statutory machinery
under the 2013 Act, with the remedies it provides, rather than
fixed by this Court on conjecture.
41. Equally, no equity lies in favour of the appellant-
Corporation. The respondent-landowners have been deprived of
the use and enjoyment of their land, and of the benefit of its
appreciation, for over thirty-five years, having received only about
Rs. 60/- per sq. yard under awards which we have held to be non
est. The acquisition proceedings lapsed on account of the default
of the acquiring authority, as we have held while answering the
first question. To mould the relief so as to fix the compensation
below what the law provides would allow the appellant-
Corporation to take advantage of its own default, at the expense
Page 40 of 42
of landowners who were not at fault. The alternative land offered
at the time of final hearing before us consists of parcels belonging
to private individuals, which the landowners are unwilling to
accept and cannot be compelled to accept. The lump sum of Rs.
47,72,32,560/- offered freezes the value as on 01.01.2014 and
deducts the award amount together with interest thereon at 12%
per annum. No acceptance of the said offer has been placed on
record by the respondent-landowners, and it cannot be
substituted for the determination of compensation under the
statute.
42. We, therefore, find no reason to mould the relief as urged.
The High Court struck the correct balance: the sub-station is
preserved, and the landowners are left to receive compensation in
accordance with law. The submissions of the respondent-
landowners merit acceptance, and the second question is
answered accordingly against the appellant-Corporation.
CONCLUSION
43. In view of the foregoing discussion, we find no merit in
these appeals. The impugned judgment dated 19.04.2018 passed
by the High Court in Writ Appeal No. 2163 of 1998, whereby the
Page 41 of 42
appropriate authorities were directed to initiate fresh acquisition
proceedings in respect of the subject land and to determine and
pay compensation in accordance with the law of land acquisition
in force on the date of such initiation, and the consequential
judgments of even date in L.A.A.S. No. 1610 of 2005 and L.A.A.S.
No. 444 of 2007, are upheld. The interim order dated 03.07.2019
stands vacated. Since the operation of the impugned judgment
remained stayed at the behest of the appellant during the
pendency of these appeals, and the period of three months fixed
by the High Court has long expired, the fresh acquisition
proceedings shall be initiated within three months, and the
compensation determined and paid as expeditiously as possible.
44. The appeals are, accordingly, dismissed. There shall be
no order as to costs. Pending application(s), if any, shall stand
disposed of.
…………………………………………J.
[SATISH CHANDRA SHARMA]
…………………………………………J.
[NONGMEIKAPAM KOTISWAR SINGH]
NEW DELHI;
NOVEMBER 27, 2026.
Page 42 of 42