DILIP DAHYABHAI PATEL vs STATE OF GUJARAT

Court
Gujarat High Court

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 5204 of 2022
==========================================================
DILIP DAHYABHAI PATEL & ORS.
Versus
STATE OF GUJARAT & ANR.
==========================================================
Appearance:
MR GM AMIN(124) for the Petitioner(s) No. 1.1,1.2,1.3,2,3
MR. HARDEEP L MAHIDA(7112) for the Respondent(s) No. 2
MS. HETAL PATEL, LD. AGP for the Respondent(s) No. 1
==========================================================
CORAM: HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE
SUNITA AGARWAL
and
HONOURABLE MR. JUSTICE DIVYESH A. JOSHI

Date : 01/10/2026

ORAL JUDGMENT
(PER : HONOURABLE THE CHIEF JUSTICE
MRS. JUSTICE SUNITA AGARWAL)
1. At the request made by Mr. Satish Upadhyay, the
learned advocate appearing for the NHAI, the affidavit filed in
compliance with the order dated 21.09.2026, without
annexing the copy of the award, is taken on record.
2. By means of the present petition, the petitioners have
prayed for the following reliefs:-
“ (A) Your Lordships may be pleased to admit this
Petition;
(B) Your Lordships may kindly be pleased to issue
appropriate writ, order or direction, directing the
respondent to comply with the award dated 18.06.2013
nd
passed by the competent authority and 2 Special Land
Acquisition Officer and be pleased to direct the
respondent to pay the compensation to the petitioner as
determined in the Award dated 18.06.2013 of the
petitioner land and construction, with running interest at
Page 1 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
18%;
(C) Your Lordships may be pleased to issue
appropriate writ or direction, awarding exemplary costs
to the respondent as the delay of 8 years has occurred
on the part of the respondent.
(D) Alternatively be pleased to directed National
Highways Authority of India to return petitioner land
and restore possession and be pleased to award
damages for depriving petitioner of its land and
construction;
(E) Any other and further relief/s as the facts and
circumstances of the case may require, also be granted. ”
3. The categorical case of the petitioners is that they have
been deprived of due compensation amount at the instance of
the NHAI and despite filing of the present writ petition in the
year 2022, payment of the due compensation amount has not
been made. The contention is that the compensation amount
with respect to the land in question was determined under the
award dated 18.06.2013 for village: Bareja and dated
30.03.2013 for village: Aslali. The original awards were,
however, reviewed by the Special Land Acquisition Officer suo
motu without there being any statutory power under the
National Highways Act, 1956. The aforesaid common awards
were revised after the enforcement of the Right to Fair
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (for short “ the Act,
2013 ” ) w.e.f. 01.01.2016 by passing separate individual
awards dated 17.12.2014 and 15.05.2015.
4. In a group of writ petitions filed by several land holders
including the petitioners herein being Special Civil
Page 2 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
Application No.10931 of 2015, the revised award dated
17.12.2014 has been set aside, restoring the original award
dated 30.03.2013. A copy of the judgment and order dated
31.01.2018 is appended at Page-’37’ of the paper-book, a
perusal whereof indicates that this Court, while setting aside
the revised award dated 17.12.2014, has categorically held
that the Land Acquisition Officer exercised review powers
which he did not have; in absence of any power of review
under the statute, the original awards could not have been
revised at the instance of the NHAI.
5. The case of the petitioners herein is that the judgment
and order dated 31.01.2018 setting aside the revised award
with respect to the lands of the petitioners herein, has not
been complied with till date. Initially, the petitioners had filed
a contempt petition being Misc. Civil Application No. 279 of
2019 pleading disobedience of the judgment and order dated
31.01.2018, however, the contempt application was disposed
of with the liberty to the petitioners to avail appropriate
remedy for enforcement of the award dated 30.03.2013, i.e.,
to seek for appropriate writ or direction in the event of the
amount awarded under the award dated 30.03.2013 was not
paid. The petitioners, in the present set of writ petitions filed
in the year 2022 after the disposal of the contempt petition,
seek a mandamus in furtherance of the direction of the Writ
Court in the judgment and order dated 18.01.2022 in view of
the observations made in the order of disposal of the
contempt petition.
6. The prayer, thus, is to issue a direction to the NHAI to
deposit the differential amount under the original award dated
Page 3 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
30.03.2013 which has been revived vide judgment and order
dated 31.01.2018 passed in the writ petition filed by the
petitioners herein being Special Civil Application No.10931 of
2015.
7. To this prayer made by the petitioners herein, in the
affidavit-in-reply filed today in the Court on behalf of the
NHAI, it is submitted that the compensation in respect of the
subject acquisition, as determined by the competent authority,
had been duly deposited as per the revised award in the year
2015 itself. Since the compensation amount was deposited
much prior to the judgment and order dated 31.01.2018,
which does not give any direction to make the payment, the
NHAI cannot be asked to make the payment under the
original award dated 30.03.2013 though it has been restored
by this Court vide judgment and order dated 31.01.2018.
8. It is also sought to be submitted in the affidavit of the
NHAI in a very surprising way that the revised award was
justified in the facts and circumstances of the present case
though the judgment and order dated 31.01.2018 setting
aside the revised award dated 17.12.2014 and reviving the
original award dated 30.03.2013, has attained finality.
9. The further submission made in the affidavit is that an
application under Section 3G(5) dated 20.04.2022 has been
filed by the NHAI challenging the determination made by the
competent authority under the original award dated
30.03.2013 invoking Section 3G(1) of the National Highways
Act, 1956. It is also submitted that the petitioners themselves
have preferred an application under Section 3G(5) on
Page 4 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
23.08.2020, and both the applications are pending
consideration before the statutory Arbitrator.
10. Mr. G.M. Amin, the learned advocate appearing for the
petitioners, however, has seriously disputed the statement
made in the affidavit about filing of the application under
Section 3G(5) by the NHAI.
11. Be that as it may, the question is of non-compliance of
the judgment and order dated 31.01.2018, whereby this Court
has revived the original award dated 30.03.2013. The fact that
the NHAI has filed an application under Section 3G(5),
challenging the original award after having lost in the
litigation before this Court vide judgment and order dated
31.01.2018, and that too, after a period of four years, is to be
taken into account to note the conduct of the NHAI.
12. To our opinion, the NHAI was bound to deposit the
entire compensation amount determined under the original
award dated 30.03.2013 or the differential amount, once the
said award was restored and revived in a reasonable time
period, which has not been done in this case. On one hand,
the NHAI is guilty of non-compliance of the judgment and
order dated 31.01.2018 of this Court revising the original
award dated 30.03.2013 which mandated the NHAI to deposit
the entire compensation amount or the differential amount, as
the case may be, determined under the said award. And on
the other, the plea is of dismissal of the present writ petition
wherein specific directions are sought to comply with the
original award dated 30.03.2013 has been taken, on the
Page 5 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
premise that the NHAI had filed an application under Section
3G(5) after a period of four years of the passing of the
judgment and order dated 31.01.2018 and after about nine
years of making of the original award.
13. From the facts stated in the affidavit of the NHAI, it is
evident that initially an illegal way had been adopted by the
NHAI by asking in writing to the competent authority to revise
the award passed under Section 3G(1) of the National
Highways Act, 1956 when there is no statutory review
provided under the said Act, 1956. The NHAI, thus,
consciously availed the remedy which was not a statutory
remedy depiste having a statutory remedy to assail the
original award under Section 3G(5) of the National Highways
Act, 1956. The fact that the original award had been revised
in the year 2015 and the revised award was allowed to stand
until it was set aside by this Court vide judgment and order
dated 31.01.2018, will not give any leverage or benefit of
limitation to the NHAI. The mere fact that the NHAI has
challenged the original award after a period of about nine
years having lost in the litigation where the revised award
was defended by it, is sufficient for us to reject the contention
of the NHAI that in view of the pendency of the application
under Section 3G(5) before the Arbitrator, it was not duty
bound to deposit the entire compensation amount or the
differential amount, as the case may be, as per the original
award dated 30.03.2013.
14. The fact that the contempt petition filed by the
petitioners had been disposed of with the observations that
Page 6 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
there was no specific direction for payment under the original
award dated 30.03.2013, will not enure any benefit to the
NHAI as the NHAI was mandated and duty bound to make
the deposits of the compensation amount determined under
the original award within a reasonable period from the date of
its revival vide judgment and order dated 31.01.2018 of this
Court.
15. For the above, in the totality of the facts and
circumstances of the present case, we take a very strong
exception to the conduct of the NHAI in dealing with the land
holders, whose lands had been acquired under the National
Highways Act, 1956. We also have a serious view about the
conduct of the officers of the NHAI for acting in this manner,
i.e., not taking proper legal advice to assail the original award
by availing appropriate statutory remedy and misleading and
misguiding the competent authority by writing letters to get
the revised awards. The NHAI is in complete disobedience of
the order of this Court and no leverage, as such, can be
provided to it.
16. We also require that the copy of this order be sent to the
Chairman/Managing Director of the NHAI, who shall initiate
an inquiry to ascertain as to the manner in which the officers
of the NHAI wrote letter to the competent authority seeking
for a revision instead of challenging the original award by
availing the statutory remedy under Section 5G(5) of the
National Highways Act. We say so as looking to the manner in
which the officers of the NHAI have acted, is also against the
own interest of the NHAI as it is saddled with the interest
Page 7 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
liability for illegal actions and inactions of its own officers.
17. With the above, we dispose of the present petition with
the direction to the NHAI to deposit the entire compensation
amount determined under the original award dated
30.03.2013 which remained unpaid (as not deposited) after
the revival of the said award by judgment and order dated
31.01.2018 within a period of four weeks from today, failing
which, it would be open for the petitioners to initiate
contempt proceedings against the officers of the NHAI.
18. We also require the competent authority to pass a
supplementary award determining the statutory interest for
the delay in payment of compensation to the petitioners-land
holders, i.e., for the reason that the differential amount under
the original award dated 30.03.2013 has not been deposited
within a reasonable period by the NHAI after the said award
was revived by the judgment and order dated 31.01.2018. The
supplementary award, determining the interest amount under
Section 80 of the Act, 2013 at the rate of 9% and 15%, shall
be determined from the date of the judgment and order dated
31.01.2018 till the date the said amount is deposited under
the said order. The said supplementary award shall be
rendered within a period of two weeks from today under due
intimation to the petitioners.
19. The process of disbursement of the compensation
deposited by the NHAI, i.e., of the differential amount under
the original award as well as the supplementary award shall
be completed, thereafter, as expeditiously as possible, on the
Page 8 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026

C/SCA/5204/2022 JUDGMENT DATED: 01/10/2026
(GJHC240110912022)
application moved by the petitioners.
20. It goes without saying that once the supplementary
award of statutory interest under Section 80 is passed by the
competent authority, the NHAI shall be obligated to deposit
the determined amount within a period of four weeks from the
date of the order passed by the competent authority. In any
case, the process of disbursement of compensation of the
differential amount as well as the amount determined under
the supplementary award under the directions issued herein
above, shall be completed after due verification about
entitlement of the land holders on a proper application moved
by them.
21. The present writ petition is, accordingly, disposed of in
the above terms.
(SUNITA AGARWAL, CJ )
(DIVYESH A. JOSHI,J)
VAHID
Page 9 of 9
Uploaded by ABDULVAHID A SHAIKH(HC00955) on Mon Oct 05 2026 Downloaded on : Mon Oct 05 16:51:41 IST 2026