Jansatta Sehkri Awas Samiti Ltd vs M/S Gobind Ram Chaprana & Sons

Court
Delhi High Court

* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Date of decision: 18 AUGUST, 2026
IN THE MATTER OF:
# CNR No. DLHC010108392020
+ O.M.P. (COMM) 199/2020 & I.A. 2641/2014
JANSATTA SEHKRI AWAS SAMITI LTD .....Petitioner
Through:

versus

M/S GOBIND RAM CHAPRANA & SONS .....Respondent
Through: Mr. Sameer Nandwani and Mr.
Aashirwad, Advs.

CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT
1. The challenge in the present Petition being O.M.P. (COMM)
199/2020 is to the Award dated 06.07.2013 passed by the Ld. Sole Arbitrator
( hereinafter referred to as the “ Impugned Award ”).
2. The facts, in brief, as borne out from the material on record, are stated
as under:
i. The Petitioner, Jansatta Sehkari Awas Samiti Ltd., is a cooperative
group housing society registered under the U.P. Group Housing
Cooperative Societies Act having its camp office at 9-10 Express
Building, Bahadur Shah Jafar Marg, New Delhi – 110002.
ii. The Respondent, M/s Gobind Ram Chaprana & Sons is a partnership
concern engaged in the business of civil construction.
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 1 of 27

22.08.2026 18:28

iii. It is stated that on 30.03.1998, the Petitioner appointed M/s Organic
India as the architect for the proposed housing project and entered
into an Agreement with it for rendering architectural and supervisory
services.
iv. It is stated that the Petitioner thereafter invited tenders through an
advertisement calling upon civil contractors for construction of 110
flats at Plot No.1, Sector – 9, Vasundhara, Ghaziabad.
v. It is stated that on 23.07.1998, the Petitioner entered into an
Agreement with the Respondent for construction of 110 flats, having
a total built-up area of approximately 1,33,000 sq. ft., for a total
contract value of Rs.7,53,44,346/- ( hereinafter referred to as the
“ Contract ”). It is further stated that the construction was to be
completed within a period of 2 (two) years from the commencement
of the work.
vi. It is stated that the Respondent deposited an amount of Rs.1,50,000/-
as earnest money, which was to be adjusted towards the security
deposit, and was also paid an advance of Rs.1,25,000/- by the
Petitioner. It is further stated that the internal electrical works were
also entrusted to the Respondent under a separate Agreement
executed on 23.07.1998.
vii. It is stated that during the period 1998-1999, several meetings were
held between the Respondent and the architect for discussions
concerning the architectural plans, structural drawings and other
construction related issues.
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 2 of 27

22.08.2026 18:28

viii. It is stated that vide letter dated 20.01.1999, the Petitioner directed the
Respondent to commence the construction work from 22.01.1999
after collecting the requisite drawings from the architect.
ix. It is stated that in its meeting held on 05.03.1999, the Managing
Committee accorded post-facto approval to a bill submitted by the
Respondent. Thereafter, on 10.04.1999, part payments were released
by the Petitioner to both the architect and the Respondent.
x. It is stated that discrepancies were subsequently noticed in the
structural drawings. Accordingly, the Secretary of the Petitioner,
addressed a letter dated 08.07.1999 to the architect highlighting such
discrepancies. Thereafter, the Engineers also addressed a
communication dated 19.09.1999 to the architect regarding the issues
in the drawings.
xi. It is stated that as no corrective action was taken by the architect, the
Secretary of the Petitioner once again addressed a letter dated
15.10.1999 pointing out the architect‟s failure to rectify the
discrepancies and alleging negligence in verifying the Measurement
Book records and the running bills.
xii. It is stated that the Managing Committee of the Petitioner, in its
meeting held on 26.12.1999, accorded post-facto approval to another
bill raised by the Respondent.
xiii. It is stated that owing to the continued delay in the execution of the
project despite substantial expenditure, the Petitioner constituted an
Enquiry Committee to examine the reasons for the delay. The Enquiry
Committee addressed letters dated 14.06.2000 and 30.06.2000 to the
architect seeking an explanation as to whether the expenditure of
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 3 of 27

22.08.2026 18:28

approximately Rs.8,00,00,000/- was commensurate with the stage of
construction and calling upon the architect to furnish the relevant
details.
xiv. It is stated that the Respondent continued to carry out the construction
work till 31.07.2000, although the progress of the work remained
slow.
xv. It is stated that being dissatisfied with the conduct of the architect,
particularly his failure to provide drawings and necessary documents,
the Petitioner appointed M/s Anil Ashok & Associates, Chartered
Accountants, vide letter dated 27.03.2001, to conduct an internal audit
of the entire construction project. It is stated that the first part of the
audit report was submitted on 15.06.2001, the second part on
25.06.2001, and the final audit report on 25.04.2002.
xvi. It is stated that a Memorandum of Compromise/Supplementary
Agreement dated 25.03.2002 was executed between the Petitioner and
Respondent for competition of the balance work ( hereinafter referred
to as the “ Supplementary Agreement ”). Under the said
supplementary agreement, the measurement work was agreed to be
completed by the Respondent.
xvii. It is stated that upon consideration of the audit findings, the General
Body Meeting of the Petitioner held on 28.04.2002 resolved to
undertake re-measurement of the civil works executed by the
Respondent along with verification of the quantities. Pursuant thereto,
a Re-measurement Committee conducted the exercise and submitted
its report containing the actual measurements and quality assessment
of the civil works.
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 4 of 27

22.08.2026 18:28

xviii. It is stated that thereafter, vide letter dated 15.07.2002, the Petitioner
addressed the architect highlighting his alleged callous, negligent and
irresponsible conduct. The architect is stated to have replied to the
said communication denying the allegations levelled against him.
xix. It is stated that the Petitioner thereafter issued a letter dated
17.01.2003 calling upon the Respondent to complete the balance work
and to reconcile the accounts between the parties.
xx. It is further stated that vide communication dated 14.02.2003, the
Petitioner once again reminded the architect of his contractual
obligations and alleged that a loss of approximately Rs.1,70,00,000/-
had been suffered on account of his negligence.
xxi. It is stated that disputes arose between the parties in consequence
thereof, and the matter was referred to arbitration, wherein Hon‟ble
Justice Mr. V.S. Aggarwal, Former Judge of this Court was appointed
as the sole arbitrator to adjudicate the disputes.
xxii. The claims made by the Respondent before the learned Sole
Arbitrator reads as under:
a) An amount of Rs.97,38,202/- payable towards the bills raised;
b) An amount of Rs.71,45,955/- payable towards the escalation
charges; and
c) An amount of Rs.42,54,869/- payable towards interest @18%
p.a. from 21.11.2005 till the petition was filed
xxiii. The Petitioner raised counter-claims. The said counter-claims are
extracted below for reference and the same reads as under:
a) over payment to the contractor Rs. 96,56,745/-;

Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 5 of 27

22.08.2026 18:28

b) highly inflated rates quoted by the claimant Rs.
2,05,76,825/-;

c) loss caused by the claimant and harassment Rs.
60,00,000/-;

d) interest at 18% per annum

In all the respondent besides costs of arbitration
claims Rs. 3,52,33,570/-. ”

xxiv. The following issues were framed by the Arbitral Tribunal on
05.12.2006:
“23. From these pleadings of the parties, this tribunal
framed the following questions in controversy on
05.12.2006:-

QUESTIONS

1. Whether Rs. 97,38,202/- is due to the claimant
for the professional work?

2. Whether the claimant is entitled to the
escalation amount of Rs. 71,45,955/-?

3. Whether the claimant is entitled to interest @
18% per annum on the sum claimed?

4. Whether the respondent is entitled to Rs.
96,56,745/- for the alleged over-payment to the
contractor?

5. Whether the respondent is entitled to Rs.
2,05,76,825/- for the alleged inflated rates charged by
the claimant?

Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 6 of 27

22.08.2026 18:28

6. Whether the respondent is entitled to Rs. 50
lakhs for the alleged delay in execution of the work?

7. Whether the respondent is entitled to interest? If
so, at what rate?

8. Relief. ”

xxv. Thereafter, vide Order dated 16.01.2007 of the Arbitral Tribunal, the
learned Sole Arbitrator, at the request of the parties, framed an
additional issue, being Issue No.7A, in the following terms:
“ 7A Whether respondent can claim the amount, if any, from the
claimant despite having filed the claim against the architecture? ”
xxvi. It is stated that the Arbitral Tribunal rendered its Award dated
06.07.2013.
xxvii. The learned Sole Arbitrator recorded that there was no dispute
between the Petitioner and the Respondent regarding the allotment of
the plot to the Petitioner for the construction of residential flats. It was
noted that, pursuant to the advertisement issued by the Petitioner
inviting tenders, a Technical Committee was constituted which
selected the Respondent as the contractor for execution of the works
under the Contract. The learned Sole Arbitrator further observed that
the Technical Committee had also recommended the engagement of
an architect and, accordingly, the construction was required to be
executed strictly in accordance with the drawings and specifications
prepared by M/s Organic India, the appointed architect.
xxviii. The learned Sole Arbitrator further noted that both parties had
adduced oral and documentary evidence in support of their respective
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 7 of 27

22.08.2026 18:28

cases. On behalf of the Respondent, the affidavit of Shri Raj Pal Singh
Kalyan, one of its partners, was tendered in evidence. On behalf of the
Petitioner, affidavits were filed by (i) Shri Ram Bahadur Rai (RW-1),
the President of the Petitioner Society from 1993 to 2003; (ii) Shri
Manoj Kumar Misra (RW-2), an allottee of a flat since July 2000; (iii)
Shri Arihan Jain (RW-3), who headed the three-member Committee
constituted to measure the civil works executed at the site; and (iv)
Shri Ashok Kumar Walia (RW-4), who had prepared and submitted
the Audit Report.
xxix. The learned Sole Arbitrator thereafter referred to and relied upon
certain material terms and conditions of the Contract, which have
been extracted hereinbelow:
“31. Before proceeding to consider the questions in
controversy, it must be mentioned that the agreement
between the parties dated 23.07.1998 is not in dispute.
The relevant extract of the same clearly indicates
certain salient features of the agreement. The
respondent through its architect had the right to alter
the drawing and the nature of the work to be carried
on by the claimant. The work had to be carried out by
the claimant. The work had to be carried out as per the
drawings and specifications prepared by M/s. Organic
India (the Architect). Paragraph No. 2.5 states that the
order to be done from time to time by the Society has to
be carried and may not be shown on the drawings.
Paragraph 2.7 permits rebate of 3% on the gross
amount of the bill excluding the cost of materials
supplied by the society. Paragraph 2.8 states that the
contractor will not claim any escalation towards
labour and material for the first thirteen months but
subsequently it could be worked out as per clause 34 of
the tender. In para 2.9 it is mentioned that in the final
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 8 of 27

22.08.2026 18:28

payment bill the total gross quantity of the materials
supplied to the contractor shall be mentioned upto the
completion of the work. The said paragraphs read as
under:-

“2.5. Ordered to be done from time to time by the
Society even though such works may not be shown on
the drawings or described in the said specifications or
the said schedule of quantities.

2.6. The said conditions, specifications and appendix
as given in tender thereto shall be read and considered
as forming part of this agreement, and the parties
hereto shall abide by, submit themselves to the
conditions and perform the Agreement on their part
respectively in such conditions as contained.

2.7. A rebate of 3% on the gross amount of the bill
excluding the cost of materials supplied by the society
will be given by the contractor.

2.8. The contractor will not claim any escalation
towards labour and material for the first thirteen
months from the date of award of work. Subsequently
escalation will be worked out as per clause 34 of the
tender and these again will be negotiated to the mutual
satisfaction of both the parties.

2.9. The following materials will be supplied by the
society at sites, rates given against each item.

i) Cement in bags @ Rs. 125/- per bag weighing 50 kg.
ii) For Steel @ Rs.1,500 per quintal.
iii) Bricks @ Rs. 1,310/- per thousand.

The cost of above materials shall be deducted from the
running account bills of the contractor in the following
manner:-
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 9 of 27

22.08.2026 18:28


a) From running account interim bills actual quantity
consumed and charged for in each respective bill.

b) In the final payment bill account, the total gross
quantities of materials supplied to the contractor upto
the completion of the work. The wastage etc shall be
borne by the contractors and any residue of the
materials shall be the property of the contractors. ”

th
xxx. The learned Sole Arbitrator observed that the 18 Running Bill had
never been submitted to the Petitioner during the subsistence of the
Contract and was produced for the first time only along with the
Statement of Claim before the Arbitral Tribunal. The learned Sole
Arbitrator found that there was no material to establish that the said
Bill had ever been forwarded to the Petitioner. It was further noticed
that, after the Petitioner pointed out discrepancies in the said Bill, the
th
Respondent itself filed a revised 18 Running Bill along with its
Rejoinder before the Arbitral Tribunal. The learned Sole Arbitrator
also took note of the fact that several Committees had been
constituted by the Petitioner and multiple reports had been prepared in
relation to the execution and measurement of the works. In these
circumstances, the learned Sole Arbitrator found it difficult to accept
th
the Respondent‟s contention that the 18 Running Bill had been
consistently raised while such disputes, inspections and measurement
exercises were simultaneously underway.
xxxi. The learned Sole Arbitrator further placed considerable reliance upon
the Supplementary Agreement executed between the parties. It was
observed that under the said Agreement, the parties had jointly
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 10 of 27

22.08.2026 18:28

measured the unfinished work, assessed the value of the balance work
at approximately Rs. 54,00,000/-, agreed that the Respondent would
complete the remaining works under a revised payment schedule, and
further agreed that an additional sum of Rs. 6,50,000/- would be
payable towards the Respondent‟s earlier claim, subject to verification
upon completion of the measurements.
xxxii. The learned Sole Arbitrator further recorded that the Respondent had
never challenged either the execution or the validity of the
Supplementary Agreement. It was held that the said Agreement
constituted a fresh and binding contract governing the completion of
the balance works and superseded the earlier disputes relating to the
unfinished work. The learned Sole Arbitrator further held that the
Supplementary Agreement prescribed a fresh payment mechanism
regulating the subsequent rights and obligations of the parties.
Consequently, it was observed that the Respondent could not
disregard the terms of the Supplementary Agreement and seek
th
recovery solely on the basis of the disputed 18 Running Bill.
xxxiii. Upon evaluating the work proved to have been executed and the
amounts found payable under the Supplementary Agreement, the
learned Sole Arbitrator concluded that the Respondent had failed to
substantiate its claim for Rs. 97,38,202/- founded upon the disputed
th
18 Running Bill. Accordingly, instead of allowing the claim in terms
of the entire Running Bill, the learned Sole Arbitrator restricted the
Respondent‟s entitlement to a sum of Rs. 14,25,000/-.
xxxiv. The learned Sole Arbitrator noted that once the parties had entered
into the Supplementary Agreement, the Respondent could not seek
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 11 of 27

22.08.2026 18:28

payment beyond what had been agreed therein. He further noted that
Supplementary Agreement did not contain any provision for payment
of escalation charges and instead, it fixed the consideration payable
for completion of the remaining work.
xxxv. The learned Sole Arbitrator further noted that the Supplementary
Agreement superseded the Respondent‟s earlier monetary claims and
barred any claim exceeding the amounts agreed therein, except the
reserved sum of Rs.6,50,000/-, which was separately allowed because
the Petitioner failed to prove overpayment.
xxxvi. The learned Sole Arbitrator thereafter proceeded to adjudicate the
disputes between the parties, including the claims preferred by the
Respondent and the counter-claims raised by the Petitioner. As a
natural corollary, the learned Sole Arbitrator rejected the counter-
claims of the Petitioner.
xxxvii. Upon such adjudication, the learned Sole Arbitrator awarded a sum of
Rs.14,25,000/- in favour of the Respondent along with interest at the
rate of 18% per annum from 25.08.2005 till 30.06.2013 i.e.
Rs.20,13,525/-.
3. Now, by way of the instant Petition, the Petitioner challenges the
findings of the learned Sole Arbitrator, on the ground that the Impugned
Award is in violation of the public policy of India. The following arguments
have been raised, praying for the setting aside of the Impugned Award:
a) It is contended that the learned Sole Arbitrator failed to determine
whether the arbitral proceedings were required to be conducted ex
aequo et bono or in the capacity of an amiable compositeur , in terms
of Section 19 of the Arbitration and Conciliation Act, 1996
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 12 of 27

22.08.2026 18:28

(hereinafter referred to as the “ Act ”). It is further contended that the
procedure adopted by the learned Sole Arbitrator at the inception of
the proceedings vitiated the entire arbitral proceedings.
b) It is further contended that the learned Sole Arbitrator failed to
consider Issue No.7A - whether the Petitioner herein can claim any
amount, if any, from the Respondent despite having already raised a
claim against the architect, which claim remained pending and
undecided. It is submitted that the failure to adjudicate upon the said
issue rendered the entire arbitral proceedings and the Impugned
Award perverse and unsustainable in law. He further stated that the
Sole Arbitrator neglected to proceed with the arbitration proceedings
as per the provisions of Section 24 of the Act.
c) It is contended that the Impugned Award is legally untenable as the
learned Sole Arbitrator failed to consider the relevant facts and
applicable contractual provisions, particularly those relating to the
issuance of the certificate of virtual completion, jointly and/or
severally by the Respondent and the Architect. It is further contended
that the learned Sole Arbitrator arrived at findings which were
inconsistent even with his own conclusions and disregarded material
documents, including the document evidencing payment of
Rs. 15,62,052/- to another contractor, namely Mr. Rehmat Ali, for
works admittedly left incomplete by the Respondent.
d) It is contended that the learned Sole Arbitrator failed to adjudicate the
disputes in accordance with the terms of the Contract and disregarded
the established usage of trade applicable to the transaction.
Consequently, the learned Sole Arbitrator is alleged to have failed to
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 13 of 27

22.08.2026 18:28

adhere to the contractual terms and conditions as well as the
applicable principles of substantive law, thereby rendering the
Impugned Award contrary to the public policy of India.
e) It is further contended that the learned Sole Arbitrator failed to give
effect to the contractual provision relating to damages for non-
completion of the works, despite the admitted position that the
Respondent had not completed the works in all respects. It is
submitted that the Petitioner had suffered losses on account of the
Respondent‟s negligence and failure to complete the works entrusted
to it. It is further contended that the Respondent‟s non-compliance
exposed the Petitioner to the risk of proceedings in relation to
procurement of the completion certificate from the competent
authority, particularly in view of the letter dated 24.09.2013 bearing
No. 1809/APD-16/138.
f) It is contended that the Impugned Award is contrary to the public
policy of India as the learned Sole Arbitrator deliberately disregarded
the rate differential amounting to more than Rs. 1,00,00,000/-, based
upon the rates quoted by the U.P. Awas & Vikas Parishad for
construction of civil projects. It is further contended that the learned
Sole Arbitrator erroneously concluded that the joint measurement of
defects in the individual flats covered the flats in their entirety and
that the value of the remaining work was only approximately
Rs. 1,00,000/-. According to the Petitioner, the joint measurement
revealed that nearly 50% of the flats remained closed and were
therefore not measured. It is alleged that the measurements
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 14 of 27

22.08.2026 18:28

undertaken were the result of collusion between the Architect and the
Respondent.
g) It is stated that the learned Sole Arbitrator neglected to decide the
issue whether the Petitioner is entitled to Rs.50,00,000/- for the
alleged delay in execution of the work, and till date the architect has
not given the completion report of the project nor any document
submitted before the learned Sole Arbitrator and as per the
Supplementary Agreement, it provided for the measurement of works
done by the Respondent or after completion of the project and the
Respondent neither completed the project nor appeared for
measurement of works done.
h) It is contended that the learned Sole Arbitrator failed to obtain expert
opinion by appointing an expert as contemplated under Section 26 of
the Act. It is further alleged that the learned Sole Arbitrator failed to
comply with the statutory mandate contained in Section 18 of the Act
and consequently rendered the Impugned Award in violation of
Section 31(3) of the Act.
4. Per contra , the learned Counsel for the Respondent has argued as
under:
a) It is contended that the delay in completion of the works was
attributable, inter alia, to delays on the part of the Petitioner in
handing over the site, repeated modifications to the site drawings and
the execution of additional works, all of which prolonged the
completion period. It is further submitted that internal disputes within
the Petitioner-Society resulted in financial constraints and delayed
payments to the Respondent, thereby constituting breaches of the
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 15 of 27

22.08.2026 18:28

Contract and further delaying completion of the works, besides
causing losses to the Respondent.
b) It is submitted that the Petitioner has failed to establish any of the
grounds contemplated under Section 34 of the Act for setting aside
the Impugned Award. Reliance has been placed upon the judgment of
this Court in NTPC Ltd. v. Larsen & Toubro, 2024 SCC OnLine Del
126 .
c) It is further submitted that the contentions advanced by the Petitioner
do not fall within the recognised ground of violation of the public
policy of India. According to the Respondent, the Petitioner‟s
challenge essentially concerns the alleged differential between the
rates quoted by the Respondent and those quoted by the U.P. Awas &
Vikas Parishad, which cannot constitute a ground for interference
under Section 34 of the Act. Reliance has been placed upon the
judgment of the Apex Court in Delhi Airport Metro Express Pvt. Ltd.
v. Delhi Metro Rail Corporation Ltd., 2021 SCC OnLine SC 695 .
5. Heard the learned Counsels for the parties and perused the material on
record.
6. Before dealing with the merits of the case, this Court deems it fit to
recall the contours within which an application under Section 34 of the Act
can be adjudicated upon, with specific emphasis on the parameter of
challenge based on violation of „public policy‟.
7. It is trite law that a challenge to the arbitral award can only be on the
grounds provided under Section 34 of the Act. The award should not be
interfered with until the conclusion arrived at is perverse. Proceedings under
Section 34 of the Arbitration Act cannot be equated with appellate
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 16 of 27

22.08.2026 18:28

jurisdiction and the court cannot reappreciate evidence. Accordingly,
interference by the court is limited to the grounds specified under the
Arbitration Act, including violation of public policy, fundamental principles
of Indian law or patent illegality going to the root of the matter. Mere errors
of law or reassessment of evidence do not justify setting aside an arbitral
award. Reference is made of the Judgment of the Apex Court in MMTC Ltd.
v. Vedanta Ltd., ( 2019) 4 SCC 163 , wherein the following observations were
made:
“ 11. As far as Section 34 is concerned, the position is well-
settled by now that the Court does not sit in appeal over the
arbitral award and may interfere on merits on the limited
ground provided under Section 34(2)(b)(ii) i.e. if the award is
against the public policy of India. As per the legal position
clarified through decisions of this Court prior to the
amendments to the 1996 Act in 2015, a violation of Indian
public policy, in turn, includes a violation of the fundamental
policy of Indian law, a violation of the interest of India,
conflict with justice or morality, and the existence of patent
illegality in the arbitral award. Additionally, the concept of
the “fundamental policy of Indian law ” would cover
compliance with statutes and judicial precedents, adopting a
judicial approach, compliance with the principles of natural
justice, and Wednesbury [Associated Provincial Picture
Houses Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 (CA)]
reasonableness. Furthermore, “ patent illegality ” itself has
been held to mean contravention of the substantive law of
India, contravention of the 1996 Act, and contravention of
the terms of the contract.

12. It is only if one of these conditions is met that the Court
may interfere with an arbitral award in terms of Section
34(2)(b)(ii), but such interference does not entail a review of
the merits of the dispute, and is limited to situations where
the findings of the arbitrator are arbitrary, capricious or
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 17 of 27

22.08.2026 18:28

perverse, or when the conscience of the Court is shocked, or
when the illegality is not trivial but goes to the root of the
matter. An arbitral award may not be interfered with if the
view taken by the arbitrator is a possible view based on facts.
(See Associate Builders v. DDA [Associate Builders v. DDA,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] . Also see ONGC
Ltd. v. Saw Pipes Ltd. [ONGC Ltd. v. Saw Pipes Ltd., (2003)
5 SCC 705] ; Hindustan Zinc Ltd. v. Friends Coal
Carbonisation [Hindustan Zinc Ltd. v. Friends Coal
Carbonisation, (2006) 4 SCC 445] ; and McDermott
International Inc. v. Burn Standard Co. Ltd. [McDermott
International Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC
181] )

13. It is relevant to note that after the 2015 Amendment to
Section 34, the above position stands somewhat modified.
Pursuant to the insertion of Explanation 1 to Section 34(2),
the scope of contravention of Indian public policy has been
modified to the extent that it now means fraud or corruption
in the making of the award, violation of Section 75 or Section
81 of the Act, contravention of the fundamental policy of
Indian law, and conflict with the most basic notions of justice
or morality. Additionally, sub-section (2-A) has been inserted
in Section 34, which provides that in case of domestic
arbitrations, violation of Indian public policy also includes
patent illegality appearing on the face of the award. The
proviso to the same states that an award shall not be set aside
merely on the ground of an erroneous application of the law
or by reappreciation of evidence.
14. As far as interference with an order made under Section
34, as per Section 37, is concerned, it cannot be disputed that
such interference under Section 37 cannot travel beyond the
restrictions laid down under Section 34. In other words, the
court cannot undertake an independent assessment of the
merits of the award, and must only ascertain that the exercise
of power by the court under Section 34 has not exceeded the
scope of the provision. Thus, it is evident that in case an
arbitral award has been confirmed by the court under Section
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 18 of 27

22.08.2026 18:28

34 and by the court in an appeal under Section 37, this Court
must be extremely cautious and slow to disturb such
concurrent findings.”

8. Reference is also made to a judgment rendered by a three-Judge
Bench of the Apex Court in OPG Power Generation (P) Ltd. v. Enexio
Power Cooling Solutions (India) (P) Ltd., (2025) 2 SCC 417, wherein the
following discussion regarding how the term „public policy‟ is to be
construed is pertinent:
“ Relevant legal principles governing a challenge to
an arbitral award
30. Before we delve into the issue/sub-issues culled out
above, it would be useful to have a look at the relevant
legal principles governing a challenge to an arbitral
award. Recourse to a court against an arbitral award
may be made through an application for setting aside
such award in accordance with sub-sections (2), (2-A)
and (3) of Section 34 of the 1996 Act. Sub-section (2)
of Section 34 has two clauses, (a) and (b). Clause (a)
has five sub-clauses which are not relevant to the
issues raised before us. Insofar as clause (b) is
concerned, it has two sub-clauses, namely, (i) and (ii).
Sub-clause (i) of clause (b) is not relevant to the
controversy in hand. Sub-clause (ii) of clause (b)
provides that if the Court finds that the arbitral award
is in conflict with the public policy of India, it may set
aside the award.

Public policy
31. “Public policy” is a concept not statutorily defined,
though it has been used in statutes, rules, notification,
etc. since long, and is also a part of common law.
Section 23 of the Contract Act, 1872 uses the
expression by stating that the consideration or object of
an agreement is lawful, unless, inter alia, opposed to
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 19 of 27

22.08.2026 18:28

public policy. That is, a contract which is opposed to
public policy is void.

35. In Renusagar Power Co. Ltd. v. General Electric
Co., 1994Supp (1) SCC 644, a three-Judge Bench of
this Court observed that the doctrine of public policy is
somewhat open—textured and flexible. By citing
earlier decisions, it was observed that there are two
conflicting positions which are referred to as the
“narrow view” and the “broad view”. According to the
narrow view, courts cannot create new heads of public
policy whereas the broad view countenances judicial
law making in these areas. In the field of private
international law, it was pointed out, courts refuse to
apply a rule of foreign law or recognise a foreign
judgment or a foreign arbitral award if it is found that
the same is contrary to the public policy of the country
in which it is sought to be invoked or enforced.
However, it was clarified, a distinction is to be drawn
while applying the rule of public policy between a
matter governed by domestic law and a matter
involving conflict of laws. It was observed that the
application of the doctrine of public policy in the field
of conflict of laws is more limited than that in the
domestic law and the courts are slower to invoke
public policy in cases involving a foreign element than
when a purely municipal legal issue is involved. It was
held that contravention of law alone will not attract the
bar of public policy, and something more than
contravention of law is required.
37. What is clear from above is that for an award to be
against public policy of India a mere infraction of the
municipal laws of India is not enough. There must be,
inter alia, infraction of fundamental policy of Indian
law including a law meant to serve public interest or
public good.”

Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 20 of 27

22.08.2026 18:28

9. This court also deems it appropriate to refer to the Supplementary
Agreement executed between the parties, which is relevant for the proper
adjudication of the present dispute and is reproduced hereinbelow:
“ 34. The respondent filed Memorandum of
Compromise between the parties dated 25.3.2002. The
said Memorandum of Compromise reads as under:-
“Memorandum of Compromise between Jansatta
Awas Samiti and M/s. Govind Ram Chaprana &
Sons:
The measurement of left over works in Jansatta
Sahkari Awas Samiti was done by the Engineers of the
society and the builder M/s. Govind Ram Chaprana &
Sons jointly. As per this measurement, the cost of left
over works was estimated (including the sanitary
fittings of Rs. 5 lac approximately) to the tune of Rs. 54
lac. In the meeting attended by the Managing
Committee of the society and the builder, it was
mutually agreed that the left over works (including the
development work as per tender specification till
25.3.2002) were to be completed within an agreed and
stipulated amount of 36,25,000/-. It was decided that
remaining material of sanitary fittings, the bill of
which is not submitted by the builder, will be provided
by the society. The description of completing left over
works and its payment scheduled will be following :-
Date of
completion
Srl.No. Block
Date of payment
of work
01.04.2002
Rs. 2,00,000/-
01.4.2004
1. D Block
14.4.2002
20.04.2002
Rs. 8,00,000/-
08.04.2002
2. E Block
14.04.2002
3. B Block 23.4.2002 05.05.2002
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 21 of 27

22.08.2026 18:28

25.5.2002 Rs. 8,00,000/-
20.05.2002
4. A' Block
20.06.2002
30.05.2002
Rs. 4,00,000/-
20.06.2002
5. C Block
05.07.2002
07.06.2002 - Rs.
4,00,000/-
Development
6.
works
10.04.2002
25.04.2002
20.06.2002 - Rs.
8,00,000/-
Water tank
and Other
woks
20.05.2002
01.06.2002
12.07.2002 - Rs.
7.
5,00,000/-

Rs. 6,50,000/- have been further included in the above
mentioned payment schedule of Rs. 36,25,000/- as per
the claim of the builder, this amount is to be paid to
him on account of previous works done by him, the
payment of which was not made to him. But the final
decision about the payment of this previous due
payment will be done after the measurement works of
civil construction till March 25, 2002 is being
completed.
Both the parties agree:
1. The measurement work will be completed by
28.04.2002.
2. After the completion of measurement work, if it is
found that the society does not have to pay to the
builder the mentioned amount of Rs. 6,50,000/- will not
be paid to the builder.
3. If after the completion of measurement work, it
transpires that the builder has to pay the society the
excess amount in that case the society will deduct his
amount from the amount to be paid to the builder
against the payment of left over works.
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 22 of 27

22.08.2026 18:28

4. 10% (maximum Rs. 3,50,000/-) of the total amount of
left over works will be paid only after the all left over
work of the society is completed.”

10. Now, this Court shall deal with the rival contentions advanced on
behalf of the parties.
11. Having considered the rival submissions and upon a comprehensive
examination of the Impugned Award, this Court finds that the challenge
raised by the Petitioner essentially seeks a re-appreciation of the evidence
and a re-adjudication of the contractual disputes which stood conclusively
determined by the learned Sole Arbitrator.
12. The learned Sole Arbitrator, after duly considering the Supplementary
Agreement executed between the parties, noted that its execution and terms
were not disputed by either party. The learned Sole Arbitrator further
recorded that, under the said Agreement, the balance work was required to
be completed by 28.04.2002, and that the value of the work remaining to be
executed was assessed at approximately Rs. 54,00,000/-, which the parties
had mutually agreed would be completed for a consideration of
Rs. 36,25,000/-.
13. The first question which the Arbitral Tribunal considered was whether
the claim of the Respondent to recover a sum of Rs.97,38,202/- for the
th
professional work, which is based on the 18 Running Bill of the
Respondent/Claimant. The Arbitral Tribunal after considering the material
th
on record came to a conclusion that there is no material to show that the 18
running bill had never been submitted nor such work had been effected. The
Arbitral Tribunal found that there was no date on which the said bill had
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 23 of 27

22.08.2026 18:28

been sent, and therefore, came to the conclusion that the contention of the
th
Respondent that the 18 running bill was never submitted, was rejected. The
Arbitral Tribunal restricted the claim only to Rs.14,25,000/-. The Arbitral
Tribunal, thereafter, has referred to a Memorandum of Compromise entered
into between the parties which details out the leftover works for which no
measurement was taken.
14. Upon considering the aforesaid Supplementary Agreement along with
the other material placed on record, the learned Sole Arbitrator rejected the
Petitioner‟s contention that the Respondent/Contractor had been paid
amounts in excess of its entitlement. On the contrary, the material on record
demonstrated that, against the agreed consideration of Rs. 36,25,000/-, the
Respondent had received only Rs. 22,00,000/- towards the work already
executed by it. Accordingly, after accounting for the payments already made
and the amount found payable under the Supplementary Agreement, the
learned Sole Arbitrator awarded a sum of Rs. 14,25,000/- in favour of the
Respondent.
15. The Arbitral Tribunal was, therefore, of the opinion that the Claimant
cannot seek any other claim as no Measurement Book could have been
produced. The Arbitral Tribunal held that though the Petitioner herein did
not produce any material, the Claimant has also not given any evidence to
support the claim.
16. This Court is in agreement with the view taken by the learned Sole
Arbitrator that the Supplementary Agreement constituted a fresh and binding
contract between the parties, governing the completion of balance works.
The said Agreement superseded the earlier disputes pertaining to the
unfinished works and further prescribed a fresh mechanism for payment,
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 24 of 27

22.08.2026 18:28

thereby governing the respective rights and obligations of the parties in
relation to the balance works.
17. The contention that the learned Sole Arbitrator failed to adjudicate
Issue No. 7A, even if assumed to be correct, does not demonstrate any error
going to the root of the Award, merely because there was a separate claim
against the Architect. In any event, the Award, read as a whole, reflects
consideration of the contractual relationship between the parties and the
material circumstances relevant to the claims.

18. The Arbitral Tribunal on the basis of the material on record came to a
conclusion that no stress has been made by the Petitioner herein that there
was delay on the part of the Respondent/Claimant in completing the flats.
The material indicates that there was change in the areas of the flats, there
was increase in number of the flats and the plans were supplied late and
therefore, the entire claim cannot be put on the Respondent herein. The
Arbitral Tribunal after considering the material also came to a conclusion
that there is nothing to show that the work done was defective in nature. On
the issue of collusion between the Respondent and the architect, the Arbitral
Tribunal held that the said issue cannot be based on conjectures and
surmises. The Arbitral Tribunal held that cross examination of the witness
suggests that the architect had suggested that no payment to be made to the
contractor, which is an indication that there was no collusion. It is further
stated that there is no material on record to authenticate the nature of the
deficiencies in the construction. The Arbitral Tribunal held that there is no
material to show that certain extra work has to be done from outside because
of the deficiencies. It is stated that the person who was to depose regarding
the deficiencies of work did not even have any civil engineering experience.
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 25 of 27

22.08.2026 18:28

19. Similarly, the Petitioner‟s contentions regarding the alleged
incomplete works, payment made to Mr. Rehmat Ali, measurements of the
flats, alleged collusion with the Architect, rate differential, delay and
damages essentially invite this Court to reassess the factual and evidentiary
findings recorded by the learned Sole Arbitrator. Such an exercise is
impermissible in proceedings under Section 34 of the Act, particularly
where the view taken by the learned Sole Arbitrator constitutes a plausible
view on the material available before him.

20. The Petitioner has also failed to demonstrate that the Impugned
Award is in conflict with the fundamental policy of Indian law or the most
basic notions of justice or morality, or that the Award suffers from patent
illegality appearing on its face and going to the root of the matter. The mere
assertion that the learned Sole Arbitrator adopted an erroneous approach,
failed to accept certain documents or arrived at a conclusion different from
that sought by the Petitioner cannot, by itself, constitute a ground under
Section 34 of the Act.
21. A careful and comprehensive perusal of the Impugned Award
demonstrates that the learned Sole Arbitrator has examined the pleadings,
documentary material, correspondence exchanged between the parties, and
the evidence led in support of their respective claims and assertions. The
Impugned Award reflects due consideration of the relevant facts and
surrounding circumstances germane to the dispute.
22. The Impugned Award reflects a plausible and reasoned interpretation
of the Contract. It is well settled that a court exercising limited supervisory
jurisdiction under Section 34 of the Act cannot re-appreciate evidence or
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 26 of 27

22.08.2026 18:28

substitute its own interpretation of contractual clauses where the view taken
by the learned Sole Arbitrator is a possible and reasonable one.
23. Viewed in its entirety, the Impugned Award reflects a reasoned and
structured adjudication of the disputes by the learned Sole Arbitrator within
the confines of the contractual terms agreed upon by the parties, the material
placed on record, and the jurisdiction vested in the learned Sole Arbitrator.
The Impugned Award demonstrates due application of mind to the
pleadings, evidence, and relevant contractual provisions.
24. In view of the foregoing discussion, this Court is of the considered
opinion that the Petitioners have failed to establish any ground under Section
34(2) or Section 34(2A) of the Act warranting interference with the
Impugned Award.
25. Accordingly, the present Petition, along with pending Application(s),
if any, stands dismissed.


SUBRAMONIUM PRASAD, J
AUGUST 18, 2026
JR
Signature Not Verified
PRATEEK
O.M.P. (COMM) 199/2020 Page 27 of 27