Sh Nimit Mundhra And Ors vs Union Of India & Ors.

Court
Delhi High Court

$~22
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Date of Decision: 18 August, 2026
# CNR No. DLHC010311982022
+ W.P.(C) 12133/2022 & CM APPL. 36263/2022
SH. NIMIT MUNDHRA AND ORS. .....Petitioners
Through: Mr. Kundan Kumar Mishra and Mr.
Ratnesh Kumar, Advocates.
versus
UNION OF INDIA & ORS. .....Respondents
Through: Ms. Arunima Dwivedi, CGSC with
Ms. Himanshi Singh and Ms.
Monalisha, Advocates.
Mr. R.V. Sinha, Mr. A.S. Singh and
Ms. Shriya Sharma, Advocates for
R-2/RLDA.
CORAM:
HON'BLE MR. JUSTICE AMIT BANSAL
AMIT BANSAL, J. (Oral)
1. The present writ petition has been filed seeking the following reliefs:
Signature Not Verified
Signed By:AARZOO
Signing Date:22.08.2026
16:47:38
W.P.(C) 12133/2022 Page 1 of 7

2. The brief facts necessary for deciding the present petition are set out
below:
2.1. It is the case of the petitioner that the respondent no.2/Rail Land
th
Development Authority (‘RLDA’) had floated a tender on 12 February,
2018 towards a Multi-Functional Complex (‘MFC’) project at Hazipur
Railway Station (‘subject site’).
2.2. The petitioner was found successful bidder and was awarded lease for
the subject site for lease period of 45 years.
2.3. A Letter of Acceptance (LoA) was given in favour of the petitioner on
nd
22 May, 2018.
2.4. Subsequently, a Lease Agreement was entered into between the
th
petitioner and the RLDA on 15 January, 2019.
2.5. The petitioner paid Rs.6,11,00,000/- as lease premium, Rs.13,86,027/-
as interest, and also deposited a bank guarantee of Rs.30,55,000/- as
Signature Not Verified
Signed By:AARZOO
Signing Date:22.08.2026
16:47:38
W.P.(C) 12133/2022 Page 2 of 7

Performance Guarantee.
2.6. As per the Lease Agreement, possession of the subject land had to be
given to the petitioner within thirty (30) days. When the petitioner visited
th
the subject site on 15 February, 2019, the possession was not handed over.
2.7. Certain Alternate sites were offered to the petitioner vide letters dated
st th
1 July, 2019 and 8 November, 2019, which the petitioner did not accept.
2.8. In December, 2019, the original subject site was offered to the
petitioner. However, the petitioner declined to accept the same on the
ground that project is no longer viable.
2.9. The petitioner requested RLDA to terminate the Lease Agreement and
th th
refund the money vide letter dated 27 July, 2020 and 13 August, 2020.
2.10. On the request of the petitioner, the Lease Agreement was terminated
st
vide letter dated 31 August, 2020.
th
2.11. Vide letter dated 29 September, 2020, an amount equal to 75%, i.e.,
Rs. 4,58,25,000/-, paid by the petitioner to RLDA was refunded. The
petitioners also have got a refund of GST amounts totalling to
th
Rs.82,48,500/- on 15 December, 2020. However, the Petitioners did not
receive the remaining outstanding amounts from RLDA.
3. Accordingly, the petitioner approached this Court by way of writ
petition being W.P.(C) 9571/2020, seeking refund of the remaining amount,
th
which was disposed of vide order dated 13 May, 2022 directing the RLDA
to decide the representation of the petitioner after granting a personal
hearing.
th
4. RLDA passed a detailed Speaking Order on 13 June, 2022 rejecting
the representation filed by the petitioner.
th
5. Being aggrieved by the aforesaid Speaking Order dated 13 June,
Signature Not Verified
Signed By:AARZOO
Signing Date:22.08.2026
16:47:38
W.P.(C) 12133/2022 Page 3 of 7

2022, the petitioner filed the present writ petition before this Court.
6. In the counter-affidavit filed on behalf of the RLDA, it is stated that
the present writ petition is not maintainable as it raises disputed questions of
fact.
7. One of the objections taken in the counter-affidavit is that the writ
petition is not maintainable in light of Section 8 of the Arbitration and
Conciliation Act, 1996 as well as Article 23 of the General Conditions of the
Lease Agreement (‘GCLA’) executed between RLDA and the petitioner.
The relevant extract from the counter-affidavit is set out below:
8. It is the contention of the petitioner that there was a delay on the part
of RLDA in handing over the original subject site and that, consequently,
the petitioner was entitled to terminate the Lease Agreement and seek refund
of the entire amount paid by it.
Signature Not Verified
Signed By:AARZOO
Signing Date:22.08.2026
16:47:38
W.P.(C) 12133/2022 Page 4 of 7

9. In this context, the Speaking Order passed by the RLDA specifically
notes that in respect of delay, RLDA was willing to adjust the period of
delay by extending the lease period. Further, the delay did not constitute a
ground for termination of the lease.
10. In this regard, reference may be made to Article 21.3 of the GCLA,
which sets out the circumstances constituting an ‘RLDA’s Event of Default’.
Article 21.3(a) provides that failure on the part of RLDA to provide the
petitioner the right of way to the site for more than twelve months would
constitute an ‘RLDA’s Event of Default’, entitling the petitioner to terminate
the agreement.
11. In the present case, the original site was offered to the petitioner on
nd
2 December, 2019, i.e. , within twelve months from the date of execution of
th
the Lease Agreement on 15 January, 2019. Thus, the Speaking Order
records that the circumstances contemplated under Article 21.3(a) had not
arisen and that there was no breach of the Lease Agreement on the part of
RLDA.
12. Further, Article 14.2.3 of the GCLA gives the petitioner a right to
seek damages in the event of any failure or delay on the part of RLDA in
handing over the right of way to the site. However, it does not confer a right
to terminate or otherwise vitiate the Lease Agreement on that account.
13. The Speaking Order further records that the petitioner, without
adhering to the provisions of Articles 21.3 and 14.2.3, chose to terminate the
Lease Agreement before commencement of Commercial Operation, thereby
attracting Clause 13 of the Special Conditions of Lease Agreement
(‘SCLA’), which provides that that in the event of termination before
commencement of Commercial Operation, RLDA shall make a Termination
Signature Not Verified
Signed By:AARZOO
Signing Date:22.08.2026
16:47:38
W.P.(C) 12133/2022 Page 5 of 7

Payment equivalent to 75% of the total amount of Lease Premium paid by
the petitioner to RLDA. The Speaking Order accordingly holds that the
decision of RLDA to invoke Clause 13 of the SCLA was just and fair.
14. It is settled law that a writ petition involving contractual disputes and
disputed questions of fact is ordinarily not maintainable under Article 226 of
the Constitution, particularly where the contract provides for an alternate
mechanism for resolution of disputes.
th
15. A Division Bench of this Court vide judgement dated 13 July, 2021
in W.P.(C) 6434/2021 titled as Rajkumari Mundra v. Union of India , while
dealing with the cancellation of the Letter of Acceptance issued in favour of
the petitioner and the subsequent issuance of a fresh tender for the same
parcel of land, held that this Court was not inclined to go into the
commercial disputes between the parties, as the same would involve
determination of disputed questions of fact, and accordingly gave liberty to
the petitioner to avail of the remedies in respect of the tender. The relevant
paragraphs of the said judgement are set out below:
“6. The Letter of Acceptance in favour of the petitioner having been cancelled,
the same raises disputes arising out of the contractual obligation. These
disputes are factual in nature and, in case, the petitioner has any grievance,
it is for the petitioner to invoke the available remedy arising from the terms
of the tender/ Letter of Acceptance. In these proceedings we are not inclined
to go into the commercial disputes between the parties which, obviously,
would involve determination of disputed questions of facts. Even otherwise,
the conduct of the petitioner demonstrates latches on the part of the petitioner,
in now raising the dispute in relation to the cancellation of the Letter of
Acceptance after the respondent issued a fresh RFP on 18.05.2021. The
petitioner did not take any steps to raise his grievance either before
18.05.2021, or even soon thereafter.
7. For the aforesaid reasons, we are also not inclined to interfere with the
fresh RFP issued on 18.05.2021. We, accordingly, dismiss this petition with
Signature Not Verified
Signed By:AARZOO
Signing Date:22.08.2026
16:47:38
W.P.(C) 12133/2022 Page 6 of 7

liberty to the petitioner to avail of his remedies in respect of the cancellation
of the Letter of Acceptance dated 09.04.2021 .”
[emphasis supplied]
16. Having heard the counsel for the parties, in the opinion of this Court,
the present writ petition raises disputed questions of fact as well as
interpretation of contractual clauses which cannot be entertained under
Article 226 of the Constitution of India. These issues necessarily have to be
decided in terms of the arbitration clause provided in the Lease Agreement.
17. Counsel for the petitioner submits that the RLDA may take a position
that disputes which are subject matter of the present petition are not covered
under the arbitration clause being ‘Excepted Matters’. As is evident from the
averments made in the counter-affidavit, RLDA itself acknowledges that the
disputes are arbitrable. Therefore, the aforesaid apprehension of petitioner
stands addressed.
18. Accordingly, the present writ petition is dismissed while leaving it
open for the petitioner to invoke the arbitration clause under the Lease
Agreement.
19. Needless to state, the time spent by the petitioner in pursuing the
present writ petition as well as the previous writ petition filed by the
petitioner before this Court would be considered for exclusion for the
purposes of computation of limitation in the arbitration proceedings.
20. Pending application stands disposed of.
AMIT BANSAL, J
AUGUST 18, 2026/ Rzu