Ashima Infrastructure Pvt Ltd vs North Delhi Municipal Corporation
- Court
- Delhi High Court
- Case type
- Original Misc Petition Commercial
- Decided on
- 11-03-2026
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Date of decision: 11 MARCH, 2026
IN THE MATTER OF:
+ O.M.P. (COMM) 53/2026 & I.A. 2281/2026, I.A. 2282/2026
ASHIMA INFRASTRUCTURE PVT LTD .....Petitioner
Through: Mr. Manoj Kumar Sahu, Advocate.
versus
NORTH DELHI MUNICIPAL CORPORATION .....Respondent
Through:
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT
1. The present petition has been filed under Section 34 of the Arbitration
and Conciliation Act, 1996 ( hereinafter referred to as “ the Act ”)
challenging the Arbitral Award dated 28.02.2025 passed by the learned Sole
Arbitrator in the arbitration proceedings between “North Delhi Municipal
Corporation v. Ashima Infrastructure Pvt Ltd.
2. By way of the Impugned Award, the learned Sole Arbitrator awarded
a sum of Rs. 12,01,34,424/-, along with pendente lite and future interest as
well as costs of arbitration in favour of the Respondent/NDMC.
3. Brief facts as borne out from the records of the present petition are
stated as under:
i. The Petitioner herein is a private limited company engaged in the
business of advertisement, publicity, outdoor publicity, etc. The
Petitioner approached the Respondent/NDMC, seeking permission to
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 1 of 14
display advertisements at specified parking sites on 18.07.2012. The
Respondent/NDMC accepted the Petitioner’s application on
19.10.2012 and called upon the Petitioner to submit a written consent,
furnish security deposit, advance license fee and advertisement tax.
ii. On 30.10.2012, the Respondent/NDMC executed a Licence
Agreement as well as a No Objection Certificate No. 962 ( hereinafter
referred to as “ NOC ”), thereby granting permission for displaying
advertisements in a total area of 8890 square feet at sites including
Kamla Nagar, Ajmeri Gate and Arya Samaj Road. Pursuant to this,
the Petitioner deposited Rs. 26,67,000/- towards security and a further
sum of Rs.8,89,000/- as advance Monthly License Fees ( hereinafter
referred to as “ MLF ”).
iii. On 27.11.2012 another Licence Agreement No.2 as well as a NOC
No. 1613 were executed by the Respondent/NDMC, thereby granting
permission for displaying advertisements in an area of 9525 square
feet at sites including Videocon Tower, Kalra Hospital and Netaji
Subash Place. Again, pursuant to this, the Petitioner furnished a sum
of Rs. 28,57,500/- towards security deposit.
iv. Between December, 2012 and January, 2013 the Petitioner by way of
several correspondences informed the Respondent/NDMC that it was
unable to carry out its operations on account of interference by the
Public Works Department ( hereinafter referred to as “ PWD ”).
v. Having come to know of the interference, the Respondent/NDMC
wrote to the Engineer-in-Chief of the PWD enquiring them regarding
such obstructions being caused under the claim that the roads were
transferred from the Municipal Corporation to the PWD. Be that as it
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 2 of 14
may, material on record indicates that on 10.03.2013 the Petitioner
was successful in erecting media structures at the specified areas.
vi. It is stated that even though the Petitioner was able to commence its
operations of displaying advertisements, hindrances continued to be
faced by the Petitioner on part of the PWD. It is the case of the
Petitioner that in ignorance of such circumstances that were beyond
the Petitioner’s control, the Respondent/NDMC demanded payment
of full MLF, even for those sites that were non-operational. Faced
with this, the Petitioner was constrained to surrender several flag
signs.
vii. Later on 16.01.2014, the Respondent/NDMC came to execute another
Licence Agreement No.3 along with NOC No. 4782, thereby granting
permission to the Petitioner for displaying advertisements at sites
including Patel Nagar and Old Rajender Nagar.
viii. It is stated in a Writ Petition bearing W.P. (C) No. 6439/2013, this
Court vide Order dated 25.02.2014, directed a joint survey between
the Municipal Corporation of Delhi ( hereinafter referred to as
“ MCD ”), PWD as well as the Petitioner herein, in order to identify
the sites where media/advertisements could be legally installed. It was
further directed that if media structures are within the authorized
zone, the PWD would not interfere. Despite these directions, it is
stated that the Respondent/NDMC failed to execute this joint survey,
leading to continued obstacles being faced by the Petitioner as well as
the disputes regarding billing.
ix. Thereafter, it transpired that notwithstanding the Order dated
25.02.2014 passed by this Court and the pending joint survey, several
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 3 of 14
flag signs of the Petitioner were objected to and even removed by the
PWD as well as the Delhi Metro Rail Corporation, yet again forcing
the Petitioner to surrender such of these sites. Despite of this, the
Respondent/NDMC continued to raise demands for the entire amount
across all three NOCs.
x. On 08.07.2014, after several requests of the Petitioner, the
Respondent/NDMC agreed to adjust the security deposits and charge
fee only for the operational media, however, it is the case of the
Petitioner that no such adjustments were reflected in the actual bills.
xi. In a complete contrast to its decision to adjust amounts, the
Respondent/NDMC pending the joint survey as ordered by this Court,
cancelled 11 sites on 26.08.2014. Faced with this, the Petitioner
approached this Court by way of a Suit bearing CS(OS) No.
2823/2014. In the said Suit, this Court vide Order 16.09.2014
restrained the Respondent/NDMC from taking any coercive action
against the Petitioner.
xii. Overlooking the stay Order dated 16.09.2014, the Respondent/NDMC
upheld its previous cancellation of 11 sites which was carried out on
26.08.2014. The Petitioner brought this action of the
Respondent/NDMC to the knowledge of this Court in CS(OS) No.
2823/2014. Vide Order dated 15.05.2015, this Court stayed the order
of the Respondent/NDMC upholding its previous cancellation and
held the same to be untenable and ignorant of the five year contractual
term between the parties.
xiii. Again, despite the stay order, certain officials of the
Respondent/NDMC on 16.07.2015 illegally removed the media
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 4 of 14
installations at 18 parking sites. Due to this, the Petitioner vide Letter
dated 25.07.2015 informed the Respondent/NDMC that on account of
the illegal removal of the media installations, it will no longer pay the
MLF for such affected sites and will adjust the costs of confiscated
structures against the outstanding dues.
xiv. On 13.04.2016, the Respondent/NDMC demanded a sum of Rs. 1.2
crores against NOC No. 962, Rs. 1.64 crores against NOC No. 1613
and Rs. 50.93 lakh against NOC No. 4782. In response to this, the
Petitioner informed the Respondent/NDMC that the calculations in
the demand letter revealed a unilateral 10% fee enhancement which
was nowhere provided for in the contractual terms agreed upon
between the parties.
xv. Respondent/NDMC on 15.06.2016 cancelled all 37 sites for which the
Licence Agreements were executed and demanded a sum of Rs. 3.61
crores from the Petitioner. Aggrieved by this action of the
Respondent/NDMC, the Petitioner filed a Suit bearing CS (COMM)
No. 1413/2016 challenging the cancellation of the 37 sites as well as
contending that the demands raised by the Respondent/NDMC
ignored the sites surrendered by the Petitioner.
xvi. The abovementioned commercial suit filed by the Petitioner was later
on withdrawn on 04.04.2016, as both parties consented to have their
disputes adjudicated through arbitration. Accordingly, this Court
appointed a Sole Arbitrator to adjudicate upon the disputes between
the parties.
xvii. Material on record indicates that in the arbitration proceedings that
were being held under the Delhi International Arbitration Centre
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 5 of 14
( hereinafter referred to as “ DIAC ”), the Petitioner failed to file its
statement of claims ( hereinafter referred to as “ SOC ”) which led to
the file being closed by the DIAC as the mandate of the Arbitral
Tribunal also came to be expired by the efflux of time.
xviii. Thereafter, the arbitration proceedings were restored by the DIAC
after the Respondent/NDMC prayed before this Court for the same.
The DIAC informed the Respondent/NDMC that it could step into the
shoes as the claimant and proceed to file its statement of claims. The
Respondent/NDMC filed its SOC on 04.01.2022 under which a total
amount of Rs. 12,01,34,424/- was claimed. The description of the
claims of the Respondent/NDMC in its SOC are stated as under:
a. Amount due on account of unpaid Monthly License Fees
(MLF) (Rs. 4,91,64,529/-).
b. Interest @ 2% per month on MLF due and payable up to
30.11.2021 (Rs. 7,09,69,895/-).
c. Future interest @2% per month on a sum of Rs. 12,01,24,424/-
from the date of filing till realization.
d. Legal costs and cost of Arbitration.
4. It is borne out from the record that the Petitioner herein was
proceeded ex-parte by the learned Sole Arbitrator, as there was no
appearance on behalf of the Petitioner, despite valid service being effected
through registered post on the directors of the Petitioner’s company being
one Mr. Himanshu and Mr. Sanjay Jain. Rather, the service upon these two
persons via speed post was returned with the mark “refused”. In addition to
service via registered post, it is noted that service via WhatsApp was also
effected.
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 6 of 14
5. On the basis of the material on record, the learned Sole Arbitrator
held that the Petitioner herein was liable to pay the MLF from 10.03.2013
for the sites mentioned in NOC Nos. 962 and 1613. The learned Sole
Arbitrator also made a preliminary observation as to the rate of interest, and
was of the opinion that since the agreement between the parties provided for
a rate of interest of 24% per annum, the same would only be applicable to
the claims. Lastly, before adjudicating upon the claims of the
Respondent/NDMC, the learned Sole Arbitrator also observed that as
against NOC No. 4782 the three month period which is a pre-requisite for
the commencement of liability to pay the MLF, would begin from
16.04.2004 only.
6. Adjudicating upon the Claim No.1 of the Respondent/NDMC, the
learned Sole Arbitrator held that the Petitioner was liable to pay MLF for
NOC Nos. 962 and 1613 from 10.03.2013, when it received an encumbrance
free site. With regards to NOC No. 4782, the Petitioner was liable to pay
MLF from 16.04.2014. While noting that a security deposit of Rs.
64,84,500/- was made by the Petitioner for all three NOCs, the same was
liable to be forfeited and adjusted due to the failure of the Petitioner to make
the payment. Therefore, the learned Sole Arbitrator directed that the said
sum of Rs. 64,84,500/- would be deducted from the total claim amount in
Claim No.1; thereby awarding a sum of Rs. 4,00,62,199/- in favour of the
Respondent/NDMC.
7. As far as Claim No.2 is concerned which is regarding the interest on
the outstanding due of MLF, the learned Sole Arbitrator awarded a sum of
Rs. 7,09,26,623/- in favour of the Respondent/NDMC.
8. Lastly, as against the Claim No.3 regarding future interest, the learned
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 7 of 14
Sole Arbitrator allowed pendente lite and future interest at the rate of 14%
per annum on the principal amounts. In addition, the learned Sole Arbitrator
also awarded the entire amount of Arbitral fee being Rs. 3,00,000/- in favour
of the Respondent/NDMC.
9. It is the foregoing observations of the learned Sole Arbitrator as well
as the Award of claims in favour of the Respondent/NDMC that are under
challenge in the present petition.
10. Alleging that the Impugned Award is patently illegal, violates the
principle of natural justice and is in conflict with the fundamental policy of
Indian law, the learned Counsel appearing for the Petitioner submits as
under:
i. The Impugned Award is liable to be set aside under Section 34
(2)(a)(iii) of the Act as the Petitioner was “otherwise unable to present
his case”. It is submitted that the learned Sole Arbitrator proceeded
ex-parte solely based on a refusal of service by a spouse at a
residential address, thereby failing to ensure effective service on the
corporate entity, i.e., the Petitioner herein. Reliance in this regard is
placed on the judgments of the Apex Court in Ssangyong Engineering
and Construction Company Limited v. National Highways Authority
of India (NHAI), (2019) 15 SCC 131 and Oil & Natural Gas
Corporation Ltd v. Saw Pipes Ltd, (2003) 5 SCC 705 .
ii. Despite the Respondent/NDMC itself having produced documents
which specified the actual area in which media installations could be
carried out by the Petitioner, the learned Sole Arbitrator went ahead
and held the Petitioner liable for paying MLF for the full areas. While
relying on the judgment of the Apex Court in National Highways
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 8 of 14
Authority of India v. P. Nagaraju, (2022) 15 SCC 1 , learned Counsel
for the Petitioner submits that the Impugned Award is liable to be set
aside as it is “based on no evidence” and also “ignores vital
evidence”.
iii. The learned Sole Arbitrator overlooked the fact that the
Respondent/NDMC despite clear directions by this Court failed to
carry out the joint survey and also violated the stay order and illegally
removed the media displays installed by the Petitioner.
iv. While ignoring the non-compliant conduct of the Respondent/NDMC,
the learned Sole Arbitrator holds the Petitioner liable towards the
payment of the entire license fee, thereby resulting in unjust
enrichment of the Respondent/NDMC. Reliance in this regard is
placed on the judgment of the Apex Court in ONGC v. Western Geco
(supra).
11. Heard the learned Counsel for the Petitioner and perused the material
on record.
12. The primary issue which arises for consideration before this Court is
as to whether the Impugned Award warrants interference in the light of the
same being passed ex-parte against the Petitioner. For adjudication on this
issue, a few facts that are noted in the Impugned Award are required to be
appreciated.
13. A reading of the Impugned Award indicates that after the learned Sole
Arbitrator was appointed by a Co-ordinate Bench of this Court vide Order
dated 04.04.2018, initially it was the Petitioner itself who failed to file its
SOC despite being called upon to do so by the DIAC. This led to the DIAC
to close the file in the matter on 17.07.2018. Thereafter, vide e-mail dated
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 9 of 14
16.11.2022, the DIAC informed the parties that the mandate of the Arbitral
Tribunal had expired, the matter was closed and advised the parties to take
appropriate steps for seeking extension of the mandate of the Arbitral
Tribunal.
14. No immediate steps were taken by either party. Thereafter, it was the
Respondent/NDMC that moved an application being I.A. No. 14236/2021
seeking the restoration of CS (COMM) No. 1413/2016. However, when the
said application came to be dismissed, the Respondent/NDMC approached
the DIAC. On 02.02.2024, the Deputy Counsel DIAC sought consent
declaration from the learned Sole Arbitrator, which was given on 06.02.2024
and the preliminary hearing was fixed on 21.02.2024.
15. It is pertinent to note that a notice for preliminary hearing was
directed to be issued to the Petitioner, returnable on 21.02.2024 at 02:30
PM. As per the tracking report which was made available to the learned Sole
Arbitrator, the notice was duly served on the Petitioner on 14.02.2024.
Despite this, none was present on behalf of the Petitioner on the date of the
preliminary hearing. Be that as it may, the learned Sole Arbitrator in the
interest of justice granted one more opportunity of four weeks to the
Petitioner to file its reply. In particular, the learned Sole Arbitrator directed
that a notice along with the SOC and copy of arbitral proceedings be served
upon the Petitioner by speed-post, e-mail id as well as Dasti, returnable on
06.04.2024.
16. As per the memo filed by the Respondent/NDMC, steps were taken to
serve the notice upon the Petitioner at the known address being 7-B,
Basement, Sanjay Nagar, Gulabi Bagh, Near NKS Hospital, Delhi – 110007.
However, since the said premises was found locked and the whereabouts of
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 10 of 14
the addressee could not be ascertained, the notice was pasted at the entrance
wall of the premises. Additionally, notice was also served to the last known
e-mail address of the Petitioner.
17. The learned Sole Arbitrator specifically notes that even though the
Respondent/NDMC had done service on the Petitioner by affixation, it was
felt that the Respondent/NDMC must make further efforts to ascertain the
whereabouts of the Petitioner, and without doing so proceeding ex-parte
may not serve the ends of justice. As such, the Counsel representing the
Respondent/NDMC before the learned Sole Arbitrator submitted that further
such steps could be taken including those to ascertain the current address of
the Petitioner. Alternatively, the Respondent/NDMC also suggested that
steps could be taken for considering an application for substituted service by
publication.
18. On 16.05.2024, Section Officer of the Respondent/NDMC submitted
before the learned Sole Arbitrator that after making efforts they were able to
trace the addresses of the Directors of the Petitioner Company, being one
Mr. Himanshu and Mr. Sanjay Jain. Accordingly, the learned Sole Arbitrator
directed that notices be issued to both the Directors at the addresses
discovered by the Respondent/NDMC, returnable on 08.07.2024.
19. Steps were taken by the Respondent/NDMC to serve notices upon Mr.
Himanshu and Mr. Sanjay Jain, and an affidavit of service was filed to this
effect. As per the affidavit of service, it was noted that service of notices
upon both the Directors was done through speed-post. It also came to light
that the Section Officer of the Respondent/NDMC personally attempted to
deliver Dasti notice to Mr. Himanshu at his residential address, however, the
same was refused by Mr. Himanshu’s wife.
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 11 of 14
20. Despite all these steps, none appeared on behalf of the Petitioner on
08.07.2024. Considering all the foregoing circumstances, the learned Sole
Arbitrator eventually concluded that the Petitioner stands duly served, rather
the Petitioner’s Directors were evading and refusing service. It is only after a
lapse of more than five months that the learned Sole Arbitrator deemed it
appropriate to continue the proceedings in the absence of the Petitioner.
21. At this juncture, this Court deems it appropriate to refer to Section 25
of the Act. Section 25 of the Act is reproduced as under:
“25. Default of a party. — Unless otherwise agreed by
the parties, where, without showing sufficient cause,—
(a) the claimant fails to communicate his statement of
claim in accordance with sub-section (1) of section 23,
the arbitral tribunal shall terminate the proceedings;
(b) the respondent fails to communicate his statement
of defence in accordance with sub-section (1) of
section 23, the arbitral tribunal shall continue the
proceedings without treating that failure in itself as an
admission of the allegations by the claimant 3 [and
shall have the discretion to treat the right of the
respondent to file such statement of defence as having
been forfeited].
(c) a party fails to appear at an oral hearing or to
produce documentary evidence, the arbitral tribunal
may continue the proceedings and make the arbitral
award on the evidence before it.”
22. As per Section 23(a) of the Act, the arbitral tribunal is entitled to
terminate the proceedings when the claimant fails to communicate his
statement of claim in accordance with Section 23(1) of the Act. As per
Section 25(b) of the Act, where the Respondent fails to communicate his
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 12 of 14
statement of defence in accordance with Section 23(1) of the Act, the
arbitral tribunal shall continue the proceedings without treating that failure
as an admission of the allegations levelled by the claimant. Lastly, under
Section 25(c) of the Act, if a party fails to appear in a hearing or produce
documentary evidence, it is open to the Arbitral Tribunal to pass an award
on the evidence before it.
23. Section 25 lays down very clearly the consequences of the failure on
part of either party, in order to ensure effectiveness of the parties’ agreement
or settlement of the disputes through arbitration. In particular, Section 25(c)
of the Act which is most relevant to the present case, clearly prescribes that
the arbitral tribunal is not precluded from proceeding with the hearing, and if
the parties are given sufficient notice in advance, but failed to respond to it,
the arbitral tribunal could is empowered to proceed with the hearing to pass
the award.
24. The facts of the present case reveal that sufficient opportunity was
afforded to the Petitioner for appearing before the learned Sole Arbitrator
after service. However, more than five months elapsed after the preliminary
hearing and yet no communication came through on part of the Petitioner.
What is more interesting is that no application for setting aside the decision
of the learned Sole Arbitrator to proceed ex-parte was ever preferred by the
Petitioner. These events do in fact indicate that the Petitioner was
somewhere determined not to appear before the learned Sole Arbitrator or
even give explanations for their non-appearance. Rather, even in the present
petition, the Petitioner has not given any explanation as to why there was no
appearance on its behalf before the learned Sole Arbitrator.
25. In these view of the circumstances, this Court finds it difficult to
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 13 of 14
agree with the objections of the Petitioner against the Impugned Award
which has been passed in light of Section 25(c) of the Act and on the basis
of the material produced before it. Moreover, this Court is also conscious of
the well settled position that the Arbitral Tribunal is the master of evidence
and the findings of fact which are arrived at by the Arbitral Tribunal on the
basis of the evidence on record are not to be scrutinized as if the Court was
sitting in appeal [Ref: Maharashtra State Electricity Distribution Company
Limited v. Datar Switchgear Limited and Others, (2018) 3 SCC 133 ].
26. Accordingly, this Court finds no merit in the contention of the
Petitioner that the Impugned Award suffers from patent illegality, is in
violation of public policy or violates the fundamental policy of Indian law
solely on account that the same was passed ex-parte against the Petitioner.
27. The other contentions of the Petitioner regarding ignorance of vital
evidence and unjust enrichment being caused to the Respondent/NDMC, are
also liable to be rejected as in the opinion of this Court, the Impugned
Award is well reasoned, takes into account all the evidence before it and the
views taken by the learned Sole Arbitrator do not shock the conscience of
this Court.
28. The Petition is accordingly dismissed along with pending
application(s), if any.
SUBRAMONIUM PRASAD, J
MARCH 11, 2026
Prateek /AP
Signature Not Verified
Signed By:RAHUL
SINGH
Signing Date:17.03.2026
10:52:41
O.M.P. (COMM) 53/2026 Page 14 of 14